CN202323783U - Hanging device for mid-span closure section hanging basket - Google Patents
Hanging device for mid-span closure section hanging basket Download PDFInfo
- Publication number
- CN202323783U CN202323783U CN 201120474187 CN201120474187U CN202323783U CN 202323783 U CN202323783 U CN 202323783U CN 201120474187 CN201120474187 CN 201120474187 CN 201120474187 U CN201120474187 U CN 201120474187U CN 202323783 U CN202323783 U CN 202323783U
- Authority
- CN
- China
- Prior art keywords
- suspender belt
- sleeve
- hanging basket
- sling
- stride
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a hanging device for a mid-span closure section hanging basket. The hanging device comprises a sling and a hanger rod for fixing the sling, a sleeve is arranged on the sling, the sling is arranged in the sleeve, and the shape of the inner cavity of the sleeve is matched with outline of the sling. By sleeving the sleeve of which shape is matched with the sling on the periphery of the sling, direct contact between the sling and concrete when a box girder is poured is avoided, and the condition that the sling is difficult to take out after the concrete is solidified is avoided, so that the sling is convenient to demould, and damage of the sling due to direct contact between the sling and the concrete can be avoided during demoulding.
Description
Technical field
The utility model relates to strides the closure segment construction equipment in a kind of, strides the suspension apparatus of closure segment Hanging Basket in particularly a kind of.
Background technology
In the field of bridge construction, cast-in-place cantilever method is claimed no support balance semi-girder method or extension (hanging) basket method again, refers in the bridge pier both sides working platform is set, and evenly piecemeal to span centre cantilever pouring cement concrete beam body, and applies prestressed job practices piecemeal.Used main equipment is Hanging Basket, and the member of Hanging Basket mainly comprises: truss, suspension system, walking system, template and stretch-draw platform five major parts, it is following to adopt Hanging Basket to carry out the operating principle of cantilever pouring: bed die, outer side form with triangular truss move forward in place after; Colligation base plate, web reinforcement and prestressed pipeline, with interior mould bases move in place after, inner formword is installed; Colligation top board reinforcing bar and prestressed corrugated conduit; Carry out beam section cantilever pouring construction, after newly watering beam section stretch-draw anchor and hole path pressure grouting, the Hanging Basket next beam section construction of carrying out in place that moves forward again; So circulation is passed, until the construction of accomplishing last beam section.
Wherein, suspender belt and back strap and lifting appliance before the suspension system of Hanging Basket comprises, its effect is that a weight concrete and a template weight part that cantilever pours into are reached on the main couple.Preceding suspender belt is made by 4 steel plates usually, and a part of Load Transfer that the effect of back strap is Hanging Basket is born is to case beam base plate, and back strap is processed by 2 steel plates usually; Interior mould bases is suspended in two internal molds through suspension apparatus and walks on the cross girders, walks the cross girders front end and is hung on the truss front beam, and the rear end is hung on the casting beams section preformed hole; Interior mould bases can slide along walking cross girders, and template all adopts combined steel, behind interior moulding/demoulding; Internal mold drops on internal mold and walks on the cross girders; Promote with artificial, can internal mold be moved to next section beam, finally after the closure segment construction is accomplished, remove Hanging Basket.
But still there is following weak point in it: because suspender belt is not dismantled before building; Build in the process; Concrete can condense on the locating hole of suspender belt; When building when accomplishing back strap and needing the demoulding, the concrete after solidifying during the big and demoulding of demoulding difficulty is prone to suspender belt is caused wearing and tearing, is unfavorable for the repeated use of suspender belt.
The utility model content
The technical problem that the utility model will solve is to overcome the above-mentioned deficiency of prior art, provide a kind of when being easy to the demoulding and the demoulding to the suspender belt damage little in stride the suspension apparatus of closure segment Hanging Basket.
For solving the problems of the technologies described above; The utility model provides following technical scheme: the suspension apparatus of striding the closure segment Hanging Basket in a kind of; Comprise suspender belt and the suspension rod that is used for fixing suspender belt; Said suspender belt is provided with sleeve, and said suspender belt is arranged on sleeve inner, and the cavity shape of said sleeve and the profile of suspender belt are suitable.
Through the suitable with it sleeve of peripheral suit shape at suspender belt; Avoided the case beam when building, suspender belt directly contacts with concrete, the situation of having avoided the concrete setting back strap to be difficult to take out; Make suspender belt be convenient to the demoulding, and can avoid because of directly contacting the damage that produces during the demoulding with concrete.
Stride in above-mentioned in the suspension apparatus of closure segment Hanging Basket, said suspender belt comprises preceding suspender belt, and the two ends of said preceding suspender belt connect with the Hanging Basket bed die with top rail respectively.Adopt above-mentioned structure, preceding top rail is linked to each other with Hanging Basket bed die front end, not only increased the intensity that connects, avoid building the situation that back strap is difficult to the demoulding through sleeve simultaneously through suspender belt.
Preferably, said sleeve set is on preceding suspender belt, and said sleeve is arranged between top rail and the Hanging Basket bed die.Adopt such structure, the zone before sleeve is arranged between top rail and the Hanging Basket bed die is arranged on suspender belt with sleeve and contacts with concrete on the concrete body, and all the other suspender belt that does not contact with concrete body parts need not be provided with sleeve.
Preferably, said suspender belt also comprises back strap, and the two ends of said back strap are connected with the Hanging Basket bed die with case beam bottom respectively.Link to each other through the main couple of suspender belt, not only increased the intensity that connects, avoid building the situation that back strap is difficult to the demoulding through sleeve simultaneously case beam bottom and Hanging Basket.
Preferably, said sleeve set is on back strap, and said sleeve is arranged between the main couple of case beam bottom and Hanging Basket.Adopt such structure, sleeve is arranged on the zone between the main couple of case beam bottom and Hanging Basket, sleeve is arranged on suspender belt contacts with concrete on the concrete body, all the other suspender belts that do not contact with the concrete body partly need not be provided with sleeve.
Stride in above-mentioned in the suspension apparatus of closure segment Hanging Basket, be provided with connecting rod between said sleeve and the suspender belt, said suspender belt is fixedly installed on the inner chamber middle part of sleeve through connecting rod.Adopt such structure, when setting up sleeve, utilize connecting rod that sleeve is connected on the suspender belt, and be embedded in case beam inside synchronously with suspender belt, when installation and removal, suspender belt does not directly contact with concrete in the location.
Preferably, said connecting rod two ends respectively with sleeve and suspender belt welding.When needs are removed suspender belt and sleeve, only need to weld releasing, can remove suspender belt and sleeve successively, have the beneficial effect of connection, easy accessibility.
Stride in above-mentioned in the suspension apparatus of closure segment Hanging Basket, said sleeve is that the steel plate of 3mm is welded by thickness.Adopt such structure, the steel plate of 3mm is seen everywhere at the construction field (site), can carry out second use to the discarded parts of job site.
In sum, owing to adopted technique scheme, compared with prior art; The beneficial effect of the utility model is: through the suitable with it sleeve of peripheral suit shape at suspender belt; Avoided the case beam when building, suspender belt directly contacts with concrete, the situation of having avoided the concrete setting back strap to be difficult to take out; Make suspender belt be convenient to the demoulding, and can avoid because of directly contacting the damage that produces during the demoulding with concrete.
Description of drawings
The utility model will explain through embodiment and with reference to the mode of accompanying drawing, wherein:
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the local enlarged diagram of A-A portion in the utility model;
Fig. 3 be sleeve partly cut open structural representation.
Mark among the figure: suspender belt-1; Preceding suspender belt-1a; Back strap-1b; Suspension rod-2; Sleeve-3; Connecting rod-4; Top rail-5; Hanging Basket bed die-6; Case beam bottom-7.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is done detailed explanation.
For the purpose, technical scheme and the advantage that make the utility model is clearer,, the utility model is further elaborated below in conjunction with accompanying drawing and embodiment.Should be appreciated that specific embodiment described herein only in order to explanation the utility model, and be not used in qualification the utility model.
Extremely shown in Figure 3 like Fig. 1; The suspension apparatus of striding the closure segment Hanging Basket in the present embodiment comprises suspender belt 1 and the suspension rod 2 that is used for fixing suspender belt 1; Hanging Basket is fixed on the case beam through suspension apparatus, and for the ease of suspender belt 1 demoulding after concreting, suspender belt 1 is provided with sleeve 3 with the suspender belt 1 of concrete contact position; Suspender belt 1 is arranged on sleeve 3 inside; The profile of the cavity shape of sleeve 3 and suspender belt 1 is suitable, and then has avoided suspender belt 1 directly to contact with the concrete that is about to build, thereby is convenient to suspender belt 1 demoulding after construction.
Extremely shown in Figure 3 like Fig. 1; The suspension apparatus of striding the closure segment Hanging Basket in the present embodiment comprises suspender belt 1 and the suspension rod 2 that is used for fixing suspender belt 1; Suspender belt 1a and back strap 1b before wherein suspender belt 1 comprises, the two ends of preceding suspender belt 1a are connected with Hanging Basket bed die 6 with top rail 5 respectively, in the outer race of preceding suspender belt 1a sleeve 3 are housed; For sleeve 3 shapes and preceding suspender belt 1a and concrete joint synapsis are adapted, sleeve 3 is arranged between top rail 5 and the Hanging Basket bed die 6; Preceding suspension rod 2 is made up of four fining twisted steels, respectively the inside and outside mould walking beam of lifting; The two ends of back strap 1b are connected with Hanging Basket bed die 6 with case beam bottom 7 respectively; Sleeve 3 is sleeved on the back strap 1b; For sleeve 3 shapes and back strap 1b and concrete contact position are adapted, the sleeve 3 on the back strap 1b is arranged between case beam bottom 7 and the Hanging Basket bed die 6.
All the other structures are please with reference to embodiment 1.
Extremely shown in Figure 3 like Fig. 1; The suspension apparatus of striding the closure segment Hanging Basket in the present embodiment comprises suspender belt 1 and the suspension rod 2 that is used for fixing suspender belt 1; Suspender belt 1a and back strap 1b before wherein suspender belt 1 comprises; The lower end of preceding suspender belt 1a is connected with bed die frame front beam key seat, and the upper end is hung on the main couple crossbeam, and every suspender belt 1 is regulated the bed die absolute altitude by two manual jack and shoulder pole girder; The lower end of back strap 1b is connected with bed die frame rear cross beam key seat, and the upper end is passed the case beam and connected, and two manual jack of 32T of every suspender belt 1 usefulness and shoulder pole girder are supported on the beam section base plate that has watered.On preceding suspender belt 1a and back strap 1b, all be set with sleeve 3; Be provided with connecting rod 4 between sleeve 3 and the suspender belt 1; Suspender belt 1 adopts the mode of spot welding to be fixedly installed on the inner chamber middle part of sleeve 3 through connecting rod 4; Be connecting rod 4 two ends respectively with sleeve 3 and suspender belt 1 welding, sleeve 3 itself is that the steel plate of 3mm is welded according to the shape of suspender belt 1 by thickness.
All the other structures are please with reference to embodiment 1.
The above is merely the preferred embodiment of the utility model; Not in order to restriction the utility model; Any modification of being done within all spirit and principles at the utility model, be equal to replacement and improvement etc., all should be included within the protection domain of the utility model.
Claims (8)
1. stride the suspension apparatus of closure segment Hanging Basket in one kind; Comprise suspender belt (1) and be used for fixing the suspension rod (2) of suspender belt (1); It is characterized in that: said suspender belt (1) is provided with sleeve (3); Said suspender belt (1) is arranged on sleeve (3) inside, and the profile of the cavity shape of said sleeve (3) and suspender belt (1) is suitable.
2. stride the suspension apparatus of closure segment Hanging Basket in according to claim 1, it is characterized in that: said suspender belt (1) comprises preceding suspender belt (1a), and the two ends of said preceding suspender belt (1a) are connected with Hanging Basket bed die (6) with top rail (5) respectively.
3. stride the suspension apparatus of closure segment Hanging Basket in according to claim 2, it is characterized in that: said sleeve (3) is sleeved on the preceding suspender belt (1a), and said sleeve (3) is arranged between top rail (5) and the Hanging Basket bed die (6).
4. stride the suspension apparatus of closure segment Hanging Basket in according to claim 1, it is characterized in that: said suspender belt (1) also comprises back strap (1), and the two ends of said back strap (1) are connected with Hanging Basket bed die (6) with case beam bottom (7) respectively.
5. stride the suspension apparatus of closure segment Hanging Basket in according to claim 4, it is characterized in that: said sleeve (3) is sleeved on the back strap (1), and said sleeve (3) is arranged between case beam bottom (7) and the Hanging Basket bed die (6).
6. stride the suspension apparatus of closure segment Hanging Basket in described according to arbitrary claim in the claim 1 to 5; It is characterized in that: be provided with connecting rod (4) between said sleeve (3) and the suspender belt (1), said suspender belt (1) is fixedly installed on the inner chamber middle part of sleeve (3) through connecting rod (4).
7. stride the suspension apparatus of closure segment Hanging Basket in according to claim 6, it is characterized in that: weld with sleeve (3) and suspender belt (1) respectively at said connecting rod (4) two ends.
8. stride the suspension apparatus of closure segment Hanging Basket according to arbitrary claim in the claim 1 to 5 in described, it is characterized in that: said sleeve (3) is that the steel plate of 3mm is welded by thickness.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120474187 CN202323783U (en) | 2011-11-24 | 2011-11-24 | Hanging device for mid-span closure section hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120474187 CN202323783U (en) | 2011-11-24 | 2011-11-24 | Hanging device for mid-span closure section hanging basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202323783U true CN202323783U (en) | 2012-07-11 |
Family
ID=46435767
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201120474187 Expired - Lifetime CN202323783U (en) | 2011-11-24 | 2011-11-24 | Hanging device for mid-span closure section hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202323783U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104074145A (en) * | 2014-06-30 | 2014-10-01 | 广东省基础工程公司 | Closure-section refit construction method for hanging basket |
CN108004924A (en) * | 2017-11-29 | 2018-05-08 | 中交路桥华南工程有限公司 | The folding method of the middle span of the double hybrid steel in rope face of double tower-mixed steel-concrete composite beam cable-stayed bridge |
CN110067211A (en) * | 2019-04-23 | 2019-07-30 | 中建市政工程有限公司 | Bridge flange plate demoulding device and construction method thereof |
-
2011
- 2011-11-24 CN CN 201120474187 patent/CN202323783U/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104074145A (en) * | 2014-06-30 | 2014-10-01 | 广东省基础工程公司 | Closure-section refit construction method for hanging basket |
CN108004924A (en) * | 2017-11-29 | 2018-05-08 | 中交路桥华南工程有限公司 | The folding method of the middle span of the double hybrid steel in rope face of double tower-mixed steel-concrete composite beam cable-stayed bridge |
CN108004924B (en) * | 2017-11-29 | 2021-01-22 | 中交路桥华南工程有限公司 | Method for folding middle span section of double-tower double-cable-surface mixed type steel-concrete superposed beam cable-stayed bridge |
CN110067211A (en) * | 2019-04-23 | 2019-07-30 | 中建市政工程有限公司 | Bridge flange plate demoulding device and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101586330B (en) | Receding construction method of cradle of continuous girder bridge made of prestressing concrete | |
CN207143755U (en) | A kind of adjustable bracket for No. 0 block of bridge pier | |
CN109267490B (en) | Long guide beam type movable formwork and construction method thereof | |
CN107338727B (en) | Integrally-disassembled and assembled anti-collision wall template and walking type rail hanging and moving system thereof | |
CN109267491B (en) | Movable formwork and construction method thereof | |
CN102493362B (en) | Construction method for midspan closure segment of longspan continuous rigid frame bridge | |
CN101781878B (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
CN104612061B (en) | A kind of suspension open type hanging basket device and construction method thereof | |
CN110528402B (en) | Construction method of ultra-wide box girder multi-truss-piece combined hanging basket | |
CN104294767B (en) | A kind of semi girder cast-in-place construction spreading Hanging Basket and construction method thereof | |
CN102094392B (en) | Lower supported hanging basket in bridge construction and application thereof | |
KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
CN208543603U (en) | Precast prestressed floor production mould and production equipment | |
CN105220619B (en) | A kind of method of quick manufacture two-wire nose circle solid pier | |
CN107905111B (en) | A kind of rigid frame-continuous girder end bay construction technology | |
CN209144661U (en) | Mould bases for bridge construction | |
CN110410109A (en) | A kind of construction of hangar tunnel lining cutting arch shifting formwork trolley and construction method | |
CN202323783U (en) | Hanging device for mid-span closure section hanging basket | |
CN206512605U (en) | A kind of overall demolition, installation anticollision wall form and its walking track crane move system | |
CN109235280A (en) | The operation platform and construction method of bridge coping | |
CN106042173A (en) | Bridge production system | |
CN114717968A (en) | Construction method for main tower of cable-stayed bridge | |
CN105088962B (en) | A kind of integral hoisting method of Wavelike steel webplate part | |
CN205474871U (en) | A main truss system that is used for wave form steel web continuous beam construction to hang a basket | |
CN209194347U (en) | The operation platform of bridge coping |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20120711 |
|
CX01 | Expiry of patent term |