CN201934812U - Urban underground pipeline shared pipeline corridor - Google Patents

Urban underground pipeline shared pipeline corridor Download PDF

Info

Publication number
CN201934812U
CN201934812U CN2010206476199U CN201020647619U CN201934812U CN 201934812 U CN201934812 U CN 201934812U CN 2010206476199 U CN2010206476199 U CN 2010206476199U CN 201020647619 U CN201020647619 U CN 201020647619U CN 201934812 U CN201934812 U CN 201934812U
Authority
CN
China
Prior art keywords
corrugated steel
shared
piping lane
pipeline
stiffening plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010206476199U
Other languages
Chinese (zh)
Inventor
战福军
何锡弌
李家荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Lianzhong Engineering Technology Co., Ltd.
Original Assignee
LIANZHONG ELECTROMECHANICAL MANUFACTURING Co Ltd NANJING CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIANZHONG ELECTROMECHANICAL MANUFACTURING Co Ltd NANJING CITY filed Critical LIANZHONG ELECTROMECHANICAL MANUFACTURING Co Ltd NANJING CITY
Priority to CN2010206476199U priority Critical patent/CN201934812U/en
Application granted granted Critical
Publication of CN201934812U publication Critical patent/CN201934812U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

An urban underground pipeline shared pipeline corridor is characterized in that two corrugated steel pipes of different diameters are connected in a sleeved manner, concrete is filled between the two corrugated steel pipes, and layer separators are arranged in an inner cavity of the inner corrugated steel pipe to form shared pipeline corridor units for multiple pipelines. The shared pipeline corridor units are connected by two flange groups arranged inside and outside to form an underground pipeline shared pipeline corridor in a demanded length, the layer separators can be used for various pipelines, and a passage is arranged in the middle of the underground pipeline shared pipeline corridor to be convenient for workers to maintain the pipelines.

Description

The shared piping lane of a kind of City Buried Pipeline
Technical field
The utility model relates to the pipeline configuration of City Buried Pipeline, the shared piping lane of especially a kind of City Buried Pipeline.
Background technique
City Buried Pipeline is the important Infrastructure in city, it is the city every profession and trade, the lifeline of organic connection in each functional zone and running, adopt plastic pipe its flame retarding of cabling and anti-corrosive properties all to have problems, reinforced concrete pipeline then rainwater leakage prevention is poor, and heavy, site operation carrying inconvenience, prior problem be plastic pipe and reinforced concrete pipeline under the situation that the modern city pavement loading increases day by day, bearing capacity is limited, working life is short.
Summary of the invention
The utility model provides a kind of City Buried Pipeline shared piping lane at the deficiency of prior art, adopts the different double-deck corrugated steel tube socket of diameter, two-layer between on-the-spot filling concrete, in the internal layer corrugated steel tube, barrier is set, it is shared to be convenient to different pipelines.
Above-mentioned purpose of the present utility model is achieved in that the shared piping lane of a kind of City Buried Pipeline, it is characterized in that: two corrugated steel tube sockets that diameter is different are set, filling concrete between two corrugated steel tubes, the corrugated steel tube inner chamber of internal layer is provided with layer every a minute retaining, constitute a shared piping lane unit, the shared piping lane of underground utility that is connected into Len req with two groups of flanges of inside and outside setting between the unit.
Said layer is the multilayer stiffening plate that distributes along the pipe range left and right sides at the piping lane internal layer every a minute retaining, stiffening plate connects with internal layer corrugated steel tube tube wall, about the stiffening plate intermediate portion that distributes be made as maintenance channel, with the stiffening plate Vertical direction many steelframes are set, steelframe connects with inner layer tube wall and stiffening plate.
Description of drawings
Fig. 1 is connection figure between the utility model piping lane unit;
Fig. 2 is the utility model piping lane sectional drawing.
Embodiment
Referring to Fig. 1, in the middle of the zinc-plated corrugated steel tube 1 and 2 of small one and large one two bores, be filled into measuring body packing (as concrete) 7, the flange 8 affixed with two corrugated steel tubes (can adopt one interior one outer two flanges to be connected, outside flange links to each other with large-diameter pipe, inner flange links to each other with small-bore pipe) on arrange that respectively wearing of some joins hole 5, in wearing connection hole 5, place axial bolts 6, tighten up with nut 3, pad is put sealing gasket 4 between flange 8, realizes many reliable connections between the shared piping lane unit.
Referring to Fig. 2, bigbore zinc-plated corrugated steel tube 1, small-bore zinc-plated corrugated steel tube 2, packing 7, ripplet steel pipe 2 inner chambers are laid " non-" font steelframe 10, are used for laying various municipal pipelines 11 on steelframe 10, the centre of " non-" font steelframe is walkway 9, convenient for maintaining.The horizontal multilayer steelframe and the inwall of small-bore bellows can adopt flexible connection, can change at any time, assemble, and can tackle the needs of various different pipelines.
During construction, corrugated steel tube can be transported to the scene, be positioned in the trench after the big or small socket, support out the space with wooden piece between two pipes, be reserved with hole on the bassoon outer wall, inject concrete formation, hole gets final product on the sealing bassoon outer wall.

Claims (2)

1. shared piping lane of City Buried Pipeline, it is characterized in that: two corrugated steel tube sockets that diameter is different are set, filling concrete between two corrugated steel tubes, the corrugated steel tube inner chamber of internal layer is provided with layer every a minute retaining, constitute a shared piping lane unit, the shared piping lane of underground utility that is connected into Len req with two groups of flanges of inside and outside setting between the unit.
2. the shared piping lane of City Buried Pipeline according to claim 1, it is characterized in that: said layer is the multilayer stiffening plate that distributes along the pipe range left and right sides at the piping lane internal layer every a minute retaining, stiffening plate connects with internal layer corrugated steel tube tube wall, about the stiffening plate intermediate portion that distributes be made as maintenance channel, with the stiffening plate Vertical direction many steelframes are set, steelframe connects with inner layer tube wall and stiffening plate.
CN2010206476199U 2010-12-08 2010-12-08 Urban underground pipeline shared pipeline corridor Expired - Lifetime CN201934812U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206476199U CN201934812U (en) 2010-12-08 2010-12-08 Urban underground pipeline shared pipeline corridor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206476199U CN201934812U (en) 2010-12-08 2010-12-08 Urban underground pipeline shared pipeline corridor

Publications (1)

Publication Number Publication Date
CN201934812U true CN201934812U (en) 2011-08-17

Family

ID=44446331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206476199U Expired - Lifetime CN201934812U (en) 2010-12-08 2010-12-08 Urban underground pipeline shared pipeline corridor

Country Status (1)

Country Link
CN (1) CN201934812U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105042213A (en) * 2015-09-08 2015-11-11 浙江鑫宙竹基复合材料科技有限公司 Prefabricated bamboo composite pipe gallery and manufacturing method thereof
CN105350572A (en) * 2015-10-29 2016-02-24 周兆弟 Assembled type underground pipe gallery
CN105600328A (en) * 2015-12-20 2016-05-25 石家庄新华能源环保科技股份有限公司 Multifunctional conveying pipeline
CN106320375A (en) * 2016-10-21 2017-01-11 中国化学工程第六建设有限公司 Prefabricated underground pipe rack and mounting method thereof
WO2018076494A1 (en) * 2016-10-31 2018-05-03 浙江鑫宙竹基复合材料科技有限公司 Embedded supporting assembly for pipe gallery
CN110645411A (en) * 2019-09-11 2020-01-03 中地国际工程有限公司 Pipeline laying method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105042213A (en) * 2015-09-08 2015-11-11 浙江鑫宙竹基复合材料科技有限公司 Prefabricated bamboo composite pipe gallery and manufacturing method thereof
CN105350572A (en) * 2015-10-29 2016-02-24 周兆弟 Assembled type underground pipe gallery
WO2017071110A1 (en) * 2015-10-29 2017-05-04 周兆弟 Assembled-type underground pipe gallery
CN105350572B (en) * 2015-10-29 2017-11-24 周兆弟 Assembled underground pipe gallery
CN105600328A (en) * 2015-12-20 2016-05-25 石家庄新华能源环保科技股份有限公司 Multifunctional conveying pipeline
CN105600328B (en) * 2015-12-20 2018-02-09 石家庄新华能源环保科技股份有限公司 Multi-functional transfer pipeline
CN106320375A (en) * 2016-10-21 2017-01-11 中国化学工程第六建设有限公司 Prefabricated underground pipe rack and mounting method thereof
WO2018076494A1 (en) * 2016-10-31 2018-05-03 浙江鑫宙竹基复合材料科技有限公司 Embedded supporting assembly for pipe gallery
CN110645411A (en) * 2019-09-11 2020-01-03 中地国际工程有限公司 Pipeline laying method

Similar Documents

Publication Publication Date Title
CN201934812U (en) Urban underground pipeline shared pipeline corridor
CN204898721U (en) Steel construction city utility tunnel
WO2018113488A1 (en) Pipe jacking and freezing system and construction method thereof
CN105064400A (en) Urban comprehensive pipe rack of steel corrugated plate structure
CN102777706A (en) Encased concrete nodular cast iron pipe
CN104110265A (en) Thixotropic slurry grouting system for large-section rectangular pipe-jacking pipeline
CN103362517A (en) Assembled jacking pipe
CN205617425U (en) Prefabricated structure of assembling of utility tunnel
CN103775100A (en) Prefabricated assembled urban comprehensive pipe gallery
CN204080862U (en) With the waterproof short tube through walls of earrings
CN203475580U (en) Multi-functional combined rainwater plastic inspection well
CN203656411U (en) Double-rubber-ring bell and spigot steel ring of large-diameter PCCP (prestressed concrete cylinder pipe) and large-diameter PCCP
CN202598018U (en) Waterproof rubber plugging device of pipelines
CN202708364U (en) Nodular cast iron pipe provided with concrete in wrapping mode
CN205908893U (en) Flat mouthful lining structure of compound pipe of fibre reinforced plastic concrete
CN205314126U (en) FRP pipe corridor
CN201803021U (en) Combustion gas underground inlet pipe
CN207392370U (en) A kind of civic building draining is managed with PE
CN105972212A (en) Prefabricated assembled pipe rack
CN206736961U (en) A kind of Novel steel-plastic composite pipe corridor
CN201606586U (en) Reinforced concrete and glass reinforced plastic composite pipe
CN201708512U (en) Large-caliber seepage-proofing cable push pipe
CN205231678U (en) Non - excavation trombone slide of power cable
CN202787471U (en) High strength steel drain pipe
CN110630822B (en) Oil-gas multiphase flow multi-cavity heat-preservation combined pipeline structure system and construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: NANJING LIANZHONG CONSTRUCTION ENGINEERING TECHNOL

Free format text: FORMER NAME: LIANZHONG ELECTROMECHANICAL MANUFACTURING CO., LTD., NANJING CITY

CP01 Change in the name or title of a patent holder

Address after: Lishui County of Nanjing City, Jiangsu province 211215 zhe Sugar Industrial Park

Patentee after: Nanjing Liantong Construction Engineering Technology Co., Ltd.

Address before: Lishui County of Nanjing City, Jiangsu province 211215 zhe Sugar Industrial Park

Patentee before: Lianzhong Electromechanical Manufacturing Co., Ltd., Nanjing City

CP03 Change of name, title or address

Address after: 211215 Zhetang Town Industrial Park, Lishui District, Nanjing City, Jiangsu Province

Patentee after: Nanjing Lianzhong Engineering Technology Co., Ltd.

Address before: 211215 Sugar Industrial Park, Lishui County, Nanjing City, Jiangsu Province

Patentee before: Nanjing Liantong Construction Engineering Technology Co., Ltd.

CP03 Change of name, title or address
CX01 Expiry of patent term

Granted publication date: 20110817

CX01 Expiry of patent term