CN201901534U - 火力发电厂锅炉汽包吊装吊具 - Google Patents

火力发电厂锅炉汽包吊装吊具 Download PDF

Info

Publication number
CN201901534U
CN201901534U CN2010206470826U CN201020647082U CN201901534U CN 201901534 U CN201901534 U CN 201901534U CN 2010206470826 U CN2010206470826 U CN 2010206470826U CN 201020647082 U CN201020647082 U CN 201020647082U CN 201901534 U CN201901534 U CN 201901534U
Authority
CN
China
Prior art keywords
support beam
weight
steel structure
structure support
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010206470826U
Other languages
English (en)
Inventor
魏海斌
杨全强
郝慧君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Shanxi Electric Power Construction Co Ltd
Original Assignee
Shanxi No4 Electric Power Construction Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi No4 Electric Power Construction Co filed Critical Shanxi No4 Electric Power Construction Co
Priority to CN2010206470826U priority Critical patent/CN201901534U/zh
Application granted granted Critical
Publication of CN201901534U publication Critical patent/CN201901534U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

本实用新型公开了一种火力发电厂锅炉汽包吊装吊具,解决了现有技术在大型锅炉汽包吊装时存在的吊装绳子处于倾斜状态导致吊装安全系数低,吊具施工操作复杂繁琐的技术问题。包括前、后钢结构支撑梁,在其上分别固定设置有左右方向重物移动滑道(3)、左右重物移动器(4)和提升大梁(5),在提升大梁(5)上固定设置有H形型钢(9)、前后方向重物移动滑道(10)和前后重物移动器(11),在前后重物移动器(11)上固定设置有小跑车(12),小跑车(12)与吊板(16)的一端固定连接在一起,吊板(16)的另一端与汽包(20)连接在一起。本实用新型能够重复利用,降低工程成本,保证了施工质量。

Description

火力发电厂锅炉汽包吊装吊具
技术领域
本发明涉及一种火力发电厂锅炉汽包吊装时所使用的一种吊装工具。
背景技术
汽包是火力发电厂锅炉主要的承压部件,也是锅炉安装中最主要、最大的单体安装部件。随着电站机组容量的不断增大,锅炉汽包重量也随之增大,300MW发电机组的汽包重约160多吨,600MW发电机组汽包重约240多吨。汽包的安装在施工现场是特别重要的,现有技术对气包的吊装是采用绳索捆绑汽包,在汽包的上下方各安装一个滑轮组后对汽包实施吊装。这种施工方法存在的问题有:在吊装过程中吊装绳子处于倾斜状态导致安全系数低,吊具施工操作复杂、繁琐,不能满足大型锅炉汽包吊装需要。
发明内容
本发明提供的火力发电厂锅炉汽包吊装吊具解决了现有技术在大型锅炉汽包吊装时存在的吊装绳子处于倾斜状态导致吊装安全系数低,吊具施工操作复杂繁琐的技术问题。
本发明是通过以下技术方案解决以上技术问题的:
火力发电厂锅炉汽包吊装吊具,包括施工现场高空中平行固定设 置的后钢结构支撑梁和前钢结构支撑梁,如图1所示将图面的左右水平方向规定为汽包吊装的前后方向,将与图面垂直水平方向规定为汽包吊装的左右方向,在所述的后钢结构支撑梁的上面和前钢结构支撑梁的上面沿梁布置的左右方向分别固定设置有左右方向重物移动滑道,在这两个左右方向重物移动滑道中均分别设置有左右重物移动器,在两个左右方向重物移动滑道中分别设置的左右重物移动器上固定设置有提升大梁,提升大梁设置于后钢结构支撑梁与前钢结构支撑梁之间的前后方向,在提升大梁上沿提升大梁布置的前后方向固定设置有H形型钢,在H形型钢上固定设置有前后方向重物移动滑道,在前后方向重物移动滑道中设置有前后重物移动器,在前后重物移动器上固定设置有小跑车,小跑车与吊板的一端固定连接在一起,吊板的另一端依次通过上下滑轮组及钢丝绳、连接转换器、销轴与汽包连接在一起。
所述的左右方向重物移动滑道是由槽钢组成,在槽钢与前、后钢结构支撑梁之间活动设置有垫板,在槽钢的外侧下端与钢结构支撑梁之间设置有凹形的限位板,两限位板扣接在槽钢的外侧与钢结构支撑梁的上板下侧起到对垫板的限位作用。
所述的小跑车包括两组垂直交叉上下固定设置的第一支撑梁和第二支撑梁,在两根第二支撑梁之间固定设置有定滑轮生根梁,定滑轮生根梁与所述的吊板的一端固定连接在一起。
本发明安全可靠、操作方便,加快施工进度,能够重复利用降低工程成本,保证了施工质量。
附图说明
图1是本发明的结构示意图
图2是本发明的重物移动器滑道、重物移动器及提升大梁之间的连接关系的结构示意图
图3是本发明的图2的A向视图
图4是本发明的小跑车12的结构示意图
图5是本发明的图1的B向视图
具体实施方式
本发明的具体实施方式如下:
火力发电厂锅炉汽包吊装吊具,如图1所示,将图面的左右水平方向规定为汽包吊装的前后方向,将与图面垂直水平方向规定为汽包吊装的左右方向,包括施工现场高空中平行固定设置的后钢结构支撑梁1和前钢结构支撑梁2,在所述的后钢结构支撑梁1的上面和前钢结构支撑梁2的上面沿梁布置的左右方向分别固定设置有左右方向重物移动滑道3,在这两个左右方向重物移动滑道3中均分别设置有左右重物移动器4,在两个左右方向重物移动滑道3中分别设置的左右重物移动器4上固定设置有提升大梁5,提升大梁5设置于后钢结构支撑梁1与前钢结构支撑梁2之间的前后方向,在提升大梁5上沿提升大梁5布置的前后方向固定设置有H形型钢9,在H形型钢9上固定设置有前后方向重物移动滑道10,在前后方向重物移动滑道10中设置有前后重物移动器11,在前后重物移动器11上固定设置有小跑车12,小跑车12与吊板16的一端固定连接在一起,吊板16的另 一端依次通过上下滑轮组及钢丝绳17、连接转换器18、销轴19与汽包20连接在一起。
所述的左右方向重物移动滑道3是由槽钢6组成,在槽钢6与前、后钢结构支撑梁之间活动设置有垫板7,在槽钢6的外侧下端与钢结构支撑梁之间设置有凹形的限位板8,两限位板8扣接在槽钢6的外侧与钢结构支撑梁的上板下侧起到对垫板7的限位作用。
所述的小跑车12包括两组垂直交叉上下固定设置的第一支撑梁13和第二支撑梁14,在两根第二支撑梁14之间固定设置有定滑轮生根梁15,定滑轮生根梁15与所述的吊板16的一端固定连接在一起。
1、设计中考虑到安全因素,安全系数取的高,吊装中滑轮倍率大,吊装中安全性能增加。
2、制作汽包提升大梁、提升小车,制作汽包吊装小梁及吊板,在汽包吊耳安装在前后侧时方便使用。滑轮组采用销轴和汽包吊耳或吊装小梁连接,便于操作,吊装提升平稳。
3、使用重物移动器(小坦克链),满足提升大梁、提升小车的移动,保证了吊装过程无论汽包倾斜还是水平吊装,吊装用钢丝绳始终垂直受力。
4、使用了四台卷扬机及上下对应的双滑轮组,保证了滑轮组不偏斜。
5、吊装设备轻便灵活,便于安装、拆卸和运输。
6、吊装设备一次性投入能重复利用,降低了工程费用。

Claims (3)

1.一种火力发电厂锅炉汽包吊装吊具,包括施工现场高空中平行固定设置的后钢结构支撑梁(1)和前钢结构支撑梁(2),其特征在于,在所述的后钢结构支撑梁(1)的上面和前钢结构支撑梁(2)的上面沿梁布置的左右方向分别固定设置有左右方向重物移动滑道(3),在这两个左右方向重物移动滑道(3)中均分别设置有左右重物移动器(4),在两个左右方向重物移动滑道(3)中分别设置的左右重物移动器(4)上固定设置有提升大梁(5),提升大梁(5)设置于后钢结构支撑梁(1)与前钢结构支撑梁(2)之间的前后方向,在提升大梁(5)上沿提升大梁(5)布置的前后方向固定设置有H形型钢(9),在H形型钢(9)上固定设置有前后方向重物移动滑道(10),在前后方向重物移动滑道(10)中设置有前后重物移动器(11),在前后重物移动器(11)上固定设置有小跑车(12),小跑车(12)与吊板(16)的一端固定连接在一起,吊板(16)的另一端依次通过上下滑轮组及钢丝绳(17)、连接转换器(18)、销轴(19)与汽包(20)连接在一起。
2.根据权利要求1所述的一种火力发电厂锅炉汽包吊装吊具,其特征在于,所述的左右方向重物移动滑道(3)是由槽钢(6)组成,在槽钢(6)与前、后钢结构支撑梁之间活动设置有垫板(7),在槽钢(6)的外侧下端与钢结构支撑梁之间设置有凹形的限位板(8),限位板(8)扣接在槽钢(6)的外侧与钢结构支撑梁的上板下侧起到对垫板(7)的限位作用。
3.根据权利要求1或2所述的一种火力发电厂锅炉汽包吊装吊具,其特征在于,所述的小跑车(12)包括两组垂直交叉上下固定设置的第一支撑梁(13)和第二支撑梁(14),在两根第二支撑梁14之间固定设置有定滑轮生根梁(15),定滑轮生根梁(15)与所述的吊板(16)的一端固定连接在一起。
CN2010206470826U 2010-12-08 2010-12-08 火力发电厂锅炉汽包吊装吊具 Expired - Lifetime CN201901534U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206470826U CN201901534U (zh) 2010-12-08 2010-12-08 火力发电厂锅炉汽包吊装吊具

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206470826U CN201901534U (zh) 2010-12-08 2010-12-08 火力发电厂锅炉汽包吊装吊具

Publications (1)

Publication Number Publication Date
CN201901534U true CN201901534U (zh) 2011-07-20

Family

ID=44272133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206470826U Expired - Lifetime CN201901534U (zh) 2010-12-08 2010-12-08 火力发电厂锅炉汽包吊装吊具

Country Status (1)

Country Link
CN (1) CN201901534U (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103612994A (zh) * 2013-12-03 2014-03-05 四川电力建设三公司 汽包单吊点倾斜吊装方法及吊装装置
CN104003312A (zh) * 2014-06-04 2014-08-27 山东电力建设第一工程公司 模块式汽包提升装置

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103612994A (zh) * 2013-12-03 2014-03-05 四川电力建设三公司 汽包单吊点倾斜吊装方法及吊装装置
CN103612994B (zh) * 2013-12-03 2015-10-28 四川电力建设三公司 汽包单吊点倾斜吊装方法
CN104003312A (zh) * 2014-06-04 2014-08-27 山东电力建设第一工程公司 模块式汽包提升装置

Similar Documents

Publication Publication Date Title
CN101389855B (zh) 用于在风轮机上执行操作的方法和系统
EP2794455B1 (en) Method and apparatus for handling wind turbine components during transport and assembly
CN102094106A (zh) 四点悬挂式大型转炉快速安装方法
RU2744782C1 (ru) Подъемная система для установки ветряной турбины и способ для операции подъема (варианты)
CN201901534U (zh) 火力发电厂锅炉汽包吊装吊具
CN204626411U (zh) 一种桩基钢筋笼安装装置
CN103967263B (zh) 液压自动爬升卸料平台
CN104677744A (zh) 一种弹翼静力加载试验装置
CN206581150U (zh) 一种自动升降全围式吊篮安装平台装置
CN203312666U (zh) 一种隔离开关更换大修升降车
CN104003312A (zh) 模块式汽包提升装置
CN216662210U (zh) 一种适用于配电室模块的桁架式起吊框
KR101387742B1 (ko) 풍력 발전기의 나셀 내부 기계 요소 이송 장치
CN201903043U (zh) 大板梁叠梁
CN214734133U (zh) 一种升降式工作台
CN201825635U (zh) 电站锅炉吊装结构
CN111532980B (zh) 一种立式高加吊装方法
RU2761006C1 (ru) Грузоподъемное устройство
KR101322917B1 (ko) 풍력발전기 설치방법 및 그 장치
CN202766210U (zh) 一种电缆盖板起降装置
CN201261862Y (zh) 箱梁移动台车
CN217578181U (zh) 一种变流器举升滑移装置机器
CN204852797U (zh) 一种用于换热器头盖的拆装设备
CN216265893U (zh) 升降式移动工作平台
CN215160192U (zh) 一种金属支撑框架

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANXI NO 4 ELECTRIC POWER CONSTRUCTION COMPANY CH

Free format text: FORMER NAME: NO.4 POWER CONSTRUCTION COMPANY OF SHANXI ELECTRIC POWER CORPORATION

CP01 Change in the name or title of a patent holder

Address after: 030012 Shanxi city of Taiyuan province Pingyang road two lane 24

Patentee after: Shanxi No.4 Electric Power Construction Company of China Energy Engineering Group

Address before: 030012 Shanxi city of Taiyuan province Pingyang road two lane 24

Patentee before: Shanxi No.4 Electric Power Construction Company

C56 Change in the name or address of the patentee

Owner name: CHINA ENERGY ENGINEERING GROUP SHANXI ELECTRIC POW

Free format text: FORMER NAME: SHANXI NO 4 ELECTRIC POWER CONSTRUCTION COMPANY CHINA ENERGY ENGINEERING GROUP

CP01 Change in the name or title of a patent holder

Address after: 030012 Shanxi city of Taiyuan province Pingyang road two lane 24

Patentee after: SHANXI ELECTRIC POWER CONSTRUCTION CO., LTD.(CEEC)

Address before: 030012 Shanxi city of Taiyuan province Pingyang road two lane 24

Patentee before: Shanxi No.4 Electric Power Construction Company of China Energy Engineering Group

CX01 Expiry of patent term