CN206189968U CN201620676652.1U CN201620676652U CN206189968U CN 206189968 U CN206189968 U CN 206189968U CN 201620676652 U CN201620676652 U CN 201620676652U CN 206189968 U CN206189968 U CN 206189968U
Authority
CN
China
Prior art keywords
plate
prefabricated
bulkhead plate
warehouse
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620676652.1U
Other languages
Chinese (zh)
Inventor
张昊
张淑媛
王振清
常晨辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201620676652.1U priority Critical patent/CN206189968U/en
Application granted granted Critical
Publication of CN206189968U publication Critical patent/CN206189968U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/51Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture specially adapted for storing agricultural or horticultural products

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种内衬塑料阶梯状预制装配式地下粮仓,包括仓底、多块预制仓壁板、仓顶、多功能柱、多层加强柱,所述仓壁板为内侧塑料板和外侧的混凝土板结合成整体的结构,周边有连接装置,通过连接装置仓壁板能与相邻仓壁板、多功能柱和多层加强柱进行连接;所述多功能柱能对仓壁板进行定位,其锚入土中的深度大于仓底深度,是承受土压力、粮食侧压力和抵抗浮力的主要受力构件;其特征在于:多功能柱从上至下分成数段,最上层的第一段内侧设有第一层仓壁板,第二段内侧先设有加强柱,使得加强柱内侧面与第一层仓壁板内侧面平齐,再在加强柱内侧面设有第二层仓壁板,使得第一、二层仓壁板部分搭接;用上述类似的设置方式,使得第二、三层仓壁板部分搭接,一直搭接至最下面一层仓壁板,形成阶梯状装配式地下粮仓。

A plastic-lined stepped prefabricated underground granary, comprising a bottom, a plurality of prefabricated wall panels, a roof, a multi-functional column, and a multi-layer reinforced column, and the wall panels are plastic panels on the inside and concrete panels on the outside Combined into an integral structure, there are connecting devices around, through which the warehouse wall panels can be connected with adjacent warehouse wall panels, multi-functional columns and multi-layer reinforcement columns; the multi-functional columns can position the warehouse wall panels, and the The depth of anchoring into the soil is greater than the depth of the bottom of the warehouse, and it is the main force-bearing member that bears the earth pressure, the lateral pressure of the grain and resists the buoyancy; There is a first layer of warehouse wall panels, and the inner side of the second section is first provided with a reinforcement column, so that the inner surface of the reinforcement column is flush with the inner surface of the first layer of warehouse wall panels, and then a second layer of warehouse wall panels is installed on the inner side of the reinforcement column. The wall panels of the first and second floors are partially overlapped; with the above-mentioned similar setting method, the wall panels of the second and third floors are partially overlapped until the bottom layer of the wall panels is overlapped to form a stepped assembly Underground granary.

Description

一种内衬塑料阶梯状预制装配式地下粮仓A stepped prefabricated underground granary lined with plastic

技术领域technical field

本实用新型涉及地下粮仓技术领域,具体涉及一种内衬塑料阶梯状预制装配式地下粮仓。The utility model relates to the technical field of underground granaries, in particular to a plastic-lined ladder-like prefabricated underground granary.

背景技术Background technique

地下粮仓建造在浅层地表下,常年低温储粮,保持粮食品质、抑制虫害发生,避免使用毒性药剂熏蒸,抵抗自然破坏和战平两用等众多优点,许多专家和学者一致认为合理推广应用地下储粮仓新体系与新技术,能够实现低温环保、节能节地、保质减损、生态储粮。Underground granaries are built under the shallow surface, which can store grain at low temperature all year round, maintain grain quality, inhibit the occurrence of pests, avoid fumigation with toxic chemicals, resist natural damage, and be used for both war and peace. Many experts and scholars agree that it is reasonable to promote the application of underground granaries The new system and new technology of grain storage can realize low-temperature environmental protection, energy saving and land saving, quality assurance and loss reduction, and ecological grain storage.

我国现有地下粮仓一般在地下水位较低的一般黄土和适合粘上性地区,如窑洞仓、喇叭仓、双曲拱仓、半地下仓、洞状喇叭仓;同时已建的地下仓多为砖砌结构,仓容小,占地面积大、机械化程度低。The existing underground granaries in my country are generally located in general loess areas with low groundwater levels and suitable for sticky areas, such as cave warehouses, trumpet warehouses, double-curved arch warehouses, semi-underground warehouses, and cave-shaped trumpet warehouses; Brick structure, small storage capacity, large floor space and low degree of mechanization.

为了建造适用在地下水位较高、复杂地质条件区域可推广应用的新型地下粮仓,一些国家专利和文献也提出了圆形粮仓,圆筒、半圆筒围成的大空间地下矩形,桩围复合式地下仓等仓型,但是上述新仓型的推广应用,还存在一些亟待解决的问题,如:(1)地下储粮仓具有高标准防水、防潮要求。确保仓体在使用年限内不漏水,不渗水;采用的卷材材料易老化,施工工序复杂,难度大,容易出现施工质量问题。(2)深基坑的湿作业环境施工周期长。基坑开挖、降水后,仓底板现浇、仓壁滑模施工需长时间在湿作业环境条件进行,劳动强度大、施工周期长,施工成本高。(3)基坑支护费用高。针对该类深基坑,“钢桩+腰梁+封水钢板”基坑支护是较为经济的方式,但费用占土建建设成本的25-30%,建设成本较高。In order to build a new type of underground granary that can be popularized and applied in areas with high groundwater levels and complex geological conditions, some national patents and documents have also proposed a circular granary, a large underground rectangle surrounded by cylinders and semi-cylinders, and a pile-enclosed compound type. However, there are still some problems to be solved urgently in the popularization and application of the above-mentioned new warehouse types, such as: (1) Underground grain storage warehouses have high standards of waterproof and moisture-proof requirements. Ensure that the warehouse body does not leak or seep within the service life; the coiled material used is easy to age, the construction process is complex and difficult, and construction quality problems are prone to occur. (2) The wet work environment of deep foundation pit has a long construction period. After foundation pit excavation and precipitation, the cast-in-place construction of the warehouse floor and the sliding form construction of the warehouse wall need to be carried out in a wet working environment for a long time, resulting in high labor intensity, long construction period and high construction cost. (3) The cost of foundation pit support is high. For this kind of deep foundation pit, "steel pile + waist beam + water sealing steel plate" foundation pit support is a more economical way, but the cost accounts for 25-30% of the civil construction cost, and the construction cost is relatively high.

申请号为CN200910207155.1的发明公开了一种地下粮仓,包括仓顶、仓壁和仓底,该仓壁外包钢,钢板既能单独作为仓壁的防水、防潮层,也能仓壁与钢板用钢构件连接形成组合结构的仓壁来防水、防潮。地下粮仓仓壁的形状为直线形或曲线形,如圆筒形、方筒形、半圆形仓壁等。该发明通过外包钢板解决了仓底板的防水防潮问题。同时在仓底进行施工时,钢板作为模板,加快施工速度,降低施工成本,但是其施工为现场浇筑施工,而且该施工方法需要进行基坑开挖,这样存在整体建造成本高,施工周期长等不足。The invention whose application number is CN200910207155.1 discloses an underground granary, which includes a roof, a wall and a bottom. The steel plates are connected by steel members to form a combined structure of the warehouse wall to prevent water and moisture. The shape of the wall of the underground granary is straight or curved, such as cylindrical, square, semicircular, etc. The invention solves the waterproof and moisture-proof problem of the bottom plate of the warehouse through the outsourcing steel plate. At the same time, when the construction is carried out at the bottom of the warehouse, the steel plate is used as a formwork to speed up the construction and reduce the construction cost. However, the construction is pouring on site, and this construction method requires excavation of the foundation pit, so the overall construction cost is high and the construction period is long. insufficient.

申请号为CN200910207154.7的发明公开了一种地下粮仓,包括仓顶、仓壁和仓底,该仓壁分为内壁和外壁,内壁与外壁之间采用连接件连成整体,内壁与外壁之间形成空腔,所述空腔用于地下粮仓漏水的检测和修复,并用于地下粮仓通风和粮情检测。该发明粮仓也需要基坑开挖,存在施工麻烦、建造成本高、施工周期长等不足。The invention with application number CN200910207154.7 discloses an underground granary, including a roof, a wall and a bottom. The wall is divided into an inner wall and an outer wall. A cavity is formed between them, and the cavity is used for detection and repair of water leakage in the underground granary, and for ventilation of the underground granary and detection of grain conditions. The granary of the invention also needs foundation pit excavation, which has disadvantages such as troublesome construction, high construction cost, and long construction period.

预制装配式结构是实现建筑结构产业化和建筑节能节排的有效途径之一,长期以来,混凝土建筑主要采用现场施工的传统作业方式,工业化程度低,水耗、能耗、人工垃圾、污水排放 量大,不符合国家节能和环保的可持续发展政策。采用装配式结构,可以工厂预制、现场装配,实现建筑结构产业化,同时可以有效提高材料在建筑节能和结构性能的效率、节约能源与资源,减少建筑垃圾和环境的不良影响、降低施工场地限制等。因此,为了提供一种“快、好、省“的地下储粮新仓型,研发预制装配式新型地下仓已成为必需。The prefabricated structure is one of the effective ways to realize the industrialization of building structures and building energy saving and emission reduction. For a long time, concrete buildings mainly adopt the traditional operation method of on-site construction, with a low degree of industrialization, water consumption, energy consumption, artificial waste, and sewage discharge. The amount is large, which does not conform to the national sustainable development policy of energy conservation and environmental protection. The prefabricated structure can be prefabricated in the factory and assembled on site to realize the industrialization of building structures. At the same time, it can effectively improve the efficiency of materials in building energy saving and structural performance, save energy and resources, reduce construction waste and adverse effects on the environment, and reduce construction site restrictions. Wait. Therefore, in order to provide a "quick, good and economical" new type of underground grain storage, it has become necessary to develop a prefabricated new type of underground storage.

实用新型内容Utility model content

本实用新型的目的在于提供一种内衬塑料阶梯状预制装配式地下粮仓,该预制装配式地下粮仓的内衬塑料板可代替防水卷材,具有较好的防水、防渗效果和综合效益;预制仓壁板可在预制构件工厂标准化生产,加工制造质量既能有效控制又节能环保,预制成品现场组装,机械化安装施工,可交叉施工,缩短施工工期。另外,预制仓体结构可作为基坑支护体系,节约基坑支护成本,降低建设投资。The purpose of this utility model is to provide a stepped prefabricated underground granary lined with plastic. The plastic lined plate of the prefabricated underground granary can replace the waterproof coiled material, and has good waterproof, anti-seepage effect and comprehensive benefits; The prefabricated warehouse wall panels can be produced in a standardized manner in the prefabricated component factory. The processing and manufacturing quality can be effectively controlled and energy-saving and environmentally friendly. The prefabricated products are assembled on site, mechanized installation and construction, and can be cross-constructed to shorten the construction period. In addition, the prefabricated warehouse structure can be used as a foundation pit support system, saving foundation pit support costs and reducing construction investment.

本实用新型的解决方案是:一种预制装配式地下粮仓,包括仓底、多块预制仓壁板、仓顶、多功能柱、多层加强柱,所述仓壁板为内侧塑料板和外侧的混凝土板结合成整体的结构,周边有连接装置,通过连接装置仓壁板能与相邻仓壁板、多功能柱和多层加强柱进行连接;所述多功能柱能对仓壁板进行定位,其锚入土中的深度大于仓底深度,是承受土压力、粮食侧压力和抵抗浮力的主要受力构件;其特征在于:多功能柱从上至下分成数段,最上层的第一段内侧设有第一层仓壁板,第二段内侧先设有加强柱,使得加强柱内侧面与第一层仓壁板内侧面平齐,再在加强柱内侧面设有第二层仓壁板,使得第一、二层仓壁板部分搭接;用上述类似的设置方式,使得第二、三层仓壁板部分搭接,一直搭接至最下面一层仓壁板,形成阶梯状装配式地下粮仓。The solution of the utility model is: a prefabricated underground granary, including the bottom of the warehouse, a plurality of prefabricated warehouse wall panels, a warehouse roof, multi-functional columns, and multi-layer reinforced columns. The warehouse wall panels are inner plastic plates and outer The concrete slabs are combined into an integral structure, and there are connecting devices around them, through which the warehouse wall panels can be connected with adjacent warehouse wall panels, multi-functional columns and multi-layer reinforced columns; Positioning, the depth of its anchoring into the soil is greater than the depth of the bottom of the warehouse, and it is the main force-bearing member that bears the earth pressure, the lateral pressure of the grain and resists the buoyancy; its feature is that the multi-functional column is divided into several sections from top to bottom. The inner side of the section is provided with the first layer of warehouse walls, and the inner side of the second section is first provided with reinforced columns, so that the inner side of the reinforced columns is flush with the inner side of the first layer of warehouse walls, and then the second layer of warehouses is installed on the inner side of the reinforced columns. Wall panels, so that the first and second storey wall panels are partially overlapped; with the above-mentioned similar setting method, the second and third storey wall panels are partially overlapped, and have been overlapped to the bottom layer of the storehouse wall panels to form a ladder Prefabricated underground granary.

本实用新型的特征在于预制仓壁板多功能柱和加强柱采用钢柱或设有钢埋件的混凝土,多功能柱与加强柱通过螺栓或焊接缝连接,多功能柱或加强柱上设有定位刚构件。多功能柱和加强柱要保证其与周围的连接构件形成一个整体共同受力,这样,用钢柱或设有钢埋件的混凝土柱能简单方便地与其连接构件焊接;多功能柱与加强柱通过螺栓或焊接缝连接成一个整体,而且随着深度的增加,二者形成的整体截面尺寸越来越大,这样,可以有效地抵抗自上而下随深度增加的土压力,而且结构设计更加经济合理。多功能柱的定位钢构件可以在预制仓壁板安装时进行精确的定位,同时在预制仓壁板与多功能柱焊接前提供固定作用。The utility model is characterized in that the prefabricated warehouse wall plate multifunctional column and the reinforced column adopt steel columns or concrete with steel embedded parts, the multifunctional column and the reinforced column are connected by bolts or welding seams, and the multifunctional column or the reinforced column is equipped with Position the rigid member. The multifunctional column and the reinforced column should ensure that they form an integral force with the surrounding connecting members, so that the steel column or the concrete column with steel embedded parts can be easily and conveniently welded to the connecting member; the multifunctional column and the reinforced column It is connected as a whole by bolts or welding seams, and as the depth increases, the overall cross-sectional size formed by the two becomes larger and larger, so that it can effectively resist the earth pressure that increases with depth from top to bottom, and the structural design is more comprehensive. Economically sound. The positioning steel member of the multifunctional column can be accurately positioned when the prefabricated warehouse wall is installed, and at the same time, it can provide a fixing function before the prefabricated warehouse wall and the multifunctional column are welded.

本实用新型的特征还在于预制仓壁板的内侧塑料板与其外侧混凝土采用锚钉连接,内侧塑料板在仓壁板下边内侧离开混凝土板端部一定距离,该距离范围内设有第二预埋钢板;在仓壁板上端设有L形第一预埋钢板,第一预埋钢板包住混凝土板的外侧边角,混凝土板的左端和右端设有U形预埋钢板,包住混凝土板左右端面的内、外侧边角。这样,预制仓壁板的内包塑料板可代替防水卷材,具有较好的防水、防渗效果和综合效益;塑料板与混凝土的锚 钉连接使二者形成一个整体,锚钉可以抵抗土压力作用下塑料与混凝土板之间剪切作用,同时锚钉与混凝土之间粘结力很好地防止塑料板与混凝土脱离。内包塑料预制仓壁板不但避免了仓壁防水卷材施工时的繁重工作,节省了仓壁防水的施工时间,降低了劳动力成本;另外,预制仓壁板可在预制构件工厂标准化生产,加工制造质量既能有效控制又节能环保,预制成品现场组装,机械化安装施工,可交叉施工,缩短施工工期。在仓壁板下边内侧离开混凝土板端部一定距离内设有第二预埋钢板,在仓壁板上端设有L形第一预埋钢板,这样,上下预制仓壁板可以通过下仓壁的第一预埋钢板和上仓壁的第二预埋钢板用焊接和连接钢板连接成一个整体受力结构;混凝土板的左端和右端设有U形预埋钢板,包住混凝土板左右端面的内、外侧边角,这样,仓壁板的左、右端的U型预埋钢板可以方便地与多功能柱或加强柱焊接成一个整体。The utility model is also characterized in that the inner plastic plate of the prefabricated warehouse wall is connected with the outer concrete by anchors, and the inner plastic plate is at a certain distance away from the end of the concrete plate on the inner side of the lower side of the warehouse wall. Steel plate: L-shaped first embedded steel plate is arranged on the top of the warehouse wall, the first embedded steel plate wraps the outer corner of the concrete slab, and the left and right ends of the concrete slab are provided with U-shaped embedded steel plates to wrap the concrete slab The inner and outer corners of the left and right end faces. In this way, the inner plastic board of the prefabricated warehouse wall board can replace the waterproof membrane, which has better waterproof, anti-seepage effect and comprehensive benefits; the plastic board and the concrete anchor are connected to form a whole, and the anchor can resist the earth pressure Under the action, there is a shearing effect between the plastic and the concrete slab, and at the same time, the bonding force between the anchor and the concrete is very good to prevent the plastic slab from detaching from the concrete. The inner plastic prefabricated warehouse wall not only avoids the heavy work during the construction of the warehouse wall waterproofing membrane, but also saves the construction time of the warehouse wall waterproof and reduces the labor cost; in addition, the prefabricated warehouse wall can be standardized in the prefabricated component factory, processed and manufactured The quality can be effectively controlled and energy-saving and environmentally friendly. Prefabricated products are assembled on site, and mechanized installation and construction can be cross-constructed to shorten the construction period. There is a second pre-embedded steel plate within a certain distance from the end of the concrete slab on the inner side of the lower side of the silo wall, and an L-shaped first pre-embedded steel plate is arranged on the top of the silo wall, so that the upper and lower prefabricated silo walls can pass through the lower silo wall. The first pre-embedded steel plate and the second pre-embedded steel plate on the upper warehouse wall are connected by welding and connecting steel plates to form an integral force-bearing structure; the left and right ends of the concrete slab are equipped with U-shaped pre-embedded steel plates to enclose the inner parts of the left and right ends of the concrete slab. , Outer corners, so that the U-shaped embedded steel plates at the left and right ends of the warehouse wall can be easily welded into a whole with the multifunctional column or the reinforced column.

本实用新型的特征还在于预制仓壁板内侧塑料板与其外侧混凝土采用锚钉连接,内侧塑料板在仓壁板下边内侧离开混凝土板端部一定距离,该距离范围内设有第二预埋钢板;在仓壁板上端设有L形第一预埋钢板,第一预埋钢板包住混凝土板的外侧边角,混凝土板的左端和右端设有预埋钢板包角,包住混凝土板左右端面的内、外侧边角,且左端设有凸式梯形或半椭圆形插头,右端设有梯形或半椭圆形凹槽。这样,预制仓壁板的内包塑料板可代替防水卷材,具有较好的防水、防渗效果和综合效益;塑料板与混凝土的锚钉连接使二者形成一个整体,锚钉可以抵抗土压力作用下塑料与混凝土板之间剪切作用,同时锚钉与混凝土之间粘结力很好地防止塑料板与混凝土脱离。内包塑料预制仓壁板不但避免了仓壁防水卷材施工时的繁重工作,节省了仓壁防水的施工时间,降低了劳动力成本;另外,预制仓壁板可在预制构件工厂标准化生产,加工制造质量既能有效控制又节能环保,预制成品现场组装,机械化安装施工,可交叉施工,缩短施工工期。在仓壁板下边内侧离开混凝土板端部一定距离内设有第二预埋钢板,在仓壁板上端设有L形第一预埋钢板,这样,上下预制仓壁板可以通过下仓壁的第一预埋钢板和上仓壁的第二预埋钢板用焊接和连接钢板连接成一个整体受力结构;混凝土板的左端和右端设有预埋钢板包角,这样可以方便地使仓壁板与周围相邻预制仓壁板及多功能柱或加强柱进行焊接连接。预制仓壁板左端设有凸式梯形或半椭圆形插头,右端设有梯形或半椭圆形凹槽,这样可以方便地使相邻预制仓壁板进行连接,从而加快施工速度,大大缩短施工周期。The utility model is also characterized in that the inner plastic plate of the prefabricated warehouse wall is connected with the outer concrete by anchors, and the inner plastic plate is separated from the end of the concrete plate by a certain distance on the inner side of the lower side of the warehouse wall, and a second pre-embedded steel plate is provided within the range of the distance ; There is an L-shaped first pre-embedded steel plate on the top of the warehouse wall, the first pre-embedded steel plate wraps the outer corner of the concrete slab, and the left and right ends of the concrete slab are provided with pre-embedded steel plate corners to wrap the left and right sides of the concrete slab. The inner and outer corners of the end face, and the left end is provided with a convex trapezoidal or semi-elliptical plug, and the right end is provided with a trapezoidal or semi-elliptical groove. In this way, the inner plastic board of the prefabricated warehouse wall board can replace the waterproof membrane, which has better waterproof, anti-seepage effect and comprehensive benefits; the plastic board and the concrete anchor are connected to form a whole, and the anchor can resist the earth pressure Under the action, there is a shearing effect between the plastic and the concrete slab, and at the same time, the bonding force between the anchor and the concrete is very good to prevent the plastic slab from detaching from the concrete. The inner plastic prefabricated warehouse wall not only avoids the heavy work during the construction of the warehouse wall waterproofing membrane, but also saves the construction time of the warehouse wall waterproof and reduces the labor cost; in addition, the prefabricated warehouse wall can be standardized in the prefabricated component factory, processed and manufactured The quality can be effectively controlled and energy-saving and environmentally friendly. The prefabricated products are assembled on site, and the mechanized installation and construction can be cross-constructed to shorten the construction period. There is a second pre-embedded steel plate within a certain distance from the end of the concrete slab on the inner side of the lower side of the silo wall, and an L-shaped first pre-embedded steel plate is arranged on the top of the silo wall, so that the upper and lower prefabricated silo walls can pass through the lower silo wall. The first pre-embedded steel plate and the second pre-embedded steel plate on the upper warehouse wall are connected by welding and connecting steel plates to form an overall force-bearing structure; the left and right ends of the concrete slab are provided with embedded steel plate corners, which can easily make the warehouse wall It is welded and connected with the surrounding adjacent prefabricated warehouse wall panels and multi-functional columns or reinforced columns. The left end of the prefabricated warehouse wall panel is provided with a convex trapezoidal or semi-elliptical plug, and the right end is provided with a trapezoidal or semi-elliptical groove, which can facilitate the connection of adjacent prefabricated warehouse wall panels, thereby speeding up the construction speed and greatly shortening the construction period. .

本实用新型的特征还在于预制仓壁板环向水平平齐,预制仓壁板通过U形预埋钢板与多功能柱或加强柱焊接在一起,在预制仓壁板内侧用第一连接钢板通过U形预埋钢板将相邻预制仓壁板焊接在一起,在环向预制仓壁板之间浇筑与预制仓壁板相同或高一级强度等级的防水混凝土。在预制仓壁板外侧,通过预制仓壁板左右端的U型预埋钢板将其与多功能柱或加 强柱焊接在一起,同时,在仓壁板内侧用第一连接钢板焊接连接,这样,多功能柱或加强柱、连接钢板、预制仓壁以及其之间的混凝土形成了整体结构,使节点具有较强的抗弯、抗剪和抗压能力,而且节点施工比较简单方便;另外,内侧钢板除受力外,还可以作为节点处的防水措施。The utility model is also characterized in that the circumferential level of the prefabricated warehouse wall plate is even, the prefabricated warehouse wall plate is welded together with the multifunctional column or the reinforced column through the U-shaped pre-embedded steel plate, and the first connecting steel plate passes through the inner side of the prefabricated warehouse wall plate. The U-shaped pre-embedded steel plate welds the adjacent prefabricated warehouse wall panels together, and pours waterproof concrete with the same or higher strength level as the prefabricated warehouse wall panels between the circumferential prefabricated warehouse wall panels. On the outer side of the prefabricated warehouse wall, it is welded with the multifunctional column or reinforced column through the U-shaped embedded steel plates at the left and right ends of the prefabricated warehouse wall, and at the same time, the first connecting steel plate is used to weld and connect the inner side of the warehouse wall. In this way, more Functional columns or reinforced columns, connecting steel plates, prefabricated warehouse walls and the concrete between them form an integral structure, which makes the joints have strong resistance to bending, shearing and compression, and the construction of joints is relatively simple and convenient; in addition, the inner steel plates In addition to stress, it can also be used as a waterproof measure at nodes.

本实用新型的特征还在于预制仓壁板环向水平平齐,每块预制仓壁板的凸式梯形或半椭圆型插头插入相邻预制仓壁板凹式梯形或半椭圆型插槽内;每块预制仓壁板与多功能柱或加强柱焊接连接,相邻预制仓壁板内侧的竖缝直接采用对接焊连接和/或用连接钢板焊接连接。首先,将第一块预制仓壁板的左右端外侧与多功能柱或加强柱焊接,然后,将其右侧相邻预制仓壁板的左端凸式梯形或半椭圆型插头插入相邻仓壁板的凹式梯形或半椭圆型插槽内并焊接连接,右端凹式梯形或半椭圆型插槽与多功能柱或加强柱焊接,按照上述焊接方法依次进行安装,直到完成该层预制仓壁板的安装。这样不但可以使预制仓壁与多功能柱或加强柱形成整体结构共同受力,而且可以使预制仓壁通过焊接在环向形成一个封闭整体进行节点的防水、防潮、防渗;另外,相邻预制仓壁板插槽式的连接方式使节点形式和施工更加简单,从而加快了施工速度,大大缩短施工周期。The utility model is also characterized in that the circumferential level of the prefabricated warehouse wall panels is even, and the convex trapezoidal or semi-elliptical plugs of each prefabricated warehouse wall panel are inserted into the concave trapezoidal or semi-elliptical slots of the adjacent prefabricated warehouse wall panels; Each prefabricated warehouse wall plate is welded to the multifunctional column or reinforced column, and the vertical joints on the inner side of the adjacent prefabricated warehouse wall plates are directly connected by butt welding and/or welded by connecting steel plates. Firstly, weld the outer sides of the left and right ends of the first prefabricated warehouse wall panel to the multi-functional column or reinforced column, and then insert the convex trapezoidal or semi-elliptical plug at the left end of the adjacent prefabricated warehouse wall panel on the right side into the adjacent warehouse wall The concave trapezoidal or semi-elliptical slot of the board is welded and connected, and the concave trapezoidal or semi-elliptical slot at the right end is welded to the multi-functional column or reinforced column, and the installation is carried out in sequence according to the above welding method until the prefabricated warehouse wall of this layer is completed board installation. In this way, not only can the prefabricated warehouse wall and the multi-functional column or reinforced column form an integral structure to bear the force together, but also the prefabricated warehouse wall can form a closed whole in the circumferential direction by welding to waterproof, moisture-proof and seepage-proof nodes; in addition, the adjacent The slot-type connection method of the prefabricated warehouse wall board makes the joint form and construction simpler, thereby speeding up the construction speed and greatly shortening the construction period.

本实用新型的特征还在于相邻的上层仓壁板与下层仓壁板上下错位搭接,搭接部位的预埋钢板用角焊焊接,然后用第二连接钢板将下层仓壁板的第一预埋钢板和上层仓壁板的第二预埋钢板垂直焊接在一起;所述第二连接钢板由直角三角形钢板切掉直角而成,且第二连接钢板为多块,沿钢板角焊均匀分布。预制仓壁板上、下两层竖向错位搭接方式使上下相邻仓壁板的连接处施工时非常方便,能够较好地保证施工质量;上、下两层仓壁板的搭接部位的通长角焊缝使上下相邻仓壁预埋钢板焊接后形成一个封闭的防水层,从而很好地防止地下水在搭接处流进或渗进地下仓内部;在结构受力方面,可以通过连接板将下仓壁板的第一钢板以及上仓壁板的第二钢板焊接在一起,从而使上下仓壁板在受力结构上成为一个整体,与多功能柱或加强柱共同抵抗土压力等外力。预制仓壁板的上、下两层错位搭接处沿环向间隔设置的第二连接钢板为加强上下相邻仓壁板的连接,将直角三角形钢板切掉直角是为了避免与上、下两层仓壁板的搭接部位的通长钢板角焊缝在空间上冲突;连接板与相邻上下预制仓壁板均垂直焊接使仓壁处连接处提高了其抵抗弯矩和剪力的能力。The utility model is also characterized in that the adjacent upper warehouse wall panels and the lower warehouse wall panels are overlapped up and down, and the pre-embedded steel plates at the overlapping parts are welded by fillet welding, and then the first joint of the lower warehouse wall panels is welded by the second connecting steel plate. The pre-embedded steel plate and the second pre-embedded steel plate of the upper warehouse wall are welded together vertically; the second connecting steel plate is formed by cutting off a right angle from a right-angled triangle steel plate, and the second connecting steel plate is a plurality of pieces, which are evenly distributed along the fillet weld of the steel plate . The prefabricated warehouse wall panel and the lower two-layer vertical dislocation overlapping method make the construction of the connection between the upper and lower adjacent warehouse wall panels very convenient, and can better ensure the construction quality; the overlapping parts of the upper and lower warehouse wall panels The full-length fillet welds form a closed waterproof layer after welding the pre-embedded steel plates of the upper and lower adjacent warehouse walls, so as to prevent groundwater from flowing into or seeping into the interior of the underground warehouse at the overlapping joints; in terms of structural stress, it can The first steel plate of the lower warehouse wall and the second steel plate of the upper warehouse wall are welded together through the connecting plate, so that the upper and lower warehouse walls become a whole in the stressed structure, and resist the soil together with the multifunctional column or the reinforced column. External force such as pressure. The second connecting steel plate at the dislocation lap of the upper and lower layers of the prefabricated warehouse wall is arranged at intervals in the circumferential direction to strengthen the connection between the upper and lower adjacent warehouse walls. The fillet welds of the full-length steel plates at the overlapping parts of the silo wall panels conflict in space; the connecting plate and the adjacent upper and lower prefabricated silo wall panels are welded vertically, so that the joints of the silo walls improve their ability to resist bending moments and shear forces .

本实用新型的特征还在于第二连接钢板的内侧,设置与第二连接钢板垂直的通长加强斜板,所述的加强斜板分别与下层仓壁板的第一预埋钢板和上层仓壁板的第二预埋钢板焊接。当粮食出仓时,预制仓壁板的上、下两层错位搭接处会留有粮食,此处粮食清清扫比较困难;搭接处设有一定坡度的斜向加强板一方面使粮食靠自流进入仓内,另一方面可以为仓壁搭接处提供防水保障,同时在结构设计方面可加强上下仓壁的连接。The utility model is also characterized in that the inner side of the second connecting steel plate is provided with a full-length reinforcing sloping plate perpendicular to the second connecting steel plate, and the reinforcing sloping plate is connected with the first pre-embedded steel plate of the lower storey wall plate and the upper storey wall respectively. The second pre-embedded steel plate of the plate is welded. When the grain is out of the warehouse, there will be grain at the upper and lower two-layer dislocation laps of the prefabricated warehouse wall panels, and it is difficult to clean the grain here; an inclined reinforcing plate with a certain slope is provided at the lap joints. Self-flowing into the warehouse, on the other hand, it can provide waterproof protection for the overlapping parts of the warehouse walls, and at the same time, the connection between the upper and lower warehouse walls can be strengthened in terms of structural design.

本实用新型的特征还在于相邻预制仓壁板内侧塑料板用连接塑料板连接,连接塑料板与预制仓壁板内侧塑料板胶粘或焊接。上、下两层仓壁板的搭接部位的连接塑料板使上下相邻仓壁内侧塑料板形成一个封闭的防水层,从而很好地防止地下水流进或渗进地下仓内部。The utility model is also characterized in that the inner plastic plates of the adjacent prefabricated warehouse wall panels are connected by connecting plastic plates, and the connecting plastic plates are glued or welded to the inner plastic plates of the prefabricated warehouse wall panels. The connecting plastic plates at the overlapping parts of the upper and lower storey wall panels make the inner plastic plates of the upper and lower adjacent storehouse walls form a closed waterproof layer, thereby preventing groundwater from flowing or infiltrating into the underground storehouse.

本实用新型的特征还在于仓底采用双面钢板混凝土组合结构,底板上下钢板与其之间的混凝土采用锚钉连接。这种双面组合结构仓壁中钢板作为仓底板的模板并代替钢筋,节省仓壁的施工费用,降低仓壁的施工难度,加快整体施工速度;双层钢板混凝土组合结构提高了仓壁的刚度和强度,有效抵抗土压力和粮食压力,有利于地下仓向更深更大的方向发张,增大了该仓型的适用范围,且更有利于粮仓防水防潮问题。The utility model is also characterized in that the bottom of the warehouse adopts a double-sided steel plate concrete composite structure, and the upper and lower steel plates on the bottom plate and the concrete between them are connected by anchors. The steel plate in the warehouse wall of this double-sided composite structure is used as the formwork of the warehouse floor and replaces the steel bar, which saves the construction cost of the warehouse wall, reduces the construction difficulty of the warehouse wall, and speeds up the overall construction speed; the double-layer steel plate concrete composite structure improves the rigidity of the warehouse wall. and strength, effectively resisting soil pressure and grain pressure, which is conducive to the expansion of the underground warehouse to a deeper and larger direction, which increases the scope of application of the warehouse type, and is more conducive to the waterproof and moisture-proof problems of the granary.

本实用新型的特征还在于仓顶采用混凝土-钢板组合结构。这样,上述结构充分发挥了混凝土的抗压和钢板的抗拉能力,使大跨度仓顶板结构受力更加合理,而且施工时可以用钢板作为模板,极大地降低了施工难度,同时也可加快施工速度。The utility model is also characterized in that the warehouse roof adopts a concrete-steel composite structure. In this way, the above-mentioned structure fully exerts the compressive resistance of concrete and the tensile capacity of steel plates, making the stress of the roof structure of large-span warehouses more reasonable, and steel plates can be used as formwork during construction, which greatly reduces the difficulty of construction and can also speed up construction. speed.

本实用新型的特征在于地下粮仓的多功能柱和加强柱采用截面形式为直线或曲线的空心柱或实心柱。The utility model is characterized in that the multifunctional column and the reinforced column of the underground granary adopt a hollow column or a solid column whose section form is a straight line or a curve.

附图说明Description of drawings

图1第一种地下仓平面布置图Figure 1 Layout plan of the first type of underground warehouse

图2第二种地下仓平面布置图Figure 2 Layout plan of the second type of underground warehouse

图3第一、二种地下仓剖面布置图Figure 3 Sectional layout of the first and second types of underground warehouses

图4第一、二种单块预制仓壁板截面示意图Figure 4 Schematic diagram of the cross-section of the first and second types of single-block prefabricated warehouse wall panels

图5第一种第一段预制混凝土板平面布置示意图Figure 5 Schematic diagram of the layout of the first section of the precast concrete slab of the first type

图6第一种第二段及以下各段预制混凝土板平面布置示意图Fig. 6 Schematic diagram of plan layout of precast concrete slabs in the second section and the following sections of the first type

图7第一、二种仓壁节点示意图Figure 7 Schematic diagram of the first and second warehouse wall nodes

图8第二种第一段预制混凝土板平面布置示意图Figure 8 Schematic diagram of the plane layout of the first section of the second type of precast concrete slab

图9第二种第二段及以下各段预制混凝土板平面布置示意图Figure 9 Schematic diagram of the plane layout of the second section and the following sections of the second type of precast concrete slab

附图中:1为多功能柱;2为加强柱;3为预制仓壁;4为仓顶;5为仓底;6为第一连接钢板;7为第二连接钢板;8为斜向加强板;9为通长角焊缝;10为进出粮口;11为覆土;12为防水混凝土;13为内侧塑料;15为第一预埋钢板;16为第二预埋钢板。In the attached drawings: 1 is the multifunctional column; 2 is the reinforced column; 3 is the prefabricated warehouse wall; 4 is the roof of the warehouse; 5 is the bottom of the warehouse; 6 is the first connecting steel plate; 7 is the second connecting steel plate; 8 is oblique reinforcement 9 is the full-length fillet weld; 10 is the grain inlet and outlet; 11 is the covering soil; 12 is waterproof concrete; 13 is the inner plastic; 15 is the first embedded steel plate; 16 is the second embedded steel plate.

具体实施方式detailed description

实施例一Embodiment one

如图1、图3、图4、图5、图7所示:本实施例提供了一种内衬塑料阶梯状预制装配式地下粮仓。包括仓底5、多块预制仓壁板3、仓顶4、多功能柱1、多层加强柱2,所述仓壁 板3为内侧塑料板13和外侧的混凝土板结合成整体的结构,周边有连接装置,通过连接装置仓壁板3能与相邻仓壁板3、多功能柱1和多层加强柱2进行连接;所述多功能柱1能对仓壁板3进行定位。多功能柱1从上至下分成数段,最上层的第一段内侧设有第一层仓壁板3,第二段内侧先设有加强柱2,使得加强柱2内侧面与第一层仓壁板3内侧面平齐,再在加强柱2内侧面设有第二层仓壁板3,使得第一、二层仓壁板3部分搭接;用上述类似的设置方式,使得第二、三层仓壁板3部分搭接,一直搭接至最下面一层仓壁板3,形成阶梯状装配式地下粮仓。As shown in Fig. 1, Fig. 3, Fig. 4, Fig. 5 and Fig. 7: this embodiment provides a stepped prefabricated underground granary lined with plastic. It includes a warehouse bottom 5, a plurality of prefabricated warehouse wall panels 3, a warehouse roof 4, a multi-functional column 1, and a multi-layer reinforced column 2. The warehouse wall panel 3 is a structure in which the inner plastic board 13 and the outer concrete board are combined into an integral structure. There is a connecting device in the periphery, through which the warehouse wall plate 3 can be connected with the adjacent warehouse wall plate 3, the multi-functional column 1 and the multi-layer reinforcement column 2; the multi-functional column 1 can position the warehouse wall plate 3. The multi-functional column 1 is divided into several sections from top to bottom, the inner side of the first section of the uppermost layer is provided with a first layer of warehouse wall plate 3, and the inner side of the second section is first provided with a reinforcing column 2, so that the inner surface of the reinforcing column 2 and the first layer The inner side of the warehouse wall plate 3 is flush, and the second layer of the warehouse wall plate 3 is provided on the inner side of the reinforcement column 2, so that the first and second layer of the warehouse wall plate 3 are partially overlapped; 1. The 3 parts of the three-layer warehouse wall panels are overlapped until they are overlapped to the bottom layer of the warehouse wall panels 3 to form a ladder-like assembled underground granary.

所述的多功能柱1和加强柱2采用钢柱或设有钢埋件的混凝土,多功能柱1与加强柱2通过螺栓或焊接缝连接。The multifunctional column 1 and the reinforced column 2 are steel columns or concrete with steel embedded parts, and the multifunctional column 1 and the reinforced column 2 are connected by bolts or welding seams.

所述的预制仓壁板3内侧塑料板13与外侧混凝土采用锚钉连接,内侧塑料板13在仓壁板3下边内侧离开混凝土板端部一定距离,该距离范围内设有第二预埋钢板16;在仓壁板上端设有L形第一预埋钢板15,第一预埋钢板包住混凝土板的外侧边角,混凝土板的左端和右端设有U形预埋钢板,包住混凝土板左右端面的内、外侧边角。The inner plastic plate 13 of the prefabricated warehouse wall panel 3 is connected with the outer concrete by anchors, and the inner plastic plate 13 is a certain distance away from the end of the concrete panel on the inner side of the lower side of the warehouse wall panel 3, and a second embedded steel plate is arranged within the distance range 16. There is an L-shaped first embedded steel plate 15 on the top of the warehouse wall, the first embedded steel plate wraps the outer corner of the concrete slab, and the left and right ends of the concrete slab are provided with U-shaped embedded steel plates to wrap the concrete The inner and outer corners of the left and right end faces of the board.

所述预制仓壁板3环向水平平齐,预制仓壁板3通过U形预埋钢板与多功能柱1或加强柱2焊接在一起,在预制仓壁板3内侧用第一连接钢板6通过U形预埋钢板将相邻预制仓壁板3焊接在一起,在环向预制仓壁板3之间浇筑与预制仓壁板3相同或高一级强度等级的防水混凝土。The prefabricated warehouse wall panel 3 is horizontally aligned in the circumferential direction, and the prefabricated warehouse wall panel 3 is welded together with the multifunctional column 1 or the reinforced column 2 through a U-shaped embedded steel plate, and the first connecting steel plate 6 is used on the inner side of the prefabricated warehouse wall panel 3 The adjacent prefabricated warehouse wall panels 3 are welded together by U-shaped pre-embedded steel plates, and waterproof concrete of the same or higher strength level than the prefabricated warehouse wall panels 3 is poured between the circumferential prefabricated warehouse wall panels 3 .

相邻的上层仓壁板3与下层仓壁板3上下错位搭接,搭接部位的预埋钢板用角焊9焊接,然后用第二连接钢板7将下层仓壁板3的第一预埋钢板15和上层仓壁板3的第二预埋钢板16垂直焊接在一起;所述第二连接钢板7由直角三角形钢板切掉直角而成,且第二连接钢板7为多块,沿钢板角焊均匀分布。The adjacent upper warehouse wall panels 3 and the lower warehouse wall panels 3 are overlapped up and down, and the embedded steel plates at the overlapping parts are welded with fillet welds 9, and then the first embedded steel plates of the lower warehouse wall panels 3 are welded by the second connecting steel plate 7. The steel plate 15 and the second pre-embedded steel plate 16 of the upper warehouse wall plate 3 are vertically welded together; the second connecting steel plate 7 is formed by cutting off a right angle from a right-angled triangle steel plate, and the second connecting steel plate 7 is a plurality of pieces, along the angle of the steel plate Weld evenly distributed.

在所述第二连接钢板7的内侧,设置与第二连接钢板7垂直的通长加强斜板8,所述的加强斜板8分别与下层仓壁板3的第一预埋钢板15和上层仓壁板3的第二预埋钢板16焊接。On the inner side of the second connecting steel plate 7, a full-length reinforcing sloping plate 8 perpendicular to the second connecting steel plate 7 is set, and the reinforcing sloping plate 8 is connected with the first embedded steel plate 15 and the upper layer of the lower warehouse wall plate 3 respectively. The second embedded steel plate 16 of the warehouse wall plate 3 is welded.

相邻预制仓壁板3内侧塑料板13用连接塑料板连接,连接塑料板与预制仓壁板3内侧塑料板13胶粘或焊接。Adjacent prefabricated warehouse wall panels 3 inner plastic plates 13 are connected with connecting plastic plates, and the connecting plastic plates are glued or welded with prefabricated warehouse wall panels 3 inner plastic plates 13 .

实施例二Embodiment two

如图2、图3、图4、图7、图8所示:本实施例提供了一种内衬塑料阶梯状预制装配式地下粮仓。包括仓底5、多块预制仓壁板3、仓顶4、多功能柱1、多层加强柱2,所述仓壁板3为内侧塑料板13和外侧的混凝土板结合成整体的结构,周边有连接装置,通过连接装置仓壁板3能与相邻仓壁板3、多功能柱1和多层加强柱2进行连接;所述多功能柱1能对仓壁板3进行定位。多功能柱1从上至下分成数段,最上层的第一段内侧设有第一层仓壁板3, 第二段内侧先设有加强柱2,使得加强柱2内侧面与第一层仓壁板3内侧面平齐,再在加强柱2内侧面设有第二层仓壁板3,使得第一、二层仓壁板3部分搭接;用上述类似的设置方式,使得第二、三层仓壁板3部分搭接,一直搭接至最下面一层仓壁板3,形成阶梯状装配式地下粮仓。As shown in Fig. 2, Fig. 3, Fig. 4, Fig. 7 and Fig. 8: this embodiment provides a stepped prefabricated underground granary lined with plastic. It includes a warehouse bottom 5, a plurality of prefabricated warehouse wall panels 3, a warehouse roof 4, a multi-functional column 1, and a multi-layer reinforced column 2. The warehouse wall panel 3 is a structure in which the inner plastic board 13 and the outer concrete board are combined into an integral structure. There is a connecting device in the periphery, through which the warehouse wall plate 3 can be connected with the adjacent warehouse wall plate 3, the multi-functional column 1 and the multi-layer reinforcement column 2; the multi-functional column 1 can position the warehouse wall plate 3. The multi-functional column 1 is divided into several sections from top to bottom, the first section of the uppermost layer is provided with a first layer of warehouse wall plate 3, and the second section of the inner side is provided with a reinforcement column 2, so that the reinforcement column 2 inner surface and the first layer The inner side of the warehouse wall plate 3 is flush, and the second layer of the warehouse wall plate 3 is provided on the inner side of the reinforcement column 2, so that the first and second layer of the warehouse wall plate 3 are partially overlapped; 1. The 3 parts of the three-layer warehouse wall panels are overlapped until they are overlapped to the bottom layer of the warehouse wall panels 3 to form a ladder-like assembled underground granary.

所述的多功能柱1和加强柱2采用钢柱或设有钢埋件的混凝土,多功能柱1与加强柱2通过螺栓或焊接缝连接。The multifunctional column 1 and the reinforced column 2 are steel columns or concrete with steel embedded parts, and the multifunctional column 1 and the reinforced column 2 are connected by bolts or welding seams.

所述预制仓壁板3内侧塑料板13与其外侧混凝土采用锚钉连接,内侧塑料板13在仓壁板3下边内侧离开混凝土板端部一定距离,该距离范围内设有第二预埋钢板16;在仓壁板上端设有L形第一预埋钢板15,第一预埋钢板包住混凝土板的外侧边角,混凝土板的左端和右端设有预埋钢板包角,包住混凝土板左右端面的内、外侧边角,且左端设有凸式梯形或半椭圆形插头,右端设有梯形或半椭圆形凹槽。The inner plastic plate 13 of the prefabricated warehouse wall panel 3 is connected with the outer concrete by anchors, and the inner plastic plate 13 is a certain distance away from the end of the concrete panel on the inner side of the lower side of the warehouse wall panel 3, and a second embedded steel plate 16 is arranged within the range of this distance. ; There is an L-shaped first embedded steel plate 15 on the top of the warehouse wall, the first embedded steel plate wraps the outer corner of the concrete slab, and the left and right ends of the concrete slab are provided with embedded steel plate corners to wrap the concrete slab The inner and outer corners of the left and right end faces, and the left end is provided with a convex trapezoidal or semi-elliptical plug, and the right end is provided with a trapezoidal or semi-elliptical groove.

所述预制仓壁板3环向水平平齐,每块预制仓壁板3的凸式梯形或半椭圆型插头插入相邻预制仓壁板3凹式梯形或半椭圆型插槽内;每块预制仓壁板3与多功能柱1或加强柱2焊接连接,相邻预制仓壁板3内侧的竖缝直接采用对接焊连接和/或用连接钢板焊接连接。The prefabricated warehouse wall panels 3 are horizontally aligned in the circumferential direction, and the convex trapezoidal or semi-elliptical plugs of each prefabricated warehouse wall panel 3 are inserted into the concave trapezoidal or semi-elliptical slots of the adjacent prefabricated warehouse wall panels 3; The prefabricated warehouse wall panel 3 is welded to the multifunctional column 1 or the reinforced column 2, and the vertical seam on the inner side of the adjacent prefabricated warehouse wall panel 3 is directly connected by butt welding and/or welded by connecting steel plates.

相邻的上层仓壁板3与下层仓壁板3上下错位搭接,搭接部位的预埋钢板用角焊9焊接,然后用第二连接钢板7将下层仓壁板3的第一预埋钢板15和上层仓壁板3的第二预埋钢板16垂直焊接在一起;所述第二连接钢板7由直角三角形钢板切掉直角而成,且第二连接钢板7为多块,沿钢板角焊均匀分布。The adjacent upper warehouse wall panels 3 and the lower warehouse wall panels 3 are overlapped up and down, and the embedded steel plates at the overlapping parts are welded with fillet welds 9, and then the first embedded steel plates of the lower warehouse wall panels 3 are welded by the second connecting steel plate 7. The steel plate 15 and the second pre-embedded steel plate 16 of the upper warehouse wall plate 3 are vertically welded together; the second connecting steel plate 7 is formed by cutting off a right angle from a right-angled triangle steel plate, and the second connecting steel plate 7 is a plurality of pieces, along the angle of the steel plate Weld evenly distributed.

在所述第二连接钢板7的内侧,设置与第二连接钢板7垂直的通长加强斜板8,所述的加强斜板8分别与下层仓壁板3的第一预埋钢板15和上层仓壁板3的第二预埋钢板16焊接。On the inner side of the second connecting steel plate 7, a full-length reinforcing sloping plate 8 perpendicular to the second connecting steel plate 7 is set, and the reinforcing sloping plate 8 is connected with the first embedded steel plate 15 and the upper layer of the lower warehouse wall plate 3 respectively. The second embedded steel plate 16 of the warehouse wall plate 3 is welded.

相邻预制仓壁板3内侧塑料板13用连接塑料板连接,连接塑料板与预制仓壁板3内侧塑料板13胶粘或焊接。Adjacent prefabricated warehouse wall panels 3 inner plastic plates 13 are connected with connecting plastic plates, and the connecting plastic plates are glued or welded with prefabricated warehouse wall panels 3 inner plastic plates 13 .

实施例三:Embodiment three:

如图1和图3所示:本实施例提供了一种内衬塑料阶梯状预制装配式地下粮仓。包括仓底5、多块预制仓壁板3、仓顶4、多功能柱1、多层加强柱2,所述仓壁板3为内侧塑料板13和外侧的混凝土板结合成整体的结构,周边有连接装置,通过连接装置仓壁板3能与相邻仓壁板3、多功能柱1和多层加强柱2进行连接;所述多功能柱1能对仓壁板3进行定位。多功能柱1从上至下分成数段,最上层的第一段内侧设有第一层仓壁板3,第二段内侧先设有加强柱2,使得加强柱2内侧面与第一层仓壁板3内侧面平齐,再在加强柱2内侧面设有第二层仓壁板3,使得第一、二层仓壁板3部分搭接;用上述类似的设置方式,使得第二、三层仓壁板3部分搭接,一直搭接至最下面一层仓壁板3,形成阶梯状装配式地下粮仓。As shown in Fig. 1 and Fig. 3: this embodiment provides a stepped prefabricated underground granary lined with plastic. It includes a warehouse bottom 5, a plurality of prefabricated warehouse wall panels 3, a warehouse roof 4, a multi-functional column 1, and a multi-layer reinforced column 2. The warehouse wall panel 3 is a structure in which the inner plastic board 13 and the outer concrete board are combined into an integral structure. There is a connecting device in the periphery, through which the warehouse wall plate 3 can be connected with the adjacent warehouse wall plate 3, the multi-functional column 1 and the multi-layer reinforcement column 2; the multi-functional column 1 can position the warehouse wall plate 3. The multi-functional column 1 is divided into several sections from top to bottom, the inner side of the first section of the uppermost layer is provided with a first layer of warehouse wall plate 3, and the inner side of the second section is first provided with a reinforcing column 2, so that the inner surface of the reinforcing column 2 and the first layer The inner side of the warehouse wall plate 3 is flush, and the second layer of the warehouse wall plate 3 is provided on the inner side of the reinforcement column 2, so that the first and second layer of the warehouse wall plate 3 are partially overlapped; 1. The 3 parts of the three-layer warehouse wall panels are overlapped until they are overlapped to the bottom layer of the warehouse wall panels 3 to form a ladder-like assembled underground granary.

所述仓底5为锥形结构,所述仓底5采用双面钢板混凝土组合结构。这种钢板混凝土组合结构中钢板作为仓底板的模板并代替钢筋,不需要在施工时铺设钢筋,节省仓壁的施工费用,降低仓底的施工难度,加快整体施工速度;双层钢板混凝土组合结构提高了仓壁的刚度和强度,有效抵抗土压力和粮食压力,有利于地下粮仓向更深更大的方向发展,增大了该仓型的适用范围,且更有利于粮仓防水防潮问题。The warehouse bottom 5 is a conical structure, and the warehouse bottom 5 adopts a double-sided steel plate concrete composite structure. In this steel plate concrete composite structure, the steel plate is used as the formwork of the warehouse floor and replaces the steel bars. It does not need to lay steel bars during construction, which saves the construction cost of the warehouse wall, reduces the construction difficulty of the warehouse bottom, and speeds up the overall construction speed; the double-layer steel plate concrete composite structure It improves the stiffness and strength of the silo wall, effectively resists earth pressure and grain pressure, and is conducive to the development of underground granaries in a deeper and larger direction, which increases the scope of application of this type of silo, and is more conducive to the waterproof and moisture-proof problems of the granary.

所述仓顶4采用双面钢板混凝土组合结构,所述仓顶4设置进出粮口10,所述仓顶4上方设置覆土11。双面钢板混凝土组合结构结构充分发挥了混凝土的抗压和钢板的抗拉能力,使大跨度仓顶板结构受力更加合理,而且施工时可以用钢板作为模板,极大地降低了施工难度,同时也可加快施工速度。进出粮口设置现代化进出粮设备,便于粮食的存放和提取。The warehouse roof 4 adopts a double-sided steel plate concrete composite structure, the warehouse roof 4 is provided with a grain inlet and outlet 10, and the warehouse roof 4 is provided with a covering soil 11. The double-sided steel plate concrete composite structure fully exerts the compressive resistance of concrete and the tensile capacity of steel plates, making the stress of the roof structure of large-span warehouses more reasonable, and the steel plates can be used as formwork during construction, which greatly reduces the difficulty of construction and at the same time It can speed up the construction speed. The entrance and exit of grain are equipped with modern grain entry and exit equipment to facilitate the storage and extraction of grain.

所述地下粮仓可以实现固态颗粒、粉末物料或液态物料的存储。该地下粮仓密封性和支撑性很好,也可以实现对粉末、液态物料的存储,配合不同的进料和出料设备,应用十分广泛。The underground granary can realize the storage of solid particles, powder materials or liquid materials. The underground granary has good airtightness and support, and can also realize the storage of powder and liquid materials. With different feeding and discharging equipment, it is widely used.

最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其他修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solution of the present invention without limitation, other modifications or equivalent replacements made by those skilled in the art to the technical solution of the present invention, as long as they do not depart from the spirit and spirit of the technical solution of the present invention All should be included in the scope of the claims of the present invention.

Claims (9)

1. the prefabricated bulkhead plate (3) of a kind of prefabricated assembled underground granary, including orlop (5), polylith, silo roof (4), multiple function (1), multilayer reinforcing prop (2), the bulkhead plate (3) combines integral knot for the concrete slab in inner side plastic plate (13) and outside There are attachment means on structure, periphery, can be added with adjacent bulkhead plate (3), multiple function (1) and multilayer by attachment means bulkhead plate (3) Strong post (2) is attached;The multiple function (1) can position to bulkhead plate (3), and its depth anchored into soil is more than orlop (5) depth, is subject to the main bearing member of soil pressure, grain lateral pressure and resistance buoyancy;It is characterized in that:Multiple function (1) it is divided into several sections from top to bottom, the first paragraph inner side of the superiors is provided with ground floor bulkhead plate (3), and second segment inner side is first provided with and adds Strong post (2) so that reinforcing prop (2) medial surface is concordant with ground floor bulkhead plate (3) medial surface, then is set in reinforcing prop (2) medial surface There is second layer bulkhead plate (3) so that first and second layer of bulkhead plate (3) part overlaps;With above-mentioned similar set-up mode so that the 2nd, three layers of bulkhead plate (3) part overlap, and overlap always to bottom one layer of bulkhead plate (3), form stepped assembled underground grain Storehouse.
2. underground granary as claimed in claim 1, it is characterised in that:Described multiple function (1) and reinforcing prop (2) uses steel Post is provided with the concrete of steel embedded part, and multiple function (1) is connected with reinforcing prop (2) by bolt or soldered.
3. underground granary as claimed in claim 1, it is characterised in that:Described prefabricated bulkhead plate (3) inner side plastic plate (13) It is connected using holdfast with outside concrete, inner side plastic plate (13) leaves concrete slab end one in the following inner side of bulkhead plate (3) Set a distance, is provided with the second pre-embedded steel slab (16) in the distance range;The pre-embedded steel slab of L-shaped first (15) is provided with bulkhead plate upper end, First pre-embedded steel slab encases the outside corner of concrete slab, and the left end and right-hand member of concrete slab are provided with U-shaped pre-embedded steel slab, encase mixed The medial and lateral corner of concrete board or so end face.
4. underground granary as claimed in claim 1, it is characterised in that:The prefabricated bulkhead plate (3) inner side plastic plate (13) with Its outside concrete is connected using holdfast, and inner side plastic plate (13) leaves concrete slab end one in the following inner side of bulkhead plate (3) Set a distance, is provided with the second pre-embedded steel slab (16) in the distance range;The pre-embedded steel slab of L-shaped first (15) is provided with bulkhead plate upper end, First pre-embedded steel slab encases the outside corner of concrete slab, and the left end and right-hand member of concrete slab are provided with pre-embedded steel slab cornerite, encase The medial and lateral corner of concrete slab or so end face, and left end is provided with that male is trapezoidal or half elliptic plug, right-hand member be provided with it is trapezoidal or Half elliptic groove.
5. underground granary as claimed in claim 3, it is characterised in that:Prefabricated bulkhead plate (3) the ring level is concordant, prefabricated Bulkhead plate (3) is welded together by U-shaped pre-embedded steel slab with multiple function (1) or reinforcing prop (2), in prefabricated bulkhead plate (3) Side is welded together contiguous prefabricated bulkhead plate (3) by U-shaped pre-embedded steel slab with the first junction steel plate (6), in the prefabricated storehouse of ring The water-proof concrete of strongest grade identical with prefabricated bulkhead plate (3) or high is poured between wallboard (3).
6. underground granary as claimed in claim 4, it is characterised in that:Prefabricated bulkhead plate (3) the ring level is concordant, every piece The male of prefabricated bulkhead plate (3) is trapezoidal or semiellipse type plug inserts that contiguous prefabricated bulkhead plate (3) female is trapezoidal or semiellipse type In slot;Every piece of prefabricated bulkhead plate (3) is welded to connect with multiple function (1) or reinforcing prop (2), in contiguous prefabricated bulkhead plate (3) The perps of side is directly connected using butt welding and/or is welded to connect with junction steel plate.
7. the underground granary as described in claim 3 or 4, it is characterised in that:Adjacent upper strata bulkhead plate (3) and lower floor's bulkhead plate (3) dislocation lap joint up and down, the pre-embedded steel slab of overlapping part is welded with fillet welding (9), then with the second junction steel plate (7) by lower floor storehouse First pre-embedded steel slab (15) of wallboard (3) and the second pre-embedded steel slab (16) vertical welding on upper strata bulkhead plate (3) are together;It is described Second junction steel plate (7) cuts away right angle and forms by right angled triangle steel plate, and the second junction steel plate (7) is polylith, along steel plate angle Weldering is uniformly distributed.
8. underground granary as claimed in claim 7, it is characterised in that:In the inner side of second junction steel plate (7), set with The vertical elongated reinforcement swash plate (8) of second junction steel plate (7), described reinforcement swash plate (8) is respectively with the of lower floor's bulkhead plate (3) Second pre-embedded steel slab (16) welding on one pre-embedded steel slab (15) and upper strata bulkhead plate (3).
9. underground granary as claimed in claim 1, it is characterised in that:Contiguous prefabricated bulkhead plate (3) inner side plastic plate (13) is used Connection plastic plate connection, connection plastic plate is gluing with prefabricated bulkhead plate (3) inner side plastic plate (13) or welds.
CN201620676652.1U 2016-06-29 2016-06-29 Prefabricated assembled underground granary of inside lining plastics echelonment Withdrawn - After Issue CN206189968U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620676652.1U CN206189968U (en) 2016-06-29 2016-06-29 Prefabricated assembled underground granary of inside lining plastics echelonment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620676652.1U CN206189968U (en) 2016-06-29 2016-06-29 Prefabricated assembled underground granary of inside lining plastics echelonment

Publications (1)

Publication Number Publication Date
CN206189968U true CN206189968U (en) 2017-05-24

Family

ID=58736266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620676652.1U Withdrawn - After Issue CN206189968U (en) 2016-06-29 2016-06-29 Prefabricated assembled underground granary of inside lining plastics echelonment

Country Status (1)

Country Link
CN (1) CN206189968U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088761A (en) * 2016-06-29 2016-11-09 河南工业大学 A kind of stepped prefabricated assembled underground granary of plastic lining
CN107503551A (en) * 2017-08-31 2017-12-22 河南工业大学 A kind of semi-underground grain horizontal warehouse with buttress support

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088761A (en) * 2016-06-29 2016-11-09 河南工业大学 A kind of stepped prefabricated assembled underground granary of plastic lining
CN106088761B (en) * 2016-06-29 2018-05-08 河南工业大学 A kind of stepped prefabricated assembled underground granary of plastic lining
CN107503551A (en) * 2017-08-31 2017-12-22 河南工业大学 A kind of semi-underground grain horizontal warehouse with buttress support
CN107503551B (en) * 2017-08-31 2023-11-21 河南工业大学 A semi-underground grain warehouse supported by buttresses

Similar Documents

Publication Publication Date Title
CN106088758B (en) A kind of bilayer assembled underground granary
CN206189968U (en) Prefabricated assembled underground granary of inside lining plastics echelonment
CN106088762B (en) A kind of prefabricated assembled round underground granary of insertion slot type encased steel plate
CN206189966U (en) Circular underground granary of slot -in type prefabricated assembled of inside and outside equal steel plated
CN106013911B (en) A kind of interior steel plated assembled circle underground granary with premoulded filler strip
CN206035051U (en) Prefabricated caulking strips's in area circular underground granary of double -layer steel plate assembled
CN206035052U (en) Prefabricated caulking strips's in area circular underground granary of outer steel plated assembled
CN206035046U (en) Inside and outside prefabricated assembled underground granary of plastics echelonment that all wraps
CN206035050U (en) Prefabricated bulkhead underground granary of slot -in type endocyst plastics
CN206035048U (en) Prefabricated assembled underground granary of interior plastic cover
CN106013909B (en) A kind of outsourcing Plastic preform assembled underground granary
CN106049948B (en) Bag Plastic preform bulkhead underground granary in a kind of insertion slot type
CN206035047U (en) Prefabricated assembled underground granary of plastic cover
CN206035043U (en) Prefabricated assembled rectangle underground granary of outer steel plated echelonment
CN206189967U (en) Circular underground granary of prefabricated assembled of inside and outside equal steel plated echelonment
CN206189414U (en) Circular underground granary of slot -in type prefabricated bulkhead of outer steel plated
CN106088759B (en) The equal stepped prefabricated assembled circular underground granary of steel plated inside and outside one kind
CN206189970U (en) Circular prefabricated assembled underground granary of inside and outside equal steel plated
CN106088764B (en) A kind of stepped prefabricated assembled circular underground granary of encased steel plate
CN106193744B (en) The round prefabricated assembled underground granary of equal steel plated inside and outside one kind
CN106088761B (en) A kind of stepped prefabricated assembled underground granary of plastic lining
CN206189971U (en) Circular underground granary of prefabricated assembled of outer steel plated
CN206438511U (en) A kind of double-deck assembled underground granary
CN106013908B (en) The plastic stepped prefabricated assembled underground granary of material inside and outside one kind
CN105971354B (en) The plastic prefabricated assembled underground granary of material inside and outside one kind

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20170524

Effective date of abandoning: 20180508

AV01 Patent right actively abandoned

Granted publication date: 20170524

Effective date of abandoning: 20180508

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned