CN201981642U - Ground water-filtering ditch used in building project - Google Patents
Ground water-filtering ditch used in building project Download PDFInfo
- Publication number
- CN201981642U CN201981642U CN2010206692094U CN201020669209U CN201981642U CN 201981642 U CN201981642 U CN 201981642U CN 2010206692094 U CN2010206692094 U CN 2010206692094U CN 201020669209 U CN201020669209 U CN 201020669209U CN 201981642 U CN201981642 U CN 201981642U
- Authority
- CN
- China
- Prior art keywords
- drainage ditch
- layer
- construction work
- ground drainage
- ditch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a ground water-filtering ditch used in a building project. The ground water-filtering ditch comprises a drainage ditch (1) arranged around a drying bed, wherein a filtering device is arranged in the drainage ditch (1); the lowest layer of the filtering device is a reinforced concrete drain board (2); and a coke slag layer (3), a big pebble layer (4), a small pebble layer (5) and a polyester needle punched geotextile (6) are sequentially arranged on the reinforced concrete drain board (2) from bottom to top. After being filtering through the polyester needle punched geotextile (6), the small pebble layer (5), the big pebble layer (4) and the coke slag layer (3), water flows to the bottom of the drainage ditch (1) through holes on the reinforced concrete drain board (2) and is drained from the drainage ditch (1). The ground water-filtering ditch has the advantages that: the filtration effect is good; and the ground water-filtering ditch is not easy to block, reliably drains and can be used for a long time.
Description
Technical field
The utility model relates to a kind of drainage ditch, particularly relates to the ground drainage ditch of using in a kind of construction work, belongs to the water discharge technology field of construction work.
Background technology
Often there is water-containing materials (as moisture flyash, mud) to need to handle after the nature mummification in the industrial construction, constantly has liquid water to secrete in the natural drying process, simultaneously with fine granular materials.Usually establishing the open drain on the drying bed next door collects moisture and enters pipeline.But because the gutter does not have effective filtration system, the blocked situation of gutter or pipeline often takes place, influence is produced normally.
The utility model content
The purpose of this utility model is, the ground of using in a kind of construction work drainage ditch is provided.Good filtration effect is not easy blockedly, and draining is reliable, can use for a long time.
The technical solution of the utility model: the ground drainage ditch of using in a kind of construction work, comprise and be located at drying bed gutter on every side, be provided with filter in the gutter, the lowermost layer of filter is the steel bar concrete band drain, top cinder layer, rubble layer, thin boulder bed and the polyester acupuncture geotextiles of being provided with successively from the bottom to top of steel bar concrete band drain.
In the ground drainage ditch of using in the aforementioned construction work, described steel bar concrete band drain is provided with the hole.
In the ground drainage ditch of using in the aforementioned construction work, described cinder layer thickness is 100~140mm.
In the ground drainage ditch of using in the aforementioned construction work, described cinder layer thickness is 120mm.
In the ground drainage ditch of using in the aforementioned construction work, described rubble layer thickness is 40~60mm.
In the ground drainage ditch of using in the aforementioned construction work, described rubble layer thickness is 50mm.
In the ground drainage ditch of using in the aforementioned construction work, the cobble particle diameter of described rubble layer is 12~20mm.
In the ground drainage ditch of using in the aforementioned construction work, described thin boulder bed thickness is 20~40mm.
In the ground drainage ditch of using in the aforementioned construction work, described thin boulder bed thickness is 30mm.
In the ground drainage ditch of using in the aforementioned construction work, the cobble particle diameter of described thin boulder bed is 5~10mm.
Compared with prior art, the utility model is gone into 1 bottom, gutter by the orifice flow on the steel bar concrete band drain 2 after polyester acupuncture geotextiles 6, thin boulder bed 5, rubble layer 4 and cinder layer 3 filter, discharge from gutter 1.Good filtration effect is not easy blockedly, and draining is reliable, can use for a long time.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Being labeled as in the accompanying drawing: 1-gutter, 2-steel bar concrete band drain, 3-cinder layer, 4-rubble layer, the thin boulder bed of 5-, 6-polyester acupuncture geotextiles.
The specific embodiment
The utility model is described in further detail below in conjunction with drawings and Examples, but not as to any restriction of the present utility model.
Embodiment.
The utility model as shown in Figure 1.The ground drainage ditch of using in a kind of construction work, comprise and be located at drying bed gutter 1 on every side, be provided with filter in the gutter 1, the lowermost layer of filter is a steel bar concrete band drain 2, top cinder layer 3, rubble layer 4, thin boulder bed 5 and the polyester acupuncture geotextiles 6 of being provided with successively from the bottom to top of steel bar concrete band drain 2.Described steel bar concrete band drain 2 is provided with the hole.Described cinder layer 3 thickness are 100~140mm, and optimum thickness is 120mm.Described rubble layer 4 thickness are 40~60mm, and optimum thickness is 50mm.The cobble particle diameter of described rubble layer 4 is 12~20mm.Described thin boulder bed 5 thickness are 20~40mm, and optimum thickness is 30mm.The cobble particle diameter of described thin boulder bed 5 is 5~10mm.
During concrete enforcement, can be in the gutter 1 bottom construct some supports, then steel bar concrete band drain 2 is supported on, make between the bottom of trench in steel bar concrete band drain 2 and gutter 1 and formed the hydrospace.Steel bar concrete band drain 2 is provided with the hole, makes water can flow into the hydrospace from the hole.It is thick earlier to lay 120mm with cinder on steel bar concrete band drain 2, forms cinder layer 3, is that the cobble shop 50mm of 12~20mm is thick with particle diameter on cinder layer 3, formation rubble layer 4.On rubble layer 4, be that the cobble shop 30mm of 5~10mm is thick, form thin boulder bed 5 with particle diameter.Lay one deck polyester acupuncture geotextiles 6 from the bottom to top successively at thin boulder bed 5 upper berth one decks at last.Have fine grain water after polyester acupuncture geotextiles 6, thin boulder bed 5, rubble layer 4 and cinder layer 3 filter from what natural drying bed was discharged, go into 1 bottom, gutter, from gutter 1, discharge by the orifice flow on the steel bar concrete band drain 2.
Claims (10)
1. the ground drainage ditch of using in the construction work, it is characterized in that: comprise being located at drying bed gutter (1) on every side, the gutter is provided with filter in (1), the lowermost layer of filter is steel bar concrete band drain (2), top cinder layer (3), rubble layer (4), thin boulder bed (5) and the polyester acupuncture geotextiles (6) of being provided with successively from the bottom to top of steel bar concrete band drain (2).
2. according to the ground drainage ditch of using in the described construction work of claim 1, it is characterized in that: described steel bar concrete band drain (2) is provided with the hole.
3. according to the ground drainage ditch of using in the described construction work of claim 1, it is characterized in that: described cinder layer (3) thickness is 100~140mm.
4. according to the ground drainage ditch of using in the described construction work of claim 3, it is characterized in that: described cinder layer (3) thickness is 120mm.
5. according to the ground drainage ditch of using in the described construction work of claim 1, it is characterized in that: described rubble layer (4) thickness is 40~60mm.
6. according to the ground drainage ditch of using in the described construction work of claim 5, it is characterized in that: described rubble layer (4) thickness is 50mm.
7. according to the ground drainage ditch of using in claim 5 or the 6 described construction works, it is characterized in that: the cobble particle diameter of described rubble layer (4) is 12~20mm.
8. according to the ground drainage ditch of using in the described construction work of claim 1, it is characterized in that: described thin boulder bed (5) thickness is 20~40mm.
9. the ground drainage ditch of using in the described according to Claim 8 construction work is characterized in that: described thin boulder bed (5) thickness is 30mm.
10. according to Claim 8 or the ground drainage ditch of using in the 9 described construction works, it is characterized in that: the cobble particle diameter of described thin boulder bed (5) is 5~10mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206692094U CN201981642U (en) | 2010-12-20 | 2010-12-20 | Ground water-filtering ditch used in building project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206692094U CN201981642U (en) | 2010-12-20 | 2010-12-20 | Ground water-filtering ditch used in building project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201981642U true CN201981642U (en) | 2011-09-21 |
Family
ID=44609105
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206692094U Expired - Fee Related CN201981642U (en) | 2010-12-20 | 2010-12-20 | Ground water-filtering ditch used in building project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201981642U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669546A (en) * | 2012-09-18 | 2014-03-26 | 贵阳铝镁设计研究院有限公司 | Method and structure for preventing drainage system of drying storage yard from being blocked |
CN103603328B (en) * | 2013-09-04 | 2015-08-26 | 韩秋华 | Latent laminar farmland high yield permanent drainage ditch |
CN106902596A (en) * | 2017-05-04 | 2017-06-30 | 石台县莘田粮油有限公司 | A kind of paddy rice skinning machine dust arrester |
-
2010
- 2010-12-20 CN CN2010206692094U patent/CN201981642U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669546A (en) * | 2012-09-18 | 2014-03-26 | 贵阳铝镁设计研究院有限公司 | Method and structure for preventing drainage system of drying storage yard from being blocked |
CN103603328B (en) * | 2013-09-04 | 2015-08-26 | 韩秋华 | Latent laminar farmland high yield permanent drainage ditch |
CN106902596A (en) * | 2017-05-04 | 2017-06-30 | 石台县莘田粮油有限公司 | A kind of paddy rice skinning machine dust arrester |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206971342U (en) | A kind of ecostagnation facility system for sponge urban construction | |
CN104174191A (en) | Integrated grit chamber for treating rainwater and treatment method | |
CN101775839A (en) | Rainwater penetrating-discharging integrated ecological system | |
CN206233333U (en) | Initial rainwater filtering, precipitating, discarding and collecting treatment system | |
CN106193183A (en) | A kind of roof rain water retracting device with backwashing system | |
CN201981642U (en) | Ground water-filtering ditch used in building project | |
CN100352946C (en) | Technique and equipment for processing blast furnace smelting slag | |
CN105735449A (en) | Urban road rainwater collection and treatment system | |
CN107905331A (en) | Stagnant system is oozed in a kind of self-cleaning of sponge city | |
CN103011532B (en) | Geological material-based rainwater quality treatment system | |
CN102512871A (en) | Sewage treatment device for construction site | |
CN206681126U (en) | One kind is used for rainwater recycle purification utilization device | |
CN203320684U (en) | Garbage filtering device under rainwater grate | |
CN105201040B (en) | Catch basin with incipient rain separation and purification function | |
CN104674933B (en) | A kind of rainwater comprehensive utilization system | |
CN101624839A (en) | Method for comprehensively discharging accumulated water of underpass roads by filtering infiltration pond | |
CN107514050A (en) | A kind of AO formula rainwater flower beds based on the storage of sponge urban rainwater, purification | |
CN207878607U (en) | A kind of diafiltration clean inlet for stom water | |
CN101619590A (en) | Method for removing underway seeper of superficial layer of filtration and infiltration well | |
CN203989972U (en) | Integrated grit chamber for treating rainwater | |
CN102617011B (en) | Infiltration chamber system for infiltrating, drying and digesting sludge | |
CN205313950U (en) | Ecological side ditch with purification performance | |
CN205205607U (en) | Curb that helps rainwater infiltration | |
CN209011284U (en) | A kind of double abandoned stream rain water separators | |
CN209989909U (en) | System is collected and recycled to industrial area rainwater |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110921 Termination date: 20141220 |
|