CN202302300U - Combined pipeline mounting operation platform - Google Patents

Combined pipeline mounting operation platform Download PDF

Info

Publication number
CN202302300U
CN202302300U CN2011203292253U CN201120329225U CN202302300U CN 202302300 U CN202302300 U CN 202302300U CN 2011203292253 U CN2011203292253 U CN 2011203292253U CN 201120329225 U CN201120329225 U CN 201120329225U CN 202302300 U CN202302300 U CN 202302300U
Authority
CN
China
Prior art keywords
platform
crossbeam
column
steel structure
plane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011203292253U
Other languages
Chinese (zh)
Inventor
李喜海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Original Assignee
ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANGANG CONSTRUCTION CONSORTIUM Co Ltd filed Critical ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Priority to CN2011203292253U priority Critical patent/CN202302300U/en
Application granted granted Critical
Publication of CN202302300U publication Critical patent/CN202302300U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to a combined pipeline mounting operation platform. The combined pipeline mounting operation platform is characterized by comprising box-shaped uprights, steel structure platforms, platform uprights and cross beams, wherein the steel structure platforms are arranged on two groups of box-shaped uprights arranged in parallel; a plurality of platform uprights are arranged along the outer side edges of the steel structure platforms; the platform uprights are connected with the cross beams by cross beam supports; each platform upright comprises a square flange, a sectional steel column and a locating grating; the square flange is arranged at the bottom of the sectional steel column; the locating grating is connected in parallel with the sectional steel column; and each cross beam support is provided with a connecting plate, a bolt hole and a locating tilt surface. Compared with the prior art, the combined pipeline mounting operation platform has the beneficial effects that: the heights of the box-shaped uprights can be designed to be not the same, so that the convenience is provided for quick assembly and transportation; the steel structure platforms not only are operation platforms of operators but also support pipelines to be paired; the pipeline lifting difficulty is lowered; the pipeline mounting quality is improved; the danger factors in construction are reduced; the construction efficiency is greatly improved; and the engineering cost is saved.

Description

Combined pipeline installation exercise platform
Technical field
The utility model relates to the piping erection field, relates in particular to a kind of combined pipeline installation exercise platform.
Background technique
At present, in the workshop pipe network was installed, pipeline generally all designed the bottom at the crownblock beam of factory building; During the pipeline lifting, both do not used the overhead traveling crane in the workshop, hydraulic pressure hangs the mounting point of also opening less than the crownblock beam bottom; The pipeline lifting can only be with methods such as chain hoist or elevators; Operating personnel's labor intensity is big, and risk factor is big, the piping erection difficult quality guarantee.
Summary of the invention
The purpose of the utility model provides a kind of combined pipeline installation exercise platform, can assemble repeated use fast, is convenient to transportation, and it is right to be used for the on-the-spot group of pipeline, reduces the piping erection difficulty.
For solving the problems of the technologies described above, the technological scheme of the utility model is:
Combined pipeline installation exercise platform; It is characterized in that; Comprise box-shaped column, steel structure platform, platform column and crossbeam; Set up steel structure platform on the box-shaped column of two groups of parallel placements, be provided with a plurality of platform columns along the outer side of steel structure platform, the platform column supports through crossbeam and is connected with crossbeam.
Said platform column comprises square flange, steel column and location grid, and square flange is located at steel column bottom, the parallel connection with steel column of location grid.
Said crossbeam supports and is provided with connecting plate, bolt hole and inclined-plane, location, and connecting plate is vertical at the side that crossbeam supports, and the opposite side that crossbeam supports is located on the inclined-plane, location.
Said crossbeam is a rod shaped object, and both sides are provided with positioning plate respectively, and the positioning plate downside is the inclined-plane, and positioning plate is provided with slotted hole, and the slotted hole length direction is parallel with the inclined-plane, and said inclined-plane is consistent with the gradient on the inclined-plane, location that crossbeam supports.
Existing technology is compared, and the beneficial effect of the utility model is: box-shaped column height can be made multiple height, is convenient to assembling fast and transportation; This platform is operating personnel's a operating platform, also supports pipeline and is used to organize right, reduces the pipeline hoisting difficulty; Improve the piping erection quality; Reduce the construction hazards, improve efficiency of construction greatly, practice thrift engineering cost.
Description of drawings
Fig. 1 is the utility model example structure schematic representation;
Fig. 2 is the side view of Fig. 1;
Fig. 3 is a crossbeam supporting structure schematic representation;
Fig. 4 is the side view of Fig. 3;
Fig. 5 is the beam structure schematic representation.
Among the figure: 1-box-shaped column 2-steel structure platform 3-platform column 4-crossbeam 5-crossbeam supports 12-positioning plate 13-slotted hole 14-inclined-plane, inclined-plane, 6-square flange 7-steel column 8-location grid 9-connecting plate 10-bolt hole 11-location 15-bolt
Embodiment
Be described further below in conjunction with the embodiment of accompanying drawing the utility model:
See Fig. 1, Fig. 2; It is the utility model combined pipeline installation exercise platform example structure schematic representation; Comprise box-shaped column 1, steel structure platform 2, platform column 3 and crossbeam 4; Set up steel structure platform 2 on the box-shaped column 1 of two groups of parallel placements, be provided with a plurality of platform columns 3 along the outer side of steel structure platform 2, platform column 3 supports 5 through crossbeam and is connected with crossbeam 4.The box-shaped column 1 usefulness bolt combination of a plurality of different heights is formed by connecting, to satisfy the setting height(from bottom) requirement.Platform column 3 comprises square flange 6, steel column 7 and location grid 8, and square flange 6 is located at steel column 7 bottoms, location grid 8 and steel column 7 parallel connections.Location grid 8 is used to adjust crossbeam 4 height.
When the utility model uses,, select the box column 1 of proper height,, will make up the position that back box column 1 is sent into piping erection with overhead traveling crane with overhead traveling crane combined box type column in the workshop 1 and steel structure platform 2 according to the duct height of workshop pipe network; Highly select location grid suitable on the platform column 38 according to crossbeam 4, it is fixing that crossbeam is supported 5 insertions; Four crossbeams 4 are placed on crossbeam support on 5, make its height identical, with bolt 15 fixed cross beams 4 with support of pipelines.
Be placed on group on the good crossbeam 4 with the overhead traveling crane pipeline to be pacified of slinging, the rolling pipeline makes it get into the axis of piping erection, with elevator pipeline is pulled on the support of pipelines, arrives the edge of crossbeam 4 up to the afterbody of pipeline; With overhead traveling crane another root pipeline is hung group on the crossbeam 4 equally, be rolled into the axial location of installation, on crossbeam 4,, repeat above-mentioned step after qualified and continue pipe laying with the welding of last root pipeline; After the piping erection of this layer height finished, the height of adjustment crossbeam 4 made it identical with following one deck support of pipelines setting height(from bottom), continued to install one deck pipeline down.
See Fig. 3, Fig. 4, crossbeam supports 5 and is provided with connecting plate 9, bolt hole 10 and inclined-plane 11, location, and connecting plate 9 is vertical at the side that crossbeam supports, and inclined-plane 11, location is located at crossbeam and is supported 5 opposite side.
See Fig. 5, crossbeam 4 is a rod shaped object, and both sides are provided with positioning plate 12 respectively, and positioning plate 12 downsides are inclined-plane 14, and positioning plate is provided with slotted hole 13, and slotted hole 13 length directions are parallel with inclined-plane 14, and inclined-plane 14 is consistent with the gradient on the inclined-plane, location 11 of crossbeam support 5.

Claims (4)

1. combined pipeline installation exercise platform; It is characterized in that; Comprise box-shaped column, steel structure platform, platform column and crossbeam; Set up steel structure platform on the box-shaped column of two groups of parallel placements, be provided with a plurality of platform columns along the outer side of steel structure platform, the platform column supports through crossbeam and is connected with crossbeam.
2. combined pipeline installation exercise platform according to claim 1 is characterized in that said platform column comprises square flange, steel column and location grid, and square flange is located at steel column bottom, the parallel connection with steel column of location grid.
3. combined pipeline installation exercise platform according to claim 1 and 2; It is characterized in that; Said crossbeam supports and is provided with connecting plate, bolt hole and inclined-plane, location, and connecting plate is vertical at the side that crossbeam supports, and the opposite side that crossbeam supports is located on the inclined-plane, location.
4. combined pipeline installation exercise platform according to claim 3; It is characterized in that said crossbeam is a rod shaped object, both sides are provided with positioning plate respectively; The positioning plate downside is the inclined-plane; Positioning plate is provided with slotted hole, and the slotted hole length direction is parallel with the inclined-plane, and said inclined-plane is consistent with the gradient on the inclined-plane, location that crossbeam supports.
CN2011203292253U 2011-09-03 2011-09-03 Combined pipeline mounting operation platform Expired - Lifetime CN202302300U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203292253U CN202302300U (en) 2011-09-03 2011-09-03 Combined pipeline mounting operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203292253U CN202302300U (en) 2011-09-03 2011-09-03 Combined pipeline mounting operation platform

Publications (1)

Publication Number Publication Date
CN202302300U true CN202302300U (en) 2012-07-04

Family

ID=46371195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203292253U Expired - Lifetime CN202302300U (en) 2011-09-03 2011-09-03 Combined pipeline mounting operation platform

Country Status (1)

Country Link
CN (1) CN202302300U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105973441A (en) * 2016-06-22 2016-09-28 文登蓝岛建筑工程有限公司 Structural board molding workbench
CN108361439A (en) * 2018-02-12 2018-08-03 安徽唯诗杨信息科技有限公司 A kind of matching tooling of chemical pipeline crane span structure
CN108591615A (en) * 2018-05-11 2018-09-28 中国十七冶集团有限公司 Pipeline rotating compensator mounting structure and its construction method on a kind of water field of big area
CN113137042A (en) * 2021-04-23 2021-07-20 李喜海 Automatic bottom-lifting type lifting platform and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105973441A (en) * 2016-06-22 2016-09-28 文登蓝岛建筑工程有限公司 Structural board molding workbench
CN108361439A (en) * 2018-02-12 2018-08-03 安徽唯诗杨信息科技有限公司 A kind of matching tooling of chemical pipeline crane span structure
CN108591615A (en) * 2018-05-11 2018-09-28 中国十七冶集团有限公司 Pipeline rotating compensator mounting structure and its construction method on a kind of water field of big area
CN113137042A (en) * 2021-04-23 2021-07-20 李喜海 Automatic bottom-lifting type lifting platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN103243926B (en) Construction method for hoisting engineering tube well stand pipe of high-rise building
CN201417657Y (en) Installation device of indoor transformer
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN106894342B (en) Pipe installing job platform and construction method
CN103243930A (en) System and method for modularized construction of super high-rise steel structures
CN202302300U (en) Combined pipeline mounting operation platform
CN201723853U (en) Integrated supporting and hanging frame with comprehensive pipeline arrangement technology for large public building installation project
CN107130770A (en) A kind of high-rise building air conditioner water vertical shaft Large Diameter Pipeline standpipe inversion construction method
CN103967284B (en) The steel column installation method of reserved stigma docking
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN109372269A (en) A kind of constructing structure of roof trusses
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN103993745A (en) Integral transfer girder hoisting device and hoisting method thereof
CN205777580U (en) A kind of automatic lifting discharging platform
CN101177933B (en) Bridge rib hoisting and supporting rack integral construction method and device
CN103939875A (en) Vertical type waste heat boiler module hanging construction method
CN202188515U (en) Multi-side detachable bound overhead torch
CN210884873U (en) Installation hanging beam and lifting device of pipeline
CN101818563B (en) Jack-up integral lifting mobile platform and using method
CN104627849B (en) Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
CN111779229A (en) Construction and installation method of large-scale ventilating duct
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN202429882U (en) Movable lifting frame
CN202082489U (en) Pipe gallery horizontal pipeline mounting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120704

CX01 Expiry of patent term