CN202194147U - Tailing dam - Google Patents

Tailing dam Download PDF

Info

Publication number
CN202194147U
CN202194147U CN201120133933XU CN201120133933U CN202194147U CN 202194147 U CN202194147 U CN 202194147U CN 201120133933X U CN201120133933X U CN 201120133933XU CN 201120133933 U CN201120133933 U CN 201120133933U CN 202194147 U CN202194147 U CN 202194147U
Authority
CN
China
Prior art keywords
tailing
dam
water
tailing dam
geomembrane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120133933XU
Other languages
Chinese (zh)
Inventor
魏群
刘尚蔚
孟凡玲
张国新
姜华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Water Resources and Electric Power
Original Assignee
North China University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Water Resources and Electric Power filed Critical North China University of Water Resources and Electric Power
Priority to CN201120133933XU priority Critical patent/CN202194147U/en
Application granted granted Critical
Publication of CN202194147U publication Critical patent/CN202194147U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/30Landfill technologies aiming to mitigate methane emissions

Abstract

The utility model relates to a tailing dam. A tailing dam water blocking device comprises a body frame and layers of water blocking boards. Each layer of water blocking board can be overlapped for installation according to actual requirements, thereby being simple in structure and convenient to use. A water drainage channel of the tailing dam further can convey oozed sewage from a tailing to a specified area along a specified channel for treatment without polluting the environment, thereby being suitable for popularization and implement. The tailing dam is fixed by a water-blocking device in a tailing fluid period, a tailing layer is formed by water drainage, a dam body is formed by sequentially overlapping, and therefore, a fixed angle (identical with a repose angle) is formed after the dam body tailing is dried, the tailing dam can be formed naturally without depending on the water blocking device and stress, and a simple tailing dam structure is achieved. The tailing dam is easy to construct, short in construction period and stable in structure.

Description

Tailing dam
Technical field
The utility model relates to the tailing dam in a kind of hydrotechnics field, particularly relates to a kind of tailing dam.
Background technology
Tailing dam is the dam formula building that utilizes mud ore deposit quarrel (mine tailing) or local material behind the hydraulic beneficiation to build up, and tailing dam need be considered moisture fluid mine tailing seeped water to handle when building to form fixedly dam body.Existing tailing dam utilizes the natural terrain of fluctuating to construct usually and forms, and building the dam is to need to consider dash infiltration structure, and charging aperture, discharge gate and clarified solution retrieval system, causes complex structure, and the difficulty of construction large period is long, and cost is high.
Summary of the invention
In order to overcome the deficiency that prior art exists, the utility model provides a kind of tailing dam special-purpose baffle device for water tailing dam of constructing.
Technical scheme: the special-purpose baffle device for water of a kind of tailing dam; Comprise the truss-like braced structures; This truss-like braced structures lower end is fixed on the concrete bearing platform, and fixing watertight shutter on this truss-like braced structures is distributed with drain hole on each watertight shutter; Be respectively arranged with rhone on the vertical pillar of each crossbeam of lattice supporting framework and both sides, the transverse row tank is communicated with water treatment system after being summarized in the vertical drainage groove.
Said trussed construction is the combining structure of a plurality of minutes truss, each minute truss each pillar suit and fixing successively.
A kind of tailing dam; Comprise mine tailing and geomembrane; Formed by several layers mine tailing layer stack combinations successively, the upstream face angle of inclination of this combining structure is consistent with the natural angle of repose of use geomembrane, and wherein said mine tailing layer is enclosed with geomembrane at least on three faces of upper and lower and upstream face.
Be provided with vertical well at tailing dam near upstream face one side, the different elevation position distribution of the borehole wall have water inlet, and the shaft bottom is communicated with at the bottom of the dam or dam outboard row aquaporin.
Impervious barrier is set at the bottom of the riverbed.
The beneficial effect of the utility model: the tailing dam of the utility model is through baffle device for water it to be fixed period at the mine tailing fluid; Draining forms the mine tailing layer; Stack forms dam body successively; Because the angle of inclination of baffle device for water adapts with the angle of repose of mine tailing dry state,, can not rely on baffle device for water and get final product the nature moulding and the power that do not suffer oppression so treat the fixed angle that forms after the dam body mine tailing drying.Thereby realized simple tailing dam structure, construction easily, short construction period, and Stability Analysis of Structures.
The tailing dam baffle device for water of the utility model is made up of the watertight shutter of main body frame and each layer; The installation that can successively superpose according to actual needs of every layer of watertight shutter; Simple in structure, easy to use, its drainage channel can be transported to the appointed area along special modality with the sewage that oozes out in the mine tailing again and handle; Free from environmental pollution, be fit to promotion and implementation.
Description of drawings
It is the tailing dam first floor that Fig. 1, Fig. 2 or Fig. 3 implement respectively, the sketch map of the second layer and three layer construction;
Fig. 4 is the folded state enlarged diagram of geomembrane;
Fig. 5 is the dam main body sketch map of piling up successively to the top;
Fig. 6 is a tailing dam structural representation of piling up moulding;
Fig. 7 is the baffle device for water structural representation.
Label 1 is the mine tailing layer among the figure, and 2 is geomembrane, and 3 is baffle device for water, and 4 is impervious barrier; 5 is watertight shutter, and 6 is vertical shaft, and 7 is drainage pipe, and 21 is subsequent use geomembrane; 31 is two lateral braces, and 32 is the vertical drainage passage, and 33 is intermediate studdle; 34 is crossbeam and transverse drainage passage, and 35 is concrete bearing platform, and 36 is the drainage channel that gathers.
The specific embodiment
Embodiment one: referring to Fig. 1-Fig. 7; A kind of tailing dam special-purpose baffle device for water of constructing comprises the truss-like braced structures, and this truss-like braced structures lower end is fixed on the concrete bearing platform 35; Fixing watertight shutter 5 on this truss-like braced structures; Be distributed with drain hole on each watertight shutter 5, each crossbeam 34 inboard of lattice supporting framework are provided with rhone, are respectively arranged with rhone 32 on the vertical pillar 31 in both sides; The transverse row tank is communicated with total rhone 36 again after being summarized in the vertical drainage groove, and total rhone 36 is communicated with water treatment system.
Trussed construction is designed to the combining structure of a plurality of minutes truss, each minute truss each pillar suit and fixing successively, also can fix respectively.
When present embodiment is implemented, stop gauge is set, the inclination angle of stop gauge is set according to the angle of repose of use mine tailing dry state in back side one side; Baffle device for water comprises the truss-like braced structures; The baffle device for water lower end is fixed on the concrete bearing platform; Fixing watertight shutter on this truss-like braced structures; Be distributed with drain hole on each watertight shutter, be respectively arranged with rhone on the vertical pillar of each crossbeam of lattice supporting framework and both sides, the transverse row tank gather with the vertical drainage groove after be communicated with water treatment system.Impervious barrier at first is set at the bottom of the riverbed.On impervious barrier, lay one deck geomembrane again, geomembrane is positioned at back side one end, and to leave surplus subsequent use.
Discharging mine tailing fluid on geomembrane, under baffle effect, the mine tailing fluid forms one deck mine tailing layer after being stopped draining.
With remaining geomembrane along inflection on the in type mine tailing course once, form the overlapping geomembrane that is positioned at the tailing dam upside, geomembrane is positioned at back side one end, and to leave surplus subsequent use.
On above-mentioned mine tailing layer and overlapping geomembrane, continue discharging mine tailing fluid, under baffle effect, the mine tailing fluid forms second layer mine tailing layer after being stopped draining.
Repeat above step successively, meet the tailing dam main body of height of dam requirement until formation; According to the mine tailing layer height, the height that increases stop gauge gradually perhaps increases the watertight shutter of stop gauge gradually.
Behind the tailing dam main body dryness finalization, cancel stop gauge, form the dam body of forming by tailing dam fully.
Vertically dig a well near upstream face one side at tailing dam, the different elevation position distribution of the borehole wall have water inlet, and the shaft bottom is communicated with at the bottom of the dam or dam outboard row aquaporin.According to the mine tailing composition, if mine tailing has noxious material, need discharge at the bottom of the dam or dam outboard row aquaporin is that water is handled.
Embodiment two: referring to Fig. 6; A kind of tailing dam; Comprise mine tailing and geomembrane, it is characterized in that, form by several layers mine tailing layer stack combinations successively; The upstream face angle of inclination of this combining structure is consistent with the natural angle of repose of use geomembrane, and wherein said mine tailing layer is enclosed with geomembrane at least on three faces of upper and lower and upstream face.Impervious barrier is set at the bottom of the riverbed.Be provided with vertical well at tailing dam near upstream face one side, the different elevation position distribution of the borehole wall have water inlet, and the shaft bottom is communicated with at the bottom of the dam or dam outboard row aquaporin.

Claims (3)

1. tailing dam; Comprise mine tailing and geomembrane; It is characterized in that; Formed by several layers mine tailing layer stack combinations successively, the upstream face angle of inclination of this combining structure is consistent with the natural angle of repose of use geomembrane, and wherein said mine tailing layer is enclosed with geomembrane at least on three faces of upper and lower and upstream face.
2. tailing dam according to claim 1 is characterized in that, is provided with vertical well at tailing dam near upstream face one side, and the different elevation position distribution of the borehole wall have water inlet, and the shaft bottom is communicated with at the bottom of the dam or dam outboard row aquaporin.
3. tailing dam according to claim 1 is characterized in that, impervious barrier is set at the bottom of the riverbed.
CN201120133933XU 2011-04-29 2011-04-29 Tailing dam Expired - Fee Related CN202194147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120133933XU CN202194147U (en) 2011-04-29 2011-04-29 Tailing dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120133933XU CN202194147U (en) 2011-04-29 2011-04-29 Tailing dam

Publications (1)

Publication Number Publication Date
CN202194147U true CN202194147U (en) 2012-04-18

Family

ID=45949066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120133933XU Expired - Fee Related CN202194147U (en) 2011-04-29 2011-04-29 Tailing dam

Country Status (1)

Country Link
CN (1) CN202194147U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628488A (en) * 2013-12-18 2014-03-12 云南农业大学 Damming method of tailing subdam
CN103866771A (en) * 2014-03-31 2014-06-18 铜陵有色金属集团股份有限公司 Method for heaping up waterproof tailing pond dam body at one time using tailing coarse sand together with geomembrane
CN103967495A (en) * 2014-04-16 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Stoping technology for dam slope tailing of tailing dam
CN104196010A (en) * 2014-08-14 2014-12-10 中国电建集团西北勘测设计研究院有限公司 Enforced preliminary settlement construction method of concrete faced rockfill dam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628488A (en) * 2013-12-18 2014-03-12 云南农业大学 Damming method of tailing subdam
CN103628488B (en) * 2013-12-18 2016-01-06 云南农业大学 A kind of damming method of mine tailing embankment dam
CN103866771A (en) * 2014-03-31 2014-06-18 铜陵有色金属集团股份有限公司 Method for heaping up waterproof tailing pond dam body at one time using tailing coarse sand together with geomembrane
CN103967495A (en) * 2014-04-16 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Stoping technology for dam slope tailing of tailing dam
CN103967495B (en) * 2014-04-16 2016-02-24 中钢集团马鞍山矿山研究院有限公司 A kind of tailing dam dam slope mine tailing stoping method
CN104196010A (en) * 2014-08-14 2014-12-10 中国电建集团西北勘测设计研究院有限公司 Enforced preliminary settlement construction method of concrete faced rockfill dam

Similar Documents

Publication Publication Date Title
US9915048B2 (en) Method for river/lake level regulation and water conservancy system
CN202194147U (en) Tailing dam
CN102140788B (en) Tailing dam construction method and special water baffle device
CN206530363U (en) One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN102860185A (en) Compound underground grain store with multifunctional passage
CN206110182U (en) Three large -scale arcading city utility tunnel
CN205242445U (en) Intelligent integrated piping lane maintenance of city underground is imported and exported
CN102174803B (en) Assembled drainage canal of debris flows and construction method thereof
CN107761763A (en) A kind of pipe gallery and its application method
CN207260281U (en) Modularization sunk type greenery patches structure
CN208266612U (en) A kind of town road structure
RU2638186C1 (en) Method of concrete dam construction in river canyon
CN213836342U (en) Overhaul water retaining structure under bridge
CN206189968U (en) Prefabricated assembled underground granary of inside lining plastics echelonment
CN205530651U (en) Attaches formula of building rainwater pump house structure
CN204919568U (en) Compound supporting construction of shallow foundation ditch
CN113833016A (en) Comprehensive structure for preventing flood, draining waterlogging and laying underground pipeline
CN207194588U (en) A kind of new semi-underground silo
CN216921556U (en) Landing stage transfer station system
CN206034382U (en) Cross a river traffic dam
CN205636755U (en) Drainage type rhombus grid's ecological bank protection
CN206554097U (en) A kind of soil-baffling structure efficiently constructed
CN105390173A (en) Disposal site of radioactive solid waste in nuclear power station
CN205259216U (en) Adopt steel truss to add concrete structure of back cover under water of muscle
CN105498351A (en) Cast-in-situ bored pile slurry deposition filtering apparatus and construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120418

Termination date: 20150429

EXPY Termination of patent right or utility model