CN202297807U - Raw material preheating device for electrolytic cell - Google Patents

Raw material preheating device for electrolytic cell Download PDF

Info

Publication number
CN202297807U
CN202297807U CN2011204056262U CN201120405626U CN202297807U CN 202297807 U CN202297807 U CN 202297807U CN 2011204056262 U CN2011204056262 U CN 2011204056262U CN 201120405626 U CN201120405626 U CN 201120405626U CN 202297807 U CN202297807 U CN 202297807U
Authority
CN
China
Prior art keywords
hollow container
raw material
crust
crust breaking
preheating device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204056262U
Other languages
Chinese (zh)
Inventor
彭优
龚克成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Chuangyuan Aluminium Industry Co Ltd
Original Assignee
Hunan Chuangyuan Aluminium Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Chuangyuan Aluminium Industry Co Ltd filed Critical Hunan Chuangyuan Aluminium Industry Co Ltd
Priority to CN2011204056262U priority Critical patent/CN202297807U/en
Application granted granted Critical
Publication of CN202297807U publication Critical patent/CN202297807U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model belongs to the technical field of aluminum cells and in particular relates to a raw material preheating device for an aluminum cell. According to the raw material preheating device for an electrolytic cell, a hollow container with upper and lower openings is arranged at a feed opening of a workbin, and is fixed on a cell body at the feed opening of the electrolytic cell; a crust hammer head is positioned in the hollow container; the lower part of the hollow container is provided with a sealing device; the sealing device can be a movable plate which is movably connected with the lower end of the hollow container; in addition, a crust hammer head baffle can be arranged on the lower part of the crust hammer head, and is fixedly connected with the crust hammer head; and the size of the crust hammer head baffle is not smaller than that of the lower opening of the hollow container. By the technical scheme, heat dissipated at the feed opening of the electrolytic cell is effectively utilized, raw materials can be preheated, energy loss is reduced, the raw material dissolving time is shortened, and the work efficiency is improved.

Description

A kind of raw material preheating device that is used for electrolyzer
Technical field
The utility model belongs to the aluminium cell technical field, is specifically related to a kind of aluminium cell raw material preheating device.
Background technology
Aluminum electrolysis needs hot conditions, and the preheating meeting of raw alumina produces great effect to the electrolysis of aluminum acting.In electrolytic aluminum crust breaking blanking process, the aluminium cell electrolysis temperature up to 940 ℃~960 ℃, the shell hole temperature behind the crust breaking is very high; Existing aluminum oxide point feeding device cutting mode is that raw material gets into electrolyzer from the hopper feed opening after the crust breaking work; And this hopper is far away apart from electrolyzer, so the heat that distribute in the shell hole is less to the influence of the material temperature in the hopper, and the aluminum oxide temperature that gets in the electrolyzer is low; Needing to absorb a large amount of heat could dissolve; Expend the energy, and that waste heat utilizes is low again, causes calorific loss.
Application number is 200820218813.8 (patent names: a kind of aluminum electrolyzing cell used built-up type crust breaking tremie pipe; Publication number: 201309969; The open date: Chinese granted patent on September 16th, 2009) discloses a kind of built-up type crust breaking tremie pipe; The tremie pipe of electrolyzer blanking system was communicated with the attacking head protective sleeve of crust breaking system before getting into the shell hole, it is transformed into built-up type crust breaking tremie pipe.Use the difference of this built-up type crust breaking tremie pipe and this patent to be: following shortcoming is arranged: (1), enclosed appts is not arranged at tremie pipe feed opening place; Raw material still directly gets in the electrolyzer; Can not effectively utilize the electrolyzer waste heat, play preheating effect raw material; (2), the crust breaking end protective sleeve is a long and narrow annular cover, after the crust breaking end protective sleeve was joined with tremie pipe, raw material blocked in the crust breaking end protective sleeve easily, caused the increase of crust breaking end and protective sleeve frictional force, thereby influenced crust breaking end work, the damage crust breaking end; (3), blanking equipment and the operation of crust breaking device separates, connect blanking equipment and crust breaking protective sleeve with tremie pipe, the blanking process extends, and causes blanking in time, influences working efficiency.
The utility model content
The purpose of the utility model is the above shortcoming that overcomes the crust breaking blanking device of plain electrolysers, and a kind of crust breaking blanking device with raw material preheating effect is provided.
For realizing above-mentioned purpose, the technical scheme that the utility model is taked is following:
A kind of raw material preheating device that is used for electrolyzer installs the hollow container of a upper and lower opening additional at hopper feed opening place, hollow container is fixed on that crust breaking end is arranged in hollow container on the electrolyzer feed opening cell body, and hollow container lower ending opening place is provided with tightness system.
Further, tightness system is a portable plate, and portable plate and hollow container lower ending opening flexibly connect.
Further, said tightness system is a baffle plate, and baffle plate is fixedly connected with crust breaking end, and the size of baffle plate is not less than the size of said hollow container lower ending opening.
The beneficial effect of the utility model is, adopt above technical scheme after:
1, the present technique scheme has installed the hollow container of a upper and lower opening additional at hopper feed opening place, and is being provided with the lower opening that tightness system comes the sealed hollow container, and raw alumina is stored hollow container earlier after hopper comes out; Because this storing device is near apart from the shell hole; Effectively absorption electrolysis groove heat carries out raw material preheating, when crust breaking end work next time, gets into electrolyzer again, raw alumina is played the effect of secondary storage preheating; Reduce energy loss; After the preheating, the dissolution rate of aluminum oxide shortens, and avoids producing bearth precipitation.
2, in the present technique scheme, because hollow container is near apart from the electrolytic bath shell hole, after the raw material in the hollow container absorbs heat, can be liquefied as stream shape object, in crust breaking end work, can not cause raw material to scatter, economize on resources, avoid dust.
3, described hollow container capacity is bigger, and blanking is fast, can not hinder crust breaking end work, can not cause damage to crust breaking head protection cover and crust breaking end, and can in time in time carry out blanking to the raw material of preheating, has improved working efficiency.
Description of drawings
In order to be illustrated more clearly in the utility model embodiment; To do briefly clearly to introduce to the accompanying drawing of required use among the embodiment below; Obviously, the accompanying drawing in describing below only is some embodiment of the utility model, for those of ordinary skills; Under the prerequisite of not paying creative work, can also obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is the structure iron of the utility model;
Fig. 2 is the structural representation of the utility model embodiment 2;
Fig. 3, Fig. 4 are the structural representations of the utility model embodiment 3;
Reference numeral: 1, hollow container 2, raw material 3, portable plate 4, spring assembly 5, crust breaking end 6, baffle plate
Embodiment
To combine the accompanying drawing among the utility model embodiment below, the technical scheme among the utility model embodiment is carried out clear, intactly description, obviously, described embodiment only is the part embodiment of the utility model, rather than whole embodiment.Based on the embodiment in the utility model, those of ordinary skills are not making the every other embodiment that is obtained under the creative work prerequisite, all belong to the scope of the utility model protection.
Embodiment 1
As shown in the figure; A kind of raw material preheating device that is used for aluminium cell installs the hollow container 1 of a upper and lower opening additional at hopper feed opening place, hollow container 1 is fixed on the electrolyzer feed opening cell body; Crust breaking end 5 is arranged in hollow container 1, and hollow container 1 bottom is provided with tightness system.When raw material 2 got in the hollow container 1, said tightness system played the effect of storage raw material 2, makes raw material 2 can reach pre-heat effect.
Embodiment 2
Like Fig. 1, shown in Figure 2; A kind of raw material preheating device that is used for aluminium cell installs the hollow container 1 of a upper and lower opening additional at hopper feed opening place, hollow container 1 is fixed on the electrolyzer top; Crust breaking end 5 is arranged in hollow container 1; Hollow container 1 bottom is provided with tightness system, and said tightness system is a portable plate 3, and said portable plate 3 flexibly connects with said hollow container 1 lower ending opening.Said movable connection method comprises, a spring assembly 4 is set, and flexibly connects portable plate and hollow container lower end through spring assembly 4; In the time of crust breaking end 5 decline crust breakings, crust breaking end 5 is exerted pressure to portable plate 3, thereby utilizes spring assembly 4 that portable plate 3 is ejected; In the shell hole that the raw material 2 entering crust breaking ends of preheating are got; After crust breaking end 5 crust breakings finished rising, portable plate 3 rebounded under the effect of spring assembly 4, carries out the storage preheating of raw material 2.
Embodiment 3
Like Fig. 3, shown in Figure 4; A kind of raw material preheating device that is used for aluminium cell installs the hollow container 1 of a upper and lower opening additional at hopper feed opening place, hollow container 1 is fixed on the electrolyzer cell body; Crust breaking end 5 is arranged in hollow container 1; Hollow container 1 bottom is provided with tightness system, and described tightness system is a baffle plate 6, and baffle plate 6 is fixedly connected with crust breaking end 5; Described fixed connection mode comprises modes such as riveted joint, welding, bolted, and the size of baffle plate 6 is not less than the size of said hollow container 1 lower ending opening.

Claims (3)

1. raw material preheating device that is used for electrolyzer; It is characterized in that; Install the hollow container of a upper and lower opening additional at said hopper feed opening place; Said hollow container is fixed on the electrolyzer feed opening cell body, and said crust breaking end is arranged in said hollow container, and said hollow container lower ending opening place is provided with tightness system.
2. a kind of raw material preheating device that is used for electrolyzer according to claim 1 is characterized in that said tightness system is a portable plate, and said portable plate and said hollow container lower ending opening flexibly connect.
3. a kind of raw material preheating device that is used for electrolyzer according to claim 1; It is characterized in that said tightness system is a baffle plate; Said baffle plate is fixedly connected with said crust breaking end, and the size of said baffle plate is not less than the size of said hollow container lower ending opening.
CN2011204056262U 2011-10-21 2011-10-21 Raw material preheating device for electrolytic cell Expired - Fee Related CN202297807U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204056262U CN202297807U (en) 2011-10-21 2011-10-21 Raw material preheating device for electrolytic cell

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204056262U CN202297807U (en) 2011-10-21 2011-10-21 Raw material preheating device for electrolytic cell

Publications (1)

Publication Number Publication Date
CN202297807U true CN202297807U (en) 2012-07-04

Family

ID=46366741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204056262U Expired - Fee Related CN202297807U (en) 2011-10-21 2011-10-21 Raw material preheating device for electrolytic cell

Country Status (1)

Country Link
CN (1) CN202297807U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108893758A (en) * 2018-06-27 2018-11-27 中南大学 A kind of alumina blanking method of pre-calcining electrolytic cell
CN113122883A (en) * 2021-03-18 2021-07-16 沈阳铝镁设计研究院有限公司 Preheating method for aluminum oxide on upper part of aluminum electrolytic cell

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108893758A (en) * 2018-06-27 2018-11-27 中南大学 A kind of alumina blanking method of pre-calcining electrolytic cell
CN113122883A (en) * 2021-03-18 2021-07-16 沈阳铝镁设计研究院有限公司 Preheating method for aluminum oxide on upper part of aluminum electrolytic cell

Similar Documents

Publication Publication Date Title
CN101771181A (en) Process for recycling waste lead batteries
CN203851502U (en) Battery pack structure of mower
CN202297807U (en) Raw material preheating device for electrolytic cell
CN101758554B (en) Tubular pile die screw
CN206947462U (en) A kind of battery recycling device
CN203533581U (en) Boiler slag discharging and humidifying device
CN204271159U (en) A kind of plug-in battery case
CN205035252U (en) Glass fuse -element shrend pelletization device
CN208839643U (en) A kind of lepidolite ore mentions lithium grinding device
CN202865872U (en) Steel pipe pile for wind power generation foundation
CN202321593U (en) Blanking baffle of pressure disengaging machine for residual anode
CN215377515U (en) Reaction tank for processing aluminum-air battery
CN202201362U (en) New transfer container barrel for lithium ion battery material
CN216837825U (en) Pitch processing is with delaying coking device
CN204570061U (en) Aluminium cell flue automatic ash removing device
CN210545330U (en) Copper disc cone machine that easily resets
CN204160027U (en) A kind of device be separated for submerged-arc welding slag, solder flux
CN203890451U (en) Anodic structure for improving discharge rate of electrolytic gas in aluminum electrolytic cell
CN202491940U (en) Feeding bucket for automatic fertilizer packing machine
CN202684718U (en) Hopper structure of planetary type roll polishing machine
CN216935976U (en) New forms of energy powder material degasification discharging device
CN215234951U (en) Iron selecting device for separating iron chips again
CN211339399U (en) Full-low-pressure closed acetylene generator with auxiliary generator
CN205574843U (en) Shape of a hoof unloading pipe
CN205133635U (en) Not excessive slag granulation facility of abundant granulation of furnace slag and grain slag enables

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120704

Termination date: 20151021

EXPY Termination of patent right or utility model