CN202482850U - Bidirectional opposite perforation conical tubular pile - Google Patents

Bidirectional opposite perforation conical tubular pile Download PDF

Info

Publication number
CN202482850U
CN202482850U CN2012200456078U CN201220045607U CN202482850U CN 202482850 U CN202482850 U CN 202482850U CN 2012200456078 U CN2012200456078 U CN 2012200456078U CN 201220045607 U CN201220045607 U CN 201220045607U CN 202482850 U CN202482850 U CN 202482850U
Authority
CN
China
Prior art keywords
pile
tubular pile
perforation
conical tubular
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200456078U
Other languages
Chinese (zh)
Inventor
雷金波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang Hangkong University
Original Assignee
Nanchang Hangkong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang Hangkong University filed Critical Nanchang Hangkong University
Priority to CN2012200456078U priority Critical patent/CN202482850U/en
Application granted granted Critical
Publication of CN202482850U publication Critical patent/CN202482850U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a bidirectional opposite perforation conical tubular pile. The wall of the conical tubular pile is provided with a plurality of groups of Y-directional opposite perforations and X-directional opposite perforations, and the same group of Y-directional opposite perforations and X-directional opposite perforations are on the same plane. The utility model has the advantages that when the bidirectional opposite perforation conical tubular pile is used in construction, the compaction effect of the adjacent pile can be effectively reduced, and the environment is clean; and the bidirectional opposite perforation conical tubular pile is also energy-saving.

Description

A kind of two-way to the bore conical pile tube
Technical field
The utility model relates to a kind of conical pipe pile, relates in particular to a kind of two-way to the bore conical pile tube.
Background technology
When at present existing conical pipe pile was constructed, particularly the hammer piling mode produced soil compaction effect and excess pore water pressure, very easily caused adjacent stake skew, even broken pile.PTC type conical pipe pile is used for the deep soft soil foundation treatment project, and main purpose is control foundation settlement and settlement after construction, improves bearing capacity of foundation soil, and conical pipe pile self bearing capacity is not a subject matter.The main cause that foundation settlement produces is because the discharge of soil body mesopore water under the outer load effect.Concerning deep soft soil foundations such as speedway, high-speed railway, road in airport, control its sedimentation, mostly is to control its settlement amount after construction, and its settlement amount after construction is controlled in the settlement amount after construction critical field.If produce more settling amount as far as possible in construction periods such as embankment, dykes and dams, roads, should water discharge as much as possible in native mesopore be reduced the water content of soil, then its settlement amount after construction will be able to reduce, and reach the purpose of control sedimentation and settlement amount after construction.
Summary of the invention
It is a kind of two-way to the bore conical pile tube that the purpose of the utility model is to provide, form two-way to the bore conical pile tube, the side friction of the polywater effect that makes full use of the conical pipe pile cavity and the performance conical pipe pile side soil body, every linear meter(lin.m.) be provided with 2 groups two-way to perforation.
The utility model realizes like this, it comprise conical pipe pile, Y to perforation, X to perforation, it is characterized in that having on the pile lining of conical pipe pile some groups of Y to perforation and X to perforation, same group of Y to perforation and X to boring a hole at grade.
The technique effect of the utility model is: be provided with two-way to the bore conical pile tube in the soft foundation; Particularly in the construction period, because the conical pipe pile own characteristic, the end that diameter is little is descending; Help bringing into play a side friction of the side soil body; The soil compaction effect of conical pipe pile also can suitably reduce simultaneously, because pile driving process can produce the excess pore water pressure, water in soil can get in the conical pipe pile rapidly on the other hand.In the construction intermittent phase, under the hydrostatic pressure effect, along with the dissipation that excess pore water is pressed, water in soil also can get into rapidly in the conical pipe pile hole.If run into mucky soil, mud can flow in the conical pipe pile perforation through two-way.If water is many in the hole, then can take the mode of drawing water that it is got rid of.Along with water level in the hole reduces, water in soil can infiltrate in the conical pipe pile again, makes the water content of soil be able to further reduction, and the intensity of soil is improved, and bearing capacity of foundation soil strengthens.Two-wayly can effectively reduce adjacent stake soil compaction effect during to the bore conical tube pile construction, cleaning ambient, two-way also have energy-conservation advantage to the bore conical pile tube.
Description of drawings
Fig. 1 is the sectional drawing of the utility model.
Fig. 2 is the sectional drawing of the utility model A-A.
Fig. 3 is the sectional drawing of the utility model B-B.
In the drawings, 1, conical pipe pile 2, Y to bore a hole 3, X is to perforation.
The specific embodiment
Like Fig. 1, Fig. 2, shown in Figure 3, the utility model realizes like this, have on the pile lining of conical pipe pile 1 some groups of Y to bore a hole 2 with X to boring a hole 3, same group of Y to bore a hole 2 with X to boring a hole 3 at grade.Two-way the bore conical pile tube is only needed to adopt special conical pipe pile punching block produce on request in factory; Method is with existing conical pipe pile production technology; Site operation adopts silent piling method pile sinking; Other operations are considered its problem of stress concentration with existing conical pipe pile construction technology, must not adopt pile vibrosinking and hammer piling mode during this structure construction.

Claims (1)

  1. One kind two-way to the bore conical pile tube, it comprise conical pipe pile, Y to perforation, X to perforation, it is characterized in that having on the pile lining of conical pipe pile some groups of Y to perforation and X to perforation, same group of Y to perforation and X to boring a hole at grade.
CN2012200456078U 2012-02-14 2012-02-14 Bidirectional opposite perforation conical tubular pile Expired - Fee Related CN202482850U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200456078U CN202482850U (en) 2012-02-14 2012-02-14 Bidirectional opposite perforation conical tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200456078U CN202482850U (en) 2012-02-14 2012-02-14 Bidirectional opposite perforation conical tubular pile

Publications (1)

Publication Number Publication Date
CN202482850U true CN202482850U (en) 2012-10-10

Family

ID=46957280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200456078U Expired - Fee Related CN202482850U (en) 2012-02-14 2012-02-14 Bidirectional opposite perforation conical tubular pile

Country Status (1)

Country Link
CN (1) CN202482850U (en)

Similar Documents

Publication Publication Date Title
CN103603342B (en) Major diameter assembled casing super-long filling pile construction method
CN102493437B (en) Grouting-type micro steel pipe pile and grouting reinforcement method
CN202913416U (en) Drainage slide-resistant pile
CN202969389U (en) Spiral shovel for clearing soil of pile core
CN202324017U (en) Grouting type micro steel pipe pile
CN103410447A (en) Square drill bit of rotary drilling rig
CN204827213U (en) Double dynamical head digs rig soon
CN202482850U (en) Bidirectional opposite perforation conical tubular pile
CN202482849U (en) Asymmetric tapered pipe pile with bidirectional counter-through-holes
CN202530449U (en) Tapered pipe pile with bidirectional misaligned through holes
CN201620413U (en) Composite foundation with PTC perforated tubular piles with caps
CN202090335U (en) Two-way paired perforation hole tubular pile
CN202482847U (en) Conical tubular pile with starlike perforated holes
CN204000846U (en) Floral tube slip casting uplift pile
CN202482848U (en) Cone-shaped tubular pile with non-through holes
CN202482851U (en) Positive temperature coefficient (PTC) type pair-punched hole conical tube pile for deep soft foundation treatment
CN204125931U (en) Foundation pile structure
CN201520973U (en) Precast pile with grouting hole
CN204753577U (en) Reverse screw stake
CN208816041U (en) A kind of drilling mechanism and rotary drilling rig
CN203174586U (en) Concrete pipe pile for reinforcing railway soft soil foundation
CN201620410U (en) PTC-type tubular pile with holes for deep soft foundation treatment
CN203569567U (en) Hydraulic eccentric pick head
CN203393703U (en) Expanded bore device of punching expanded bore filling pile
CN202745037U (en) Non-through perforated tubular pile for processing deep soft foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20130214