CN202425368U - Greening planting soil slope structure capable of reducing floor slab load - Google Patents

Greening planting soil slope structure capable of reducing floor slab load Download PDF

Info

Publication number
CN202425368U
CN202425368U CN2011205638114U CN201120563811U CN202425368U CN 202425368 U CN202425368 U CN 202425368U CN 2011205638114 U CN2011205638114 U CN 2011205638114U CN 201120563811 U CN201120563811 U CN 201120563811U CN 202425368 U CN202425368 U CN 202425368U
Authority
CN
China
Prior art keywords
layer
soil slope
slope structure
load
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011205638114U
Other languages
Chinese (zh)
Inventor
何斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Pubang Landscape Design & Construction Co ltd
Original Assignee
Guangzhou Pubang Landscape Design & Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Pubang Landscape Design & Construction Co ltd filed Critical Guangzhou Pubang Landscape Design & Construction Co ltd
Priority to CN2011205638114U priority Critical patent/CN202425368U/en
Application granted granted Critical
Publication of CN202425368U publication Critical patent/CN202425368U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Cultivation Of Plants (AREA)

Abstract

The utility model discloses a greening planting soil slope structure capable of reducing the load of a floor slab, and aims to provide a planting soil slope means which is low in cost, is convenient to operate and brings large landscape ecologic benefits. The height of the soil slope is increased by pre-filling foam boards in the soil slope without increasing the floor slab load. The technical key of the utility model is as follows: the greening planting soil slope structure comprises, from upper down, a surface soil layer, a coating geotextile layer, a foam board stack, a bottom geotextile layer, a drainage layer and a water-proof layer, which are closely connected with one another. The utility model belongs to the technical field of ecological restoration and landscape design in residential districts.

Description

A kind of planting technique slight slope structure that lowers the floor load
Technical field
The utility model relates to a kind of planting technique slight slope structure that lowers the floor load, belongs to residential area restoration of the ecosystem and landscape design technical field.
Background technology
Afforestation is the main means that realize that the residential area environmental ecology is repaired.Building on basement roof (floor) and the residential area garden landscape is many.Real estate project now; Major part all is provided with underground garage; The realtor is from the purpose of economic benefit and cost control; General all can require the design load of basement roof made just satisfy earthing and be backfilling into an equal plane of road in the garden, do not reserve earthing design load more than needed to afforestation heap slope.On the other hand; Park and garden design requires again usually to organize and enclosed space through slight slope landform, greening, garden structure or the like unit; Particularly the landform mound slope of greening is even more important, so the contradiction of a cost and gardens effect is just arranged, also builds the condition of a lot of restrictions of having brought to gardens here.The park and garden design in past has taked some measures to make the not enough contradiction of load up, and measure mainly contains following two kinds: a, below slight slope, fill out haydite, and the thin hole material of rubble or the like light specific gravity, thus increase total backfill height; B, with the mode of manual stirring, with perlite particle, sand, haydite, humus soil or the like are mixed in the backfill soil by a certain percentage, are made into light soil, thus the whole proportion that alleviates backfill soil increases the backfill height.Above-mentioned two kinds of methods, be to have relaxed the not enough contradiction of load to a certain extent, but they all have deficiency separately, enumerate below: below slight slope, fill out the method for haydite, cost is higher, and is long in time limit; Constructing operation is not convenient; Backfill highly generally can not surpass 600mm; The back water content of raining increases, and proportion enlarges markedly, if drain untimely maybe be influential to top board structure; Time has been grown beneath haydite layer can be by the crushing of the overburden layer of top, and whole earthing height has certain decline; The method of manual stirring light soil backfill, cost is very high, and is long in time limit; The whole cohesive force of light soil reduces, and planting superincumbent shrub wind resistance and steadiness has certain weakening.
The utility model content
To the problems referred to above, the utility model discloses the planting technique slight slope structure of low, the easy to operate attenuating floor load of a kind of cost.
The technical scheme of the utility model is such: a kind of planting technique slight slope structure that lowers the floor load; Each layer is from top to bottom: outer topsoil, coating geotechnique layer of cloth, foam sheetpile, bottom geotechnique layer of cloth, hydrophobic layer and watertight composition, close proximity between each layer.
In above-mentioned a kind of planting technique slight slope structure that lowers the floor load, described outer topsoil is sloping shape.
Above-mentioned a kind of planting technique slight slope structure that lowers the floor load, described coating geotechnique layer of cloth edge should go out 30~100cm than foam sheetpile layer edge is wide.
The used cystosepiment of present technique is expandable polystyrene plate (EPS), and its correlated performance is following:
A. owing to 95% be air in its volume, unit weight is extremely light, density 20~60kg/m 3
B. compressive strength 80~300kPa, earthing height theoretical maximum reaches more than 10 meters on it.Select the proper compression strength specification for use in response to cost control and actual requirement in the practical operation of gardens.
C. warm tolerance is general, when temperature is higher than 70 ℃, foams along with the increase of the blowing agent that discharges; 220 ℃ (approximately) begins to decompose, and uses and should note avoiding when depositing.
D. nontoxic, waterproof, corrosion-resistant, insulation, water insoluble, but be dissolved in organic solvent, should avoid contact.
E. physical and chemical performance is stable under the normal temperature normality, and the years up to a hundred are wanted in degraded under the nature.
F. easy compressive deformation, under the power effect that reaches its compressive strength, volume compression is out of shape about 10%.In addition, in long-term use, the dynamic load of top earthing can make it produce fatigue strength, thereby the bearing capacity of plate is descended, and distortion further strengthens, and generally needs the time more than 50 years and this situation occurs.So the height suggestion of using present technique backfill foam sheetpile is in 3 meters.
Compared with prior art, the utlity model has following beneficial effect:
1. at the bottom of the cost, the duration is short, and comprehensive unit price is about 180~200 yuan/cubic metre, is 1/2 of light soil backfill, 1/3 of pure haydite backfill; It is backfill that cystosepiment is promptly piled, and need not any building by laying bricks or stones and surrounds;
2. constructing operation is convenient, only need simply pile up and fix simple operation;
3. backfill is highly big, satisfies the greening landform fully and piles sloping requirement;
4. the draining hydrophobic performance is good, and foam belongs to hydrophobic material, and the following infiltration of soil can flow to the bottom hydrophobic layer fast on the foam pile surface, does not produce ponding;
5. top board structure there is not influence; The foam moisture content is extremely low, and the back foam pile of raining can not absorb water and increase unit weight, and haydite and light soil moisture content behind rain is high; Particularly can increase by 2~3 times, moment live load that can be very big under the situation that water fails in time to drain to the top board increase at unit weight when raining heavyly;
6. plant and plant superincumbent shrub wind resistance and not influence of steadiness.
Description of drawings
Fig. 1 the utility model structural representation;
Wherein: outer topsoil 1, coat geotechnological layer of cloth 2, foam sheetpile 3, bottom geotechnique layer of cloth 4, hydrophobic layer 5, watertight composition 6.
Embodiment
Below in conjunction with specific embodiment the utility model is done further to specify, but do not constitute any restriction the utility model.
Consult Fig. 1, a kind of planting technique slight slope structure that lowers the floor load, each layer is from top to bottom: outer topsoil 1, coat geotechnological layer of cloth 2, foam sheetpile 3, bottom geotechnique layer of cloth 4, hydrophobic layer 5, watertight composition 6, wherein extexine 1 is shaped as sloping shape.The preparation method of the structure of this attenuating floor load is: carry out watertight composition 6 earlier at basement roof earlier, carry out top board hydrophobic layer 5 then, on hydrophobic layer 5, cover two-layer 150 gram bottom geotextiles 4 again; Needs according to the greening landform; Use specification to pile up the height of slight slope projection soil face as 2000mm * 1000mm * 200mm industry cystosepiment in the place that needs are piled up slight slope, foam sheetpile 3 can be put the shape on slope according to the Adjusting Shape of the slight slope top, slope of serving as reasons to periphery; Piled after the foam sheetpile 3; Coat geotechnological layer of cloth 2 with one deck 150 grams and cover foam sheetpile 3 surfaces; Push down the edge that coats geotechnological layer of cloth 2 with certain backfill soil then, thus make whole foam sheetpile 3 can be not or elsewhere move can be under the pressure of backfill soil owing to cover the coating geotechnique layer of cloth 2 on cystosepiment surface toward middle contraction; The length of 50cm should be reserved in the cloth two ends during covering, promptly obtains the landform of slight slope shape at last by greening landform requirement backfill soil.
Case history 1
Project name: the Guangzhou flower is all formed a team in project first phase north and south, Poly city.
Gardens time of completion: in May, 2009
The practical implementation situation: this project adopts the planting technique slight slope structure of the utility model to carry out top board backfill heap slope, and foam sheetpile maximum height is 1.2 meters.Stay under the situation of load more than needed for greening heap slope at the top board load, made abundant landform heap slope, do not need the top board structure reinforcement, provide cost savings.The existing heap of cystosepiment material during construction, about 9000 square metres of integrated greening area, the heap cystosepiment was accomplished in one day, did not need other masonry construction or on-the-spot reprocessing to handle big time saver.Engineering completion so far, greening heap hillside fields shape keeps good, does not sink basically or subsides.Plant grows fine, and wind do not occur under the normal supporting condition and blows down plant.
The cost contrast: the utility model way comprehensive unit price is 180~200 yuan/cubic metre; Pure haydite back-filling way comprehensive unit price is about 700 yuan/cubic metre; Light soil back-filling way comprehensive unit price is about 400 yuan/cubic metre.
Case history 2
Project name: swimming pool district, the project center, Poly Longjiang, Shuande
Gardens time of completion: in May, 2011
The practical implementation situation: this project adopts the planting technique slight slope structure of the utility model to carry out top board backfill heap slope, and foam sheetpile maximum height is 2.3 meters.Engineering is accomplished and is not occurred so far obviously sinking or other harmful effect.

Claims (3)

1. planting technique slight slope structure that lowers the floor load; It is characterized in that; Each layer is from top to bottom: outer topsoil (1), coat geotechnological layer of cloth (2), foam sheetpile (3), bottom geotechnique layer of cloth (4), hydrophobic layer (5) watertight composition (6), close proximity between each layer.
2. a kind of planting technique slight slope structure that lowers the floor load according to claim 1 is characterized in that outer topsoil (1) is sloping shape.
3. a kind of planting technique slight slope structure that lowers the floor load according to claim 1 is characterized in that, coating geotechnological layer of cloth (2) edge should be than the wide 30~100cm of going out in foam sheetpile layer (3) edge.
CN2011205638114U 2011-12-28 2011-12-28 Greening planting soil slope structure capable of reducing floor slab load Expired - Fee Related CN202425368U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205638114U CN202425368U (en) 2011-12-28 2011-12-28 Greening planting soil slope structure capable of reducing floor slab load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205638114U CN202425368U (en) 2011-12-28 2011-12-28 Greening planting soil slope structure capable of reducing floor slab load

Publications (1)

Publication Number Publication Date
CN202425368U true CN202425368U (en) 2012-09-12

Family

ID=46774854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205638114U Expired - Fee Related CN202425368U (en) 2011-12-28 2011-12-28 Greening planting soil slope structure capable of reducing floor slab load

Country Status (1)

Country Link
CN (1) CN202425368U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193060A (en) * 2014-09-29 2016-12-07 浙江普天园林建筑发展有限公司 The method on top board greening heap slope, storehouse, a kind of ground
CN113404063A (en) * 2021-07-07 2021-09-17 中铁一局集团厦门建设工程有限公司 Basement roof backfilling structure and construction process

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193060A (en) * 2014-09-29 2016-12-07 浙江普天园林建筑发展有限公司 The method on top board greening heap slope, storehouse, a kind of ground
CN106193061A (en) * 2014-09-29 2016-12-07 浙江普天园林建筑发展有限公司 The method on top board greening heap slope, storehouse, a kind of ground
CN106193058A (en) * 2014-09-29 2016-12-07 浙江普天园林建筑发展有限公司 The method on top board greening heap slope, storehouse, a kind of ground
CN113404063A (en) * 2021-07-07 2021-09-17 中铁一局集团厦门建设工程有限公司 Basement roof backfilling structure and construction process

Similar Documents

Publication Publication Date Title
CN204662499U (en) Concrete of basement exterior wall, waterproof, fertile groove integrated construction structure
CN102322155B (en) Unconcerned table Great Wall extra large, multi-functional and Prevention of Sandstorm
CN207469269U (en) A kind of hydraulic engineering High strength geogrid structure class ecological revetment
CN102953353B (en) Microbial river embankment reinforcement ecological slope protection technology
CN201390973Y (en) Pile-plate foundation for self-supporting iron tower
CN204139199U (en) For the gear protection structure of levelling of the land
CN206428709U (en) A kind of highway slope protection
CN202425368U (en) Greening planting soil slope structure capable of reducing floor slab load
CN107142814B (en) A kind of sponge urban ecology pavement rainwater utilization structure
CN102943480B (en) Loess foundation pit supporting method
CN203498860U (en) Anchor rod foundation structure with concrete blocks for photovoltaic module brackets
CN107178021B (en) A kind of sponge urban ecology square rainwater utilization structure enhancing water storage
CN209194466U (en) Reservoir bank seepage prevention structure
CN203007967U (en) Photovoltaic plant component bracket foundation for plateau Gobi sandy soil regions
CN203475486U (en) Basement producing no water buoyancy
CN202577316U (en) Structure of miniature piles in combination with composite soil nailing wall
CN202047535U (en) Microtopographic structure for planting trees on roofs
CN206319379U (en) A kind of greenery patches level distribution structure for improving water-holding capacity
CN202850062U (en) Water buoyant control device for construction or for structures
CN205012318U (en) Soft soil foundation treatment device
CN201099945Y (en) Architecture energy-saving planting landscape roof plate
CN205046589U (en) Waterproof structure of basement
CN201080614Y (en) Slope type dry method red mud storage yard water drainage structure
CN210563030U (en) Inverted beam green plant roof structure
CN109763682B (en) Underground refrigeration house structure and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120912

Termination date: 20121228