CN202338290U - Integrated tubular column with double-seal gas lift well completion - Google Patents
Integrated tubular column with double-seal gas lift well completion Download PDFInfo
- Publication number
- CN202338290U CN202338290U CN2011204042448U CN201120404244U CN202338290U CN 202338290 U CN202338290 U CN 202338290U CN 2011204042448 U CN2011204042448 U CN 2011204042448U CN 201120404244 U CN201120404244 U CN 201120404244U CN 202338290 U CN202338290 U CN 202338290U
- Authority
- CN
- China
- Prior art keywords
- oil
- packer
- oil pipe
- gaslift
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 210000002445 nipple Anatomy 0.000 claims description 17
- 102000029828 Melanin-concentrating hormone receptor Human genes 0.000 claims description 5
- 108010047068 Melanin-concentrating hormone receptor Proteins 0.000 claims description 5
- 230000000694 effects Effects 0.000 abstract description 8
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 238000000034 method Methods 0.000 abstract description 4
- 238000000605 extraction Methods 0.000 abstract 1
- 239000003921 oil Substances 0.000 description 30
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 14
- 238000012360 testing method Methods 0.000 description 10
- 239000003129 oil well Substances 0.000 description 3
- 238000011084 recovery Methods 0.000 description 3
- 239000007788 liquid Substances 0.000 description 2
- 230000001737 promoting effect Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000010779 crude oil Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The integrated pipe string with double gas seals and gas lift well completion is applied to oil production wells in oil fields. The connection relationship from bottom to top is as follows: the upper part of the oil pipe shoe is connected with a ball seat, and the upper part of the ball seat is connected with a mechanically-set lower packer and a hydraulically-set upper packer; 35-60 oil pipes are connected between the upper hydraulically-set packer and the lower mechanically-set packer; the 35-60 oil pipes are connected with a depth-correcting short circuit, and the upper part of the depth-correcting short circuit is connected with a gas-lift working barrel provided with a blind valve through an oil pipe; the upper portion of an upper packer of the hydraulic setting is connected with a telescopic pipe, the upper portion of the telescopic pipe is connected with an oil pipe, the upper portion of the oil pipe is connected with 3-15 gas-lift working cylinders with blind valves, the upper ends of the gas-lift working cylinders with the blind valves on the upper portion are connected with the oil pipe, and the oil pipe is connected to a wellhead all the time. The effect is as follows: the two packers can be tested and gas-lift oil extraction can be carried out. The working procedures are reduced, the working time is shortened, and finally the working cost is reduced.
Description
Technical field
The utility model relates to oil recovery technique field, oil field, and particularly a kind of down-hole oil production tubing string is the two envelope of an a kind of band gaslift completion integrated pipe column.
Background technology
At present, the potentiality oil reservoir of some oil well is in the bottom of Water Flooding Layer, and Water Flooding Layer is referred to as high Water Flooding Layer.The flow string that in such oil well, is lowered to should have the function of the high Water Flooding Layer of shutoff, and can exploit bottom potentiality oil reservoir.Consult Fig. 1.The gaslift completion tubular column that is lowered at this oil well generally all is to adopt two envelope gas lift strings of giving up.The high Water Flooding Layer of shutoff mainly realizes that by lower packet 2, intubate 12, upper packer 3 two packers adopt and set the same packer of principle.Completion tubular column is made up of oil pipe 4 and gaslift seating nipple 11.Consult Fig. 2.Tubing string is lowered to process; Following pair of tube sealing post of elder generation; Promptly being lowered to upper packer 3, lower packet 2, two packers connects high Water Flooding Layer 8, two packers of shutoff through intubate 12 and sets simultaneously; Sleeve pipe 1 and the annular space that sets tubing string are suppressed checking upper packer 3 whether set, trip out the tubing string of giving up after setting.Be lowered to completion tubular column completion again with some gaslift seating nipples 11.
The subject matter that this completion tubular column exists is: (1) two envelopes and gaslift completion tubular column are through tubing string operation completion twice down, and the activity duration is long, has increased operating cost.(2) since two envelope to set principle the same, set simultaneously, lower packet can't verify whether set, thereby can not guarantee the effect of the high Water Flooding Layer of shutoff.(3) if will let the potentiality oil reservoir combination producing of high Water Flooding Layer and bottom later on, operation again, is salvaged two envelopes at lift pipe string, descend the completion gas lift string again, needs operation again, the increase operating cost.
The utility model content
The purpose of the utility model is: the two envelope of a kind of band gaslift completion integrated pipe column is provided, can tests two packers and seal the promoting the circulation of qi act oil recovery of going forward side by side.Reach and both can improve the high Water Flooding Layer effect of shutoff, create a kind of convenience for later high Water Flooding Layer utilization again, reduce flow chart, shorten the activity duration, finally reduce operating cost.
The technical scheme that the utility model adopts is: the two envelope of band gaslift completion integrated pipe column, mainly form by tubing shoe, ball seat, mechanical-set lower packet, the dark short circuit in school, the gaslift seating nipple of adorning blind valve, the upper packer of hydraulic setting, telescoping tube.It is characterized in that: annexation is from bottom to top: the top at tubing shoe connects ball seat, and ball seat top connects the upper packer of mechanical-set lower packet and hydraulic setting; Between the upper packer of hydraulic setting and mechanical-set lower packet, be connected with 35~60 oil pipes; On these 35~60 oil pipes, be connected with the dark short circuit in school, and the top of dark short circuit is connected with a gaslift seating nipple that blind valve is housed through oil pipe in the school; Top at the upper packer of hydraulic setting is connected with telescoping tube; The top of telescoping tube is connected with oil pipe; The top of oil pipe connects 3~15 gaslift seating nipples that blind valve is housed, and is connected with oil pipe in the upper end of the gaslift seating nipple that blind valve is housed on top, and oil pipe is connected to well head always.
What described mechanical-set lower packet adopted is the RTTS packer that positive tube post, pressurization set, and guarantees the effect that sets of mechanical-set lower packet;
What the upper packer of described hydraulic setting adopted is that the MCHR packer that sets is suppressed in classification.
The beneficial effect of the utility model: the two envelope of the utility model band gaslift completion integrated pipe column, can test two packers and seal the promoting the circulation of qi act oil recovery of going forward side by side.If will produce high Water Flooding Layer later on,, take out the tubing string operation and needn't go up working rig through pulling the blind valve in the gaslift seating nipple out.Reach and both can improve the high Water Flooding Layer effect of shutoff, create a kind of convenience for later high Water Flooding Layer utilization again, reduce flow chart, shorten the activity duration, finally reduce operating cost.
Description of drawings
Fig. 1 is existing gas lift string structural profile sketch map.
Fig. 2 is the gaslift completion integrated pipe column structural profile sketch map of the two envelopes of the utility model.
Among the figure, the 1-sleeve pipe, the mechanical-set lower packet of 2-, the upper packer of 3-hydraulic setting, the 4-oil pipe, 5-potentiality oil reservoir, the 6-tubing shoe, the 7-ball seat, the high Water Flooding Layer of 8-, the dark short circuit in 9-school, 10-telescoping tube, 11-are equipped with the gaslift seating nipple of blind valve, 12-intubate.
The specific embodiment
Embodiment 1: the two envelope of band gaslift completion integrated pipe column is successfully tried out at 3 mouthfuls of wells, is 4733.5-4751.0m (totally three sections) with high watered-out well section, and potentiality oil reservoir well section is that a bite well of 4806.0-4808.0m is that example is elaborated to the present invention.
Consult Fig. 2.The two envelope of the utility model band gaslift completion integrated pipe columns mainly are made up of the dark short circuit of tubing shoe 6, ball seat 7, mechanical-set lower packet 2, school 9, gaslift seating nipple 11, the upper packer 3 of hydraulic setting, the telescoping tube 10 of adorning blind valve.
Two envelope gaslift completion integrated pipe columns annexation from bottom to top are: the top at tubing shoe 6 connects ball seat 7, and ball seat 7 tops connect the upper packer 3 of mechanical-set lower packet 2 and hydraulic setting.What mechanical-set lower packet 2 adopted is the RTTS packer that positive tube post, pressurization set.What the upper packer 3 of hydraulic setting adopted is that the MCHR packer that sets is suppressed in classification.Between the upper packer 3 of hydraulic setting and mechanical-set lower packet 2, be connected with 37 oil pipes.On these 37 oil pipes, be connected with a dark short circuit 9 in school, and the top of dark short circuit 9 is connected with a gaslift seating nipple 11 that blind valve is housed through oil pipe in the school.Top at the upper packer 3 of hydraulic setting is connected with a telescoping tube 10; The top of telescoping tube 10 is connected with oil pipe 4; The top of oil pipe 4 connects five gaslift seating nipples 11 that blind valve is housed; Upper end at the gaslift seating nipple 11 that blind valve is housed on top is connected with oil pipe 4, and oil pipe 4 is connected to well head always.
That oil pipe 4 adopts is 73mm (2
7/ 8 " oil pipe), external upset tubing footwear 6 depth of setting 4770.04m, ball seat 7 depth of setting 4769.90m; mechanical-set lower packet 2 envelope position 4759.35m; 9 times dark 4720.01m of the dark pipe nipple in school, the upper packer 3 envelope position 3994.74m of hydraulic setting, 10 times dark 3974.37m of telescoping tube.Dark 2319.97m under the 5# gas lift valve, dark 2048.42m under the 4# gas lift valve, dark 1719.45m under the 3# gas lift valve, dark 1380.16m under the 2# gas lift valve, dark 965.45m under the 1# gas lift valve.Be lowered to 2 altogether
7/ 8 " the P110E*5.51mm oil pipe is 493.
(1) operation process
1, in sleeve pipe 1, is lowered to the two envelope of band gaslift completion integrated pipe column.
2, set, test the mechanical-set lower packet of envelope.Just changeing 8 circles, pressurization 9t, RTTS packer setting, envelope position 4759.35m; Connect that cementing truck is counter suppresses pipeline and pressure testing 30MPa/30min does not fall, to the RTTS testing seal about packer: the anti-15MPa that suppresses, oil pipe does not return liquid, tests the involution lattice.
3, set, test the mechanical-set lower packet of envelope.Throwing diameter is the steel ball of 28mm, waits ball and takes a seat; Connect cementing truck forehand pressure pipeline and pressure testing 30MPa/30min does not fall; Classification is just suppressing 7,14,21MPa, each voltage stabilizing 10min, annular space does not return liquid, 7 " MCHR packer setting, an envelope position 3994.74m.To the MCHR testing seal about packer: the anti-15MPa/30min of suppressing does not fall, and tests the involution lattice.
4, completion.Just suppressing 28MPa, shooting down ball seat, tearing blowout preventer set open, the dress production tree.
5, pulling gas lift valve.Pull the blind valve in the above six grades of gas lift valves of upper packer of hydraulic setting out, drop into the gas lift valve that designs.
(2) condition of production
This gas well gas is lifted and is gone into operation, 85 tons of day production fluids, and 62 tons of daily output crude oil are produced stable.
Claims (3)
1. the two envelope of a band gaslift completion integrated pipe column mainly is made up of tubing shoe (6), ball seat (7), mechanical-set lower packet (2), the dark short circuit in school (9), the gaslift seating nipple (11) of adorning blind valve, the upper packer (3) of hydraulic setting, telescoping tube (10); It is characterized in that: annexation is from bottom to top: the top at tubing shoe (6) connects ball seat (7), and ball seat (7) top connects the upper packer (3) of mechanical-set lower packet (2) and hydraulic setting; Between the upper packer (3) of hydraulic setting and mechanical-set lower packet (2), be connected with 35~60 oil pipes; On these 35~60 oil pipes, be connected with the dark short circuit in school (9), and the top of dark short circuit (9) is connected with a gaslift seating nipple (11) that blind valve is housed through oil pipe in the school; Top at the upper packer (3) of hydraulic setting is connected with telescoping tube (10); The top of telescoping tube (10) is connected with oil pipe (4); The top of oil pipe (4) connects 3~15 gaslift seating nipples (11) that blind valve is housed; Upper end at the gaslift seating nipple (11) that blind valve is housed on top is connected with oil pipe (4), and oil pipe (4) is connected to well head always.
2. the two envelope of band according to claim 1 gaslift completion integrated pipe column is characterized in that: what described mechanical-set lower packet (2) adopted is the RTTS packer that positive tube post, pressurization set.
3. the two envelope of band according to claim 1 gaslift completion integrated pipe column, it is characterized in that: what the upper packer of described hydraulic setting (3) adopted is that the MCHR packer that sets is suppressed in classification.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204042448U CN202338290U (en) | 2011-10-21 | 2011-10-21 | Integrated tubular column with double-seal gas lift well completion |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204042448U CN202338290U (en) | 2011-10-21 | 2011-10-21 | Integrated tubular column with double-seal gas lift well completion |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202338290U true CN202338290U (en) | 2012-07-18 |
Family
ID=46486983
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011204042448U Expired - Fee Related CN202338290U (en) | 2011-10-21 | 2011-10-21 | Integrated tubular column with double-seal gas lift well completion |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202338290U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106812510A (en) * | 2015-12-01 | 2017-06-09 | 中国石油天然气股份有限公司 | Tubular string and well completion method |
CN108625822A (en) * | 2018-05-08 | 2018-10-09 | 海峰深水(天津)技术服务有限公司 | Multistage sequentially triggered emergency system capable of automatically shearing tubular column and sealing well |
CN112780184A (en) * | 2019-11-11 | 2021-05-11 | 中国石油化工股份有限公司 | Self-balancing anti-pollution well completion pipe string for gas well |
-
2011
- 2011-10-21 CN CN2011204042448U patent/CN202338290U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106812510A (en) * | 2015-12-01 | 2017-06-09 | 中国石油天然气股份有限公司 | Tubular string and well completion method |
CN108625822A (en) * | 2018-05-08 | 2018-10-09 | 海峰深水(天津)技术服务有限公司 | Multistage sequentially triggered emergency system capable of automatically shearing tubular column and sealing well |
CN108625822B (en) * | 2018-05-08 | 2024-04-02 | 海一峰深水(天津)技术服务有限公司 | Multistage sequential triggering emergency system capable of automatically shearing tubular column and sealing well hole |
CN112780184A (en) * | 2019-11-11 | 2021-05-11 | 中国石油化工股份有限公司 | Self-balancing anti-pollution well completion pipe string for gas well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201212387Y (en) | Gas injection, gas production and brine discharge integration process pipe column for underground gas storage | |
CN202900205U (en) | Multifunctional oil testing and well completion integrated pipe column | |
CN201593405U (en) | Integrated tubular column for horizontal well completion and fracturing production | |
CN202882846U (en) | Downhole isolating valve | |
CN201915931U (en) | Special setting ball seat for fracture of horizontal well | |
CN204941480U (en) | The horizontal well completion sleeve pipe of segmentation exploitation and the tubing string of formation thereof can be realized | |
CN203531877U (en) | Underground coal mine fracturing connecting device | |
CN103266865B (en) | A kind of big orifice packer for oil well | |
CN202338290U (en) | Integrated tubular column with double-seal gas lift well completion | |
CN204827256U (en) | Seal up and adopt down screen pipe and fill sand control integration operating tool string | |
CN203050662U (en) | Hydraulic sliding sleeve switch | |
CN104989325B (en) | A kind of method using two-tube gas well liquid loading tubing string gas production arranged side by side | |
CN104806196A (en) | Casing floating system for horizontal well | |
CN202152670U (en) | Construction pipe column for horizontal well sectional measure | |
CN201620854U (en) | Double-element split type plunger gas lift tool | |
CN203008883U (en) | Steam injection oil production technique pipe column | |
CN103452496B (en) | Integral type of adopting thick oil thermal extraction note automatically switches and produces joint | |
CN203394480U (en) | Oil-water well layering acidizing device | |
CN201857941U (en) | Anti-leakage and bottom water coning delay integrated string of horizontal well | |
CN205036361U (en) | Perforation seperated layer water injection integration tubular column | |
CN201225121Y (en) | Oil gas well selective completion tool | |
CN201620840U (en) | Circulating sliding sleeve | |
CN205297515U (en) | Coiled tubing drags hydraulic jet fracturing unit | |
CN204312021U (en) | A kind of washing well hydraulic control annular packer | |
CN203488143U (en) | Automatic mud grouting float-collar float shoe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120718 Termination date: 20201021 |