CN202380387U - Construction structure for carrying out prefabricated erection of box beams on bridge - Google Patents
Construction structure for carrying out prefabricated erection of box beams on bridge Download PDFInfo
- Publication number
- CN202380387U CN202380387U CN2011205282684U CN201120528268U CN202380387U CN 202380387 U CN202380387 U CN 202380387U CN 2011205282684 U CN2011205282684 U CN 2011205282684U CN 201120528268 U CN201120528268 U CN 201120528268U CN 202380387 U CN202380387 U CN 202380387U
- Authority
- CN
- China
- Prior art keywords
- bridge
- bridge pier
- abutment
- bent cap
- pier bent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a construction structure for carrying out prefabricated erection of box beams on a bridge, which comprises a side span bridge abutment of a first span and two side bridge piers of a second span, wherein the side span bridge abutment and the side bridge piers are sequentially arranged; a bridge abutment capping is erected on the side span bridge abutment; a first bridge pier bent cap and a second bridge pier bent cap are respectively erected on the two side bridge piers; at least two support cushions are respectively arranged on the bridge abutment capping and the first and second bridge pier bent caps at intervals; and the box beams are longitudinally erected on the support cushions correspondingly arranged on the side span bridge abutment and the first bridge pier bent cap and on the support cushions correspondingly arranged on the first bridge pier bent cap and the second bridge pier bent cap. The structure is not influenced by the geographical environment, so that the construction structure is suitable for areas with large fluctuation of the geographical altitude difference; and in the process of moving the beams, the installation of large-scale equipment such as a gantry crane and a bridge girder erection machine is omitted, and thus, the labor production efficiency is improved, the cost is saved and the construction period is saved.
Description
Technical field
The utility model relates to the constructing structure of bridge, relates in particular on bridge, to carry out the beam prefabricated constructing structure that sets up of case.
Background technology
In bridge construction, prefabricated case beam is to build a kind of bridge superstructure form that bridge construction the most generally adopts.At present for the prestressed concrete continuous rigid-framed bridge of crossing over deep valley, great river, torrent.Substructure master's bridge bridge pier adopts the hollow thin-wall pier, pile foundation, and superstructure master bridge adopts the job practices of cantilever pouring to construct, and adopts post-tensioned prestressed box beam for the access bridge superstructure more.Case beam for the sheet number is many is prefabricated at precasting yard; Erection construction is more common method by setting a roof beam in place in proper order successively, and few for case beam sheet number, the physical features at the access bridge place discrepancy in elevation again rises and falls big; When physical features is complicated; By routine at precasting yard prefabricated case beam, erection method, the construction relatively the difficulty, also unreasonable economically.
Learn the patent of having authorized through retrieval:
1 application number is that the Chinese patent of CN201010232662.3 discloses " mounting method of post tensioned prestressed concrete box girders ", the present invention relates to a kind of mounting method of post tensioned prestressed concrete box girders.The mounting method of post tensioned prestressed concrete box girders; It is characterized in that it comprises the steps: 1) installation of bracing or strutting arrangement: in a tension of prestressed tendon section; Direction along post tensioned prestressed concrete box girders is installed is laid first bracing frame and second bracing frame; On first bracing frame, lay first slideway, on second bracing frame, lay second slideway; 2) installation of post tensioned prestressed concrete box girders: 1. adopting hoisting weight is that the 100t straddle truck is placed on the handling of 5-12 piece post tensioned prestressed concrete box girders on first slideway and second slideway of bracing or strutting arrangement; 2. through bottle gouard moved by hands post tensioned prestressed concrete box girders is walked on first slideway and second slideway two adjacent post tensioned prestressed concrete boxes are carried out assembly unit.
2 application numbers are: the Chinese patent of CN201010285591.3 discloses " the empty prefabricate of a kind of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit "; The invention discloses the empty prefabricate of a kind of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit, it is characterized in that may further comprise the steps: 1) set up high stake prefabricated platform; 2) between high stake prefabricated platform and bridge pier, set up and move joist steel pipe holder and steel slide rail; 3) on high stake prefabricated platform, build the matching beam section; 4) the matching beam section that will build is built new beam section as the end mould of the next one new beam Duan Yiduan to be poured; 5) after new beam section is built, the matching beam section is transported to design attitude as beam section to be assembled, simultaneously new beam section is moved forward as next matching beam section; 6) the coupling face that beam section to be assembled is vertically moved on to the assembled beam section end is as the spliced girder section, the position of adjustment spliced girder section make its meet with bridge pier on the assembled beam section requirement of splicing; 7) spliced girder section and assembled beam section are spliced.Job practices of the present invention through the beam section prefabricate and deposit beam for a long time, effectively make the precast beam section under free state, accomplish most of shrinkage strain of beam body, it is poor because of the different contractions that produce in the length of time to eliminate the adjacent beams section, thereby the elimination crack.
The 1st the disclosed patent of patent " mounting method of post tensioned prestressed concrete box girders " rises and falls big at topographical elevation difference, inapplicable in the bridge in the river, mountain valley that physical features is complicated.
The empty prefabricate of the disclosed case deck-molding of the 2nd patent, move beam, deposit beam, the goal of the invention of the job practices of assembly unit is to eliminate the crack.
Summary of the invention
The purpose of the utility model is to overcome the deficiency of prior art; Provide a kind of and rise and fall greatly at topographical elevation difference, a kind of beam prefabricated constructing structure that sets up of case that on bridge, carries out when physical features is complicated adopts this structure to improve labor productivity; Practice thrift cost, saved the duration.
A kind of beam prefabricated constructing structure that sets up of case that on bridge, carries out of the utility model; It comprises the both sides bridge pier that the first end bay abutment and second of striding that sets gradually; Put on the shelf at described end bay abutment and to be provided with abutment platform cap; The first bridge pier bent cap and the second bridge pier bent cap on the bridge pier of described both sides, have been set up respectively; On described abutment platform cap, the first and second bridge pier bent caps, be arranged at intervals with at least two bearing pad stones respectively, all longitudinally setting up the case beam on the bearing pad stone of end bay abutment and the corresponding setting of the first bridge pier bent cap and on the bearing pad stone of the first bridge pier bent cap and the corresponding setting of the second bridge pier bent cap.
The advantage of the utility model: prefabricated the setting up of this structure case beam can utilize Bei Leiliang to construct on spanning, and Bei Leiliang can set up and remove at any time, and is very convenient, not influenced by geographical environment, thereby it is big to be applicable to that topographical elevation difference rises and falls, the physical features areas with complicated; Again owing to saved the installation of main equipments such as straddle truck, bridge formation machine when moving beam, thereby improve labor productivity, practiced thrift cost, saved the duration, and economical rationality.
Description of drawings
Fig. 1 is a kind of structural representation that on bridge, carries out the beam prefabricated constructing structure that sets up of case of the utility model;
Fig. 2 is the vertical view of structure shown in Figure 1.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the utility model is done to describe in detail.
A kind of beam prefabricated constructing structure that sets up of case that on bridge, carries out of the utility model shown in accompanying drawing; It comprises first striding 1 end bay abutment and second and stride 2 both sides bridge pier of setting gradually; Put on the shelf at described end bay abutment and to be provided with abutment platform cap 4; The first bridge pier bent cap 5-1 and the second bridge pier bent cap 5-2 on the bridge pier of described both sides, have been set up respectively; On described abutment platform cap, the first and second bridge pier bent caps, be arranged at intervals with at least two bearing pad stone 6-2,7-2,8-2 respectively, on the bearing pad stone of end bay abutment and the corresponding setting of the first bridge pier bent cap, longitudinally set up the first case beam of striding, as a kind of embodiment of the utility model; First strides four case beam 12-1,12-2,12-3,12-4 is set; On the bearing pad stone of the first bridge pier bent cap and the corresponding setting of the second bridge pier bent cap, longitudinally set up the second case beam of striding, as a kind of embodiment of the utility model, second strides four case beam 13-1,13-2,13-3,13-4 is set.
Claims (1)
1. one kind is carried out the beam prefabricated constructing structure that sets up of case on bridge; It is characterized in that: it comprises the both sides bridge pier that the first end bay abutment and second of striding that sets gradually; Put on the shelf at described end bay abutment and to be provided with abutment platform cap; The first bridge pier bent cap and the second bridge pier bent cap on the bridge pier of described both sides, have been set up respectively; On described abutment platform cap, the first and second bridge pier bent caps, be arranged at intervals with at least two bearing pad stones respectively, all longitudinally setting up the case beam on the bearing pad stone of end bay abutment and the corresponding setting of the first bridge pier bent cap and on the bearing pad stone of the first bridge pier bent cap and the corresponding setting of the second bridge pier bent cap.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205282684U CN202380387U (en) | 2011-12-16 | 2011-12-16 | Construction structure for carrying out prefabricated erection of box beams on bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205282684U CN202380387U (en) | 2011-12-16 | 2011-12-16 | Construction structure for carrying out prefabricated erection of box beams on bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202380387U true CN202380387U (en) | 2012-08-15 |
Family
ID=46628900
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011205282684U Expired - Lifetime CN202380387U (en) | 2011-12-16 | 2011-12-16 | Construction structure for carrying out prefabricated erection of box beams on bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202380387U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103981803A (en) * | 2014-05-30 | 2014-08-13 | 中铁第一勘察设计院集团有限公司 | Prefabricated assembled combination type door-shaped pillar and construction method thereof |
CN113373799A (en) * | 2021-05-26 | 2021-09-10 | 北京交通大学 | Mortise and tenon type spliced pier structure and implementation method thereof |
-
2011
- 2011-12-16 CN CN2011205282684U patent/CN202380387U/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103981803A (en) * | 2014-05-30 | 2014-08-13 | 中铁第一勘察设计院集团有限公司 | Prefabricated assembled combination type door-shaped pillar and construction method thereof |
CN103981803B (en) * | 2014-05-30 | 2016-04-13 | 中铁第一勘察设计院集团有限公司 | The combined gate pier of precast assembly and construction method thereof |
CN113373799A (en) * | 2021-05-26 | 2021-09-10 | 北京交通大学 | Mortise and tenon type spliced pier structure and implementation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102121234B (en) | Quick construction method of two-tower five-span steel truss girder cable-stayed bridge | |
CN100441779C (en) | Space-precasting translation-emplacing method for bridge construction | |
CN104499433B (en) | One wears high ferro low clearance erecting beam construction method under acutangulating intersection | |
CN103669226B (en) | River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method | |
CN102587286A (en) | Simply supported-continuous construction method for bridge superstructure | |
CN101424073A (en) | Bridge deck and steel girder second combination method for whole arch precasted steel-concrete composite continuous box girder | |
CN110820561A (en) | Large cantilever prestress bent cap support device and construction method | |
CN109778700B (en) | Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road | |
CN105648924A (en) | Construction method of multi-span simply-supported steel truss girder bridge | |
CN208917702U (en) | Fish-bellied type concrete box girder cast-in-place construction formwork-support | |
CN110117933B (en) | Cast-in-situ movable formwork for pier top of segmental beam | |
CN102493349B (en) | Method for prefabricating and erecting box girders by using bailey beam | |
CN110656570A (en) | Telescopic pedestrian bridge, construction device and construction method | |
CN202369933U (en) | Trestle bridge cantilever beam lifting system and bridge surface precast beam erecting construction system | |
CN106012863B (en) | A kind of hoisting gate frame and its application method in special-shaped antisymmetry steel Construction of Pylon | |
CN101324054A (en) | Incremental launching positioning construction method of bridge subsection girder temporary pier | |
CN202380387U (en) | Construction structure for carrying out prefabricated erection of box beams on bridge | |
CN112160247B (en) | Construction method of asynchronous hydraulic creeping formwork for hollow high pier of limited space pier group | |
CN202989781U (en) | Width widened cast-in-place box beam moving support | |
CN203654200U (en) | No. 0 block support for box girder of river-crossing prestressed concrete continuous beam bridge | |
CN112878171A (en) | Large-span steel structure arch bridge and construction method | |
CN202369930U (en) | Door opening type bearing framed bent device for multiplayer concrete box girder | |
CN102535339A (en) | Bracket for thin-wall hollow high-pier cantilever perfusing continuous beam and constructing method thereof | |
CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
CN214271705U (en) | Bent cap reinforcing bar ligature bed-jig |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20120815 |