CN102605964A - Separately mounted grille on elevator shaft opening and construction method of separately mounted grille - Google Patents
Separately mounted grille on elevator shaft opening and construction method of separately mounted grille Download PDFInfo
- Publication number
- CN102605964A CN102605964A CN2012100982398A CN201210098239A CN102605964A CN 102605964 A CN102605964 A CN 102605964A CN 2012100982398 A CN2012100982398 A CN 2012100982398A CN 201210098239 A CN201210098239 A CN 201210098239A CN 102605964 A CN102605964 A CN 102605964A
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- circular hole
- hole
- nut
- elevator shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a construction method for a separately mounted grille on an elevator shaft opening. The method includes steps of detaching a shear wall formwork; mounting a crossbeam; placing a bottom beam; placing a baffle plate; mounting upright columns; mounting a top beam; and reinforcing. The construction method is safe and reliable, installation and detachment are simple, transfer use consumption is free, construction cost is lowered effectively, protection to new poured shear wall concrete finished products is facilitated, and the construction method is applicable to shear wall elevator shaft opening in different widths and edge-adjacent holes in different widths.
Description
Technical field
The invention belongs to a kind of architectural furniture and job practices, especially relate to a kind of elevator shaft road junction bulk type iron railings and job practices.
Background technology
Existing commonly used elevator shaft road junction protective equipment often adopts fixedly iron railings or set up the steel pipe guardrail of welding; Instruments carryings such as the whole carrying of the former iron railings difficulty is fragile greatly, welding machine are time-consuming, the waste of embedded iron parts immobilization material is big, the fixing destructible shear wall concrete structure and the insecure potential safety hazard that exists of newly building of expansion bolt; The latter protects imprecision and is prone to and is destroyed, and has potential safety hazard.
Summary of the invention
The purpose of this invention is to provide a kind of elevator shaft road junction bulk type iron railings and job practices that is used for security protection, each member can be made convenient transportation in factory's batch machining; Adopt the sleeve spanner to install, safe and reliable, mounting or dismounting are simple; No consumption is used in turnover; Effectively reduce construction cost, the shear wall concrete finished product that helps newly building protection is applicable to the shear wall elevator shaft road junction of different in width and faces the hole, limit.
The objective of the invention is to realize like this; A kind of elevator shaft road junction bulk type iron railings, be characterized in this elevator shaft road junction bulk type iron railings security protection facility mainly by along elevator shaft road junction metope from bottom to top horizontal arrangement bottom girder, baffle plate, two crossbeams, capping beams, in the middle of crossbeam, pass and insert respectively up and down the column evenly arranged by a determining deviation along metope in back timber and the bottom girder circular hole the circular hole and on the baffle plate in the pipe, pass shear wall pre-embedded bolt hole be fixed on the set bolt at crossbeam two ends, vertically pass back timber and top cross beam about each one vertically add fixing bolt and form.Bottom girder is made by square steel, and circular hole is bored along a determining deviation in its end face middle part, so that column inserts.Baffle plate is welded by steel pipe and band steel, and this steel pipe is evenly arranged by a determining deviation, so that column inserts.Crossbeam is made by square steel, and its end face and bottom surface middle part symmetry and evenly bore circular hole by a determining deviation is so that column inserts; Have circular hole on the crossbeam top and bottom between this external the right and left circular hole, above circular hole less penetrate so that add fixing bolt; Following circular hole is bigger, is convenient to nut and sleeve spanner and stretches into and reinforce operation, symmetry and have slotted hole by certain spacing before and after the crossbeam facade; Front slotted hole width is bigger; Nut is satisfied in this hole and the sleeve spanner stretches into operation, and back slotted hole width is less, and this hole satisfies that set bolt penetrates and the fixed by nut crossbeam; Per two adjacent oval distance between borehole are 1/4 of slotted hole length, from the shear wall concrete, carry out the set bolt installation in the different spacing pre-embedded bolt hole to satisfy.Capping beam is made by square steel, and circular hole is bored along a determining deviation in its middle part, bottom surface, so that column inserts; Have circular hole on the crossbeam top and bottom between this external the right and left circular hole, below circular hole less penetrate so that add fixing bolt; Top circular hole is bigger, is convenient to nut and gets into reinforcing.Column is made by round steel.Add fixing bolt and make with full silk screw rod, tighten reinforcing with each nut up and down, the upper cap nut after the reinforcing is in the capping beam square steel, and following nut effectively prevents artificially to become flexible dismounting with common spanner in the crossbeam square steel.Set bolt is a gib headed bolt, reinforces with penetrating in the pre-embedded bolt hole and in the crossbeam slotted hole from shear wall, and it is fixing in crossbeam, to adopt the sleeve spanner to tighten with nut.
Elevator shaft of the present invention road junction bulk type iron railings job practices is: and shear wall formwork dismounting-crossbeam installation-bottom girder puts-and baffle plate puts-installation-reinforcing of column installation-capping beam.Shear wall formwork is removed: during dismounting shear wall formwork is added fixing bolt and extract out, reserve shear wall formwork and reinforce the pre-embedded bolt hole, and iron railings installation position metope and earth material are cleaned out; Crossbeam is installed: formwork reinforcement pre-embedded bolt hole penetrates from the shear wall back side set bolt; Adjusting position, the crossbeam left and right sides selects slotted hole to entangle anchor stud head to make the two ends extension elongation about equally; Fastening the hold-doun nut installation in the crossbeam slotted hole nut with the sleeve spanner, consistency from top to bottom all alignd its each circular hole of crossbeam up and down when two crossbeams were installed up and down on same vertical line; Bottom girder is put: bottom girder is put along the wall limit on the terrace of position placed in the middle, elevator shaft road junction, and the bottom girder end face is opened one of circular hole and is faced up; Baffle plate is put: baffle plate is erected be superimposed upon on the bottom girder, baffle plane is close to the left and right sides, elevator shaft road junction shear wall metope, the steel pipe on the baffle plate in the outside and the socket of each steel pipe all aim at the circular hole at bottom girder top; Column is installed: from two crossbeam top and bottom circular holes, insert the steel pipe socket that passes in the baffle plate to column downwards by root and inject in the bottom girder tip circle hole; Capping beam is installed: capping beam is lifted each circular hole alignment post top of its bottom is pressed down again, each column top is all anchored in the capping beam circular hole; Reinforce: according to distance between capping beam and crossbeam; The nut that full silk is added the fixing bolt top is screwed to earlier and adds appropriate location, fixing bolt stage casing; To add fixing bolt again inserts from the circular hole of capping beam top and makes this nut in capping beam; Add the fixing bolt lower end in putting in crossbeam end face circular hole, will add fixing bolt lower end snail cap with the sleeve spanner again and put in and tighten reinforcing in the crossbeam.
Elevator shaft road junction bulk type iron railings and job practices that the present invention proposes, each member can be made convenient transportation in factory's batch machining; Adopt the sleeve spanner to install, safe and reliable, mounting or dismounting are simple; No consumption is used in turnover; Effectively reduce construction cost, the shear wall concrete finished product that helps newly building protection is applicable to the shear wall elevator shaft road junction of different in width and faces the hole, limit.
Combine accompanying drawing and embodiment that elevator shaft road junction bulk type iron railings and the job practices that the present invention proposes is further described at present.
Description of drawings
Fig. 1 is the elevator shaft road junction bulk type iron railings front elevation view that the present invention proposes.
Fig. 2 is the elevator shaft road junction bulk type iron railings side elevational view that the present invention proposes.
Among Fig. 1, Fig. 2:
1, bottom girder 2, baffle plate 3, crossbeam 4, column 5, capping beam 6, set bolt 7, formwork reinforcement pre-embedded bolt hole 8, add fixing bolt 9, steel pipe 10, elevator shaft road junction.
The specific embodiment
From Fig. 1, Fig. 2, can find out: elevator shaft road junction bulk type iron railings is this elevator shaft road junction bulk type iron railings security protection facility, mainly by along elevator shaft road junction metope from bottom to top the bottom girder of horizontal arrangement (1), baffle plate (2), two crossbeams (3), capping beam (5), in the middle of crossbeam, pass and insert respectively up and down the column (4) evenly arranged by a determining deviation along metope in back timber and the bottom girder circular hole the circular hole and on the baffle plate in the pipe, pass shear wall pre-embedded bolt hole (7) be fixed on the set bolt (6) at crossbeam two ends, vertically pass back timber (5) and top cross beam (3) about each one vertically add fixing bolt (8) and form.Bottom girder (1) is made by square steel, and circular hole is bored along a determining deviation in its end face middle part, so that column (4) inserts.Baffle plate (2) is welded by steel pipe and band steel, and this steel pipe is evenly arranged by a determining deviation, so that column (4) inserts.Crossbeam (3) is made by square steel, and its end face and bottom surface middle part symmetry and evenly bore circular hole by a determining deviation is so that column (4) inserts; Have circular hole on the crossbeam top and bottom between this external the right and left circular hole, above circular hole less penetrate so that add fixing bolt (8); Following circular hole is bigger, is convenient to nut and sleeve spanner and stretches into and reinforce operation, symmetry and have slotted hole by certain spacing before and after crossbeam (3) facade; Front slotted hole width is bigger; Nut is satisfied in this hole and the sleeve spanner stretches into operation, and back slotted hole width is less, and this hole is satisfied set bolt (6) and penetrated and the fixed by nut crossbeam; Per two adjacent oval distance between borehole are 1/4 of slotted hole length, from the shear wall concrete, carry out set bolt (6) installation in the different spacing pre-embedded bolt hole (7) to satisfy.Capping beam (5) is made by square steel; Circular hole is bored along a determining deviation in its middle part, bottom surface, so that column (4) inserts, has circular hole on crossbeam (3) top and bottom between this external the right and left circular hole; Following circular hole is less; Penetrate so that add fixing bolt (8), above circular hole bigger, be convenient to nut and get into reinforce.Column (4) is made by round steel.Add fixing bolt (6) and make with full silk screw rod, tighten reinforcing with each nut up and down, the upper cap nut after the reinforcing is in capping beam (5) square steel, and following nut effectively prevents artificially to become flexible dismounting with common spanner in crossbeam (3) square steel.Set bolt (6) is a gib headed bolt, reinforces with penetrating in pre-embedded bolt hole (7) and in crossbeam (3) slotted hole from shear wall, in crossbeam (3), adopts the sleeve spanner to tighten fixing with nut.
Elevator shaft of the present invention road junction bulk type iron railings job practices is: and shear wall formwork dismounting-crossbeam (3) installation-bottom girder (1) puts-and baffle plate (2) puts-column (4) installation-capping beam (5) installation-reinforcing.Shear wall formwork is removed: during dismounting shear wall formwork is added fixing bolt and extract out, reserve shear wall formwork and reinforce pre-embedded bolt hole (7), and iron railings installation position metope and earth material are cleaned out; Crossbeam (3) is installed: formwork reinforcement pre-embedded bolt hole (7) penetrates from the shear wall back side set bolt (6); Adjusting crossbeam (3) position, the left and right sides selects slotted hole to entangle set bolt (6) head to make the two ends extension elongation about equally; Fastening the hold-doun nut installation in crossbeam (3) slotted hole nut with the sleeve spanner, consistency from top to bottom all alignd its each circular hole of crossbeam (3) up and down when two crossbeams (3) were installed up and down on same vertical line; Bottom girder (1) is put: bottom girder (1) is put along the wall limit on the terrace of position placed in the middle, elevator shaft road junction, and bottom girder (1) end face is opened one of circular hole and is faced up; Baffle plate (2) is put: baffle plate (2) is erected be superimposed upon on the bottom girder (1), the left and right sides, elevator shaft road junction shear wall metope is close on baffle plate (2) plane, the steel pipe on the baffle plate (2) in the outside and the socket of each steel pipe all aim at the circular hole at bottom girder (1) top; Column (4) is installed: from the circular hole of two crossbeams (3) top and bottom, insert the steel pipe socket that passes in the baffle plate (2) to column (4) downwards by root and inject in bottom girder (1) the tip circle hole; Capping beam (5) is installed: capping beam (5) is lifted each circular hole alignment post (4) top of its bottom is pressed down again, each column (4) top is all anchored in capping beam (5) circular hole; Reinforce: according to distance between capping beam (5) and crossbeam (3); The nut that the full silk of general adds fixing bolt (8) top is screwed to earlier and adds fixing bolt (8) appropriate location, stage casing; To add fixing bolt (8) again inserts from the circular hole of capping beam (5) top and makes this nut in capping beam; Add fixing bolt (8) lower end in putting in crossbeam (3) end face circular hole, will add fixing bolt (8) lower end nut with the sleeve spanner again and put in and tighten reinforcing in the crossbeam.
Claims (7)
1. elevator shaft road junction bulk type iron railings, it is characterized in that this elevator shaft road junction bulk type iron railings security protection facility mainly by along elevator shaft road junction metope from bottom to top the bottom girder of horizontal arrangement (1), baffle plate (2), two crossbeams (3), capping beam (5), in the middle of crossbeam, pass and insert respectively up and down the column (4) evenly arranged by a determining deviation along metope in back timber and the bottom girder circular hole the circular hole and on the baffle plate in the pipe, pass shear wall pre-embedded bolt hole (7) be fixed on the set bolt (6) at crossbeam two ends, vertically pass capping beam (5) and top cross beam (3) about each one vertically add fixing bolt (8) and form.
2. elevator shaft according to claim 1 road junction bulk type iron railings is characterized in that bottom girder (1) is made by square steel, and circular hole is bored along a determining deviation in its end face middle part, so that column (4) inserts; Baffle plate (2) is welded by steel pipe and band steel, and this steel pipe is evenly arranged by a determining deviation, so that column (4) inserts.
3. elevator shaft according to claim 1 road junction bulk type iron railings is characterized in that crossbeam (3) is made by square steel, its end face and bottom surface middle part symmetry and evenly bore circular hole by a determining deviation; So that column (4) inserts, have circular hole on the crossbeam top and bottom between this external the right and left circular hole, above circular hole less; So that adding fixing bolt (8) penetrates; Following circular hole is bigger, is convenient to nut and sleeve spanner and stretches into and reinforce operation, symmetry and have slotted hole by certain spacing before and after crossbeam (3) facade; Front slotted hole width is bigger; Nut is satisfied in this hole and the sleeve spanner stretches into operation, and back slotted hole width is less, and this hole is satisfied set bolt (6) and penetrated and the fixed by nut crossbeam; Per two adjacent oval distance between borehole are 1/4 of slotted hole length, from the shear wall concrete, carry out set bolt (6) installation in the different spacing pre-embedded bolt hole (7) to satisfy.
4. elevator shaft according to claim 1 road junction bulk type iron railings is characterized in that capping beam (5) is made by square steel, and circular hole is bored along a determining deviation in its middle part, bottom surface; So that column (4) inserts; Have circular hole on crossbeam (3) top and bottom between this external the right and left circular hole, below circular hole less penetrate so that add fixing bolt (8); Top circular hole is bigger, is convenient to nut and gets into reinforcing.
5. elevator shaft according to claim 1 road junction bulk type iron railings; It is characterized in that column (4) made by round steel; Add fixing bolt (8) and make with full silk screw rod, with up and down respectively a nut tighten reinforcing, the upper cap nut after the reinforcing is in capping beam (5) square steel; Following nut effectively prevents artificially to remove with common spanner is loosening in crossbeam (3) square steel.
6. elevator shaft according to claim 1 road junction bulk type iron railings; It is characterized in that set bolt (6) is a gib headed bolt; Reinforce with penetrating in pre-embedded bolt hole (7) and in crossbeam (3) slotted hole from shear wall, in crossbeam (3), adopt the sleeve spanner to tighten fixing with nut.
7. the job practices of an elevator shaft according to claim 1 road junction bulk type iron railings, its construction sequence is: shear wall formwork is removed, and---crossbeam (3) is installed, and---bottom girder (1) is put, and---baffle plate (2) is put, and---column (4) is installed---capping beam (5) installations---reinforcing;
A, shear wall formwork are removed: during dismounting shear wall formwork is added fixing bolt and extract out, reserve shear wall formwork and reinforce pre-embedded bolt hole (7), and iron railings installation position metope and earth material are cleaned out;
B, crossbeam (3) are installed: formwork reinforcement pre-embedded bolt hole (7) penetrates from the shear wall back side set bolt (6); Adjusting crossbeam (3) position, the left and right sides selects slotted hole to entangle set bolt (6) head to make the two ends extension elongation about equally; Fastening the hold-doun nut installation in crossbeam (3) slotted hole nut with the sleeve spanner, consistency from top to bottom all alignd its each circular hole of crossbeam (3) up and down when two crossbeams (3) were installed up and down on same vertical line;
C, bottom girder (1) are put: bottom girder (1) is put along the wall limit on the terrace of position placed in the middle, elevator shaft road junction, and bottom girder (1) end face is opened one of circular hole and is faced up;
D, baffle plate (2) are put: baffle plate (2) is erected be superimposed upon on the bottom girder (1), the left and right sides, elevator shaft road junction shear wall metope is close on baffle plate (2) plane, the steel pipe on the baffle plate (2) in the outside and the socket of each steel pipe all aim at the circular hole at bottom girder (1) top;
E, column (4) are installed: from the circular hole of two crossbeams (3) top and bottom, insert the steel pipe socket that passes in the baffle plate (2) to column (4) downwards by root and inject in bottom girder (1) the tip circle hole;
F, capping beam (5) install: capping beam (5) is lifted each circular hole alignment post (4) top of its bottom is pressed down again, each column (4) top is all anchored in capping beam (5) circular hole;
G, reinforcing: according to distance between capping beam (5) and crossbeam (3); The nut that the full silk of general adds fixing bolt (8) top is screwed to earlier and adds fixing bolt (8) appropriate location, stage casing; To add fixing bolt (8) again inserts from the circular hole of capping beam (5) top and makes this nut in capping beam; Add fixing bolt (8) lower end in putting in crossbeam (3) end face circular hole, will add fixing bolt (8) lower end nut with the sleeve spanner again and put in and tighten reinforcing in the crossbeam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210098239.8A CN102605964B (en) | 2012-04-06 | 2012-04-06 | Separately mounted grille on elevator shaft opening and construction method of separately mounted grille |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210098239.8A CN102605964B (en) | 2012-04-06 | 2012-04-06 | Separately mounted grille on elevator shaft opening and construction method of separately mounted grille |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102605964A true CN102605964A (en) | 2012-07-25 |
CN102605964B CN102605964B (en) | 2015-03-11 |
Family
ID=46523693
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210098239.8A Active CN102605964B (en) | 2012-04-06 | 2012-04-06 | Separately mounted grille on elevator shaft opening and construction method of separately mounted grille |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102605964B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104723092A (en) * | 2015-03-20 | 2015-06-24 | 国家电网公司 | Clamping device and method used for guaranteeing equality of extension lengths of two ends of through bolt |
CN110924431A (en) * | 2019-11-22 | 2020-03-27 | 上海二十冶建设有限公司 | Comprehensive pipe gallery faces limit protector |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3425165A (en) * | 1967-11-24 | 1969-02-04 | Gen Safety Inc | Extensible gate for elevator shafts |
CN101177981A (en) * | 2007-12-18 | 2008-05-14 | 张家港固耐特围栏系统有限公司 | Fence |
CN201661081U (en) * | 2010-04-13 | 2010-12-01 | 中建七局第二建筑有限公司 | Elevator shaft safety protection device |
CN202139986U (en) * | 2011-06-14 | 2012-02-08 | 中国建筑第五工程局有限公司 | Protective door for construction elevator |
-
2012
- 2012-04-06 CN CN201210098239.8A patent/CN102605964B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3425165A (en) * | 1967-11-24 | 1969-02-04 | Gen Safety Inc | Extensible gate for elevator shafts |
CN101177981A (en) * | 2007-12-18 | 2008-05-14 | 张家港固耐特围栏系统有限公司 | Fence |
CN201661081U (en) * | 2010-04-13 | 2010-12-01 | 中建七局第二建筑有限公司 | Elevator shaft safety protection device |
CN202139986U (en) * | 2011-06-14 | 2012-02-08 | 中国建筑第五工程局有限公司 | Protective door for construction elevator |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104723092A (en) * | 2015-03-20 | 2015-06-24 | 国家电网公司 | Clamping device and method used for guaranteeing equality of extension lengths of two ends of through bolt |
CN110924431A (en) * | 2019-11-22 | 2020-03-27 | 上海二十冶建设有限公司 | Comprehensive pipe gallery faces limit protector |
Also Published As
Publication number | Publication date |
---|---|
CN102605964B (en) | 2015-03-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211447708U (en) | Super high-rise building construction elevator feeding platform support system that encorbelments | |
CN108005401A (en) | A kind of support and change method of the column of existing frame structure base isolation reinforcement | |
CN103306214A (en) | Novel reinforcement device for reinforced concrete beam and floor slab and construction method thereof | |
CN106400691A (en) | Integrated construction process for anti-collision wall formwork | |
CN107165056B (en) | Anti-overturning steel bar bracket for cantilever bent cap concrete pouring and mounting method thereof | |
CN103552911B (en) | A kind of movable boom hoisting and the construction installation method of use thereof | |
WO2020098394A1 (en) | Gob-side entry confined concrete supporting construction device and mechanized construction method | |
CN105347142B (en) | A kind of building hoist is mounted on the threading installation method on basement roof | |
CN202945798U (en) | Overhanging type scaffold corner device | |
CN103161313A (en) | Connection method of main reinforcement of constructional column of infilled wall and framed girder | |
CN102605964B (en) | Separately mounted grille on elevator shaft opening and construction method of separately mounted grille | |
CN206071096U (en) | The underpinning device of load bearing wall in brick mix structure | |
CN211899791U (en) | Prefabricated floor preformed hole adopts and wears steel pull rod to consolidate masonry structure | |
CN204343642U (en) | Builder's jack corner support frame | |
CN103993738A (en) | Floor penetrating and anchoring type overhanging unloading steel platform | |
CN204023422U (en) | A kind of assembling Coping Construction operating platform | |
CN111691300A (en) | A concrete placement support device for steel-concrete composite beam | |
CN206591839U (en) | A kind of reinforcing bar posting having enough to meet the need | |
CN206034929U (en) | Hoisting frame of dress behind concrete square column capital | |
CN210507514U (en) | Rib column type anchor rod retaining wall structure without groove | |
CN203603490U (en) | Supporting structure used for erecting formwork truss on prefabricated beam | |
CN113338537A (en) | Construction method of ultrahigh large-section concrete frame column | |
CN107630563B (en) | Elevator shaft protective door fixing device | |
CN205224571U (en) | Anchor of builder's jack | |
CN204040495U (en) | A kind of suspension fixing support rack of high-order cast-in fixing bolt |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |