CN202718375U - Installation and operation platform of high-altitude cantilever structure - Google Patents

Installation and operation platform of high-altitude cantilever structure Download PDF

Info

Publication number
CN202718375U
CN202718375U CN 201220051472 CN201220051472U CN202718375U CN 202718375 U CN202718375 U CN 202718375U CN 201220051472 CN201220051472 CN 201220051472 CN 201220051472 U CN201220051472 U CN 201220051472U CN 202718375 U CN202718375 U CN 202718375U
Authority
CN
China
Prior art keywords
platform
section bar
high altitude
installation
operation platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220051472
Other languages
Chinese (zh)
Inventor
姜志浩
史继心
张琨
黄刚
于力海
彭云涛
吕雄
周三明
明磊
叶勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd, China Construction Steel Structure Corp Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN 201220051472 priority Critical patent/CN202718375U/en
Application granted granted Critical
Publication of CN202718375U publication Critical patent/CN202718375U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses an installation and operation platform of a high-altitude cantilever structure. The installation and operation platform is characterized by comprising section bar hoops, suspenders, diagonal members, a platform and horizontal pull rods. The suspenders are arranged on a side face of the platform, the section bar hoops are fixedly arranged at the top of the suspenders, the horizontal pull rods are arranged between the section bar hoops, and the diagonal members are arranged between the section bar hoops and the platform. Reinforcing ribs are arranged at intersected joints of the platform and the suspenders. Foot planks or steel plate screens are paved on the platform. Reinforcing ribs are arranged at intersected joints of the horizontal and vertical rods. A layer of scaffolds is erected on the section bar platform. Brackets of the high-altitude cantilever structure are fixedly connected with the section bar hoops. The installation and operation platform of the high-altitude cantilever structure provided by the utility model has the beneficial effects that (1), the spliced steel platform can reduce dangers of installation, correction and erection of a welding platform of the high-altitude cantilever structure; (2) the integral construction progress can be accelerated; and (3) the labor cost can be effectively reduced and the economical benefits are remarkable.

Description

Suspended structure at high altitude fitting operation platform
Technical field
The utility model relates to a kind of suspended structure at high altitude fitting operation platform.
Background technology
At present, the installing engineering of steel work cantilevered structure generally adopts scaffolding steel pipe or section bar to set up operating platform.The method is applicable to the lower situation of building height, uses duration, consumes manually greatly, is not suitable for super highrise building.And during scattered steel pipe assembly unit, very easily form coming off of steel pipe and fastener, and cause object to hit injury.And suspended structure at high altitude fitting operation platform can effectively avoid object to hit injury, guarantees Construction of Steel Structure safety.
The utility model content
Technical problem to be solved in the utility model provides a kind of suspended structure at high altitude fitting operation platform, adopts welding or bolt to connect, and installs simple and easyly, uses reliably, can effectively avoid the danger of work high above the ground.
Technical problem to be solved in the utility model is achieved through the following technical solutions:
A kind of suspended structure at high altitude fitting operation platform is characterized in that: comprise shaped steel anchor ear, suspension rod, diagonal member, platform and girt; Described platform side facade arranges suspension rod, and the top fixed steel hoop of suspension rod is provided with girt between the shaped steel anchor ear, is provided with diagonal member between shaped steel anchor ear and the platform.
The Nodes that described platform and suspension rod intersect arranges stiffener.
Lay scaffold floor or expanded metal lath above the described platform.
The described Node configuration stiffener that intersects at level and vertical bar.
Set up one deck scaffold on the described platform.
The bracket of described suspended structure at high altitude is fixedly connected with the shaped steel anchor ear.
The utlity model has following beneficial effect:
1. this assembling type steel platform can reduce the danger that high-altitude steel structure installation, correction, jig are set up;
2. can accelerate the integral construction progress;
3. can effectively reduce labor cost, remarkable in economical benefits.
Description of drawings
Fig. 1 the utility model elevation;
Fig. 2 the utility model side view;
Fig. 3 the utility model top view;
Among the figure, 1-shaped steel anchor ear, 2-suspension rod, 3-diagonal member, 4-platform, 5-girt, 6-bracket, 7-scaffold.
The specific embodiment
Shown in Fig. 1-3, a kind of suspended structure at high altitude fitting operation platform is characterized in that: comprise shaped steel anchor ear 1, suspension rod 2, diagonal member 3, platform 4 and girt 5; Described platform 4 side elevations arrange suspension rod 2, and the top fixed steel hoop 1 of suspension rod 2 is provided with girt 5 between the shaped steel anchor ear 1, be provided with diagonal member 3 between shaped steel anchor ear 1 and the platform, forms thus the overall structure of an operating platform.
Described platform 4 arranges stiffener with the Nodes that suspension rod 2 intersects, and the described Node configuration stiffener that intersects at level and vertical bar is for the further reinforcing between the operating platform connector.
Lay scaffold floor or expanded metal lath above the described platform 4.
Set up one deck scaffold 7 on the described platform 4.
The bracket 6 of described suspended structure at high altitude is fixedly connected with shaped steel anchor ear 1.Because the bracket 6 of cantilevered structure root is by directly stretching out in the agent structure, can bear the cantilevered structure of whole outside fully, therefore hanging a weight at overhanging bracket 6 is feasible less than the operating platform of cantilevered structure.
The operating platform installation process, should guarantee that agent structure constructed completely, and possess certain intensity, can bear cantilevered structure, the deadweight of steel platform and basic operation personnel live load fully, can place section steel platform, platform is installed and is adopted lifting appliance to cooperate lifting.
Concrete operation step is:
1. externally stretch bracket 6 sizes according to relevant drawings such as structural drawings and architectural drawings and spacing is determined;
2. select to make the section bar of operating platform according to the size of overhanging bracket and span design, all nodes of operating platform are welding, at the crossing Node configuration stiffener of platform 4 levels and vertical bar;
3. at floor manufacture complete operation platform, and lay scaffold floor or expanded metal lath in the above;
4. weld vertical scaffold 7 at platform 4 side elevations, as the security protection maintenance system;
5. utilize tower crane lifting operating platform.
The lifting idiographic flow is: operating platform setting-out → operating platform makes → welds external maintenance structure → operating platform and install → carry out cantilevered structure install, proofread and correct, weld → dismounting → the next position of finishing using recycles.
After finishing using, lifting appliance cooperates to be removed, and forwards other position construction week to and uses.

Claims (6)

1. a suspended structure at high altitude fitting operation platform is characterized in that: comprise shaped steel anchor ear, suspension rod, diagonal member, platform and girt; Described platform side facade arranges suspension rod, and the top fixed steel hoop of suspension rod is provided with girt between the shaped steel anchor ear, is provided with diagonal member between shaped steel anchor ear and the platform.
2. suspended structure at high altitude fitting operation platform as claimed in claim 1 is characterized in that: the Nodes that described platform and suspension rod intersect arranges stiffener.
3. suspended structure at high altitude fitting operation platform as claimed in claim 1 is characterized in that: lay scaffold floor or expanded metal lath above the described platform.
4. suspended structure at high altitude fitting operation platform as claimed in claim 1 is characterized in that: the described Node configuration stiffener that intersects at level and vertical bar.
5. suspended structure at high altitude fitting operation platform as claimed in claim 1 is characterized in that: set up one deck scaffold on the described platform.
6. such as the described suspended structure at high altitude fitting operation of one of claim 1 to 5 platform, it is characterized in that: the bracket of described suspended structure at high altitude is fixedly connected with the shaped steel anchor ear.
CN 201220051472 2012-02-17 2012-02-17 Installation and operation platform of high-altitude cantilever structure Expired - Fee Related CN202718375U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220051472 CN202718375U (en) 2012-02-17 2012-02-17 Installation and operation platform of high-altitude cantilever structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220051472 CN202718375U (en) 2012-02-17 2012-02-17 Installation and operation platform of high-altitude cantilever structure

Publications (1)

Publication Number Publication Date
CN202718375U true CN202718375U (en) 2013-02-06

Family

ID=47620201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220051472 Expired - Fee Related CN202718375U (en) 2012-02-17 2012-02-17 Installation and operation platform of high-altitude cantilever structure

Country Status (1)

Country Link
CN (1) CN202718375U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206075A (en) * 2013-04-26 2013-07-17 中国化学工程第三建设有限公司 Suspension platform for construction of steel reinforced concrete cantilever structure
CN103485524A (en) * 2013-10-11 2014-01-01 四川省第四建筑工程公司 Bracket type overhanging scaffold and construction method thereof at erection time
CN114105001A (en) * 2021-11-16 2022-03-01 中建三局集团有限公司 Assembled tower crane body overhanging platform and mounting method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206075A (en) * 2013-04-26 2013-07-17 中国化学工程第三建设有限公司 Suspension platform for construction of steel reinforced concrete cantilever structure
CN103485524A (en) * 2013-10-11 2014-01-01 四川省第四建筑工程公司 Bracket type overhanging scaffold and construction method thereof at erection time
CN103485524B (en) * 2013-10-11 2016-03-23 四川省第四建筑工程公司 Corbel type builder's jack and construction when setting up thereof
CN114105001A (en) * 2021-11-16 2022-03-01 中建三局集团有限公司 Assembled tower crane body overhanging platform and mounting method thereof
CN114105001B (en) * 2021-11-16 2023-07-18 中建三局集团有限公司 Tower body overhanging platform of assembled tower crane and mounting method thereof

Similar Documents

Publication Publication Date Title
CN103758341B (en) Steel column drum rack support type hydraulic lifting overall steel platform cross truss layer construction method
CN107558723B (en) Method for manufacturing and installing hanging bracket of hanging basket for inclined roof
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN205077845U (en) Hydraulic intelligent climbing operation scaffold for core barrel well of building
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103422668A (en) Construction method of super-thick large-slope shear wall and hydraulic self-jacking inclined creeping framework thereof
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN104831939A (en) Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN111472530A (en) Flower basket pull rod I-shaped steel cantilever bearing frame for constructional engineering and mounting method thereof
CN202718375U (en) Installation and operation platform of high-altitude cantilever structure
CN203034779U (en) Self-lifting-type scaffold operating platform
CN202227701U (en) Spliced type horizontal channel device
CN202945798U (en) Overhanging type scaffold corner device
CN102061810B (en) Construction method of safe flat net positioned on periphery of building
CN102287045B (en) Square steel tube lifting outside scaffold
CN201908447U (en) Lift-type horizontal safety net
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN105347142A (en) Plate penetrating installing method for installing construction lifting machine on basement top plate
CN102979297A (en) Hanging type stairwell operating platform mechanism and construction method thereof
CN102277900A (en) Sectional-stacking jacking mounting method of vase-shaped space steel structure
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN204343642U (en) Builder's jack corner support frame
CN102022003A (en) Suspended ceiling keel sheet assembling and hoisting method
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130206

Termination date: 20200217

CF01 Termination of patent right due to non-payment of annual fee