CN104196010A - Enforced preliminary settlement construction method of concrete faced rockfill dam - Google Patents

Enforced preliminary settlement construction method of concrete faced rockfill dam Download PDF

Info

Publication number
CN104196010A
CN104196010A CN201410399139.8A CN201410399139A CN104196010A CN 104196010 A CN104196010 A CN 104196010A CN 201410399139 A CN201410399139 A CN 201410399139A CN 104196010 A CN104196010 A CN 104196010A
Authority
CN
China
Prior art keywords
foundation ditch
water
little
dam body
water level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410399139.8A
Other languages
Chinese (zh)
Inventor
蔡新合
雷艳
魏坚政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Northwest Engineering Corp Ltd
Original Assignee
PowerChina Northwest Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Northwest Engineering Corp Ltd filed Critical PowerChina Northwest Engineering Corp Ltd
Priority to CN201410399139.8A priority Critical patent/CN104196010A/en
Publication of CN104196010A publication Critical patent/CN104196010A/en
Pending legal-status Critical Current

Links

Abstract

The invention belongs to the technical field of water conservancy and hydropower projects, and particularly provides an enforced preliminary settlement construction method of a concrete faced rockfill dam. The method comprises the following steps that (1), a small foundation pit is filled with water; (2), a large foundation pit is filled with water; (3), a dam body of the large foundation pit is soaked; (4), the water of the large foundation pit is drained. According to the enforced preliminary settlement construction method of the concrete faced rockfill dam, during the preliminary settlement period after dam filling is completed and before concrete face construction is carried out, the position, below the elevation of the downstream highest tailwater level of the rockfill dam, of the dam body is soaked with water, dam body deformation generated after concrete face construction is reduced, and therefore the influence of the deformation on a concrete face is reduced, and a foundation is laid for concrete face crack resisting and control over concrete face separation.

Description

A kind of rock is forced pre-sedimentation construction method
Technical field
The invention belongs to Hydraulic and Hydro-Power Engineering technical field, be specifically related to a kind of rock and force pre-sedimentation construction method.
Background technology
Reinforced concrete face rockfill dam is a kind of new dam type that the later stage seventies in last century starts to grow up, it embodies the good feature of safety, economy, easy construction and compliance in practice, although start late but develop very fast, the favor of Shen Shouba work circle.According to incompletely statistics, by September, 2011, in the world built, at the rock of building and planning to build, from engineering quantity, height of dam, to project scale, all occupy the forefront.Along with the accumulation of Dam Construction experience and the raising of design level, the height of rock is also in continuous increase, and Shuibuya Dam is up to 233m, is the highest built rock in the world, also becomes the successful case of the high rock of 250m level.
According to literature search, all there is the vertical pressure seam to a certain degree shear failure situation that is squeezed in the concrete slab of the superelevation face dam of height of dam more than 150m; Purple Ping Pumianbanba after having experienced the test of " 5.12 " Wenchuan earthquake, horizontal construction joint generation faulting of slab ends between two, three phase panels, the vertical pressure property seam in two, the riverbed destruction that is squeezed, three phase panel top occurrence of large-area are come to nothing.According to existing Surveillance on Haemorrhagic, all there is certain Rheological Deformation in ultra-high concrete panel dam, although relative height of dam, the amplitude of its distortion is less, but because the ability of loose rock dam rigid panel adaptive deformation is poor, the trend of dam deformation and size directly have influence on distortion and the stress proterties of panel and seam.
According to existing engineering experience and time, show, larger late dam body deformability, the impacts such as the distortion of counter plate amount of deflection and stress (inclined slope aspect, dam axial), all side seams and vertical lap seam are larger, and the dam body of face dam is in the Deformation control of construction period and runtime and be predicted as one of main restricting factor of face dam safety.
Therefore, in order to prevent and to reduce or remit that panel comes to nothing and crack, avoid the panel vertical lap seam destruction that is squeezed, to guarantee dam structure safety, try every possible means to control late dam body deformability amount, especially the dam deformation amount after panel construction, be solve that rock panel comes to nothing, one of the effective measures of crack, squeeze and destroy.
Summary of the invention
The object of the invention is to overcome the technical barrier of rock, solve technically the panel crack prevention and crack resistance problem of Concrete Face Rockfill Dam.
For this reason, the invention provides a kind of rock and force pre-sedimentation construction method, comprise the steps:
1) water-filling of little foundation ditch: to little foundation ditch water filling, make little Water Level in Foundation Pit reach predetermined high water level by water pump;
2) large filling water in foundation pit: the water in little foundation ditch enters large foundation ditch by reverse osmosis gutter and dam body surface, meanwhile, control water pump to water filling in little foundation ditch, make water level in little foundation ditch maintain all the time predetermined high water level, when the water level of large foundation ditch reaches predetermined high water level, stop to water filling in little foundation ditch;
3) dam body of large foundation ditch soaks: the water level of large foundation ditch reaches after predetermined high water level, and the dam body of large foundation ditch is soaked 3~7 days;
4) draining of large foundation ditch: after the dam body of large foundation ditch soaks and finishes, by water pump, from the upstream of the building that upstream intercepts water in little foundation ditch, draw water, the water level of little foundation ditch reduces, make to form water-head between large foundation ditch and little foundation ditch, water in large foundation ditch infiltrates little foundation ditch by reverse osmosis gutter and dam body surface, the water level of little foundation ditch and large foundation ditch stops pumping for water pump while reducing to predetermined low water stage, completes the draining of large foundation ditch.
Above-mentioned reverse osmosis gutter is arranged in the toe board of dam body bottom.
Above-mentioned predetermined high water level is the high tailrace level in dam body downstream.
Above-mentioned predetermined low water stage is reverse osmosis gutter elevation.
On above-mentioned dam body, be provided with a plurality of osmometers.
In the drainage procedure of above-mentioned large foundation ditch, control the water-head between large foundation ditch and little foundation ditch, make the bed course district of dam body not produce seepage failure and cave in.
Beneficial effect of the present invention: this rock provided by the invention forces the settlement reservation of pre-sedimentation construction method after dam has filled, before construction of concrete face slab in the phase, the dam body below high tailrace level elevation in loose rock dam downstream is soaked, reduced the distortion of dam body after construction of concrete face slab, thereby reduced the impact of this distortion for concrete slab, for cracking resistance, the coming to nothing of concrete slab of control of concrete slab are laid a good foundation; Meanwhile, due to the enforcement of pre-sedimentation techniques, can shorten the settlement reservation phase, for concrete slab is constructed and created conditions in advance; And then created condition for the generating in advance of engineering, and lay a good foundation for improving the economic benefit of engineering.
Below with reference to accompanying drawing, the present invention is described in further details.
Accompanying drawing explanation
Fig. 1 is the schematic diagram that rock is forced pre-sedimentation construction method.
Description of reference numerals: 1, concrete slab; 2, bed course district; 3, toe board; 4, reverse osmosis gutter; 5, little foundation ditch; 6, building intercepts water in upstream; 7, large foundation ditch; 8, building intercepts water in downstream.
The specific embodiment
Embodiment 1:
In order to overcome the technical barrier of rock, solve technically the panel crack prevention and crack resistance problem of Concrete Face Rockfill Dam, the present embodiment provides a kind of rock as shown in Figure 1 to force pre-sedimentation construction method, utilize the building that intercepts water of dam body upstream and downstream, as: upstream cofferdam, downstream cofferdam or block the permanent concrete structure of foundation ditch, form water storage foundation ditch with two sides side slope, wherein, the foundation ditch intercepting water between building 6 in the concrete slab 1 of dam body upstream face and upstream is little foundation ditch 5, the foundation ditch intercepting water between building 8 in the concrete slab 1 of dam body upstream face and downstream is large foundation ditch 7, its detailed process work progress comprises the steps:
1) water-filling of little foundation ditch 5: to little foundation ditch 5 water fillings, make little foundation ditch 5 water levels reach predetermined high water level by water pump; And the wherein said predetermined high water level high tailrace level that is dam body downstream; The required time of water filling is determined according to water pump size and little foundation ditch 5 capacity selected.
2) water-filling of large foundation ditch 7: the water in little foundation ditch 5 enters large foundation ditch 7 by reverse osmosis gutter 4 and dam body surface, simultaneously, control water pump to the interior water filling of little foundation ditch 5, make the interior water level of little foundation ditch 5 maintain all the time predetermined high water level, when the water level of large foundation ditch 7 reaches predetermined high water level, stop to the interior water filling of little foundation ditch 5; Wherein, described reverse osmosis gutter 4 is arranged in the toe board 3 of dam body bottom.
3) dam body of large foundation ditch 7 soaks: the water level of large foundation ditch 7 reaches after predetermined high water level, the dam body of large foundation ditch 7 is soaked 3~7 days, due in large foundation ditch 7 water filling processes, bottom dam body is all immersed in water all the time, and large foundation ditch 7 water-fillings soak 3~7 day time after finishing again, the stockpile of extent of flooding is fully soaked, allow dam body fully soaks, sedimentation, to reach the object of the pre-sedimentation of immersion of expection, simultaneously, there is sedimentation and deformation in stockpile, thereby can reduce the humidifying distortion of stockpile after retaining under deadweight condition.
4) draining of large foundation ditch 7: after the dam body of large foundation ditch 7 soaks and finishes, by water pump, from 5 upstreams of upstream intercepting water building 6 in little foundation ditch, draw water, the water level of little foundation ditch 5 reduces, make to form water-head between large foundation ditch 7 and little foundation ditch 5, water in large foundation ditch 7 infiltrates little foundation ditch 5 by reverse osmosis gutter 4 and dam body surface, the water level of little foundation ditch 5 and large foundation ditch 7 stops pumping for water pump while reducing to predetermined low water stage, completes the draining of large foundation ditch 7; Wherein, described predetermined low water stage is reverse osmosis gutter 4 elevations.
This rock that the present embodiment provides forces the settlement reservation of pre-sedimentation construction method after dam has filled, before concrete slab 1 construction in the phase, the dam body below high tailrace level elevation in loose rock dam downstream is soaked, reduced the distortion of the rear dam body of concrete slab 1 construction, thereby reduced the impact of this distortion for concrete slab 1, for cracking resistance, the coming to nothing of concrete slab 1 of control of concrete slab 1 are laid a good foundation.
Embodiment 2:
On the basis of embodiment 1, on described dam body, be provided with a plurality of osmometers, in the water-filling of large foundation ditch 7 and the drainage procedure of large foundation ditch 7, for monitoring dam osmotic pressure situation everywhere, to can adjust scheme in time.
In addition, in the drainage procedure of large foundation ditch 7, control the water-head between large foundation ditch 7 and little foundation ditch 5, make the bed course district 2 of dam body not produce seepage failure and cave in; And water level extent, according to 8.2,8.3 cited formula in 10.2,10.3 cited formula or SL274-2001 < < rolling earth-rock dam design specifications > > in DL/T5395-2007 < < rolling earth-rock dam design specifications > >, the parameter that employing Practical Project is corresponding, supposes that different water-heads carries out tentative calculation between large foundation ditch 7 and little foundation ditch 5.According to result of calculation, choose bed course district 2 and do not produce seepage failure and cave in corresponding Series of Water potential difference, and the maximum value of choosing this Series of Water potential difference is as final definite water-head.Generally, when 2 surfaces, bed course district adopt mortar or Extrusion Wall protection, water-head is 1m left and right.
When carrying out the draining of large foundation ditch 7, observe the infiltration face on dam body surface, if find, there are the phenomenon appearance such as loosening, fragmentation is extruded in bed course district 2, and stop in time the draining to large foundation ditch 7, avoids the generation seepage deformation of dam body surface, localized landslip to destroy.
And the scheme for irrigation and drainage of drawing water of large foundation ditch 7 is corresponding volume and times of pumping of drawing water of the every decline 0.1m of water level during according to the pumpage of water pump and large foundation ditch 7, the shape of little foundation ditch 5, the large foundation ditch 7 of calculation of capacity and little foundation ditch 5 interior different water level, according to the water-head of large foundation ditch 7 and little foundation ditch 5, calculate the Seepage flow time between large foundation ditch 7 and little foundation ditch 5 again, in the water-head between large foundation ditch 7 and little foundation ditch 5, do not destroy and formulate under the prerequisite in bed course district 2.
The settlement reservation of the present invention after dam has filled, before construction of concrete face slab is in the phase, the dam body below high tailrace level elevation in loose rock dam downstream is soaked, reduced the distortion of dam body after construction of concrete face slab, thereby reduced the impact of this distortion for concrete slab, for cracking resistance, the coming to nothing of concrete slab of control of concrete slab are laid a good foundation; Meanwhile, due to the enforcement of pre-sedimentation techniques, can shorten the settlement reservation phase, for concrete slab is constructed and created conditions in advance; And then created condition for the generating in advance of engineering, and lay a good foundation for improving the economic benefit of engineering.
More than exemplifying is only to illustrate of the present invention, does not form the restriction to protection scope of the present invention, within the every and same or analogous design of the present invention all belongs to protection scope of the present invention.

Claims (6)

1. rock is forced a pre-sedimentation construction method, it is characterized in that: comprise the steps:
1) water-filling of little foundation ditch (5): to little foundation ditch (5) water filling, make little foundation ditch (5) water level reach predetermined high water level by water pump;
2) large foundation ditch (7) water-filling: the water in little foundation ditch (5) enters large foundation ditch (7) by reverse osmosis gutter (4) and dam body surface, simultaneously, control water pump to the interior water filling of little foundation ditch (5), make the interior water level of little foundation ditch (5) maintain all the time predetermined high water level, when the water level of large foundation ditch (7) reaches predetermined high water level, stop to the interior water filling of little foundation ditch (5);
3) dam body of large foundation ditch (7) soaks: the water level of large foundation ditch (7) reaches after predetermined high water level, and the dam body of large foundation ditch (7) is soaked 3~7 days;
4) draining of large foundation ditch (7): after the dam body of large foundation ditch (7) soaks and finishes, by water pump, from the upstream of the building (6) that upstream intercepts water in little foundation ditch (5), draw water, the water level of little foundation ditch (5) reduces, make to form water-head between large foundation ditch (7) and little foundation ditch (5), water in large foundation ditch (7) infiltrates little foundation ditch (5) by reverse osmosis gutter (4) and dam body surface, the water level of little foundation ditch (5) and large foundation ditch (7) stops pumping for water pump while reducing to predetermined low water stage, completes the draining of large foundation ditch (7).
2. rock as claimed in claim 1 is forced pre-sedimentation construction method, it is characterized in that: described reverse osmosis gutter (4) is arranged in the toe board (3) of dam body bottom.
3. rock as claimed in claim 1 is forced pre-sedimentation construction method, it is characterized in that: described predetermined high water level is the high tailrace level in dam body downstream.
4. rock as claimed in claim 1 is forced pre-sedimentation construction method, it is characterized in that: described predetermined low water stage is reverse osmosis gutter (4) elevation.
5. rock as claimed in claim 1 is forced pre-sedimentation construction method, it is characterized in that: on described dam body, be provided with a plurality of osmometers.
6. rock as claimed in claim 1 is forced pre-sedimentation construction method, it is characterized in that: in the drainage procedure of described large foundation ditch (7), control the water-head between large foundation ditch (7) and little foundation ditch (5), make the bed course district (2) of dam body not produce seepage failure and cave in.
CN201410399139.8A 2014-08-14 2014-08-14 Enforced preliminary settlement construction method of concrete faced rockfill dam Pending CN104196010A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410399139.8A CN104196010A (en) 2014-08-14 2014-08-14 Enforced preliminary settlement construction method of concrete faced rockfill dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410399139.8A CN104196010A (en) 2014-08-14 2014-08-14 Enforced preliminary settlement construction method of concrete faced rockfill dam

Publications (1)

Publication Number Publication Date
CN104196010A true CN104196010A (en) 2014-12-10

Family

ID=52081363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410399139.8A Pending CN104196010A (en) 2014-08-14 2014-08-14 Enforced preliminary settlement construction method of concrete faced rockfill dam

Country Status (1)

Country Link
CN (1) CN104196010A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111811468A (en) * 2020-09-04 2020-10-23 四川大学 Prediction method for settlement deformation of high core rock-fill dam
CN113091848A (en) * 2021-04-08 2021-07-09 中国电建集团贵阳勘测设计研究院有限公司 Method and device for measuring water level of concrete faced rockfill dam reservoir

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100016667A (en) * 2008-08-05 2010-02-16 주식회사 엠. 에이. 피. 코리아 Soil improvement method of soft clay using spread method landfill cover soil on the water surface
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
CN202194147U (en) * 2011-04-29 2012-04-18 华北水利水电学院 Tailing dam
CN103572747A (en) * 2013-11-15 2014-02-12 付文堂 Method for burying drainage-seepage body of reverse filtering pipe in tailing dam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100016667A (en) * 2008-08-05 2010-02-16 주식회사 엠. 에이. 피. 코리아 Soil improvement method of soft clay using spread method landfill cover soil on the water surface
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
CN202194147U (en) * 2011-04-29 2012-04-18 华北水利水电学院 Tailing dam
CN103572747A (en) * 2013-11-15 2014-02-12 付文堂 Method for burying drainage-seepage body of reverse filtering pipe in tailing dam

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张伟等: "积石峡水电站面板堆石坝湿化变形控制研究", 《人民黄河》, vol. 36, no. 3, 31 March 2014 (2014-03-31) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111811468A (en) * 2020-09-04 2020-10-23 四川大学 Prediction method for settlement deformation of high core rock-fill dam
CN113091848A (en) * 2021-04-08 2021-07-09 中国电建集团贵阳勘测设计研究院有限公司 Method and device for measuring water level of concrete faced rockfill dam reservoir

Similar Documents

Publication Publication Date Title
CN205134283U (en) Base concrete panel rock -fill dam
CN204023501U (en) A kind of reinforcement Anti-seeping technology structure for earth and rockfill dam
CN101644041B (en) Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof
CN105297685B (en) A kind of pedestal CFRD and its construction method
CN103526721A (en) Permeable spur dike with pile foundations
CN202989867U (en) Junked tire protective surface combined steel-structure check dam
CN104196010A (en) Enforced preliminary settlement construction method of concrete faced rockfill dam
CN202730785U (en) Anti-floating blind ditch water drainage structure for underground structure
CN101476309A (en) Dam body prepressing inverted filling construction method for ultra-high concrete panel rock-fill dam
CN103061351B (en) Prevent the device that basement bottom board swells, seeps water
CN204023520U (en) A kind of dam body water draining structure improving loose rock dam shock resistance
CN203808020U (en) Concrete face rock-fill dam structure with mudstone damming materials
CN202787282U (en) Step type wet masonry rock berm roadbed side slope
CN203530921U (en) Water-permeable pile foundation spur dike
CN203795389U (en) Dam body sectioning structure of concrete face rockfill dam with large overburden depth
CN105970882A (en) Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN207484405U (en) A kind of concrete cut
CN204676491U (en) A kind of reservoir seepage-proofing structure
CN201598645U (en) Advanced water stop post-pouring belt for base soleplate
CN103758081A (en) Floating self-adjustment water-stopping dam
CN104047273B (en) Power station dissipation and scouring wall and construction method thereof
CN203924150U (en) EPR deformation joint is repaired water-stopping structure
CN206768890U (en) A kind of reinforcement operation platform of the building foundation of river bank
CN104695392A (en) Plunge pool structure used for high arch dam, narrow canyon and large-flow flood discharge hole
CN202519689U (en) Bearing steel plate earth-rock combination cofferdam structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Cai Xinhe

Inventor after: Xie Xiaoping

Inventor after: Yang Cunlong

Inventor after: Lei Yan

Inventor after: Wang Side

Inventor after: Wei Jianzheng

Inventor after: Su Xiaojun

Inventor after: Zhang Wei

Inventor before: Cai Xinhe

Inventor before: Lei Yan

Inventor before: Wei Jianzheng

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160317

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 survey and Design Institute of the northwest department of science and technology

Applicant after: Co., Ltd of northwest survey and design research institute of electricity Jian group of China

Applicant after: The Yellow River Upstream Hydropower Development Co., Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 survey and Design Institute of the northwest department of science and technology

Applicant before: Co., Ltd of northwest survey and design research institute of electricity Jian group of China

RJ01 Rejection of invention patent application after publication

Application publication date: 20141210

RJ01 Rejection of invention patent application after publication