CN202359544U - Compacting device for earthwork in slope section - Google Patents

Compacting device for earthwork in slope section Download PDF

Info

Publication number
CN202359544U
CN202359544U CN201120495435XU CN201120495435U CN202359544U CN 202359544 U CN202359544 U CN 202359544U CN 201120495435X U CN201120495435X U CN 201120495435XU CN 201120495435 U CN201120495435 U CN 201120495435U CN 202359544 U CN202359544 U CN 202359544U
Authority
CN
China
Prior art keywords
compacting
excavator
plate
earthwork
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120495435XU
Other languages
Chinese (zh)
Inventor
李雄
唐静
张志华
梁飞
王安邦
梁春红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
Third Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Third Engineering Division filed Critical Third Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201120495435XU priority Critical patent/CN202359544U/en
Application granted granted Critical
Publication of CN202359544U publication Critical patent/CN202359544U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model provides a compacting device for earthwork in a slope section. The compacting device comprises a flat-plate compacting head, wherein the flat-plate compacting head is composed of a compacting plate, a stiffening plate and a connecting rod; the compacting plate is a rectangular thick steel plate; the lower surface of the compacting plate is flat, and a cylindrical connecting seat is arranged at the centre of the upper surface of the compacting plate; the stiffening plate is radially connected around the outer wall of the connecting seat; the connecting seat is connected with one end of the connecting rod, and the other end of the connecting rod is connected with a small boom of an excavator; the small boom of the excavator is hinged with a large boom of the excavator; and the large boom of the excavator is connected with an excavator body. The compacting device for earthwork in the slope section disclosed by the utility model is less in one-time investment, saving in cost, good in applicability, and safe and reliable in compacting process; and the alternating compaction of a compacting flat plate is driven by the reciprocating motion of a hydraulic cylinder of the excavator, so that construction efficiency is higher than that of a manual compactor, thus shortening the construction period and ensuring the construction quality of compaction for earthwork on a slope surface. The compacting device for earthwork in the slope section can be widely applied to compacting processes for artificial lakes, water conservancy projects, and earthwork slope surfaces such as engineering foundation-pit side slopes.

Description

Slope section cubic metre of earth and stone tamping unit
Technical field
The utility model relates to a kind of slope section ground works tamping apparatus.
Background technology
Slope section ground works is common in the compacting engineering of riverbank, loke shore and the bank protection soil body; With the loke shore afforestation project is example; Engineering construction mainly comprises the smooth compacting of the backfilling of earthwork of loke shore bottom, loke shore sandy gravel, loke shore sand gravel; Loke shore geotextiles, geomembrane, geotextiles, the compacting of each layer of loke shore placed rockfill.Because it is rugged that most of lake strandline shapes are wriggled; The face operation on the slope of heavy road roller tool can only adopt conventional artificial ramming mode to reinforce, and not only needs a large amount of rammer and labour; Machinery take with labour cost input huge, and reinforcing dynamics and quality are undesirable.Therefore, the compacting engineering construction task difficulty of loke shore slope is bigger, and is anxious to be solved.
The utility model content
The purpose of the utility model provides a kind of slope section cubic metre of earth and stone tamping unit, solves low loke shore slope and is not easy the low-cost technical problem of compacting fast.
For realizing above-mentioned purpose, the utility model adopts following technical scheme:
A kind of slope section cubic metre of earth and stone tamping unit comprises dull and stereotyped compacting head, and the said dull and stereotyped head that rams is by compacting plate, stiffener and connecting rod; Said compacting plate is the steel plate of rectangle; Smooth below the compacting plate, there is a columnar Connection Block center above, the radial stiffener that is connected with around the outer wall of Connection Block; Connection Block is connected with an end of connecting rod; The other end of connecting rod is connected with the petty action arm of excavator, and the little swing arm of excavator and the big swing arm of excavator are hinged, and the big swing arm of excavator is connected with the excavator car body.
Said stiffener is a right-angled triangle, evenly is equally spaced around Connection Block right-angle side and Connection Block welding, another right-angle side and the welding of compacting plate.
Compared with prior art the utlity model has following characteristics and beneficial effect: the utility model overcome conventional heavy-duty road roller tool can't be on slope operation and manual work cost drop into huge, the unfavorable shortcoming of compacting effect, having solved the efficient technical problem of accomplishing the slope compacting of guaranteeing the quality.
The utility model is simple in structure, and is easy to make, and it is convenient to use; It is installed on the excavator; Reciprocating motion through the excavator hydraulic cylinder drives dull and stereotyped alternately the ramming of compacting, tamps the cubic metre of earth and stone, shakes from top to bottom during the compacting construction and rams; Overlapped between adjacent two compacting faces, thus the earthwork compacting construction quality of loke shore slope guaranteed.
The utility model is disposable, and less input, practiced thrift cost, and applicability is good; It is safe and reliable to ram process, compares with common artificial ramming, and the compacting quality of earthwork construction is apparently higher than the hand compaction quality; Reach the unapproachable tamped strength of hand compaction, guaranteed the construction quality of loke shore slope, and efficiency of construction has been higher than artificial rammer far away; Shortened the construction period of this operation greatly, for great amount of time has been got in later operation construction.
The utility model can be widely used in slope ground workss such as artificial lake, hydraulic engineering.
Description of drawings
Below in conjunction with accompanying drawing the utility model is done further detailed explanation.
Fig. 1 is the structural representation of the utility model.
Fig. 2 is that the structure master of the utility model looks sketch map.
Fig. 3 is the structure schematic top plan view of the utility model.
Fig. 4 is the work sketch map of the utility model.
Reference numeral: 1-compacting plate, 2-stiffener, 3-connecting rod, 4-Connection Block, the little swing arm of 5-excavator, the big swing arm of 6-excavator, 7-excavator car body.
The specific embodiment
Embodiment is referring to Fig. 1, Fig. 2, shown in Figure 3, and a kind of slope section cubic metre of earth and stone tamping unit comprises dull and stereotyped compacting head; The said dull and stereotyped head that rams is by compacting plate 1, stiffener 2 and connecting rod 3, and said compacting plate 1 be the steel plate of rectangle, tamp plate 1 below smooth; There is a columnar Connection Block 4 center above, the radial stiffener 2 that is connected with around the outer wall of Connection Block 4, and said stiffener 2 is a right-angled triangle; Thickness is 30 millimeters, evenly is equally spaced around Connection Block 4 right-angle side and Connection Block 4 welding; Another right-angle side welds with compacting plate 1, has guaranteed the rigidity of compacting plate 1, and Connection Block 4 is connected with an end of connecting rod 3; Simple, the manufacturing easily of whole apparatus structure uses easy equally.
Referring to shown in Figure 4; The other end of connecting rod 3 is connected with the petty action arm 5 of excavator; The petty action arm 5 of excavator is hinged with the big swing arm 6 of excavator; The big swing arm 6 of excavator is connected with excavator car body 7, utilizes the reciprocating motion of excavator hydraulic cylinder to drive dull and stereotyped alternately the ramming of compacting, tamps the cubic metre of earth and stone.
The course of work of the utility model, concrete steps are following:
Step 1 is cleared up the backfill of slope earlier before the construction, needs bigger stone, rubbish and other the waste material thereof of cleaning particle diameter;
Step 2 before use slope section cubic metre of earth and stone tamping unit is tamped, adopts excavator that precompressed is carried out on the slope and handles;
Step 3 through precompressed, makes its surfacing, begins compacting;
Step 4, when construction compacting changes excavator bucket into process slope section cubic metre of earth and stone tamping unit, and the reciprocating motion through the excavator hydraulic cylinder drives alternately ramming of front plate vibrator, tamps the cubic metre of earth and stone;
Step 5 after compacting is accomplished, is checked the benefit rammer to whole loke shore slope, and accomplishing does not have leak source, no blind spot, and so far, construction finishes.
The utility model is disposable, and less input, practiced thrift cost, and applicability is good; It is safe and reliable to ram process, shakes from top to bottom during the compacting construction and rams, overlapped between adjacent two compacting faces; Compare with common artificial ramming, the compacting quality of earthwork construction has reached the unapproachable tamped strength of hand compaction apparently higher than the hand compaction quality; Guaranteed the construction quality of loke shore slope; And efficiency of construction is higher than artificial rammer far away, has shortened the construction period of this operation greatly, for great amount of time has been got in later operation construction.
The embodiment of the utility model: the slope ground works compacting of certain loke shore 1 ︰ 2; Having adopted the utility model that excavator is installed the slope section cubic metre of earth and stone tamping unit that processes rams by force; Guaranteed the cubic metre of earth and stone construction quality of whole loke shore slope; And engineering was poured water in advance in 4 days smoothly, the greenery patches engineering was completed in 18 days in advance.
Analyze through actual measuring and calculating, if this project adopts artificial ramming, machinery adopts vibrations rammer (HZ-400): the tamping plate area is S 1=0.28 ㎡; Because the loke shore gradient is bigger, the personnel operation difficulty, the construction operating mode is relatively poor, and the actual measurement rammer is per hour walked about 100 meters; Working time calculated by 8 hours every days: every artificial vibrations ramming function finished surface amasss and is S 2=S 1V=0.28 * 100 * 8=224 ㎡, total upgrade a slope area are 19000 ㎡, and it is S/S that a rammer is tamped a needs fate fully 2=19000/224=85 days; Record the artificial rammer compacting of employing through test and just can reach requirement of strength 8 times; If adopt 30 rammers then to need 85 * 8/30=23 days could accomplish all tamping operations; Calculate labour cost (workman every day 100 yuan) according to rammer one people; Rammer adopts to be bought, and the market inquiry is 3800 yuan every, then: labour cost=30 * 23 * 1 * 100=69000 unit, the mechanical expense=3800 * 30=114000 unit, total cost M 1=69000+114000=183000 unit.
Adopt the dynamic compaction machinery of the utility model digging machine repacking to construct, through on-the-spot actual measuring and calculating, a digging machine approximately can be tamped 3600 ㎡ every day, is 19000 ㎡ and always tamp the slope area, and needing fate is 19000/3600 ≈ 6 days; According to working every day 8 hours, hourly rate is to calculate 320 yuan (comprising labour cost and machinery expense), and daily rate is 320 * 8=2560 unit, total cost M 2=2560 * 6=15360 unit, the difference of both expenses is a 183000-15360=167640 unit.
Therefore adopting this technology has been this project direct saving 16.764 ten thousand yuan, the more important thing is and adopts the method to shorten construction period greatly, and guaranteed construction quality, pouring water smoothly for engineering provides the condition of putting forward earlier.

Claims (2)

1. a slope section cubic metre of earth and stone tamping unit comprises dull and stereotyped compacting head, it is characterized in that: the said dull and stereotyped head that rams is by compacting plate (1), stiffener (2) and connecting rod (3); Said compacting plate (1) is the steel plate of rectangle; Smooth below the compacting plate (1), there is a columnar Connection Block (4) center above, the radial stiffener (2) that is connected with around the outer wall of Connection Block (4); Connection Block (4) is connected with an end of connecting rod (3); The other end of connecting rod (3) is connected with the little swing arm (5) of excavator, and the little swing arm (5) of excavator is hinged with the big swing arm (6) of excavator, and the big swing arm (6) of excavator is connected with excavator car body (7).
2. slope according to claim 1 section cubic metre of earth and stone tamping unit; It is characterized in that: said stiffener (2) is a right-angled triangle; Evenly be equally spaced around Connection Block (4) right-angle side and Connection Block (4) welding, another right-angle side and compacting plate (1) welding.
CN201120495435XU 2011-12-02 2011-12-02 Compacting device for earthwork in slope section Expired - Fee Related CN202359544U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120495435XU CN202359544U (en) 2011-12-02 2011-12-02 Compacting device for earthwork in slope section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120495435XU CN202359544U (en) 2011-12-02 2011-12-02 Compacting device for earthwork in slope section

Publications (1)

Publication Number Publication Date
CN202359544U true CN202359544U (en) 2012-08-01

Family

ID=46570739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120495435XU Expired - Fee Related CN202359544U (en) 2011-12-02 2011-12-02 Compacting device for earthwork in slope section

Country Status (1)

Country Link
CN (1) CN202359544U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032789A (en) * 2014-06-27 2014-09-10 国家电网公司 Earthwork punning structure used with excavator
CN107489151A (en) * 2017-09-29 2017-12-19 王世松 A kind of flexible water construction equipment
CN107542089A (en) * 2017-10-09 2018-01-05 宁德市益升智能科技有限公司 A kind of water conservancy equipment
CN107653870A (en) * 2016-07-23 2018-02-02 赵彦杰 Tamp dykes and dams equipment
CN107663855A (en) * 2016-07-27 2018-02-06 赵彦杰 Tamp dykes and dams equipment
CN107663856A (en) * 2016-07-28 2018-02-06 赵彦杰 Tamp dykes and dams equipment
CN107740400A (en) * 2017-10-18 2018-02-27 楼德耀 It is a kind of can flexible modulation road slope tamping unit
CN110331711A (en) * 2019-07-24 2019-10-15 河南省公路工程局集团有限公司 A kind of road and bridge bridge approach changeover portion compacting construction machinery
CN111608167A (en) * 2020-06-09 2020-09-01 中建八局第二建设有限公司 Excavator accessory welding steel plate formula ramming machine

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032789A (en) * 2014-06-27 2014-09-10 国家电网公司 Earthwork punning structure used with excavator
CN107653870A (en) * 2016-07-23 2018-02-02 赵彦杰 Tamp dykes and dams equipment
CN107663855A (en) * 2016-07-27 2018-02-06 赵彦杰 Tamp dykes and dams equipment
CN107663856A (en) * 2016-07-28 2018-02-06 赵彦杰 Tamp dykes and dams equipment
CN107489151A (en) * 2017-09-29 2017-12-19 王世松 A kind of flexible water construction equipment
CN107489151B (en) * 2017-09-29 2018-10-26 宿州市众力保温节能材料有限公司 A kind of flexible water construction equipment
CN107542089A (en) * 2017-10-09 2018-01-05 宁德市益升智能科技有限公司 A kind of water conservancy equipment
CN107740400A (en) * 2017-10-18 2018-02-27 楼德耀 It is a kind of can flexible modulation road slope tamping unit
CN110331711A (en) * 2019-07-24 2019-10-15 河南省公路工程局集团有限公司 A kind of road and bridge bridge approach changeover portion compacting construction machinery
CN111608167A (en) * 2020-06-09 2020-09-01 中建八局第二建设有限公司 Excavator accessory welding steel plate formula ramming machine

Similar Documents

Publication Publication Date Title
CN202359544U (en) Compacting device for earthwork in slope section
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN103926377B (en) Testing device for valve pipe slip casting model and testing method thereof
CN202898930U (en) By-river reinforced roadbed structure
CN103184734A (en) Implanted and grouted compound pile and construction method
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN105781556A (en) Construction method for shield to penetrate through shallow-covered urban landscape lake downwards
CN105714773A (en) Foundation treatment method
CN107287999A (en) Rigid pile composite foundation united drainage consolidation reinforces highway soft soil ground construction
CN110965416A (en) Bamboo reinforcement system for reinforcing high-fill roadbed in mountainous area and construction method
CN201826245U (en) Hydraulic vibrating rammer
CN203213101U (en) Embedding grouting combined pile
CN101591903A (en) Method for processing long-pile short-pier composite foundation
CN109537582B (en) Construction method for CFG pile front cut pile head and earth mould pouring pile cap
CN103993533B (en) For the comprehensive debulking methods of Canal in Loess Area high-filled embankment
CN213390201U (en) Earth-rock dam soft foundation treatment structure with reinforced vibro-replacement gravel pile and rockfill
CN110029626B (en) Reinforcing treatment method for revetment foundation on soft stratum slope
CN102352627A (en) Static pressure reinforcing treatment method for pile with unqualified bearing capacity
CN208455387U (en) Mountain highway, which is filled out, digs intersection road structure
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN207295765U (en) Tunnel engineering construction platform back structure
KR100607536B1 (en) Tamper equipped with Towing device
CN102605775B (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method
CN211200425U (en) High side slope composite supporting construction that fills of gravel soil

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120801

Termination date: 20191202