CN202513536U - Cable support for power tunnel - Google Patents

Cable support for power tunnel Download PDF

Info

Publication number
CN202513536U
CN202513536U CN2012201818254U CN201220181825U CN202513536U CN 202513536 U CN202513536 U CN 202513536U CN 2012201818254 U CN2012201818254 U CN 2012201818254U CN 201220181825 U CN201220181825 U CN 201220181825U CN 202513536 U CN202513536 U CN 202513536U
Authority
CN
China
Prior art keywords
electric power
support bar
power tunnel
cable bearer
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012201818254U
Other languages
Chinese (zh)
Inventor
唐兆连
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012201818254U priority Critical patent/CN202513536U/en
Application granted granted Critical
Publication of CN202513536U publication Critical patent/CN202513536U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model relates to a cable support for a power tunnel. The cable support comprises two opposite supporting frames, wherein the supporting frames comprise multiple connected supporting bars. The end portion of each supporting bar is positioned on a same circumference, and each supporting bar is equipped with a cross arm for placing cables; thus, when the supporting frames are installed, gaps exist between the supporting bars and a pipeline; and ground wires are arranged in the gaps so that installation of the ground wires is very convenient. The end part of each supporting bar of the supporting frame is positioned on the inner wall of the pipeline, and the supporting frames are not fixedly connected with the pipeline; installation of the cable support is convenient; and when the expansion and contraction ratios of the cable support and the pipeline are different, the pipeline and the cable support are not damaged, thereby greatly prolonging the service life of the pipeline and the cable support.

Description

A kind of electric power tunnel is used cable bearer
Technical field
The utility model relates to a kind of cable support device, relates to a kind of electric power tunnel specifically and uses cable bearer.
Background technology
The urban electric power line cordization is world today's Development Trend and since underground cable line compare with overhead wire have circuit safe and reliable to operation, receive that the outside destroy possibility is little, the influence that do not receive factors such as atmospheric conditions, urban look do not had advantage such as negative effect and be widely used in building in modern times.Along with transformer station entering UrbaniZed Area, the especially city center of voltage levels, through the heavy in section power cable electric power is sent into this powering mode of city center and arise at the historic moment.
Receive restrictions such as various underground piping calibers and construction technology, it is very inconvenient to reserve, install cable bearer and cabling in the underground piping.Present employed cable bearer is that cable bearer is fixedly connected with pipeline mostly, then cable is placed on the cable bearer, and cable bearer and pipeline are connected to one, and installs inconvenient; And the expansion and contraction of cable bearer and pipeline is different, fragile cable bearer and pipeline, reduction of service life greatly; After cable bearer was installed, earth connection was difficult for installing.
The utility model content
The problem that the utility model will solve is to above problem, provides a kind of easy for installation, long service life, the easy-to-install electric power tunnel of earth connection to use cable bearer.
For addressing the above problem; The technical scheme that the utility model adopted is: a kind of electric power tunnel is used cable bearer; Comprise two bracing frames that are oppositely arranged; Support frame as described above comprises a plurality of support bars that link together, and the end of each support bar is positioned on the same circumference, and said support bar is provided with the cross-arm of placing cable.
As a kind of prioritization scheme, the upper and lower of support frame as described above is respectively arranged with link, and said link and bracing frame removably connect.
A kind of concrete prioritization scheme, the link on support frame as described above top is provided with a plurality of through holes.
A kind of concrete prioritization scheme, the link of support frame as described above bottom is provided with pedal, and said pedal and link removably connect.
As a kind of prioritization scheme, said link is a connecting rod, and the two ends of one of them connecting rod bend to the same side.
As a kind of prioritization scheme, support frame as described above is connected with fixed lever.
A kind of concrete prioritization scheme, the quantity of said fixed lever are two.
As a kind of prioritization scheme, said cross-arm is provided with bearing, and said bearing is provided with arc groove, and the top of said bearing is provided with fixed cap.
As a kind of prioritization scheme, the quantity of said support bar is three.
A kind of concrete prioritization scheme, the support bar in the middle of being positioned at is provided with three cross-arms, is positioned at wherein that the support bar of an end is provided with a cross-arm, and the support bar that is positioned at the other end is provided with two cross-arms.
The utility model is taked above technical scheme; Have the following advantages: because the end of each support bar is positioned on the same circumference; Said support bar is provided with the cross-arm of placing cable, so after bracing frame is installed, have the gap between support bar and the pipeline; Earth connection is arranged between the gap, and earth connection is easy for installation; The end of each support bar of bracing frame is positioned on the inwall of pipeline; Bracing frame is not fixedly connected with pipeline, and cable bearer is easy for installation, under cable bearer and pipeline expansion and contraction condition of different; Can not damage pipeline and cable bearer, prolong the useful life of pipeline and cable bearer greatly.
Below in conjunction with accompanying drawing and embodiment the utility model is described further.
Description of drawings
Accompanying drawing be among the utility model embodiment a kind of electric power tunnel with the structural representation of cable bearer.
Among the figure:
The 1-pipeline; The 2-connecting rod; The 3-pedal; The 4-support bar; The 5-cross-arm; The 6-bearing; The 7-fixed lever; The 8-connecting rod; The 9-through hole; The 10-fixed cap.
Embodiment
Embodiment: shown in accompanying drawing; A kind of electric power tunnel is used cable bearer, comprises two bracing frames that are oppositely arranged, and bracing frame comprises a plurality of support bars 4 that link together; The end of each support bar 4 is positioned on the same circumference, and support bar 4 is provided with the cross-arm 5 of placing cable.
The quantity of support bar 4 is three, and the support bar 4 in the middle of being positioned at is provided with three cross-arms 5, is positioned at wherein that the support bar 4 of an end is provided with a cross-arm 5, and the support bar 5 that is positioned at the other end is provided with two cross-arms 5.
Can increase or reduce the quantity of support bar 4 and cross-arm 5 as required.
The upper and lower of bracing frame is respectively arranged with link, and link and bracing frame removably connect.
The link on bracing frame top is provided with a plurality of through holes 9, can illuminating lamp be installed through through hole 9 on link, and the quantity of through hole 9 is three in the present embodiment, can increase or reduce the quantity of through hole 9 as required.
The link of bracing frame bottom is provided with pedal 3, and pedal 3 removably connects with link.
Link is a connecting rod, and the two ends of one of them connecting rod bend to the same side.
Two ends are positioned at the top of bracing frame to the connecting rod 8 of the same side bending, and through hole 9 is positioned at the centre position of connecting rod 8, and the connecting rod of pedal 3 and bracing frame bottom 2 is connected through screw bolt and nut.
Connecting rod 2 and connecting rod 8 and support bar 4 are connected through screw bolt and nut, and support bar 4, connecting rod 2 and connecting rod 8 removably connect, and be easy for installation.
Link also can adopt other structures, as long as can two bracing frames be linked together.
Bracing frame is connected with fixed lever 7, and the quantity of fixed lever 7 is two, can increase or reduce the quantity of fixed lever 7 as required.
Fixed lever 7 and support bar 4 vertical settings, fixed lever 7 are along the axial setting of pipeline, and fixed lever 7 welds with the support bar that is positioned at the centre 4.
Cross-arm 5 is provided with bearing 6; Bearing 6 is provided with arc groove; Cable is placed in the arc groove on the bearing 6, and the top of bearing 6 is provided with fixed cap 10, and fixed cap 10 is provided with connecting hole; Cross-arm 5 be provided with fixed cap 10 on the corresponding connecting hole of connecting hole, fixed cap 10 is fixedly connected with cross-arm 5 through screw bolt and nut.
Support bar 4, connecting rod 2, connecting rod 8, cross-arm 5 and fixed lever 7 are processed by angle steel, also can adopt other steel materials to process, and for example also can use channel-section steel to process.
During use; Two bracing frames are oppositely arranged in the pipeline 1; The junction of adjacent support bar 4 is positioned on the inwall of pipeline 1, and the connecting rod of the support bar 4 of foot and bottom 2 is fixedly connected through screw bolt and nut, and the connecting rod on the support bar 4 of topmost and top 2 is fixedly connected through screw bolt and nut; Pedal 3 and connecting rod 2 are fixedly connected through screw bolt and nut, and support bar 4, connecting rod 2 and connecting rod 8 form polygonized structures.
Along pipeline 1 some groups of cable beareves axially are set, the support bar 4 in some groups of cable beareves all is fixedly connected with fixed lever 7, ground wire directly is connected with fixed lever 7 and gets final product, ground wire is easy for installation.

Claims (10)

1. an electric power tunnel is used cable bearer; Comprise two bracing frames that are oppositely arranged; It is characterized in that: support frame as described above comprises a plurality of support bars (4) that link together, and the end of each support bar (4) is positioned on the same circumference, and said support bar (4) is provided with the cross-arm (5) of placing cable.
2. a kind of electric power tunnel as claimed in claim 1 is used cable bearer, it is characterized in that: the upper and lower of support frame as described above is respectively arranged with link, and said link and bracing frame removably connect.
3. a kind of electric power tunnel as claimed in claim 2 is used cable bearer, it is characterized in that: the link on support frame as described above top is provided with a plurality of through holes (9).
4. a kind of electric power tunnel as claimed in claim 2 is used cable bearer, it is characterized in that: the link of support frame as described above bottom is provided with pedal (3), and said pedal (3) removably connects with link.
5. use cable bearer like one of them described a kind of electric power tunnel of claim 2-4, it is characterized in that: said link is a connecting rod, and the two ends of one of them connecting rod bend to the same side.
6. use cable bearer like one of them described a kind of electric power tunnel of claim 1-4, it is characterized in that: support frame as described above is connected with fixed lever (7).
7. a kind of electric power tunnel as claimed in claim 6 is used cable bearer, it is characterized in that: the quantity of said fixed lever (7) is two.
8. use cable bearer like one of them described a kind of electric power tunnel of claim 1-4, it is characterized in that: said cross-arm (5) is provided with bearing (6), and said bearing (6) is provided with arc groove, and the top of said bearing (6) is provided with fixed cap (10).
9. use cable bearer like one of them described a kind of electric power tunnel of claim 1-4, it is characterized in that: the quantity of said support bar (4) is three.
10. a kind of electric power tunnel as claimed in claim 9 is used cable bearer; It is characterized in that: the support bar (4) in the middle of being positioned at is provided with three cross-arms (5); Be positioned at wherein that the support bar of an end (4) is provided with a cross-arm (5), the support bar (5) that is positioned at the other end is provided with two cross-arms (5).
CN2012201818254U 2012-04-17 2012-04-17 Cable support for power tunnel Expired - Fee Related CN202513536U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201818254U CN202513536U (en) 2012-04-17 2012-04-17 Cable support for power tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201818254U CN202513536U (en) 2012-04-17 2012-04-17 Cable support for power tunnel

Publications (1)

Publication Number Publication Date
CN202513536U true CN202513536U (en) 2012-10-31

Family

ID=47065993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201818254U Expired - Fee Related CN202513536U (en) 2012-04-17 2012-04-17 Cable support for power tunnel

Country Status (1)

Country Link
CN (1) CN202513536U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104052009A (en) * 2014-06-19 2014-09-17 国网四川省电力公司成都市新都供电分公司 Hoop type cable duct cable support
CN111030030A (en) * 2019-12-25 2020-04-17 安徽鑫铂铝业股份有限公司 High-strength light high-speed rail tunnel cable support frame aluminum profile and preparation process thereof
CN114914859A (en) * 2022-06-01 2022-08-16 山东方特管业有限公司 SMC composite cable support convenient to rust-resistant losing of construction theftproof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104052009A (en) * 2014-06-19 2014-09-17 国网四川省电力公司成都市新都供电分公司 Hoop type cable duct cable support
CN111030030A (en) * 2019-12-25 2020-04-17 安徽鑫铂铝业股份有限公司 High-strength light high-speed rail tunnel cable support frame aluminum profile and preparation process thereof
CN111030030B (en) * 2019-12-25 2021-02-19 安徽鑫铂铝业股份有限公司 High-strength light high-speed rail tunnel cable support frame aluminum profile and preparation process thereof
CN114914859A (en) * 2022-06-01 2022-08-16 山东方特管业有限公司 SMC composite cable support convenient to rust-resistant losing of construction theftproof
CN114914859B (en) * 2022-06-01 2023-07-14 山东方特管业有限公司 SMC composite cable support convenient to construction theftproof rust-resistant

Similar Documents

Publication Publication Date Title
CA2974994C (en) Utility tower lifting device
CN202513536U (en) Cable support for power tunnel
CN204357150U (en) Wall support frame
CN204568983U (en) A kind of adjustable height cable reel stent assembly
CN201610978U (en) Pipe rack convenient for installing and repairing multilayer pipeline
CN201234081Y (en) 220kV bus support column porcelain bottle inspection rack
CN203260976U (en) Cable termination tower
CN104518469A (en) Tool for assembling flexible bus and use method of tool
CN204089082U (en) Lighting proof strip device
CN215009423U (en) Assembled arc power cable support
CN205206451U (en) Wire pole and electric wire protective case
CN103452371B (en) Integral sleeve suspension chimney
CN203674590U (en) Stand construction platform
CN202769052U (en) Pipeline movable cradle
CN201605806U (en) Supporting device used for placing concrete of reserved holes of vertical pipes or sleeves
CN201605864U (en) Narrow base tower for power transmission line
CN202165696U (en) Cable bridge fixing support clamping device of joist steel
CN102570363B (en) A kind of insulator bracket of outdoor junction direct current busbar
CN210315660U (en) Utility tunnel supporting structure
CN200967424Y (en) Inclined bracing wire
CN210163007U (en) Movable hoisting frame for tunnel
CN204459461U (en) A kind of electric wire, cable bearer
CN216240012U (en) Electric pole convenient for mounting accessories
CN205195215U (en) Stand combination type cable support
CN205296967U (en) Circular steel pipe pole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121031

Termination date: 20150417

EXPY Termination of patent right or utility model