CN204898721U - Steel construction city utility tunnel - Google Patents

Steel construction city utility tunnel Download PDF

Info

Publication number
CN204898721U
CN204898721U CN201520668252.1U CN201520668252U CN204898721U CN 204898721 U CN204898721 U CN 204898721U CN 201520668252 U CN201520668252 U CN 201520668252U CN 204898721 U CN204898721 U CN 204898721U
Authority
CN
China
Prior art keywords
steel
main body
gallery main
piping lane
integrated piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520668252.1U
Other languages
Chinese (zh)
Inventor
左清军
李鹏飞
李春波
陈可
胡圣松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Chongqing Jiaotong University
Original Assignee
China Three Gorges University CTGU
Chongqing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU, Chongqing Jiaotong University filed Critical China Three Gorges University CTGU
Priority to CN201520668252.1U priority Critical patent/CN204898721U/en
Application granted granted Critical
Publication of CN204898721U publication Critical patent/CN204898721U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a steel construction city utility tunnel, includes that polylith ripple steel sheet moves about freely and quickly the corridor main part that fissure of displacement concatenation is formed, and each ripple steel sheet edge all around is provided with the concatenation hole, and it is fixed that polylith ripple steel sheet passes through the bolt concatenation, be equipped with cable support, pipeline bracket in the corridor main part, be equipped with the access path in the corridor main part. The utility model relates to a steel construction city utility tunnel can overcome effectively that reinforced concrete utility tunnel construction quality is wayward among the prior art, construction cycle long, the cost drops into great etc. Defect.

Description

The city integrated piping lane of a kind of steel work
Technical field
The city integrated piping lane of a kind of steel work of the utility model, belongs to Transport Facility Construction technical field.
Background technology
Along with a large amount of sharp increase of urban population, the infrastructure construction in city more and more receives the concern of more people.Pipe gallery is common trench again, namely under town road, a underground gallery is built, by included in the lump for the various pipelines such as communication, the various cable of electric power and plumbing, heat supply, air feed, and the facilities such as special maintenance and ventilation opening are set, unified implementation management, saves pipeline self independently soil excavation, can more effective using underground space resource, avoid that urban road is zippered repeatedly to be excavated and backfill, reduce the impact on urban traffic.The cost dropped into due to city integrated piping lane initial stage is than high a lot of separately laying in the past, and need based on management maintenance and maintenance, generally need to arrange the passage for overhauling wherein, this just causes the pipe gallery civil engineering scale of construction larger, cost is high, which also limits applying of it.The pipe gallery of what present use was maximum is reinforced concrete structure, usual prefabricated construction, transport waits and comparatively bothers, and larger the installations inconvenience of volume, globality is poor, and speed of application is comparatively slow, and therefore investment comparatively greatly, also slow down the promotion rate of city integrated piping lane.
Summary of the invention
For solving the problems of the technologies described above, the utility model provides a kind of steel work city integrated piping lane, effectively can overcome that steel concrete pipe gallery construction quality in prior art is wayward, long construction period, cost drop into larger etc. defect.
The technical scheme that the utility model adopts is:
The city integrated piping lane of a kind of steel work, comprise polylith corrugated steel in length and breadth the fissure of displacement splicing composition gallery main body, each block corrugated steel edge is provided with splicing hole, polylith corrugated steel is fixing by bolt splicing, be provided with cable support, support of pipelines in described gallery main body, in described gallery main body, be provided with access path.
The cross section of described gallery main body is circle, tubulose arch or the shape of a hoof.
Described cable support is made up of arc channel-section steel, horizontal angle steel, sole bar angle, is connected between them by connecting bolt.
Described support of pipelines is made up of arc channel-section steel, transverse channel steels, longitudinal channel-section steel, is connected between them by connecting bolt.
Described arc channel-section steel shape and gallery main body cambered surface direction match, and arc channel-section steel is distributed with bolt hole, and its pitch-row is identical with the splicing hole pitch-row in gallery main body cambered surface direction, and gallery main body is connected by connecting bolt with arc channel-section steel.
The described inside and outside surface of gallery main body is coated with corrosion protection, temperature-resistant insulation layer.
Described gallery bottom part body is provided with concrete platform.
Described gallery main body to be connected with connecting bolt by adpting flange with fork place turning round, turn round and fork place tube wall on offer access hole and ventilation opening, corrugated steel seam and flange connections are coated with waterproof sealing agent.
The city integrated piping lane of a kind of steel work of the utility model, an overall structure is become after corrugated steel installation, better can bear the differential settlement caused by various unfavorable conditions, and its intensity, rigidity and stability can reach corresponding requirement.More flexible design can produce different size and section form simultaneously, meet the different requirements of main line and branch line, easy for installation, speed of application is fast, comparatively economical, can reduce due to the impact of construction on urban highway traffic, replace the piping lane of reinforced concrete structure, the advantage of better performance corrugated steel, reduces the cost of pipe gallery, accelerates urban infrastructure construction.
Accompanying drawing explanation
Fig. 1 is the section structure schematic diagram of the utility model pipe gallery.
Fig. 2 is support and the corrugated steel connection diagram of the utility model pipe gallery.
Fig. 3 is the assembled drawing of fissure of displacement bolt of the gallery main body corrugated steel of the utility model pipe gallery.
Fig. 4 is the connecting bolt drawing of the utility model pipe gallery.
In figure, 1-gallery main body, 2-concrete platform, 3-corrosion protection, temperature-resistant insulation layer, 4-splices hole, 5-corrugated steel seam, 6-corrugated steel, 7-connecting bolt, 8-support of pipelines, 9-cable support, 10-arc channel-section steel, 11-rubber sheet gasket.
Detailed description of the invention
As shown in Fig. 1 ~ Fig. 4, the city integrated piping lane of a kind of steel work, comprise polylith corrugated steel 6 in length and breadth the fissure of displacement splicing composition gallery main body 1.Fissure of displacement splicing is exactly make each splicing seams all not point-blank, mutually staggers, can avoid the quality due to the whole piping lane of stress influence like this.
Corrugated steel 6 thickness is between 3mm ~ 10mm, each block corrugated steel 6 edge is provided with splicing hole 4, polylith corrugated steel 6 is fixing by bolt splicing, is provided with cable support 9, support of pipelines 8, is provided with access path in described gallery main body 1 in described gallery main body 1.
The cross section of described gallery main body 1 is circle, tubulose arch or the shape of a hoof.This several cross sectional shape can make the piping lane of buried underground stressed more even on the one hand, also can more utilize the space of piping lane to carry out laying cable and pipeline etc. simultaneously.
Described cable support 9 is made up of arc channel-section steel 10, horizontal angle steel, sole bar angle, is connected between them by connecting bolt 7.
Described support of pipelines 8 is made up of arc channel-section steel 10, transverse channel steels, longitudinal channel-section steel, is connected between them by connecting bolt 7.
Described arc channel-section steel 10 shape and gallery main body 1 cambered surface direction match, and arc channel-section steel 10 is distributed with bolt hole, and its pitch-row is identical with splicing hole 4 pitch-row in gallery main body 1 cambered surface direction, and gallery main body 1 is connected by connecting bolt 7 with arc channel-section steel 10.
The described inside and outside surface of gallery main body 1 is coated with corrosion protection, temperature-resistant insulation layer 3.Such as can with organic siliconresin etc.Service property (quality) and the service time of comprehensive gallery can be ensured.
Be provided with concrete platform 2 bottom described gallery main body 1, so that fixed-piping support 8, cable support 9, form access path simultaneously, be convenient to staff and pass through.
Gallery main body 1 to be connected with connecting bolt 7 by adpting flange with fork place turning round.Turn round and fork place tube wall on offer access hole and ventilation opening, when can carry out good ventilation and final-period management maintenance when using so that normal in pipeline, staff can pass in and out easily, maintenance and ventilate and can share.Corrugated steel seam 5 and flange connections are coated with waterproof sealing agent, carry out waterproof sealing.

Claims (8)

1. the city integrated piping lane of steel work, comprise polylith corrugated steel (6) in length and breadth the fissure of displacement splicing composition gallery main body (1), it is characterized in that, each block corrugated steel (6) edge is provided with splicing hole (4), polylith corrugated steel (6) is fixing by bolt splicing, be provided with cable support (9), support of pipelines (8) in described gallery main body (1), in described gallery main body (1), be provided with access path.
2. the city integrated piping lane of a kind of steel work according to claim 1, is characterized in that, the cross section of described gallery main body (1) is circular, tubulose arch or the shape of a hoof.
3. the city integrated piping lane of a kind of steel work according to claim 1, it is characterized in that, described cable support (9) is made up of arc channel-section steel (10), horizontal angle steel, sole bar angle, is connected between them by connecting bolt (7).
4. the city integrated piping lane of a kind of steel work according to claim 1, it is characterized in that, described support of pipelines (8) is made up of arc channel-section steel (10), transverse channel steels, longitudinal channel-section steel, is connected between them by connecting bolt (7).
5. the city integrated piping lane of a kind of steel work according to claim 3 or 4, it is characterized in that, described arc channel-section steel (10) shape and gallery main body (1) cambered surface direction match, arc channel-section steel (10) is distributed with bolt hole, its pitch-row is identical with splicing hole (4) pitch-row in gallery main body (1) cambered surface direction, and gallery main body (1) is connected by connecting bolt (7) with arc channel-section steel (10).
6. the city integrated piping lane of a kind of steel work according to claim 1, it is characterized in that, the inside and outside surface of described gallery main body (1) is coated with corrosion protection, temperature-resistant insulation layer (3).
7. the city integrated piping lane of a kind of steel work according to claim 1, is characterized in that, described gallery main body (1) bottom is provided with concrete platform (2).
8. the city integrated piping lane of a kind of steel work according to claim 1, it is characterized in that, described gallery main body (1) to be connected with connecting bolt (7) by adpting flange with fork place turning round, turn round and fork place tube wall on offer access hole and ventilation opening, corrugated steel seam (5) and flange connections are coated with waterproof sealing agent.
CN201520668252.1U 2015-08-31 2015-08-31 Steel construction city utility tunnel Expired - Fee Related CN204898721U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520668252.1U CN204898721U (en) 2015-08-31 2015-08-31 Steel construction city utility tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520668252.1U CN204898721U (en) 2015-08-31 2015-08-31 Steel construction city utility tunnel

Publications (1)

Publication Number Publication Date
CN204898721U true CN204898721U (en) 2015-12-23

Family

ID=54920910

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520668252.1U Expired - Fee Related CN204898721U (en) 2015-08-31 2015-08-31 Steel construction city utility tunnel

Country Status (1)

Country Link
CN (1) CN204898721U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105908778A (en) * 2016-06-23 2016-08-31 中交第公路勘察设计研究院有限公司 Comprehensive pipe rack for corrugated spiral pipe structure
CN106759482A (en) * 2017-01-06 2017-05-31 重庆微轨科技有限公司 A kind of overall stainless steel structure type underground pipe gallery
CN107299574A (en) * 2017-08-03 2017-10-27 中冶京诚工程技术有限公司 Inside terrace of steel buckled plate city utility tunnel
CN107327633A (en) * 2017-06-02 2017-11-07 安徽奥睿德科技发展有限公司 It is a kind of to be used for the segmental timbering of fixed -piping in underground pipe gallery
CN107345402A (en) * 2017-07-13 2017-11-14 重庆微轨科技有限公司 A kind of insulated compound structure underground pipe gallery electric power dedicated bay
CN107905257A (en) * 2017-11-24 2018-04-13 上海市机械施工集团有限公司 A kind of construction method of city integrated piping lane
CN108547316A (en) * 2018-04-23 2018-09-18 哈尔滨工业大学 The double-deck corrugated steel construction for underground pipe gallery
CN110607804A (en) * 2018-06-14 2019-12-24 中冶京诚工程技术有限公司 Underground comprehensive pipe gallery
CN111677005A (en) * 2020-05-09 2020-09-18 首钢集团有限公司 Steel utility tunnel
CN112761681A (en) * 2021-02-04 2021-05-07 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment
CN112855180A (en) * 2020-12-31 2021-05-28 苏交科集团股份有限公司 Comprehensive pipe gallery assembled structure constructed by shield method and construction method thereof

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105908778A (en) * 2016-06-23 2016-08-31 中交第公路勘察设计研究院有限公司 Comprehensive pipe rack for corrugated spiral pipe structure
CN106759482A (en) * 2017-01-06 2017-05-31 重庆微轨科技有限公司 A kind of overall stainless steel structure type underground pipe gallery
CN107327633A (en) * 2017-06-02 2017-11-07 安徽奥睿德科技发展有限公司 It is a kind of to be used for the segmental timbering of fixed -piping in underground pipe gallery
CN107345402A (en) * 2017-07-13 2017-11-14 重庆微轨科技有限公司 A kind of insulated compound structure underground pipe gallery electric power dedicated bay
CN107299574A (en) * 2017-08-03 2017-10-27 中冶京诚工程技术有限公司 Inside terrace of steel buckled plate city utility tunnel
CN107905257A (en) * 2017-11-24 2018-04-13 上海市机械施工集团有限公司 A kind of construction method of city integrated piping lane
CN108547316A (en) * 2018-04-23 2018-09-18 哈尔滨工业大学 The double-deck corrugated steel construction for underground pipe gallery
CN108547316B (en) * 2018-04-23 2020-12-11 哈尔滨工业大学 Double-layer corrugated steel structure for underground comprehensive pipe gallery
CN110607804A (en) * 2018-06-14 2019-12-24 中冶京诚工程技术有限公司 Underground comprehensive pipe gallery
CN111677005A (en) * 2020-05-09 2020-09-18 首钢集团有限公司 Steel utility tunnel
CN112855180A (en) * 2020-12-31 2021-05-28 苏交科集团股份有限公司 Comprehensive pipe gallery assembled structure constructed by shield method and construction method thereof
CN112761681A (en) * 2021-02-04 2021-05-07 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment
CN112761681B (en) * 2021-02-04 2022-04-22 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment

Similar Documents

Publication Publication Date Title
CN204898721U (en) Steel construction city utility tunnel
CN202969415U (en) Multifunctional assembled comprehensive pipe gallery
CN105064400A (en) Urban comprehensive pipe rack of steel corrugated plate structure
CN104747206B (en) Shield tunnel segment structure considering municipal cable pipelines and installing method
US10030792B2 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof
CN106381885B (en) A kind of Underground Steel pipe gallery with skeleton
CN202247950U (en) Quadrate culvert member
CN204040062U (en) Prefabricated wedge shape flexible interface assembling piping lane
CN104265306A (en) Municipal shield tunnel
CN105507346A (en) Prefabricated underground pipe gallery
CN109881705A (en) A kind of prefabricated assembled concrete pipe gallery consolidates water-tight device and method
CN104410031B (en) A kind of pre-fabricated electric cables comb
CN205477664U (en) Twin side heading method undercut tunnel utility tunnel
CN204151824U (en) A kind of glass reinforced plastic underground comprehensive pipe network common trench
CN106759485A (en) A kind of prefabricated piping lane of two-piece unit formula and installation method
CN205296347U (en) Arrangement structure that utility tunnel internal drain pipe said
KR20150059640A (en) Perpendicular hall module and construction method for perpendicular hall using the same
CN202324155U (en) Adjustable corrugated prestress anti-pollution drainage culvert
CN205400736U (en) CRD undercut tunnel utility tunnel
CN210315654U (en) Urban tunnel, rail transit interval tunnel and utility tunnel co-construction structure
CN204113295U (en) A kind of municipal shield tunnel
CN103032099A (en) Prefabricated partition wall structure of lateral smoke discharge passage of shield tunnel
CN205348225U (en) Prefabricated assembled underground pipe gallery
CN202260356U (en) Special cable holder structure for pipeline
CN204959797U (en) Steel buckled plate structure city utility tunnel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151223

Termination date: 20160831