CN202645031U - Building construction guardrail - Google Patents

Building construction guardrail Download PDF

Info

Publication number
CN202645031U
CN202645031U CN 201220326307 CN201220326307U CN202645031U CN 202645031 U CN202645031 U CN 202645031U CN 201220326307 CN201220326307 CN 201220326307 CN 201220326307 U CN201220326307 U CN 201220326307U CN 202645031 U CN202645031 U CN 202645031U
Authority
CN
China
Prior art keywords
hole
steel tube
fixing
fixing pieces
connection block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220326307
Other languages
Chinese (zh)
Inventor
李万军
贾志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN 201220326307 priority Critical patent/CN202645031U/en
Application granted granted Critical
Publication of CN202645031U publication Critical patent/CN202645031U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a building construction guardrail which comprises fixing pieces and a steel tube. Each fixing piece is composed of a connection block and a fixing section which is arranged on one side or opposite two sides of the connection block, the through hole a for a bolt to pass through is arranged on the fixing piece, a through hole b for the steel tube to pass through is arranged on the connection block, and two ends of the steel tube penetrate through the through hole b to be installed between the two fixing pieces. The building construction guardrail changes a traditional triangular support into the fixing pieces, fixing sections of the fixing pieces are fixed on a column through expansion screws, two ends of the steel tube penetrate through the through hole b on the connection block to be installed between the two fixing pieces, and a defect that the triangular support placed on a floor prevents a material conveying dolly for conveying materials or operating personnel from passing through. Simultaneously, two ends of the steel tube only need pass through the through hole b to be installed on the fixing pieces, so that construction members are saved, installation is convenient, and time and labor are saved.

Description

A kind of building operations guardrail
Technical field
The utility model relates to a kind of building facilities, is specifically related to a kind of building operations guardrail.
Background technology
The form of structure of existing highrise building all is to adopt frame construction, and reinforced concrete column need to be built first in the house of frame construction when building, then build brick wall by laying bricks or stones between pillar and pillar.In order to prevent that agent structure from construction period falling from high altitude occuring, falling from high altitude etc. occurs when the workman builds brick wall by laying bricks or stones, is equipped with guardrail usually between the pillar of constructing and pillar.Existing guardrail is comprised of the triangular supports at two ends and many steel pipes that are installed between two triangular supports, two triangular supports are installed in respectively on two adjacent two pillars, one side of triangular supports is parallel with pillar, and be fixed on the pillar, the two ends of every steel pipe are installed on the triangular supports by the fastener level respectively.This triangular supports takes up room larger, disturb more to follow-up construction operation, owing to need constantly to transport building materials, mortar etc. toward construction place in work progress, material conveying trolley or operating personnel are affected seriously by triangular supports when especially carrying out outer-wall building.Therefore, when existing suchlike construction operation conflict, morely all this Three-legged support is removed, namely protection is cancelled, cause the construction period potential safety hazard larger.
The utility model content
For above shortcomings in the prior art, the utility model provides a kind of building operations guardrail, has both solved the security protection problem of construction period, has reduced again the interference to construction.
To achieve these goals, the technical solution adopted in the utility model is as follows:
A kind of building operations guardrail, comprise fixture and steel pipe, described fixture is comprised of with the canned paragraph that is arranged on contiguous block one side or relative both sides contiguous block, described canned paragraph is provided with the through hole a that passes through for screw, described contiguous block is provided with the through hole b that passes for steel pipe, and the two ends of steel pipe are respectively passed a through hole b and are installed between two fixtures.
Beneficial effect of the present utility model really is: the utility model building operations guardrail changes traditional triangular supports into fixture, the canned paragraph of fixture is fixed on the pillar by swell fixture, the through hole b that the two ends of steel pipe are respectively passed on the contiguous block is installed between two fixtures, has overcome the interference of traditional triangle shape support and has transported the material conveying trolley of material or operating personnel's defective.Simultaneously, the two ends of steel pipe only need be passed through hole b and can be installed on the fixture, saving member not only, and also easy for installation, time saving and energy saving.
Description of drawings
Fig. 1 is structural representation of the present utility model.
The specific embodiment
The utility model is described in further detail below in conjunction with the specific embodiment.
Referring to Fig. 1: the building operations guardrail, comprise fixture and steel pipe 4, fixture is two, is provided with steel pipe 4 between two fixtures.Fixture is comprised of with the canned paragraph 2 that is arranged on contiguous block 3 one sides or relative both sides contiguous block 3.Canned paragraph 2 is provided with the through hole a that passes through for swell fixture 5, and contiguous block 3 is provided with the through hole b that passes for steel pipe 4, and the two ends of steel pipe 4 are respectively passed through hole b and are installed between two fixtures.Contiguous block 3 is rectangular block or arc piece, also can be other arbitrary shape.
In the present embodiment, the relative both sides of contiguous block 3 are equipped with canned paragraph 2, two through hole a that supply swell fixture 5 to pass through are set on each canned paragraph 2, during use, adopt swell fixture that fixture is fixed on the cylinder 1, correspondence is fixed 2 ~ 4 fixtures respectively on adjacent two cylinders 1, and the through hole b that the two ends of steel pipe 4 are passed respectively on the corresponding fixture is installed between two fixtures.Material conveying trolley or operating personnel can pass through from the below of contiguous block 3 easily, overcome the obstruction of traditional triangle shape support and transported the material conveying trolley of material or the defective that the workman passes through, and, the two ends of steel pipe 4 only need to be passed through hole b and get final product in the utility model, saving member not only, and easy for installation, time saving and energy saving.
Need to prove at last, above embodiment is only in order to the technical solution of the utility model to be described but not the restriction technologies scheme, although the applicant has been described in detail the utility model with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, those are made amendment to the technical solution of the utility model or are equal to replacement, and do not break away from aim and the scope of the technical program, all should be encompassed in the middle of the claim scope of the present utility model.

Claims (1)

1. building operations guardrail, it is characterized in that, comprise fixture and steel pipe, described fixture is comprised of with the canned paragraph that is arranged on contiguous block one side or relative both sides contiguous block, described canned paragraph is provided with the through hole a that passes through for screw, described contiguous block is provided with the through hole b that passes for steel pipe, and the two ends of steel pipe are respectively passed a through hole b and are installed between two fixtures.
CN 201220326307 2012-07-06 2012-07-06 Building construction guardrail Expired - Fee Related CN202645031U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220326307 CN202645031U (en) 2012-07-06 2012-07-06 Building construction guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220326307 CN202645031U (en) 2012-07-06 2012-07-06 Building construction guardrail

Publications (1)

Publication Number Publication Date
CN202645031U true CN202645031U (en) 2013-01-02

Family

ID=47414155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220326307 Expired - Fee Related CN202645031U (en) 2012-07-06 2012-07-06 Building construction guardrail

Country Status (1)

Country Link
CN (1) CN202645031U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756361A (en) * 2016-03-09 2016-07-13 临沂大学 Building protection device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756361A (en) * 2016-03-09 2016-07-13 临沂大学 Building protection device
CN105756361B (en) * 2016-03-09 2018-09-14 临沂大学 A kind of construction safety device

Similar Documents

Publication Publication Date Title
CN204139327U (en) Gas concrete out-hung panel waves node
CN202302307U (en) Pipeline suspension combination in combination with assembly type spread method
CN103255909A (en) Wall connecting attachment device of construction engineering outer wall scaffold
CN202645031U (en) Building construction guardrail
CN206927478U (en) A kind of detachable simple gantry crane
CN102926554A (en) Steel hanging seat formwork support and construction method thereof
CN202936996U (en) Wall connecting piece for scaffold
CN202645033U (en) Building operation guardrail adopting clamping ring type fixing pieces
CN202645030U (en) Building construction guardrail adopting steel bar ring fixing pieces
CN202627550U (en) Construction guardrail adopting welding type fixing pieces
CN202047580U (en) Bolt pin type wall connecting piece for scaffold
CN204040556U (en) A telescopic graduation two electronic box protection canopy
CN204001802U (en) A kind of fence assembly and adopt this fence assembly and the construction protection railing that forms
CN204113295U (en) A kind of municipal shield tunnel
CN202645034U (en) Building construction guardrail made of bending-type fixing pieces
CN202148599U (en) Container combined steel-structure building
CN110030005A (en) The light-duty guarantor's circle support system of shield tunnel and its construction method
CN105587132A (en) Building guardrail for civil engineering
CN205134635U (en) Permanent stone that is full of fire prevention heat insulation structure
CN205035948U (en) Concatenation formula steel construction board
CN202209055U (en) Protection rail for construction site
CN204174850U (en) High-altitude stereo cross-operation chassis
CN104047418B (en) The construction method of the exterior coaster of high-rise building roofing truss
CN103215051B (en) Local-slippage construction method of furnace column
CN202055496U (en) Easy-to-adjust moving operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130102

Termination date: 20150706

EXPY Termination of patent right or utility model