CN201943054U - Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type - Google Patents

Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type Download PDF

Info

Publication number
CN201943054U
CN201943054U CN2011200523311U CN201120052331U CN201943054U CN 201943054 U CN201943054 U CN 201943054U CN 2011200523311 U CN2011200523311 U CN 2011200523311U CN 201120052331 U CN201120052331 U CN 201120052331U CN 201943054 U CN201943054 U CN 201943054U
Authority
CN
China
Prior art keywords
section
tunnel
diversion
diversion tunnel
vertical shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200523311U
Other languages
Chinese (zh)
Inventor
任苇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
PowerChina Northwest Engineering Corp Ltd
Original Assignee
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTHWEST HYDRO CONSULTING ENGINEERS CHECC filed Critical NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority to CN2011200523311U priority Critical patent/CN201943054U/en
Application granted granted Critical
Publication of CN201943054U publication Critical patent/CN201943054U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a spillway tunnel, in particular to a spillway tunnel rebuilt from a diversion tunnel through adopting a dragon tail tilting type, which is characterized in that the spillway tunnel comprises an intake tower, the diversion tunnel, a vertical shaft section, a horizontal turning section, a lock chamber section and a downstream energy dissipation section, wherein the intake tower is communicated with the front end of the diversion tunnel, the tail part of a combining section of the diversion tunnel is connected with the vertical shaft section, the upper end of the vertical shaft section is communicated with the front end of the horizontal turning section, the lower end of the vertical shaft section is communicated with a tunnel body of the diversion tunnel, and the tail end of the horizontal turning section is provided with the lock chamber section and the downstream energy dissipation section. The spillway tunnel has the characteristics that the structure in the tunnel is simple, the construction process is easy to operate, the service gate stress can be reduced, the downstream energy dissipation problem is easy to solve, and the construction cost is reduced.

Description

A kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel
Technical field
The utility model relates to a kind of flood discharging tunnel, particularly a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel.
Background technology
In Hydraulic and Hydro-Power Engineering, article one, the cost of Diversion Tunnel is up to ten million yuan even more than one hundred million unit, after construction diversion finishes, often it is transformed into flood discharging tunnel, Pai Shadong, diversion tunnel etc., and be transformed into flood discharging tunnel, be adopt in China's hydroelectric project maximum, the imperial new line pattern of normal employing of past, it is new to have occurred level rotary flow, vertical shaft eddy flow etc. in recent years.
Above-mentioned Diversion Tunnel is transformed into the thinking of flood discharging tunnel, consider the safety of tunnel itself, and it is stressed to reduce gate, all at tunnel import barrier current, gate is installed,, entrance gate is closed if destruction appears washing away etc. in tunnel, Background Job door, energy-dissipating installation, current in the emptying hole are to reach the purpose to overhauling in the hole.
No matter adopt traditional dragon new line pattern, still level rotary flow, the vertical shaft eddy flow pattern that occurs in recent years, all take this scheme of carrying out renovation and utilization in import, current are generally free flow in the hole, and often there are high speed current problems such as cavitation erosion in flow velocity height, fluidised form complexity in the hole, also to take methods such as impact-resisting wear-resisting, aeration on the structure, stressed complexity, the construction process requirement height, corresponding cost also improves.
Summary of the invention
The purpose of this utility model is in order to solve the problems of the technologies described above, and a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel is provided, and it is simple that it has the hole inner structure, and construction technology is operated easily; It is stressed to improve Service gate; The Dissipation of Energy in downstream is solved easily, reduced characteristics such as cost cost.
To achieve these goals, the utility model adopts following technical scheme: a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel, it is characterized in that, comprising: intake tower, Diversion Tunnel, vertical shaft section, flat bank section and lock chamber section and downstream energy dissipating section; Described intake tower is communicated with the Diversion Tunnel front end, Diversion Tunnel adapter section afterbody connects the vertical shaft section, vertical shaft section upper end is communicated with flat bank section front end, and vertical shaft section lower end is communicated with the hole body of Diversion Tunnel, and described flat bank section end is provided with lock chamber section and downstream energy dissipating section.
Described Diversion Tunnel end is provided with the block section.
Described intake tower is provided with the later stage water inlet.
Be provided with cone valve in the described block section.
Described flat bank section connects the diameter of the turning radius at vertical shaft section place greater than 5 times of Diversion Tunnels.
Described flat bank section outlet crossfades into square cross-section by round section.
Compared with prior art, the utlity model has following advantage:
(1) the hole inner structure is simple: because Service gate is positioned at the tunnel outlet, therefore, the above tunnel of runtime gate is pressurized tunnel, therefore, can require Diversion Tunnel once to build up and press circle according to operation condition, the cavitation erosion problem that high-velocity flow brings does not exist substantially, and the hole inner structure is simple, and construction technology is operated easily;
The all corresponding reduction of intractability of structure problems such as (2) the stressed improvement of Service gate: through after the vertical shaft section, upper pond level reduces with outlet base plate head difference, and hydraulics, gate are stressed;
(3) Dissipation of Energy solves easily: same, because the existence of vertical shaft section, upper pond level significantly reduces with outlet base plate head difference, even there are problems such as cavitation erosion in the energy dissipater, because outside the hole, the maintenance condition is good, the downstream Dissipation of Energy solves easily.
Description of drawings
Below in conjunction with specific embodiments and the drawings the utility model is further specified, but not as to qualification of the present utility model:
Fig. 1 is the flood discharging tunnel floor map that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel of the utility model embodiment;
Fig. 2 is the vertical section schematic diagram of Fig. 1.
Among the figure: 1, vertical shaft section; 2, flat bank section; 3, lock chamber section; 4, downstream energy dissipating section; 5, block section; 6, cone valve; 7, later stage water inlet; 8, intake tower; 9, river; 10, Diversion Tunnel; 11, upper pond level.
The specific embodiment
The structure that is not described in detail in an embodiment, its structure is identical with existing known structure.
Embodiment 1
A kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel comprises: intake tower 8, Diversion Tunnel 10, vertical shaft section 1, flat bank section 2, lock chamber section 3 and downstream energy dissipating section 4; Described intake tower 8 is communicated with Diversion Tunnel 10 front ends, Diversion Tunnel 10 adapter section afterbodys connect vertical shaft section 1, vertical shaft section upper end is communicated with flat bank section 2 front ends, and vertical shaft section 1 lower end is communicated with the hole body of Diversion Tunnel 10, and described flat bank section 2 ends are provided with lock chamber section 3 and downstream energy dissipating section 4.
Embodiment 2
A kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel comprises: intake tower 8, Diversion Tunnel 10, vertical shaft section 1, flat bank section 2, lock chamber section 3 and downstream energy dissipating section 4; Described intake tower 8 is communicated with Diversion Tunnel 10 front ends, Diversion Tunnel 10 adapter section afterbodys connect vertical shaft section 1, vertical shaft section upper end is communicated with flat bank section 2 front ends, and vertical shaft section 1 lower end is communicated with the hole body of Diversion Tunnel 10, and described flat bank section 2 ends are provided with lock chamber section 3 and downstream energy dissipating section 4; Described Diversion Tunnel 10 ends are provided with block section 5; Or described intake tower 8 is provided with later stage water inlet 7; Or be provided with cone valve 6 in the described block section 5; Or flat bank section 2 connects the diameter of the turning radius at vertical shaft section 1 place greater than 5 times of Diversion Tunnels 10; Or 2 outlets of flat bank section crossfade into square cross-section by round section; Flood discharging tunnel of the present utility model can be one or more combination of above-mentioned feature.
Embodiment 3
As shown in Figures 1 and 2, a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel, comprise: intake tower 8, Diversion Tunnel 10, vertical shaft section 1, flat bank section 2, lock chamber section 3 and downstream energy dissipating section 4, flat bank section 2 is parallel with horizontal plane respectively with Diversion Tunnel 10, Diversion Tunnel 10 adapter section afterbodys connect vertical shaft section 1, vertical shaft section 1 lower end is communicated with the hole body of Diversion Tunnel 10, to reduce upper pond level 11 and lower exit head difference, the front end of Diversion Tunnel 10 is connected with intake tower 8, described intake tower 8 is provided with later stage water inlet 7, and later stage water inlet 7 and intake tower 8 are arranged at the upstream in river 9; Described vertical shaft section 1 upper end is communicated with flat bank section 2 front ends simultaneously, assurance outlet flood discharging tunnel is chosen stream and is chosen into the river course, lock chamber section 3 and downstream energy dissipating section 4 are arranged in outlet, Diversion Tunnel 10 is a pressurized tunnel before the runtime lock chamber section 3, need before lock chamber section 3 service gates, add access door in case of necessity, downstream energy dissipating section 4 adopts the flip trajectory bucket mode according to the landform geological conditions.The end of Diversion Tunnel 10 is provided with block section 5, can make the water of the Diversion Tunnel 10 of flowing through enter vertical shaft section 1, and then flows out by flat bank section 2, lock chamber section 3, downstream energy dissipating section 4; Be provided with cone valve 6 in the block section 5, when the maintenance flood discharging tunnel, can open cone valve 6 water in the flood discharging tunnel is got rid of fully, make things convenient for the workman to enter maintenance.
Diversion Tunnel 10 once built up according to permanent operation build in the construction period, be round reinforced concrete structure, head should calculate (with reference to Guangzhou pumped storage power plant diversion tunnel method for designing) by carrying out the stress coupling according to " hydraulic tunnel design specifications " requirement by the seepage field analysis during greater than 150m; Vertical shaft section 1 is round reinforced concrete structure, highly is subjected to downstream work lock chamber 3 bottom Height control (work lock chamber section 3 bottom elevations calculate the principle design according to waterpower in " hydraulic tunnel design specifications "); Flat bank section 2 turning radius be round reinforced concrete structure greater than footpath, 5 times of holes in the hole in, and outlet crossfades into square cross-section by round section, this section purpose is set is that assurance exports flood discharging tunnel and chooses stream and choose into the river course; Carry out according to occluding body designing requirement in " hydraulic tunnel design specifications " block section 5, should choose approved product according to design head, flow when in the block section 5 cone valve 6 being set.

Claims (6)

1. a flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel is characterized in that, comprising: intake tower (8), Diversion Tunnel (10), vertical shaft section (1), flat bank section (2), lock chamber section (3) and downstream energy dissipating section (4); Described intake tower (8) is communicated with Diversion Tunnel (10) front end, Diversion Tunnel (10) adapter section afterbody connects vertical shaft section (1), vertical shaft section upper end is communicated with flat bank section (2) front end, vertical shaft section (1) lower end is communicated with the hole body of Diversion Tunnel (10), and described flat bank section (2) end is provided with lock chamber section (3) and downstream energy dissipating section (4).
2. a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel according to claim 1 is characterized in that described Diversion Tunnel (10) end is provided with block section (5).
3. a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel according to claim 1 is characterized in that described intake tower (8) is provided with later stage water inlet (7).
4. a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel according to claim 2 is characterized in that, is provided with cone valve (6) in described block section (5).
5. a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel according to claim 1 is characterized in that the turning radius that described flat bank section (2) connection vertical shaft section (1) is located is greater than the diameter of 5 times of Diversion Tunnels (10).
6. a kind of flood discharging tunnel that adopts " dragon sticks up tail " pattern to reconstruct by Diversion Tunnel according to claim 1 is characterized in that described flat bank section (2) outlet crossfades into square cross-section by round section.
CN2011200523311U 2011-03-02 2011-03-02 Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type Expired - Lifetime CN201943054U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200523311U CN201943054U (en) 2011-03-02 2011-03-02 Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200523311U CN201943054U (en) 2011-03-02 2011-03-02 Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type

Publications (1)

Publication Number Publication Date
CN201943054U true CN201943054U (en) 2011-08-24

Family

ID=44470402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200523311U Expired - Lifetime CN201943054U (en) 2011-03-02 2011-03-02 Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type

Country Status (1)

Country Link
CN (1) CN201943054U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898880A (en) * 2014-04-14 2014-07-02 黄河勘测规划设计有限公司 Method for rebuilding diversion tunnel of reservoir to form flood discharging tunnel in backfilling mode
CN108193651A (en) * 2018-03-15 2018-06-22 中国电建集团成都勘测设计研究院有限公司 Water consolidates separate type ditch water process scupper arrangement

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898880A (en) * 2014-04-14 2014-07-02 黄河勘测规划设计有限公司 Method for rebuilding diversion tunnel of reservoir to form flood discharging tunnel in backfilling mode
CN103898880B (en) * 2014-04-14 2016-03-16 黄河勘测规划设计有限公司 The method of reservoir Diversion Tunnel backfill reconstruction flood discharging tunnel
CN108193651A (en) * 2018-03-15 2018-06-22 中国电建集团成都勘测设计研究院有限公司 Water consolidates separate type ditch water process scupper arrangement

Similar Documents

Publication Publication Date Title
CN102162230B (en) Design method for reconstructing diversion tunnel into flood discharge tunnel in 'tail-raising' mode
CN203256704U (en) Water filling and pressure balancing device used for plane gate
CN104179159B (en) Power station bright flowing full tail water system
CN201214781Y (en) Horizontal rotational flow energy dissipating flood discharging hole
CN201874614U (en) Drainage structure for emptying overhaul of derivation tunnel
CN201915368U (en) Dam structure with water flow self-dissipation and energy-dissipation function
CN107740389B (en) Diversion tunnel structure and plugging construction method thereof
CN204343269U (en) Device of power station layering water intaking
CN105369784B (en) Ditch water process scupper structure and ditch water process water discharge method
CN204185835U (en) Power station free pressure flow tail water discharge
CN212077859U (en) Tunnel structure capable of being used for diversion, flood discharge and emptying
CN201762695U (en) Structure applicable to large and medium-sized mechanical device to enter long tunnel for overhaul
CN202181543U (en) Flood discharge tunnel structure
CN201943054U (en) Spillway tunnel rebuilt from diversion tunnel through adopting dragon tail tilting type
CN102720168A (en) Apparatus and method for controlling ecological flow
CN205259201U (en) Device is arranged in accuse of tunnel groundwater
CN104120692A (en) Construction layout method for one-cavity and double-layer combination of guiding cavity and emptying cavity
CN201943053U (en) Flow-guiding and flood-discharging hole structure
CN202500121U (en) Device for controlling ecological flow
CN203021973U (en) Sand intercepting groove
CN104099909B (en) Based on the flood discharge generating sync energy dissipater of flood-discharge tunnel
CN103939257B (en) Turbine-generator units
CN206752427U (en) A kind of power station ground power house tailrace outlet structure and its power station
CN205776115U (en) Diversion tunnel lock chamber maintenance structure
CN103967685B (en) A kind of stream energy conversion device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: HYDROCHINA XIBEI ENGINEERING CORPORATION

Free format text: FORMER NAME: NORTHWEST HYDROELECTRIC INVESTIGATION + DESIGN INSTITUTE OF CHINA HYDROPOWER ENGINEERING CONSULTING

Owner name: CHINA ELECTRIC POWER CONSTRUCTION GROUP NORTHWEST

Free format text: FORMER NAME: HYDROCHINA XIBEI ENGINEERING CORPORATION

CP01 Change in the name or title of a patent holder

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee after: POWERCHINA NORTHWEST ENGINEERING Co.,Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee before: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee after: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee before: Northwest Hydro Consulting Engineers, CHECC

CX01 Expiry of patent term

Granted publication date: 20110824

CX01 Expiry of patent term