CN202672167U CN2012202770407U CN201220277040U CN202672167U CN 202672167 U CN202672167 U CN 202672167U CN 2012202770407 U CN2012202770407 U CN 2012202770407U CN 201220277040 U CN201220277040 U CN 201220277040U CN 202672167 U CN202672167 U CN 202672167U
Authority
CN
China
Prior art keywords
nose girder
steel sheet
sheet pile
guide
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012202770407U
Other languages
Chinese (zh)
Inventor
吴金安
魏雪松
夏国权
贾双
马美晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG JINHAO TRAFIFIC ENGINEERING Co Ltd
Original Assignee
ZHEJIANG JINHAO TRAFIFIC ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG JINHAO TRAFIFIC ENGINEERING Co Ltd filed Critical ZHEJIANG JINHAO TRAFIFIC ENGINEERING Co Ltd
Priority to CN2012202770407U priority Critical patent/CN202672167U/en
Application granted granted Critical
Publication of CN202672167U publication Critical patent/CN202672167U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

A steel sheet pile cofferdam structure located in a foundation pit comprises steel sheet piles, positioning piles, guide beams and inner supports. Meshing openings of the steel sheet piles are fastened with one another to form seal drums along the inner side of the foundation pit. The horizontal annular guide beams are closely attached to the inner sides of steel sheet piles. The positioning piles are distributed at intervals on the inner sides of the guide beams and fixedly connected with the guide beams. The guide beams are layered along the depth direction of the foundation pit. The inner supports are distributed at intervals between guide beams on the same layer on opposite sides of the foundation pit. Guide beam supports disposed at intervals are rested on the lower sides of the guide beams. Each guide beam support is welded by a horizontal support and an inclined support. Guide beam positioning parts disposed at intervals are pressed on the upper sides of the guide beams. Each guide beam positioning part is welded by a horizontal pressing part and an inclined pulling part. The guide beam supports and the guide beam positioning parts are in up and down one-to-one correspondence and fixedly integrated with the positioning piles. The technical problem that steel sheet pile cofferdam lapping cannot be performed smoothly in traditional deep foundation pits due to insufficient strength of the guide beams is solved. Construction is simple, and construction period is shortened.

Description

A kind of steel sheet pile cofferdam structure
Technical field
The utility model relates to the cofferdam structure of a kind of cofferdam structure, particularly a kind of steel sheet pile.
Background technology
Development along with national economy, the bridges in highway engineering span ability is more and more stronger, for reaching, the coordination with surrounding environment do not affect navigation simultaneously, cushion cap is embedded in the underground degree of depth also to be increased gradually, requirement to bracing of foundation pit is more and more higher, the sloping method of putting of using is in the past excavated, and the supporting method such as timber supporting, shaped steel supporting, steel pipe pile supporting can't satisfy present construction requirement.Owing to need to do the dry application worker during foundation pit construction in the water, at this moment just need the water and soil gear to use steel sheet pile or other temporary structure that the water and soil in the outside is carried out shutoff in the foundation ditch outside Here it is steel sheet-pile cofferdam.Steel sheet-pile cofferdam is to use steel sheet pile by the root inserted to play, and an integral body is sealed in mutually snap-in at last between the steel sheet pile.Steel sheet-pile cofferdam is generally by guide pile, and nose girder and steel sheet pile form.Guide pile is timber or reinforced concrete pipe pile, and nose girder is generally the lumps of wood or shaped steel, and particularly in the larger engineering of foundation depth, if strength deficiency, the steel sheet-pile cofferdam that is easy to cause overlap joint can't carry out traditional nose girder smoothly.
The utility model content
The purpose of this utility model provides a kind of steel sheet pile cofferdam structure, solves the steel sheet-pile cofferdam that causes because of the nose girder strength deficiency in the deep foundation ditch and overlaps the technical problem that can't carry out smoothly.
For achieving the above object, the utility model adopts following technical scheme:
A kind of steel sheet pile cofferdam structure, be positioned within the foundation ditch, comprise steel sheet pile, guide pile, nose girder and inner support, the mutual fastening of the articulation port of described steel sheet pile surrounds the sealing cylinder along the foundation ditch inboard, described nose girder is close to the steel sheet pile inboard and is horizontal annular, described guide pile is fixedly connected with along the distribution of nose girder clear width and with nose girder, described nose girder arranges along the layering of foundation depth direction, be fixed with inner support spaced apart between the same layer nose girder of the relative both sides of foundation ditch, the nose girder that bogie side frame has the interval to arrange under the described nose girder supports, nose girder supports and is welded by horizontal brace and diagonal brace, described nose girder upside is pressed with the nose girder keeper that the interval arranges, the nose girder keeper is welded by horizontal casting die and oblique pull part, and described nose girder supports and the up and down one by one corresponding setting of nose girder keeper, and all with on the guide pile is connected to one.
Described sealing cylinder can be individual layer or bilayer.
The shape of described sealing cylinder can be circle, rectangle or nose circle shape.
Described guide pile can be timber or reinforced concrete pile.
Described nose girder is that single Pin, two Pin or three Pin models shaped steel identical and that length is identical is spliced.
Described nose girder supports and the connected mode of nose girder keeper and guide pile is welding or anchoring.
Described horizontal brace, diagonal brace, horizontal casting die and oblique pull part can be channel-section steel, i iron or H shaped steel.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model has overcome the steel sheet-pile cofferdam that causes because of the nose girder strength deficiency in traditional deep foundation ditch and has overlapped the technical problem that can't carry out smoothly, and easy construction is saved the duration.
The utility model can be widely used in the construction of foundation ditch cofferdam structure.
Description of drawings
The utility model is described in more detail below in conjunction with accompanying drawing.
Fig. 1 is plan structure schematic diagram of the present utility model.
Fig. 2 is the side-looking structural representation of nose girder and guide pile connected node among the utility model embodiment one.
Fig. 3 is the side-looking structural representation of nose girder and guide pile connected node among the utility model embodiment two.
Fig. 4 is the side-looking structural representation of nose girder and guide pile connected node among the utility model embodiment three.
Reference numeral: 1-steel sheet pile, 2-guide pile, 3-nose girder, 4-scotch, the support of 5-nose girder, 5.1-horizontal brace, 5.2-diagonal brace, 6-nose girder keeper, the horizontal casting die of 6.1-, 6.2-oblique pull part.
The specific embodiment
Embodiment one is referring to shown in Fig. 1-2, a kind of steel sheet pile cofferdam structure, be positioned within the foundation ditch, comprise steel sheet pile 1, guide pile 2, nose girder 3 and inner support, the mutual fastening of the articulation port of described steel sheet pile 1 surrounds the sealing cylinder along the foundation ditch inboard, described nose girder 2 is close to steel sheet pile 1 inboard and is horizontal annular, be plugged with scotch 4 between steel sheet pile 1 and the nose girder, described guide pile 2 is fixedly connected with along the distribution of nose girder 3 clear widths and with nose girder 3, described nose girder 3 arranges along the layering of foundation depth direction, be fixed with inner support spaced apart between the same layer nose girder 3 of the relative both sides of foundation ditch, the nose girder that 3 times bogie side frames of described nose girder have the interval to arrange supports 5, nose girder supports and is welded by horizontal brace 5.1 and diagonal brace 5.2, described nose girder 3 upsides are pressed with the nose girder keeper 6 that the interval arranges, nose girder keeper 6 is welded by horizontal casting die 6.1 and oblique pull part 6.2, and described nose girder supports 5 and the up and down one by one corresponding setting of nose girder keeper, and all with guide pile 2 on built-in fitting be connected to one.
Described sealing cylinder is individual layer or bilayer.Described sealing cylinder be shaped as circle, rectangle or nose circle shape.Described guide pile 2 is timber or reinforced concrete pile.Described nose girder 3 is spliced for single Pin, two Pin or three Pin models shaped steel identical and that length is identical.
Described nose girder support 5 and nose girder keeper 6 are welding or anchoring with the connected mode of guide pile 2.Described horizontal brace 5.1, diagonal brace 5.2, horizontal casting die 6.1 and oblique pull part 6.2 are channel-section steel, i iron or H shaped steel.
The sealing cylinder is single rectangular in the present embodiment, guide pile 2 is reinforced concrete pile, nose girder 3 is single Pin i iron, horizontal brace 5.1, diagonal brace 5.2, be i iron, horizontal casting die 6.1 and oblique pull part 6.2 are channel-section steel, need in advance at the pre-buried steel part in the guide pile junction of steel concrete, guide pile 2 be with horizontal brace 5.1, diagonal brace 5.2, horizontal casting die 6.1 and oblique pull part 6.2 be welded to connect.
Embodiment two is referring to shown in Figure 3, and different from embodiment one is that nose girder 3 is two Pin i iron.
Embodiment three is referring to shown in Figure 4, and all different from embodiment one and two is that nose girder 3 is three Pin i iron.
Construction sequence of the present utility model is as follows:
Step 1: in foundation ditch,, and carry out red timber at gray line and identify along the axis gray line of being sidelong the steel sheet pile articulation port in the foundation ditch by design axis requirements.
Step 2: make guide pile by the axis gray line.
Step 3: the welding nose girder supports and the nose girder keeper on the guide pile.
Step 3: nose girder lifting is put in place, along the sign of guide pile nose girder is installed, and is welded and fixed with guide pile, check and approve the nose girder center line whether on the axis gray line of steel sheet pile articulation port.
Step 4: check whether steel sheet pile is straight, intact before the heavy steel sheet pile, guarantee during piling that the stake top is suitable for reading straight, reach design elevation.
Step 5: use two transits vertically to control, if deviation occurs, revise at any time by loop wheel machine levelling suspension centre orientation.The discovery verticality exceeds standard, and must extract the steel sheet pile stake of again performing fighting.
Step 6: after steel sheet pile is delivered to design elevation, continue to repeat the construction of next pile.

Claims (7)

1. steel sheet pile cofferdam structure, be positioned within the foundation ditch, comprise steel sheet pile (1), guide pile (2), nose girder (3) and inner support, the mutual fastening of articulation port of described steel sheet pile (1) surrounds the sealing cylinder along the foundation ditch inboard, described nose girder (2) is close to steel sheet pile (1) inboard and is horizontal annular, be plugged with scotch (4) between steel sheet pile (1) and the nose girder, described guide pile (2) is fixedly connected with along the distribution of nose girder (3) clear width and with nose girder (3), described nose girder (3) arranges along the layering of foundation depth direction, be fixed with inner support spaced apart between the same layer nose girder (3) of the relative both sides of foundation ditch, it is characterized in that: the nose girder that the lower bogie side frame of described nose girder (3) has the interval to arrange supports (5), nose girder supports and is welded by horizontal brace (5.1) and diagonal brace (5.2), described nose girder (3) upside is pressed with the nose girder keeper (6) that the interval arranges, nose girder keeper (6) is welded by horizontal casting die (6.1) and oblique pull part (6.2), described nose girder supports (5) and up and down one by one corresponding setting of nose girder keeper (6), and all is connected to one with guide pile (2).
2. a kind of steel sheet pile cofferdam structure according to claim 1 is characterized in that: described sealing cylinder is individual layer or bilayer.
3. a kind of steel sheet pile cofferdam structure according to claim 1 is characterized in that: described sealing cylinder be shaped as circle, rectangle or nose circle shape.
4. a kind of steel sheet pile cofferdam structure according to claim 1, it is characterized in that: described guide pile (2) is timber or reinforced concrete pile.
5. a kind of steel sheet pile cofferdam structure according to claim 1, it is characterized in that: described nose girder (3) is spliced for single Pin, two Pin or three Pin models shaped steel identical and that length is identical.
6. a kind of steel sheet pile cofferdam structure according to claim 1 is characterized in that: described nose girder supports the connected mode of (5) and nose girder keeper (6) and guide pile (2) for welding or anchoring.
7. a kind of steel sheet pile cofferdam structure according to claim 1, it is characterized in that: described horizontal brace (5.1), diagonal brace (5.2), horizontal casting die (6.1) and oblique pull part (6.2) are channel-section steel, i iron or H shaped steel.
CN2012202770407U 2012-06-13 2012-06-13 Steel sheet pile cofferdam structure Expired - Fee Related CN202672167U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012202770407U CN202672167U (en) 2012-06-13 2012-06-13 Steel sheet pile cofferdam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012202770407U CN202672167U (en) 2012-06-13 2012-06-13 Steel sheet pile cofferdam structure

Publications (1)

Publication Number Publication Date
CN202672167U true CN202672167U (en) 2013-01-16

Family

ID=47493076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012202770407U Expired - Fee Related CN202672167U (en) 2012-06-13 2012-06-13 Steel sheet pile cofferdam structure

Country Status (1)

Country Link
CN (1) CN202672167U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114596A (en) * 2013-02-05 2013-05-22 东南大学 Novel heated steering wheel (HSW) working pile method formation pit timbering structure and construction method thereof
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer
CN106592598A (en) * 2016-11-25 2017-04-26 中铁三局集团有限公司 Same-layer double-beam large-diameter steel pipe support and deep foundation pit combined inner support formed thereby
CN113073667A (en) * 2021-04-06 2021-07-06 北京华昊水利水电工程有限责任公司 Assembled cofferdam structure and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114596A (en) * 2013-02-05 2013-05-22 东南大学 Novel heated steering wheel (HSW) working pile method formation pit timbering structure and construction method thereof
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer
CN106592598A (en) * 2016-11-25 2017-04-26 中铁三局集团有限公司 Same-layer double-beam large-diameter steel pipe support and deep foundation pit combined inner support formed thereby
CN113073667A (en) * 2021-04-06 2021-07-06 北京华昊水利水电工程有限责任公司 Assembled cofferdam structure and construction method

Similar Documents

Publication Publication Date Title
CN107268636A (en) The diaphragm wall foundation ditch that the steel cylinder or steel sheet pile of a kind of seal groove and occlusion structure are constituted is with going along with sb. to guard him and construction method
CN202492865U (en) Correction device of transmission tower
CN202672167U (en) Steel sheet pile cofferdam structure
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN110344335B (en) Method for constructing steel trestle, initial platform and cofferdam in bridge construction process
CN102864780A (en) Supporting structure and supporting method of foundation pit
CN105350526B (en) Method for setting up steel platform
CN105863042A (en) All-steel structure building and construction method thereof
CN109356169B (en) Foundation pit row pile supporting system and construction method thereof
CN106812144A (en) Double-wall steel cofferdam construction method
CN106088131A (en) Armored concrete cross tower crane and construction method thereof
CN109281313A (en) A kind of Prefabricated composite box diaphram wall and its construction method
CN205024712U (en) Modular tower crane basis
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN106759563A (en) A kind of device for pile foundation repairing and reinforcing and the construction method using the device
CN211333866U (en) High-speed railway beam-making pedestal suitable for unfavorable geology
CN202830936U (en) Supporting structure of foundation pit
CN111305182A (en) Soft foundation reinforcement construction method
CN209339171U (en) A kind of transmission line of electricity assembled sheet pile composite foundation
CN201756699U (en) Hoop type steel sheet pile cofferdam platform
CN207295746U (en) A kind of bucket foundation steel sheet pile combined type cofferdam
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN205000340U (en) Regard as foundation ditch of vertical cantilever fulcrum to go along with sb. to guard him system with underground continuous wall
CN104088288A (en) Manufacturing method and application of container caisson
CN208219667U (en) Foundation pit supporting construction based on campshed and inner support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: ZHEJIANG GUANGDA JINHAO TRAFFIC ENGINEERING CO., L

Free format text: FORMER NAME: ZHEJIANG JINHAO TRAFFIC ENGINEERING CO., LTD.

CP03 Change of name, title or address

Address after: Hangzhou City, Zhejiang province 310000 Jiubao East e-commerce Park 25 Building 5 floor

Patentee after: Zhejiang Everbright Jin Hao Traffic Engineering Co., Ltd.

Address before: Hangzhou City, Zhejiang province 310051 Binjiang District No. 2031 Jiangling Road, building 25 floor room division Qianjiang

Patentee before: Zhejiang Jinhao Trafific Engineering Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116

Termination date: 20150613

EXPY Termination of patent right or utility model