CN106939579A - A kind of parallel pipe laying type permeable spur - Google Patents
A kind of parallel pipe laying type permeable spur Download PDFInfo
- Publication number
- CN106939579A CN106939579A CN201710115208.1A CN201710115208A CN106939579A CN 106939579 A CN106939579 A CN 106939579A CN 201710115208 A CN201710115208 A CN 201710115208A CN 106939579 A CN106939579 A CN 106939579A
- Authority
- CN
- China
- Prior art keywords
- dam
- steel pipe
- abutment
- sheet pile
- parallel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 51
- 239000010959 steel Substances 0.000 claims abstract description 51
- 238000011144 upstream manufacturing Methods 0.000 claims abstract description 16
- 239000004567 concrete Substances 0.000 claims abstract description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 16
- 238000011065 in-situ storage Methods 0.000 claims description 4
- 239000000758 substrate Substances 0.000 claims description 3
- 239000013049 sediment Substances 0.000 abstract description 5
- 238000010276 construction Methods 0.000 abstract description 3
- 239000000463 material Substances 0.000 abstract description 2
- 238000005406 washing Methods 0.000 abstract 1
- 238000009738 saturating Methods 0.000 description 4
- 235000008429 bread Nutrition 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000010881 fly ash Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 208000035126 Facies Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011230 binding agent Substances 0.000 description 1
- 235000013339 cereals Nutrition 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
Abstract
The invention discloses a kind of parallel pipe laying type permeable spur, by burying the steel-tube construction of multigroup connection and parallel arrangement in groynes dam body, steel pipe axis is projected in the horizontal plane has certain angle with the axis of dam, is distributed in " eight " font;Dam body bottom is provided with the concrete sheet-piling for surrounding arrangement, and upstream and downstream side and the axis of dam on dam are arranged in parallel, be arranged vertically at abutment with the axis of dam.Compared with existing permeable spur, the present invention can preferably stationary flow, weaken whirlpool behind dam, reduce washing away for abutment part material, while the bottom flow velocity of current at groynes downstream can also be reduced, promote sediment settlement to make beach to deposit.
Description
Technical field
The invention belongs to river improvement field, and in particular to a kind of parallel pipe laying type permeable spur structure.
Background technology
Groynes is the class hydraulic structure for river regulation, and its riverbank one end connects with embankment in " fourth " font, because
And gain the name " groynes ".Groynes has a variety of river regulation functions, and on the one hand it can protect riverbank not flow direct erosion to avoid
Brush destruction is drawn, while it also has improvement navigation channel, protects river facies and safeguard a variety of functions such as Ecology variation.Groynes is divided into impermeable
Water groynes and permeable spur.Existing permeable spur is generally hydraulic sheeting permeable spur and well stanchion permeable spur, and both are saturating
Water groynes is compared to non-permeable spur, and its water flow structure is increasingly complex, and main flow can not only produce vertical pivot whirlpool after abutment separation
Whirlpool, can also produce the flat axle whirlpool in nearly bottom.Lean on the flow velocity into Ba Zhouduanmianchu larger in downstream from the current passed through between dam body, one
Aspect can cause channel scour serious, threaten engineering structure safety, on the other hand reduce model to the backwater zone behind dam and flow velocity
Enclose and cause unstable interference, beach is made in influence sediment settlement and alluvial.
In the existing technical scheme on permeable spur, authorized patent of invention ZL201310521749.6 is used
It is that some groups of sections are square, on the one hand the permeable hole of horizontal direction arrangement can cause permeable hole to produce stress concentration phenomenon,
The structure safety of groynes is threatened, on the other hand, horizontally disposed permeable hole is poor for the energy dissipating effect of saturating dam current.
The content of the invention
For the defect of existing permeable spur, washed away the invention provides a kind of be able to can reduce at abutment in minimum degree,
Weaken whirlpool behind dam, stablize permeable current, while reducing the parallel pipe laying type permeable spur of reinforcing of groynes downstream bottom flow velocity.
In order to solve the above technical problems, the technical solution adopted in the present invention is:
A kind of parallel pipe laying type permeable spur.The groynes includes dam body, sheet pile, abutment linking beam and abutment base plate, its
In,
The dam body is entity structure, and it is semicircle that abutment, which is overlooked, overall in round table-like;The sheet pile is arranged at groynes dam
The bottom of body, wherein, it is arranged in parallel in sheet pile described in the upstream side and downstream of dam body and the axis of dam, and dam heel and dam site phase
Connect, at abutment, sheet pile is arranged vertically with the axis of dam, and abutment circular arc substrate and sheet pile are tangent, vertically adjacent to sheet pile between
Connected by abutment linking beam, improve the stability of the groynes dam foundation, the abutment linking beam is arranged at the bottom of abutment base plate;
Steel pipe, one group two-by-two of the steel pipe are embedded with inside the dam body, every group of steel pipe is in horizontal plane projection rule
"eight" shape, is parallel to each other for two layers, vertical spacing is at least twice of caliber in perpendicular, above and below two adjacent groups steel pipe;
In one group of steel pipe, the steel pipe nozzle horizontal range of upstream side two is more than the steel pipe nozzle horizontal range of downstream two.
Preferably, joint is left on the top of sheet pile, sheet pile is connected with the groynes dam foundation by concrete cast-in-situ.
Abutment linking beam sheet pile vertical with adjacent two is connected in 45 degree of angles, the abutment base plate and sheet pile and abutment
The cast-in-place connection of linking beam.
Wherein, the diameter of steel tube is less than 1m, more than 3D, and D is the maximum grain size of gravel that is likely to occur in the section of place.
Preferably, it is in 10 ° to 30 ° of angle that the axis of the steel pipe is projected with Parallel to the flow direction in the horizontal plane, described
Projection and horizontal direction of the axis of steel pipe in perpendicular are in the angle between 5 ° to 20 °.
More specifically, upper strata steel pipe nozzle is higher in upstream face side, it is relatively low in downstream face side;Described lower floor's steel pipe
The mouth of pipe is relatively low in upstream face side, higher in downstream face side, so as to form staggeredly pipe laying.
Preferably, the depth of water at the place of the steel pipe upstream face spout tops position should be greater than critical submergence depth, with present
Trip face steel pipe nozzle bottom position should be at least above more than dam foundation face 1m, wherein, critical depth isD was water
The internal diameter of steel pipe, unit m;V is the maximal rate that place river is likely to occur, m/s;C is relevant with water inlet geometry
Parameter, general reference《Intake of hydropower station design specification》Specified in value, typically take 0.55, typically take 0.55.
Preferably, the sheet pile is generally reinforced concrete sheet pile.Preferably mixed using impact-resisting wear-resisting near steel pipe
Miscellaneous flyash concrete.
The beneficial effects of the present invention are:The present invention is projected in " eight " font by embedded parallel arrangement in horizontal plane
Pipe laying group, is allowed to compared to common permeable spur, the present invention can be more preferably to saturating dam current energy dissipating, and stationary flow weakens whirlpool behind dam
Whirlpool, while reducing groynes downstream bottom flow velocity, promotes sediment settlement to make beach to deposit.A kind of pipe laying type permeable spur, passes through three
The cast-in-place connection of sheet pile foundation and linking beam that bread cloth is put, substantially increases resistance to overturning of the groynes in dynamic water and durable
Property.
Brief description of the drawings
Fig. 1 is the arrangement top view of embodiment of the present invention groynes;
Fig. 2 is embodiment of the present invention groynes upstream side elevational view;
Fig. 3 is embodiment of the present invention groynes downstream side elevational view;
Fig. 4 is embodiment of the present invention groynes dam foundation schematic diagram;
Fig. 5 is embodiment of the present invention groynes according to A-A profiles in Fig. 1.
Embodiment
Describe the embodiment of patent of the present invention in detail below in conjunction with accompanying drawing, the protection domain of patent of the present invention is not
It is limited only to the description of present embodiment.
The embodiment provides a kind of parallel pipe laying type permeable spur, it arranges top view and sectional view such as Fig. 1
With shown in Fig. 5.This pipe laying type permeable spur that interlocks includes concrete sheet-piling 1, the dam body 2 by being embedded with small-caliber steel pipe 3, abutment and connected
Binder 4 and abutment base plate 5.
Dam body 2 is entity structure, and abutment is semicircle, overall in round table-like.The abutment contacts smooth with the water surface, excessively level
It is suitable.Sheet pile 1 is concrete sheet-piling 1, and it is arranged in parallel in upstream and downstream side and the axis of dam, and dam heel and dam site connect.At abutment
Vertical axis of dam arrangement, and abutment circular arc substrate and sheet pile 1 are tangent, vertically adjacent to sheet pile between connected by abutment linking beam
4, abutment linking beam is arranged at the bottom of abutment base plate 5.Joint 6 is left on concrete sheet-piling top, and sheet pile passes through with the groynes dam foundation
Concrete cast-in-situ is connected.Wherein, abutment linking beam 4 is connected with two adjacent vertical plates stake 1 in 45 degree of angles.Abutment base plate 5 and plate
Stake 1 and abutment linking beam 4 are connected by concrete cast-in-situ, so, and groynes dam body 2 and dam foundation sheet pile 1 be firm, and to be combined into one whole
Body, can effectively be less than to flow the scour around for the dam foundation, improve groynes overall stability and durability.
The steel pipe 3 buried in dam body 2 arranges that the diameter of steel pipe 3 is in 0.5m between 1m approximately along Parallel to the flow direction.The steel
The axis of pipe 3 is projected with Parallel to the flow direction in 10 ° to 30 ° of angle in the horizontal plane, and the axis of the steel pipe 3 is in perpendicular
Interior projection and horizontal direction are in the angle between 5 ° to 20 °.One group two-by-two of the steel pipe 3, is regularly distributed in "eight" shape
In dam.Every group of steel pipe about 3 parallel layered laminate bury.When to flow, a part of current are stopped by groynes dam body 2, pass through abutment
Bypass, another part current import groynes downstream by steel pipe 3.Due to steel pipe, group carries the elevation angle, and every group of steel pipe 3 is in water
Projected in plane in "eight" shape wherein, in one group of steel pipe, the steel pipe opening horizontal range of upstream side two is more than the steel pipe opening of downstream two
Horizontal range, sweeps along the current of silt to enter after the pipe laying with positive slope, velocity in pipes slows down.Gushed in current from the downstream mouth of pipe
After going out, the current in one group of steel pipe are after collision efficiency, and water velocity is greatly reduced, so that sediment settlement, alluvial.Steel pipe
3 mouths of pipe are relatively low in upstream face side, higher in downstream face side, and the upstream face spout tops of steel pipe 3 should be greater than away from water surface depth
Critical submergence depth, while downstream face steel pipe nozzle bottom position should be at least above more than dam foundation face 1m, wherein, critical depth isD was the internal diameter of water steel pipe, unit m;V is the maximal rate that place river is likely to occur, m/s;C is with entering
The relevant parameter of mouth of a river geometry, typically takes 0.55.So produce in upstream and downstream side to threaten groynes structure
Air-breathing funnel-form whirlpool.
With reference to existing construction technology and material, sheet pile 1 is generally reinforced concrete sheet pile.Using anti-near the steel pipe
Wearability is rushed preferably to adulterate flyash concrete.
In summary, the present invention passes through the steel-tube construction that multigroup connection is buried in groynes dam body and is arranged in parallel, steel pipe
Axis is projected in the horizontal plane has certain angle with the axis of dam, is distributed, is allowed to compared to common permeable spur in " eight " font,
The present invention can be more preferably to saturating dam current energy dissipating, and stationary flow weakens whirlpool behind dam, while reducing groynes downstream bottom flow velocity, promotees
Enter sediment settlement and make beach to deposit.Pipe laying type permeable spur of the present invention, the sheet pile foundation put by three bread cloths and linking beam
Cast-in-place connection, substantially increases resistance to overturning and durability of the groynes in dynamic water.
Claims (8)
1. a kind of parallel pipe laying type permeable spur, it is characterised in that the groynes includes dam body, sheet pile, abutment linking beam and dam
Head base plate, wherein,
The dam body is in integrally round table-like, and abutment is semicircle;The sheet pile is arranged at the bottom of groynes dam body, wherein, on dam
Sheet pile described in the upstream side and downstream of body is arranged in parallel with the axis of dam, and dam heel and dam site connect, at abutment, sheet pile and dam
Axis is arranged vertically, and abutment circular arc substrate and sheet pile are tangent, vertically adjacent to sheet pile between connected by abutment linking beam, institute
State the bottom that abutment linking beam is arranged at abutment base plate;
Steel pipe, one group two-by-two of the steel pipe are embedded with inside the dam body, every group of steel pipe is in " eight " in horizontal plane projection rule
Font, is parallel to each other for two layers, vertical spacing is at least twice of caliber in perpendicular, above and below two adjacent groups steel pipe;At one group
In steel pipe, the steel pipe nozzle horizontal range of upstream side two is more than the steel pipe nozzle horizontal range of downstream two.
2. parallel pipe laying type permeable spur according to claim 1, it is characterised in that leave joint on the top of sheet pile,
Sheet pile is connected with the groynes dam foundation by concrete cast-in-situ.
3. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the abutment linking beam and adjacent two
Vertical sheet pile is in 45 degree of angle connections, the abutment base plate and sheet pile and the cast-in-place connection of abutment linking beam.
4. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the diameter of steel tube is less than 1m, greatly
In 3D, D is the maximum grain size of gravel being likely to occur in the section of place.
5. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the axis of the steel pipe is in horizontal plane
Upper projection and Parallel to the flow direction are in 10 ° to 30 ° of angle, the projection and horizontal direction of the axis of the steel pipe in perpendicular
In the angle between 5 ° to 20 °.
6. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the embedded steel pipe of institute is in tilted layout,
The side of upstream face is relatively low, higher in the side of downstream face.
7. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the steel pipe upstream face spout tops
The depth of water at the place of position should be greater than critical submergence depth, while downstream face steel pipe nozzle bottom position should be at least above dam foundation face 1m
More than, wherein, critical depth isD was the internal diameter of water steel pipe, unit m;V is what place river was likely to occur
Maximal rate, m/s;C is the parameter relevant with water inlet geometry.
8. parallel pipe laying type permeable spur according to claim 1, it is characterised in that the sheet pile is armoured concrete slab
Stake.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710115208.1A CN106939579B (en) | 2017-02-28 | 2017-02-28 | A kind of parallel pipe laying type permeable spur |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710115208.1A CN106939579B (en) | 2017-02-28 | 2017-02-28 | A kind of parallel pipe laying type permeable spur |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106939579A true CN106939579A (en) | 2017-07-11 |
CN106939579B CN106939579B (en) | 2019-07-12 |
Family
ID=59469109
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710115208.1A Expired - Fee Related CN106939579B (en) | 2017-02-28 | 2017-02-28 | A kind of parallel pipe laying type permeable spur |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106939579B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112761106A (en) * | 2021-01-21 | 2021-05-07 | 交通运输部天津水运工程科学研究所 | Ecological spur dike permeates water |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001248135A (en) * | 2000-03-03 | 2001-09-14 | Kawasaki Steel Corp | Jacket structure |
CN201459674U (en) * | 2009-09-01 | 2010-05-12 | 黄河水利委员会黄河水利科学研究院 | PHC tubular pile dam |
JP2010180637A (en) * | 2009-02-06 | 2010-08-19 | Maeda Kosen Co Ltd | Groin work and method of constructing the same |
CN102154999A (en) * | 2011-04-11 | 2011-08-17 | 水利部交通运输部国家能源局南京水利科学研究院 | Diversion ecological spur dike |
CN103526721A (en) * | 2013-10-29 | 2014-01-22 | 中国水电顾问集团成都勘测设计研究院有限公司 | Permeable spur dike with pile foundations |
CN204626327U (en) * | 2015-03-05 | 2015-09-09 | 上海勘测设计研究院有限公司 | Groynes group under the condition of deep water low beach protects beach structure |
CN205653749U (en) * | 2016-05-11 | 2016-10-19 | 亿利首建生态科技有限公司 | River course butyl dam structure and spur dike protection system |
-
2017
- 2017-02-28 CN CN201710115208.1A patent/CN106939579B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001248135A (en) * | 2000-03-03 | 2001-09-14 | Kawasaki Steel Corp | Jacket structure |
JP2010180637A (en) * | 2009-02-06 | 2010-08-19 | Maeda Kosen Co Ltd | Groin work and method of constructing the same |
CN201459674U (en) * | 2009-09-01 | 2010-05-12 | 黄河水利委员会黄河水利科学研究院 | PHC tubular pile dam |
CN102154999A (en) * | 2011-04-11 | 2011-08-17 | 水利部交通运输部国家能源局南京水利科学研究院 | Diversion ecological spur dike |
CN103526721A (en) * | 2013-10-29 | 2014-01-22 | 中国水电顾问集团成都勘测设计研究院有限公司 | Permeable spur dike with pile foundations |
CN204626327U (en) * | 2015-03-05 | 2015-09-09 | 上海勘测设计研究院有限公司 | Groynes group under the condition of deep water low beach protects beach structure |
CN205653749U (en) * | 2016-05-11 | 2016-10-19 | 亿利首建生态科技有限公司 | River course butyl dam structure and spur dike protection system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112761106A (en) * | 2021-01-21 | 2021-05-07 | 交通运输部天津水运工程科学研究所 | Ecological spur dike permeates water |
Also Published As
Publication number | Publication date |
---|---|
CN106939579B (en) | 2019-07-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105507335B (en) | Steel sheet-pile cofferdam foundation pit back cover structure and construction method | |
CN206706772U (en) | A kind of double steel sheet pile supporting construction | |
CN106759066A (en) | A kind of method of mountain area side slope water conservancy diversion energy dissipating prevention and control geological disaster | |
CN202577349U (en) | Large immersed tube tunnel dry dock floor structure | |
CN104594287A (en) | Ecological and economic bank protection structure | |
CN204282308U (en) | A kind of lattice guest gabion composite material dam adapting to deep covering layer | |
CN106939580B (en) | A kind of pipe laying type permeable spur that interlocks | |
CN213952260U (en) | Cofferdam structure combining steel sheet pile and steel pipe pile | |
CN206956686U (en) | A kind of hydraulic reclamation area gabion discharge opening | |
CN106939579A (en) | A kind of parallel pipe laying type permeable spur | |
CN202450491U (en) | Open type flood discharge structure at dam crest | |
CN205604186U (en) | Clay core morals and manners material dam | |
CN204676485U (en) | A kind of Eco-economic Type bank protection structure | |
CN101705668B (en) | Damming water conservancy project construction structure constructed in flowing water and construction method thereof | |
CN203821306U (en) | Flexible anti-scour protection pad | |
CN216041278U (en) | Novel pile foundation scour prevention structure | |
CN105970882A (en) | Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof | |
CN205604273U (en) | Last cofferdam of sandy silt | |
CN102828489B (en) | System for arranging piles to fix riverbed main stream | |
CN205907658U (en) | Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body | |
CN205475148U (en) | River course truss -like draws anchor to prevent floating device | |
CN102425151A (en) | Thickness-variable integral type anti-scour gabion for village residential house foundation | |
CN208934101U (en) | A kind of pump lock foundation pit enclosure structure | |
CN206680947U (en) | Steel water stone separates blocking dam | |
CN207988083U (en) | The orthogonal anti-structure of drainning off floodwaters of Gobi Region solar energy optical-thermal place |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190712 |
|
CF01 | Termination of patent right due to non-payment of annual fee |