CN201991013U - High-piled tower footing structure of tower crane concrete-filled steel tube - Google Patents

High-piled tower footing structure of tower crane concrete-filled steel tube Download PDF

Info

Publication number
CN201991013U
CN201991013U CN2011200495379U CN201120049537U CN201991013U CN 201991013 U CN201991013 U CN 201991013U CN 2011200495379 U CN2011200495379 U CN 2011200495379U CN 201120049537 U CN201120049537 U CN 201120049537U CN 201991013 U CN201991013 U CN 201991013U
Authority
CN
China
Prior art keywords
steel pipe
concrete
tower
pipe column
cushion cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200495379U
Other languages
Chinese (zh)
Inventor
金瓯
胡正华
赵林峰
郑笑芳
姜莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENZHOU CONSTRUCTION GROUP CO Ltd
Original Assignee
WENZHOU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENZHOU CONSTRUCTION GROUP CO Ltd filed Critical WENZHOU CONSTRUCTION GROUP CO Ltd
Priority to CN2011200495379U priority Critical patent/CN201991013U/en
Application granted granted Critical
Publication of CN201991013U publication Critical patent/CN201991013U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

A high-piled tower footing structure of a tower crane concrete-filled steel tube belongs to the technical field of building construction and comprises four cast-in-place concrete piles and four steel pipe columns, wherein each cast-in-place concrete pile has a buried length of 40m and a diameter ranging from 600mm to 800mm, and is arranged on a base. Each steel pipe column has a wall thickness of 8mm, a diameter of 600mm, and is sleeved to each cast-in-place place concrete pile. A bearing platform is arranged at the tops of the steel pipe columns to match with the steel pipe columns, the lower end of each steel pipe column stretches into foundation soil in a depth ranging from 2400mm to 2480mm. The length of each steel pipe column, from the bottom of the bearing platform to the upper portion of the steel pipe column above the foundation soil, ranges from 4m to 7m. The top of each steel pipe column is anchored into the bearing platform with a length of 150mm, a first concrete layer is poured into the cast-in-place concrete piles and the steel pipe columns, and a second concrete layer is poured into the bearing platform. The high-piled tower footing structure of the concrete filled steel tube can be constructed simultaneously with engineering piles in an advance project and does not take up project period. A tower crane assembly can be finished before large area of earth is excavated. Basements can be used in advance when base boards are constructed. The structure has the advantages of being simple in structure, good in safety, convenient to construct, short in project period, small in steel consumption and low in cost.

Description

The high stake of a kind of tower crane concrete filled steel tube tower-base structure
Technical field
The utility model belongs to technical field of building construction, is specifically related to the high stake of a kind of tower crane concrete filled steel tube tower-base structure.
Background technology
Along with building land day is becoming tight, architectural space has constantly become inexorable trend to high-altitude and underground development now, and pillar crane is absolutely necessary as the vertical transport instrument.In the basement construction stage tower crane is set, can cooperates basement construction, therefore need before excavation of foundation pit, in foundation ditch, to be provided with tower crane.
The tower crane tradition has following several method: 1, tower crane stands on the basement roof that closes on main building, the one, underground engineering construction difficulty progress is slow, the 2nd, the basement roof structure bearing capacity generally can not satisfy the requirement of bearing the tower crane load, also need to add vertical support, also have certain technical difficulty and security risk at underfloor; 2, before formal engineering excavation, with the buried tower that stands in advance below basement bottom board of column foot, it is simple that this method seems operation, but the column foot foundation ditch is too dark, and constructional difficulties is relatively more difficult when tower crane is removed in the future; 3, the high stake of steel lattice column column foot is a upper end pre-buried steel lattice column when the construction cast-in-place concrete pile, and rotate easily steel lattice column mounting plane position, and the method steel using amount is big, the expense height, and the steel lattice column welding quality be cannot say for sure to demonstrate,prove; 4, the high stake of cast-in-place concrete pile column foot, pile body need add steel hoop, adds the oblique steel of weldering between the stake and supports, and construction is complicated, and is easy to generate horizontal fracture in pile body and the cushion cap junction certain limit, has potential safety hazard.
The utility model content
At the above-mentioned problems in the prior art, the purpose of this utility model is to provide a kind of easy construction, the high stake of concrete filled steel tube tower-base structure that security performance is good.
The high stake of described a kind of concrete filled steel tube tower-base structure, the castinplace pile that is arranged on substrate that comprises the Φ 600-800 of 4 length 40m that bury, thick Φ 600 steel pipe columns of position outsourcing 8mm that expose on every castinplace pile foundation soil, described steel pipe column upper end is equipped with the cushion cap of 3300 * 3300 * (1350-1600) mm, it is characterized in that steel pipe column wraps in the upper end of castinplace pile outward, pipe column lower end stretches into length 2400-3000mm in the foundation soil, steel pipe column upper end expose foundation soil above to length between the cushion cap bottom be 4-7m, it is 150mm that its top anchors into cushion cap length, simultaneously setting up the column cap anchor rib at its top anchors in the cushion cap, be cast with first layer of concrete in described castinplace pile and the steel pipe column respectively, be cast with second layer of concrete in the described cushion cap.
The high stake of described a kind of concrete filled steel tube tower-base structure, it is characterized in that described cushion cap intersects to form steel skeleton construction by cushion cap reinforcing cage and the Φ 8@400 tension rib of Φ 14@200, form by the cast of second layer of concrete again, four jiaos of cushion cap are made as salient angle, salient angle is provided with the dark beam of right-angled intersection of (1100-1350mm) * 1200 mm(h * b), and the dark beam of described right-angled intersection respectively is provided with the principal rod of 7 Φ 25 and first stirrup of Φ 8@200 up and down.
The high stake of described a kind of concrete filled steel tube tower-base structure, be provided with reinforcing cage in described castinplace pile of its feature and the steel pipe column, described reinforcing cage forms steel frame construction by second stirrup of vertical applied force muscle and Φ 8@200, formed by the cast of first layer of concrete, described vertical applied force muscle comprises steel bar stress and the Φ 12@2000 reinforcing rib of 8 Φ 20mm again.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that described castinplace pile and steel pipe column lap-joint also are equipped with the additional muscle of 8 Φ 25mm of reinforcement effect.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that described steel pipe column stretches into the 3rd stirrup of the Φ 8@100 of cushion cap place reinforcing cage.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that the described first layer of concrete intensity is C25.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that the described second layer of concrete intensity is C35.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that described steel pipe column upper end welding column cap anchor rib, and lap length 120 ㎜, described column cap anchor rib are that 8 Φ, 20, the three stirrups are Φ 8@100, anchor into cushion cap length 1300 ㎜.
The high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that being provided with water-stopping structure between described castinplace pile and building base plate.
The construction process of the high stake of described a kind of concrete filled steel tube tower-base structure is characterized in that comprising the steps:
1) build priming concrete pile hole underground digging earlier, the cast-in-place concrete pile pore-forming, at castinplace pile top pre-buried steel tubing string, anchorage length is 2400-2480mm, puts into reinforcing cage again, pours into a mould first layer of concrete;
2) dig the earthwork of column foot cushion cap, stone bolt cutter pile crown, column cap anchor rib in welded steel pipe column top waters the cushion cap bed course again, colligation cushion cap reinforcing bar, shuttering, pre-buried tower crane built-in fitting waters cushion cap second layer of concrete.
By adopting above-mentioned technology, compared with prior art, the beneficial effects of the utility model are as follows:
1) construction of the high stake of concrete filled steel tube described in the utility model tower-base structure can be constructed simultaneously with the advance works stake, does not take the duration, and tower crane is installed and can be finished before the large tracts of land soil excavation, just can use in advance during the basement bottom board construction;
2) simple in structure, and safety is good;
3) easy construction, the duration is short;
4) tower-base structure steel using amount of the present utility model is few, and cost is low.
Description of drawings
Fig. 1 is a vertical view structural representation of the present utility model;
Fig. 2 is the structural representation of the utility model bored concrete pile and steel pipe column;
Fig. 3 is an A-A sectional drawing among Fig. 2;
Fig. 4 is a B-B sectional drawing among Fig. 2.
Among the figure: 1-castinplace pile, 2-cushion cap, 201-tension rib, 202-cushion cap reinforcing cage, 203-second layer of concrete, the dark beam of 204-right-angled intersection, the 205-principal rod, 206-first stirrup, 3-the 3rd stirrup, the 4-steel pipe column, 5-ground, 6-reinforcing cage, 601-vertical applied force muscle, 602-second stirrup, 603-adds muscle, 7-first layer of concrete, 8-column cap anchor rib anchor.
The specific embodiment
The utility model will be further described below in conjunction with Figure of description and embodiment:
Shown in Fig. 1-4, the high stake of a kind of concrete filled steel tube tower-base structure, the castinplace pile that is arranged on substrate 1 that comprises the Φ 600-800 of 4 length 40m that bury, thick Φ 600 steel pipe columns 4 of position outsourcing 8mm that expose on every castinplace pile 1 ground 5 soil, described steel pipe column 4 upper ends are equipped with the cushion cap 2 of 3300 * 3300 * (1350-1600) mm, the steel pipe column 4 outer upper ends that wrap in castinplace pile 1, length 2400-3000mm in ground 5 soil is stretched in steel pipe column 4 lower ends, be preferably 2400-2480mm, steel pipe column 4 upper ends expose foundation soil above to length between cushion cap 2 bottoms be 4-7m, it is 150mm that its top anchors into cushion cap length, simultaneously setting up the column cap anchor rib at its top anchors in the cushion cap, being cast with intensity in described castinplace pile 1 and the steel pipe column 4 respectively is first layer of concrete 7 of C25, and being cast with intensity in the described cushion cap 2 is C35 second layer of concrete 203.Be provided with reinforcing cage 6 in described castinplace pile 1 and the steel pipe column 4, described reinforcing cage 6 forms steel frame construction by vertical applied force muscle 601 and Φ 8@,200 second stirrup 602, formed by 7 cast of first layer of concrete, described vertical applied force muscle 601 comprises steel bar stress and the Φ 12@2000 reinforcing rib of 8 Φ 20mm again.Castinplace pile 1 and steel pipe column 4 lap-joints also are equipped with the additional muscle 603 of 8 Φ 25mm of reinforcement effect.
As shown in Figure 1, described cushion cap 2 intersects to form steel skeleton construction by cushion cap reinforcing cage 202 and the Φ 8@400 tension rib 201 of Φ 14@200, form by 203 cast of second layer of concrete again, four jiaos of cushion cap 2 are made as salient angle, salient angle is provided with the dark beam 204 of right-angled intersection of (1100-1350mm) * 1200 mm(h * b), and the dark beam 204 of described right-angled intersection respectively is provided with the principal rod 205 of 7 Φ 25 and the stirrup 206 of Φ 8@200 up and down.
As shown in Figure 2, described steel pipe column 4 upper ends welding column cap anchor rib 8, lap length 120 ㎜, described column cap anchor rib 8 Φ 20, the three stirrups 3 are the reinforcing bar of Φ 8@100, anchor into cushion cap length 1300 ㎜.Be provided with water-stopping structure between described castinplace pile 1 and building base plate.
Construction process as the high stake of the described a kind of concrete filled steel tube of Fig. 1-4 tower-base structure, comprise the steps: 1) build priming concrete pile hole underground digging earlier, the cast-in-place concrete pile pore-forming, at castinplace pile top pre-buried steel tubing string, anchorage length is 2400-3000mm, be preferably 2400-2480mm, put into reinforcing cage again, pour into a mould first layer of concrete 7; 2) dig the earthwork of column foot cushion cap, stone bolt cutter pile crown, welded steel pipe column top anchor rib again, water the cushion cap bed course, colligation cushion cap reinforcing bar, shuttering, pre-buried tower crane built-in fitting waters cushion cap second layer of concrete 203, have simple in structure, safety good, easy construction, the duration is short, steel using amount is few, cost is low advantage.

Claims (9)

1. the high stake of concrete filled steel tube tower-base structure, the castinplace pile that is arranged on substrate (1) that comprises the Φ 600-800 of 4 length 40m that bury, thick Φ 600 steel pipe columns of position outsourcing 8mm (4) that expose on every castinplace pile (1) foundation soil, described steel pipe column (4) upper end is equipped with the cushion cap (2) of 3300 * 3300 * (1350-1600) mm, it is characterized in that the outer upper end that wraps in castinplace pile (1) of steel pipe column (4), length 2400-3000mm in the foundation soil is stretched in steel pipe column (4) lower end, steel pipe column (4) upper end expose foundation soil above to length between cushion cap (2) bottom be 4-7m, it is 150mm that its top anchors into cushion cap length, simultaneously setting up column cap anchor rib anchor (8) at its top goes in the cushion cap, be cast with first layer of concrete (7) respectively in described castinplace pile (1) and the steel pipe column (4), be cast with second layer of concrete (203) in the described cushion cap (2).
2. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure, it is characterized in that described cushion cap (2) intersects to form steel skeleton construction by cushion cap reinforcing cage (202) and the Φ 8@400 tension rib (201) of Φ 14@200, form by second layer of concrete (203) cast again, four jiaos of cushion cap (2) are made as salient angle, salient angle is provided with the dark beam of right-angled intersection (204) of (1100-1350mm) * 1200 mm, and the dark beam of described right-angled intersection (204) respectively is provided with the principal rod (205) of 7 Φ 25 and first stirrup (206) of Φ 8@200 up and down.
3. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure, be provided with reinforcing cage (6) in described castinplace pile of its feature (1) and the steel pipe column (4), described reinforcing cage (6) forms steel frame construction by vertical applied force muscle (601) and Φ 8@,200 second stirrup (602), formed by first layer of concrete (7) cast, described vertical applied force muscle (601) comprises steel bar stress and the Φ 12@2000 reinforcing rib of 8 Φ 20mm again.
4. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure is characterized in that described castinplace pile (1) and steel pipe column (4) lap-joint also are equipped with the additional muscle (603) of 8 Φ 25mm of reinforcement effect.
5. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure is characterized in that described steel pipe column (4) stretches into the 3rd stirrup (3) of the Φ 8@100 of cushion cap place reinforcing cage.
6. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure is characterized in that described first layer of concrete (7) intensity is C25.
7. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure is characterized in that described second layer of concrete (203) intensity is C35.
8. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure, it is characterized in that described steel pipe column upper end welding column cap anchor rib (8), lap length 120 ㎜, described column cap anchor rib (8) is 8 Φ 20, the 3rd stirrup (3) is Φ 8@100, anchors into cushion cap length 1300 ㎜.
9. the high stake of a kind of concrete filled steel tube according to claim 1 tower-base structure is characterized in that being provided with water-stopping structure between described castinplace pile (1) and building base plate.
CN2011200495379U 2011-02-28 2011-02-28 High-piled tower footing structure of tower crane concrete-filled steel tube Expired - Lifetime CN201991013U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200495379U CN201991013U (en) 2011-02-28 2011-02-28 High-piled tower footing structure of tower crane concrete-filled steel tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200495379U CN201991013U (en) 2011-02-28 2011-02-28 High-piled tower footing structure of tower crane concrete-filled steel tube

Publications (1)

Publication Number Publication Date
CN201991013U true CN201991013U (en) 2011-09-28

Family

ID=44667502

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200495379U Expired - Lifetime CN201991013U (en) 2011-02-28 2011-02-28 High-piled tower footing structure of tower crane concrete-filled steel tube

Country Status (1)

Country Link
CN (1) CN201991013U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162258A (en) * 2011-02-28 2011-08-24 温州建设集团有限公司 Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof
CN103255779A (en) * 2013-05-19 2013-08-21 上海庞源机械租赁股份有限公司 Concrete foundation of tower crane
CN103498482A (en) * 2013-09-30 2014-01-08 上海建工七建集团有限公司 Three-pile lattice type combined tower crane foundation structure
CN106088132A (en) * 2016-06-15 2016-11-09 中国建筑第八工程局有限公司 Armored concrete M shape tower crane and construction method thereof
CN106088131A (en) * 2016-06-15 2016-11-09 中国建筑第八工程局有限公司 Armored concrete cross tower crane and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162258A (en) * 2011-02-28 2011-08-24 温州建设集团有限公司 Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof
CN102162258B (en) * 2011-02-28 2012-02-22 温州建设集团有限公司 Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof
CN103255779A (en) * 2013-05-19 2013-08-21 上海庞源机械租赁股份有限公司 Concrete foundation of tower crane
CN103498482A (en) * 2013-09-30 2014-01-08 上海建工七建集团有限公司 Three-pile lattice type combined tower crane foundation structure
CN106088132A (en) * 2016-06-15 2016-11-09 中国建筑第八工程局有限公司 Armored concrete M shape tower crane and construction method thereof
CN106088131A (en) * 2016-06-15 2016-11-09 中国建筑第八工程局有限公司 Armored concrete cross tower crane and construction method thereof

Similar Documents

Publication Publication Date Title
CN102162258B (en) Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN105089061B (en) Ultra-deep foundation pit supporting method
CN205742213U (en) Foundation pit supporting construction
CN108842791B (en) Detachable load pile anchor multistage supporting structure and construction method
CN102182325A (en) Storey adding method for existing building basement with frame structure and independent foundation
CN104947682A (en) Foundation pit support construction method and device thereof
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN201991013U (en) High-piled tower footing structure of tower crane concrete-filled steel tube
CN206928305U (en) A kind of rigid passive area buttress type supporting construction
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN103938634A (en) Deep foundation pit supporting structure and construction method
CN205024712U (en) Modular tower crane basis
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN216041201U (en) Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards
CN105064711A (en) Method for constructing underground garage between residential buildings
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN203034476U (en) Tower crane base structure in type of combination of steel latticework columns and concrete bearing platform shaped like Chinese character 'hui'
CN101187207A (en) Concrete pedestal pile construction equipment and its construction method
CN216339582U (en) Combined inclined support for foundation pit support
CN206562618U (en) A kind of basin excavation steel structure horizontal bracing unit
CN217174802U (en) Deep basal pit advance support's combination supporting construction
JP6867664B1 (en) Foundation structure of structure, foundation construction method, and support pipe material used for foundation
CN108005086A (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN213477808U (en) Structure is found fast to steel construction underground garage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20110928

Effective date of abandoning: 20120222