CN106939579A - A kind of parallel pipe laying type permeable spur - Google Patents

A kind of parallel pipe laying type permeable spur Download PDF

Info

Publication number
CN106939579A
CN106939579A CN201710115208.1A CN201710115208A CN106939579A CN 106939579 A CN106939579 A CN 106939579A CN 201710115208 A CN201710115208 A CN 201710115208A CN 106939579 A CN106939579 A CN 106939579A
Authority
CN
China
Prior art keywords
dam
steel pipe
abutment
sheet pile
parallel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710115208.1A
Other languages
Chinese (zh)
Other versions
CN106939579B (en
Inventor
陈斯煜
赵二峰
林潮宁
朱延涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201710115208.1A priority Critical patent/CN106939579B/en
Publication of CN106939579A publication Critical patent/CN106939579A/en
Application granted granted Critical
Publication of CN106939579B publication Critical patent/CN106939579B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment

Abstract

The invention discloses a kind of parallel pipe laying type permeable spur, by burying the steel-tube construction of multigroup connection and parallel arrangement in groynes dam body, steel pipe axis is projected in the horizontal plane has certain angle with the axis of dam, is distributed in " eight " font;Dam body bottom is provided with the concrete sheet-piling for surrounding arrangement, and upstream and downstream side and the axis of dam on dam are arranged in parallel, be arranged vertically at abutment with the axis of dam.Compared with existing permeable spur, the present invention can preferably stationary flow, weaken whirlpool behind dam, reduce washing away for abutment part material, while the bottom flow velocity of current at groynes downstream can also be reduced, promote sediment settlement to make beach to deposit.

Description

A kind of parallel pipe laying type permeable spur
Technical field
The invention belongs to river improvement field, and in particular to a kind of parallel pipe laying type permeable spur structure.
Background technology
Groynes is the class hydraulic structure for river regulation, and its riverbank one end connects with embankment in " fourth " font, because And gain the name " groynes ".Groynes has a variety of river regulation functions, and on the one hand it can protect riverbank not flow direct erosion to avoid Brush destruction is drawn, while it also has improvement navigation channel, protects river facies and safeguard a variety of functions such as Ecology variation.Groynes is divided into impermeable Water groynes and permeable spur.Existing permeable spur is generally hydraulic sheeting permeable spur and well stanchion permeable spur, and both are saturating Water groynes is compared to non-permeable spur, and its water flow structure is increasingly complex, and main flow can not only produce vertical pivot whirlpool after abutment separation Whirlpool, can also produce the flat axle whirlpool in nearly bottom.Lean on the flow velocity into Ba Zhouduanmianchu larger in downstream from the current passed through between dam body, one Aspect can cause channel scour serious, threaten engineering structure safety, on the other hand reduce model to the backwater zone behind dam and flow velocity Enclose and cause unstable interference, beach is made in influence sediment settlement and alluvial.
In the existing technical scheme on permeable spur, authorized patent of invention ZL201310521749.6 is used It is that some groups of sections are square, on the one hand the permeable hole of horizontal direction arrangement can cause permeable hole to produce stress concentration phenomenon, The structure safety of groynes is threatened, on the other hand, horizontally disposed permeable hole is poor for the energy dissipating effect of saturating dam current.
The content of the invention
For the defect of existing permeable spur, washed away the invention provides a kind of be able to can reduce at abutment in minimum degree, Weaken whirlpool behind dam, stablize permeable current, while reducing the parallel pipe laying type permeable spur of reinforcing of groynes downstream bottom flow velocity.
In order to solve the above technical problems, the technical solution adopted in the present invention is:
A kind of parallel pipe laying type permeable spur.The groynes includes dam body, sheet pile, abutment linking beam and abutment base plate, its In,
The dam body is entity structure, and it is semicircle that abutment, which is overlooked, overall in round table-like;The sheet pile is arranged at groynes dam The bottom of body, wherein, it is arranged in parallel in sheet pile described in the upstream side and downstream of dam body and the axis of dam, and dam heel and dam site phase Connect, at abutment, sheet pile is arranged vertically with the axis of dam, and abutment circular arc substrate and sheet pile are tangent, vertically adjacent to sheet pile between Connected by abutment linking beam, improve the stability of the groynes dam foundation, the abutment linking beam is arranged at the bottom of abutment base plate;
Steel pipe, one group two-by-two of the steel pipe are embedded with inside the dam body, every group of steel pipe is in horizontal plane projection rule "eight" shape, is parallel to each other for two layers, vertical spacing is at least twice of caliber in perpendicular, above and below two adjacent groups steel pipe; In one group of steel pipe, the steel pipe nozzle horizontal range of upstream side two is more than the steel pipe nozzle horizontal range of downstream two.
Preferably, joint is left on the top of sheet pile, sheet pile is connected with the groynes dam foundation by concrete cast-in-situ.
Abutment linking beam sheet pile vertical with adjacent two is connected in 45 degree of angles, the abutment base plate and sheet pile and abutment The cast-in-place connection of linking beam.
Wherein, the diameter of steel tube is less than 1m, more than 3D, and D is the maximum grain size of gravel that is likely to occur in the section of place.
Preferably, it is in 10 ° to 30 ° of angle that the axis of the steel pipe is projected with Parallel to the flow direction in the horizontal plane, described Projection and horizontal direction of the axis of steel pipe in perpendicular are in the angle between 5 ° to 20 °.
More specifically, upper strata steel pipe nozzle is higher in upstream face side, it is relatively low in downstream face side;Described lower floor's steel pipe The mouth of pipe is relatively low in upstream face side, higher in downstream face side, so as to form staggeredly pipe laying.
Preferably, the depth of water at the place of the steel pipe upstream face spout tops position should be greater than critical submergence depth, with present Trip face steel pipe nozzle bottom position should be at least above more than dam foundation face 1m, wherein, critical depth isD was water The internal diameter of steel pipe, unit m;V is the maximal rate that place river is likely to occur, m/s;C is relevant with water inlet geometry Parameter, general reference《Intake of hydropower station design specification》Specified in value, typically take 0.55, typically take 0.55.
Preferably, the sheet pile is generally reinforced concrete sheet pile.Preferably mixed using impact-resisting wear-resisting near steel pipe Miscellaneous flyash concrete.
The beneficial effects of the present invention are:The present invention is projected in " eight " font by embedded parallel arrangement in horizontal plane Pipe laying group, is allowed to compared to common permeable spur, the present invention can be more preferably to saturating dam current energy dissipating, and stationary flow weakens whirlpool behind dam Whirlpool, while reducing groynes downstream bottom flow velocity, promotes sediment settlement to make beach to deposit.A kind of pipe laying type permeable spur, passes through three The cast-in-place connection of sheet pile foundation and linking beam that bread cloth is put, substantially increases resistance to overturning of the groynes in dynamic water and durable Property.
Brief description of the drawings
Fig. 1 is the arrangement top view of embodiment of the present invention groynes;
Fig. 2 is embodiment of the present invention groynes upstream side elevational view;
Fig. 3 is embodiment of the present invention groynes downstream side elevational view;
Fig. 4 is embodiment of the present invention groynes dam foundation schematic diagram;
Fig. 5 is embodiment of the present invention groynes according to A-A profiles in Fig. 1.
Embodiment
Describe the embodiment of patent of the present invention in detail below in conjunction with accompanying drawing, the protection domain of patent of the present invention is not It is limited only to the description of present embodiment.
The embodiment provides a kind of parallel pipe laying type permeable spur, it arranges top view and sectional view such as Fig. 1 With shown in Fig. 5.This pipe laying type permeable spur that interlocks includes concrete sheet-piling 1, the dam body 2 by being embedded with small-caliber steel pipe 3, abutment and connected Binder 4 and abutment base plate 5.
Dam body 2 is entity structure, and abutment is semicircle, overall in round table-like.The abutment contacts smooth with the water surface, excessively level It is suitable.Sheet pile 1 is concrete sheet-piling 1, and it is arranged in parallel in upstream and downstream side and the axis of dam, and dam heel and dam site connect.At abutment Vertical axis of dam arrangement, and abutment circular arc substrate and sheet pile 1 are tangent, vertically adjacent to sheet pile between connected by abutment linking beam 4, abutment linking beam is arranged at the bottom of abutment base plate 5.Joint 6 is left on concrete sheet-piling top, and sheet pile passes through with the groynes dam foundation Concrete cast-in-situ is connected.Wherein, abutment linking beam 4 is connected with two adjacent vertical plates stake 1 in 45 degree of angles.Abutment base plate 5 and plate Stake 1 and abutment linking beam 4 are connected by concrete cast-in-situ, so, and groynes dam body 2 and dam foundation sheet pile 1 be firm, and to be combined into one whole Body, can effectively be less than to flow the scour around for the dam foundation, improve groynes overall stability and durability.
The steel pipe 3 buried in dam body 2 arranges that the diameter of steel pipe 3 is in 0.5m between 1m approximately along Parallel to the flow direction.The steel The axis of pipe 3 is projected with Parallel to the flow direction in 10 ° to 30 ° of angle in the horizontal plane, and the axis of the steel pipe 3 is in perpendicular Interior projection and horizontal direction are in the angle between 5 ° to 20 °.One group two-by-two of the steel pipe 3, is regularly distributed in "eight" shape In dam.Every group of steel pipe about 3 parallel layered laminate bury.When to flow, a part of current are stopped by groynes dam body 2, pass through abutment Bypass, another part current import groynes downstream by steel pipe 3.Due to steel pipe, group carries the elevation angle, and every group of steel pipe 3 is in water Projected in plane in "eight" shape wherein, in one group of steel pipe, the steel pipe opening horizontal range of upstream side two is more than the steel pipe opening of downstream two Horizontal range, sweeps along the current of silt to enter after the pipe laying with positive slope, velocity in pipes slows down.Gushed in current from the downstream mouth of pipe After going out, the current in one group of steel pipe are after collision efficiency, and water velocity is greatly reduced, so that sediment settlement, alluvial.Steel pipe 3 mouths of pipe are relatively low in upstream face side, higher in downstream face side, and the upstream face spout tops of steel pipe 3 should be greater than away from water surface depth Critical submergence depth, while downstream face steel pipe nozzle bottom position should be at least above more than dam foundation face 1m, wherein, critical depth isD was the internal diameter of water steel pipe, unit m;V is the maximal rate that place river is likely to occur, m/s;C is with entering The relevant parameter of mouth of a river geometry, typically takes 0.55.So produce in upstream and downstream side to threaten groynes structure Air-breathing funnel-form whirlpool.
With reference to existing construction technology and material, sheet pile 1 is generally reinforced concrete sheet pile.Using anti-near the steel pipe Wearability is rushed preferably to adulterate flyash concrete.
In summary, the present invention passes through the steel-tube construction that multigroup connection is buried in groynes dam body and is arranged in parallel, steel pipe Axis is projected in the horizontal plane has certain angle with the axis of dam, is distributed, is allowed to compared to common permeable spur in " eight " font, The present invention can be more preferably to saturating dam current energy dissipating, and stationary flow weakens whirlpool behind dam, while reducing groynes downstream bottom flow velocity, promotees Enter sediment settlement and make beach to deposit.Pipe laying type permeable spur of the present invention, the sheet pile foundation put by three bread cloths and linking beam Cast-in-place connection, substantially increases resistance to overturning and durability of the groynes in dynamic water.

Claims (8)

1. a kind of parallel pipe laying type permeable spur, it is characterised in that the groynes includes dam body, sheet pile, abutment linking beam and dam Head base plate, wherein,
The dam body is in integrally round table-like, and abutment is semicircle;The sheet pile is arranged at the bottom of groynes dam body, wherein, on dam Sheet pile described in the upstream side and downstream of body is arranged in parallel with the axis of dam, and dam heel and dam site connect, at abutment, sheet pile and dam Axis is arranged vertically, and abutment circular arc substrate and sheet pile are tangent, vertically adjacent to sheet pile between connected by abutment linking beam, institute State the bottom that abutment linking beam is arranged at abutment base plate;
Steel pipe, one group two-by-two of the steel pipe are embedded with inside the dam body, every group of steel pipe is in " eight " in horizontal plane projection rule Font, is parallel to each other for two layers, vertical spacing is at least twice of caliber in perpendicular, above and below two adjacent groups steel pipe;At one group In steel pipe, the steel pipe nozzle horizontal range of upstream side two is more than the steel pipe nozzle horizontal range of downstream two.
2. parallel pipe laying type permeable spur according to claim 1, it is characterised in that leave joint on the top of sheet pile, Sheet pile is connected with the groynes dam foundation by concrete cast-in-situ.
3. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the abutment linking beam and adjacent two Vertical sheet pile is in 45 degree of angle connections, the abutment base plate and sheet pile and the cast-in-place connection of abutment linking beam.
4. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the diameter of steel tube is less than 1m, greatly In 3D, D is the maximum grain size of gravel being likely to occur in the section of place.
5. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the axis of the steel pipe is in horizontal plane Upper projection and Parallel to the flow direction are in 10 ° to 30 ° of angle, the projection and horizontal direction of the axis of the steel pipe in perpendicular In the angle between 5 ° to 20 °.
6. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the embedded steel pipe of institute is in tilted layout, The side of upstream face is relatively low, higher in the side of downstream face.
7. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the steel pipe upstream face spout tops The depth of water at the place of position should be greater than critical submergence depth, while downstream face steel pipe nozzle bottom position should be at least above dam foundation face 1m More than, wherein, critical depth isD was the internal diameter of water steel pipe, unit m;V is what place river was likely to occur Maximal rate, m/s;C is the parameter relevant with water inlet geometry.
8. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the sheet pile is armoured concrete slab Stake.
CN201710115208.1A 2017-02-28 2017-02-28 A kind of parallel pipe laying type permeable spur Expired - Fee Related CN106939579B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710115208.1A CN106939579B (en) 2017-02-28 2017-02-28 A kind of parallel pipe laying type permeable spur

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710115208.1A CN106939579B (en) 2017-02-28 2017-02-28 A kind of parallel pipe laying type permeable spur

Publications (2)

Publication Number Publication Date
CN106939579A true CN106939579A (en) 2017-07-11
CN106939579B CN106939579B (en) 2019-07-12

Family

ID=59469109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710115208.1A Expired - Fee Related CN106939579B (en) 2017-02-28 2017-02-28 A kind of parallel pipe laying type permeable spur

Country Status (1)

Country Link
CN (1) CN106939579B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761106A (en) * 2021-01-21 2021-05-07 交通运输部天津水运工程科学研究所 Ecological spur dike permeates water

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001248135A (en) * 2000-03-03 2001-09-14 Kawasaki Steel Corp Jacket structure
CN201459674U (en) * 2009-09-01 2010-05-12 黄河水利委员会黄河水利科学研究院 PHC tubular pile dam
JP2010180637A (en) * 2009-02-06 2010-08-19 Maeda Kosen Co Ltd Groin work and method of constructing the same
CN102154999A (en) * 2011-04-11 2011-08-17 水利部交通运输部国家能源局南京水利科学研究院 Diversion ecological spur dike
CN103526721A (en) * 2013-10-29 2014-01-22 中国水电顾问集团成都勘测设计研究院有限公司 Permeable spur dike with pile foundations
CN204626327U (en) * 2015-03-05 2015-09-09 上海勘测设计研究院有限公司 Groynes group under the condition of deep water low beach protects beach structure
CN205653749U (en) * 2016-05-11 2016-10-19 亿利首建生态科技有限公司 River course butyl dam structure and spur dike protection system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001248135A (en) * 2000-03-03 2001-09-14 Kawasaki Steel Corp Jacket structure
JP2010180637A (en) * 2009-02-06 2010-08-19 Maeda Kosen Co Ltd Groin work and method of constructing the same
CN201459674U (en) * 2009-09-01 2010-05-12 黄河水利委员会黄河水利科学研究院 PHC tubular pile dam
CN102154999A (en) * 2011-04-11 2011-08-17 水利部交通运输部国家能源局南京水利科学研究院 Diversion ecological spur dike
CN103526721A (en) * 2013-10-29 2014-01-22 中国水电顾问集团成都勘测设计研究院有限公司 Permeable spur dike with pile foundations
CN204626327U (en) * 2015-03-05 2015-09-09 上海勘测设计研究院有限公司 Groynes group under the condition of deep water low beach protects beach structure
CN205653749U (en) * 2016-05-11 2016-10-19 亿利首建生态科技有限公司 River course butyl dam structure and spur dike protection system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761106A (en) * 2021-01-21 2021-05-07 交通运输部天津水运工程科学研究所 Ecological spur dike permeates water

Also Published As

Publication number Publication date
CN106939579B (en) 2019-07-12

Similar Documents

Publication Publication Date Title
CN105507335B (en) Steel sheet-pile cofferdam foundation pit back cover structure and construction method
CN206706772U (en) A kind of double steel sheet pile supporting construction
CN106759066A (en) A kind of method of mountain area side slope water conservancy diversion energy dissipating prevention and control geological disaster
CN202577349U (en) Large immersed tube tunnel dry dock floor structure
CN104594287A (en) Ecological and economic bank protection structure
CN204282308U (en) A kind of lattice guest gabion composite material dam adapting to deep covering layer
CN106939580B (en) A kind of pipe laying type permeable spur that interlocks
CN213952260U (en) Cofferdam structure combining steel sheet pile and steel pipe pile
CN206956686U (en) A kind of hydraulic reclamation area gabion discharge opening
CN106939579A (en) A kind of parallel pipe laying type permeable spur
CN202450491U (en) Open type flood discharge structure at dam crest
CN205604186U (en) Clay core morals and manners material dam
CN204676485U (en) A kind of Eco-economic Type bank protection structure
CN101705668B (en) Damming water conservancy project construction structure constructed in flowing water and construction method thereof
CN203821306U (en) Flexible anti-scour protection pad
CN216041278U (en) Novel pile foundation scour prevention structure
CN105970882A (en) Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN205604273U (en) Last cofferdam of sandy silt
CN102828489B (en) System for arranging piles to fix riverbed main stream
CN205907658U (en) Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body
CN205475148U (en) River course truss -like draws anchor to prevent floating device
CN102425151A (en) Thickness-variable integral type anti-scour gabion for village residential house foundation
CN208934101U (en) A kind of pump lock foundation pit enclosure structure
CN206680947U (en) Steel water stone separates blocking dam
CN207988083U (en) The orthogonal anti-structure of drainning off floodwaters of Gobi Region solar energy optical-thermal place

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190712

CF01 Termination of patent right due to non-payment of annual fee