A kind of permeable pile foundation groynes
Technical field
The present invention relates to a kind of pile foundation groynes, especially relate to a kind of permeable pile foundation groynes, belong to Hydraulic and Hydro-Power Engineering Building Design technical field of construction.
Background technology
At present in Hydraulic and Hydro-Power Engineering, for fear of or alleviate current to bank slope and toe thereof or the scour to other buildings and basis thereof, groynes need be set changes the direction of a stream of water, but due to bank slope toe or other building foundation erosion resistibilities poor, direct fill block stone throwing on this basis, code is built reinforced gabion, the groynes of the formation such as concreting structure all easily collapses along with basic scour, do not reach the object of the protection bank slope of changing the direction of a stream of water, thereby bring more serious consequence, as produce economic loss or adjacent building and collapse and bring economic loss and social negative effect etc.Therefore, adopt permeable pile foundation groynes, get final product underpinning, improve this basic erosion resistibility, can guarantee again to change the direction of a stream of water, reach the anti-brush object of drawing.
Summary of the invention
Technical problem to be solved by this invention is: providing a kind of can effectively reinforce not meeting the basis of antiscour requirement, improves the permeable pile foundation groynes of its erosion resistibility.
For solving the problems of the technologies described above adopted technical scheme, be: a kind of permeable pile foundation groynes, comprise bank slope be connected with the toe of this bank slope do not meet the basis that antiscour requires, also comprise the discontinuous reinforcing pile group consisting of at least three reinforcing piles, each root reinforcing pile of described discontinuous reinforcing pile group is all vertically arranged in and described does not meet in the basis that antiscour requires.
Further, described reinforcing pile is for be pressed into the described precast concrete pile not meeting in the basis that antiscour requires by plant equipment, or for cast-in-place at the described Grouting not meeting in the basis that antiscour requires.
Be further, described permeable pile foundation groynes also comprises concrete dam facing, each root reinforcing pile of described discontinuous reinforcing pile group all has an external part, described external part protrudes upward the described basic upper surface that antiscour requires that do not meet, and described concrete dam facing is supported on the top of described external part.
Further, the cast-in-place connection of external part of described concrete dam facing and described each root reinforcing pile.
Further, at the upstream side of described concrete dam facing, be also furnished with waterwall, on described waterwall, be provided with the water hole along water (flow) direction.
Further, described waterwall and described concrete dam facing are structure as a whole.
Further, the end of the end of described waterwall and described concrete dam facing is connected with bank slope or the bank slope toe of corresponding position respectively.
The invention has the beneficial effects as follows: owing to having arranged the discontinuous reinforcing pile group being formed by least three reinforcing piles described in not meeting the basis that antiscour requires, like this, by each root reinforced column of described discontinuous reinforcing pile group, can by described do not meet basis that antiscour requires connect into one firmly whole, realization does not meet to described basic effective reinforcing that antiscour requires, and reaches and improves the described basic erosion resistibility that antiscour requires that do not meet.
Accompanying drawing explanation
Fig. 1 is the layout plan of a kind of permeable pile foundation groynes of the present invention;
Fig. 2 is the 1-1 sectional view of Fig. 1;
Fig. 3 is the 2-2 sectional view of Fig. 2.
In figure, be labeled as: bank slope 1, the basis 2 that does not meet antiscour requirement, reinforcing pile 3, discontinuous reinforcing pile group 4, concrete dam facing 5, external part 6, waterwall 7, water hole 8.
The specific embodiment
As shown in Figure 1, Figure 2 and shown in Fig. 3, be a kind of can effectively reinforcing not meeting the basis of antiscour requirement provided by the invention, improve the permeable pile foundation groynes of its erosion resistibility.Described permeable pile foundation groynes comprises that bank slope 1 is connected with toe with this bank slope 1 does not meet the basis 2 that antiscour requires, also comprise the discontinuous reinforcing pile group 4 consisting of at least three reinforcing piles 3, each root reinforcing pile 3 of described discontinuous reinforcing pile group 4 is all vertically arranged in and described does not meet in the basis 2 that antiscour requires.Owing to having arranged the discontinuous reinforcing pile group 4 being formed by least three reinforcing piles 3 described in not meeting the basis 2 that antiscour requires, like this, by each root reinforced column 3 of described discontinuous reinforcing pile group 4, can by described do not meet basis 2 that antiscour requires connect into one firmly whole, realization is to the described effective reinforcing that does not meet the basis 2 that antiscour requires, and reaches and improves the described basic erosion resistibility that antiscour requires that do not meet.
In above-mentioned embodiment, in order effectively to change the flow direction of current, with the degradation degree that does not meet the basis 2 that antiscour requires that alleviates that current pair are connected with the toe of described bank slope 1, each root reinforcing pile 3 of described discontinuous reinforcing pile group 4 is all arranged to an external part 6, and make described external part 6 protrude upward the described upper surface that does not meet the basis 2 that antiscour requires, and then a concrete dam facing 5 is set, make described concrete dam facing 5 be supported on the top of described external part 6; And described concrete dam facing 5 and the external part 6 of described each root reinforcing pile 3 are arranged to cast-in-place syndeton.Like this; the current that do not meet behind the basis 2 that antiscour requires described in the scour of bottom between each root reinforcing pile pass through between described discontinuous reinforcing pile group; reach the object that upsets current and loss flow energy, thereby protection bank slope and toe thereof or other buildings and basis thereof are not destroyed.
Further, in order to improve to greatest extent the ability of upset current and the loss flow energy of described permeable pile foundation groynes, and then described in improving, do not meet the erosion resistibility on the basis 2 of antiscour requirement, to protect bank slope and toe thereof or other buildings and basis thereof not to be destroyed, upstream side at described concrete dam facing 5 is also furnished with waterwall 7, is provided with the water hole 8 along water (flow) direction on described waterwall 7; And described waterwall 7 and described concrete dam facing 5 are structure as a whole; And then the end of the end of described waterwall 7 and described concrete dam facing 5 is connected with bank slope 1 or the bank slope toe of corresponding position respectively.Simultaneously, described concrete dam facing 5 and described concrete dam facing 5 are structure as a whole, the end of the end of described waterwall 7 and described concrete dam facing 5 is connected with bank slope 1 or the bank slope toe of corresponding position respectively, can also effectively improves intensity and the impact resistance of described permeable pile foundation groynes self.
In conjunction with existing bank slope ruggedized construction technology, described reinforcing pile 3 can be for being pressed into the described precast concrete pile not meeting in the basis 2 that antiscour requires by plant equipment, also can be for cast-in-place at the described Grouting not meeting in the basis 2 that antiscour requires.