CN202139986U CN 201120198586 CN201120198586U CN202139986U CN 202139986 U CN202139986 U CN 202139986U CN 201120198586 CN201120198586 CN 201120198586 CN 201120198586 U CN201120198586 U CN 201120198586U CN 202139986 U CN202139986 U CN 202139986U
Authority
CN
China
Prior art keywords
protective door
door
construction
construction elevator
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120198586
Other languages
Chinese (zh)
Inventor
蒋治国
唐恩宽
刘文伍
廖练红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN 201120198586 priority Critical patent/CN202139986U/en
Application granted granted Critical
Publication of CN202139986U publication Critical patent/CN202139986U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Elevator Door Apparatuses (AREA)

Abstract

The utility model provides a protective door for a construction elevator. The protective door for the construction elevator is characterized by comprising a hinge connection device, a door body, a barrier device and a foot protecting plate, wherein the upper part of the door body is connected with a building wall body through the hinge connection device, the barrier device is transversely arranged in the building wall body at the middle lower part of the elevator, and the foot protecting plate is arranged at the lower part of the door body. The protective door for the construction elevator has the advantages that as the protective door is directly arranged at the inner part of a door frame, space of a wall surface is not occupied, and follow-up constructions cannot be affected; as the protective door is formed by welding on-site remaining reinforcing steel bars, the production cost is greatly reduced; free turning and opening of the protective door are realized; the defect that the traditional protective door is firmly fixed and cannot be opened is overcome; and the protective door is very beneficial for the in and out requirements for the constructions in an elevator well.

Description

A kind of construction elevator mouth protective door
Technical field
The utility model relates to building trade, particularly a kind of construction elevator mouth protective door.
Background technology
All kinds of highrise buildings all are designed with a large amount of elevators; Greatly facilitate people's trip and daily life, but simultaneously also for the safety management work in the work progress brings challenges, for the architectural complex of the big scale of construction; The lift port that each constructing operation layer all has quantity not wait needs protection; Such elevator hole is with countless, and the emphasis of hole protection certainly will the becoming site safety management before formal elevator door Installation and Debugging, therefore safe and reliable protective door device must be arranged.
The elevator protective door that uses in the reality was taked the reinforced mesh welding in the past, directly was fixed on the shear wall of both sides with expansion bolt; Should waste a large amount of expansion bolts, again because of the both sides shear wall has been covered certain area by protective door, for follow-up plastering construction is made troubles; The workman can remove protective door when carrying out plastering construction; In most cases can not get timely recovery, can bring great potential safety hazard, and dismounting work has also caused certain waste in man-hour to site safety.
Summary of the invention
The purpose of the utility model is for simplified structure, and recycling avoids influencing follow-up construction, and the spy provides a kind of construction elevator mouth protective door.
The utility model provides a kind of construction elevator mouth protective door, it is characterized in that: described construction elevator mouth protective door comprises hinge joining means 1, door body 2, the device 3 of blocking, foot guard plate 4;
Wherein: the top of door body 2, the device 1 that is connected through the hinge is connected with construction wall 5, and the device 3 of blocking laterally is installed in 5 li of the construction walls of lift port middle and lower part, and foot guard plate 4 is installed in the bottom of a body 2.
Described door body 2 is the frame construction of reinforcing bar welding.
Described hinge joining means 1 does, the reinforcing bar annulus that is fixed on the body 2 directly is enclosed within formed structure on the steel pipe that is embedded in the body of wall 5, and the steel pipe that is fixed in the hinge joining means 1 in the body of wall connects through bolt, or the mode of boring is installed in the body of wall.
Can realize upwards freely opening of door, tension member is set, connect, can fix the protective door that turns over rope at end face.
The advantage of the utility model:
The described construction elevator mouth of the utility model protective door, protective door directly is contained in doorframe inside, does not take the metope space, follow-up construction is not caused obstacle.Protective door greatly reduces cost of manufacture by the clout reinforcing bar welding at scene.Protective door has been realized freely being flipped open, and it is fixing dead to have overcome in the past protective door, and the drawback that can not open helps the construction turnover needs in the elevator shaft very much.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is done further detailed explanation:
Fig. 1 is a construction elevator mouth protective door mounting structure sketch map;
Fig. 2 is the sketch map that steel pipe is installed through bolt in the hinge joining means;
Fig. 3 is the sketch map that steel pipe is installed through bore mode in the hinge joining means.
The specific embodiment
Embodiment 1
Present embodiment provides a kind of construction elevator mouth protective door, it is characterized in that: described construction elevator mouth protective door comprises hinge joining means 1, door body 2, the device 3 of blocking, foot guard plate 4;
Wherein: the top of door body 2, the device 1 that is connected through the hinge is connected with construction wall 5, and the device 3 of blocking laterally is installed in 5 li of the construction walls of lift port middle and lower part, and foot guard plate 4 is installed in the bottom of a body 2.
Described door body 2 is the frame construction of reinforcing bar welding.
Described hinge joining means 1 is that the reinforcing bar annulus that is fixed on the body 2 directly is enclosed within formed structure on the steel pipe that is embedded in the body of wall 5.
The steel pipe that is fixed in the hinge joining means 1 in the body of wall connects through bolt.
Can realize upwards freely opening of door, tension member is set, connect, can fix the protective door that turns over rope at end face.
Embodiment 2
Present embodiment provides a kind of construction elevator mouth protective door, it is characterized in that: described construction elevator mouth protective door comprises hinge joining means 1, door body 2, the device 3 of blocking, foot guard plate 4;
Wherein: the top of door body 2, the device 1 that is connected through the hinge is connected with construction wall 5, and the device 3 of blocking laterally is installed in 5 li of the construction walls of lift port middle and lower part, and foot guard plate 4 is installed in the bottom of a body 2.
Described door body 2 is the frame construction of reinforcing bar welding.
Described hinge joining means 1 is that the reinforcing bar annulus that is fixed on the body 2 directly is enclosed within formed structure on the steel pipe that is embedded in the body of wall 5.
Be fixed on the steel pipe in the body of wall in the hinge joining means 1, be installed in the body of wall through the mode of holing.
Can realize upwards freely opening of door, tension member is set, connect, can fix the protective door that turns over rope at end face.

Claims (3)

1. construction elevator mouth protective door, it is characterized in that: described construction elevator mouth protective door comprises hinge joining means (1), door body (2), the device of blocking (3), foot guard plate (4);
Wherein: the top of door body (2), the device that is connected through the hinge (1) is connected with construction wall (5), and the device of blocking (3) laterally is installed in construction wall (5) lining of lift port middle and lower part, and foot guard plate (4) is installed in the bottom of a body (2).
2. according to the described construction elevator mouth of claim 1 protective door, it is characterized in that: described door body (2) is the frame construction of reinforcing bar welding.
3. according to the described construction elevator mouth of claim 1 protective door, it is characterized in that: described hinge joining means (1) is that the reinforcing bar annulus that is fixed on the body (2) directly is enclosed within formed structure on the steel pipe that is embedded in the body of wall (5).
?
CN 201120198586 2011-06-14 2011-06-14 Protective door for construction elevator Expired - Fee Related CN202139986U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120198586 CN202139986U (en) 2011-06-14 2011-06-14 Protective door for construction elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120198586 CN202139986U (en) 2011-06-14 2011-06-14 Protective door for construction elevator

Publications (1)

Publication Number Publication Date
CN202139986U true CN202139986U (en) 2012-02-08

Family

ID=45551048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120198586 Expired - Fee Related CN202139986U (en) 2011-06-14 2011-06-14 Protective door for construction elevator

Country Status (1)

Country Link
CN (1) CN202139986U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605964A (en) * 2012-04-06 2012-07-25 中国十七冶集团有限公司 Separately mounted grille on elevator shaft opening and construction method of separately mounted grille
CN107630563A (en) * 2017-08-22 2018-01-26 中国十七冶集团有限公司 A kind of protective door for elevator shaft fixing device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605964A (en) * 2012-04-06 2012-07-25 中国十七冶集团有限公司 Separately mounted grille on elevator shaft opening and construction method of separately mounted grille
CN102605964B (en) * 2012-04-06 2015-03-11 中国十七冶集团有限公司 Separately mounted grille on elevator shaft opening and construction method of separately mounted grille
CN107630563A (en) * 2017-08-22 2018-01-26 中国十七冶集团有限公司 A kind of protective door for elevator shaft fixing device
CN107630563B (en) * 2017-08-22 2022-01-18 中国十七冶集团有限公司 Elevator shaft protective door fixing device

Similar Documents

Publication Publication Date Title
CN102583131B (en) A kind of elevator shaft wall adopting combined shaft frame to assemble
CN208884773U (en) A kind of vertical piece attachment device of assembly concrete shear wall
CN103912011B (en) The prefabricated assembled underground structure of open cut
Labò et al. Design of diagrid exoskeletons for the retrofit of existing RC buildings
CN101603338B (en) Assembly integrated precast concrete shear wall and construction method thereof
CN202139986U (en) Protective door for construction elevator
KR20130018343A (en) Seismic retrofit method of src enlarged section using connection joint with anchor plate and steel bar tie
CN101487290A (en) Construction method for construction floating window
CN106088642B (en) The anti-bend reinforced structure and its construction method of a kind of prefabricated hollow floor
CN203213344U (en) Assembled integral type reinforced concrete shear wall structure with high industrialization rate
CN207647215U (en) Punch ruggedized construction after a kind of shear wall large area
CN103243931B (en) Multi-story masonry unit-door external elevator structure and construction method thereof
CN105804416B (en) The attachment structure of prefabrication tower crane
CN205296407U (en) Embedded steel construction assembly house post roof beam connection structure
CN203201171U (en) Unit door type multi-floor masonry residential building structure with additional elevator
CN103352579B (en) Adopt strengthening reconstruction masonry structure and the construction method of additional shelter bridge and additional elevator
CN201236506Y (en) Wire holes on communication machine room floor
CN216340069U (en) Assembled reinforced concrete antidetonation post
KR101248509B1 (en) Building Remodeling Construction Method Using Precast Concrete Panel, and Remodeled Building Thereof
CN204897084U (en) Steel construction elevartor shaft
CN204098519U (en) Do not register one's residence balcony rapid reinforcement structure in old community
CN111749353A (en) Replaceable energy consumption connecting device for self-resetting shear wall
CN106906923A (en) The attachment means of fabricated shear wall horizontal joint and connection method
CN207406012U (en) Construction lift tool formula overhangs escape way
CN109680868A (en) Complete prefabricated ribbed plate exterior wall single storey industry workshop

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120208