CN201843338U CN2010205999669U CN201020599966U CN201843338U CN 201843338 U CN201843338 U CN 201843338U CN 2010205999669 U CN2010205999669 U CN 2010205999669U CN 201020599966 U CN201020599966 U CN 201020599966U CN 201843338 U CN201843338 U CN 201843338U
Authority
CN
China
Prior art keywords
bearing plate
garter spring
pipeline
joint
bed die
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010205999669U
Other languages
Chinese (zh)
Inventor
严朝学
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010205999669U priority Critical patent/CN201843338U/en
Application granted granted Critical
Publication of CN201843338U publication Critical patent/CN201843338U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)

Abstract

The utility model relates to a bottom die for jointing a penetrable hole of a pipeline of cement floors. The bottom die is characterized in that the bottom die comprises a hoop used for locating and clamping a pipeline; the upper end part of the hoop is connected with a bottom supporting plate; a pipeline through hole with the same circle center with the loop is arranged on the bottom supporting plate; both the hoop and the bottom supporting plate are formed by combining two half bodies; the lugs are respectively arranged at the butting parts at the two sides of the two half bodies of the loop; and the lugs at the butting parts are respectively connected with one another. The bottom die is mainly used for jointing the penetrable hole of the construction pipeline penetrating among floors, has simple structure, needs few manufacture materials, has low cost, is convenient in operation, can greatly reduce the working intensity and can improve the working efficiency.

Description

The joint filling bed die of cement floor pipe perforation
Technical field
The utility model relates to a kind of joint filling bed die of cement floor pipe perforation.
Background technology
Building storey generally all is provided with a lot of pipelines, and as water pipe, gas pipe and fulgurite etc., these pipelines need pass through the concrete floor of each floor, and floor needs boring earlier so that pipeline can pass.Pipeline between every layer need be blocked the gap between pipeline and the perforation after perforation is connected, and the first, can strengthen fastening pipeline; The second, can prevent that the upper strata from leaking or foreign material to lower floor, the 3rd, can protect the safe privacy of each layer resident family.
Caulking joint at present generally adopts cardboard or other sheet material to entangle pipeline in lower floor, and on the upper strata with wire with cardboard or other sheet material through the perforation tension to touch lower floor's ceiling, just can the casting cement caulking joint, after waiting to the cement solidifies, pull down cardboard or other sheet material, cut wire; Also have in lower floor and adopt the supporter supports cardboard, in a word, the general used material of caulking joint mostly is disposable use, waste resource, and troublesome poeration, and labour intensity is big, and operating efficiency is lower.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of this utility model is to provide a kind of joint filling bed die of simple in structure, easy to operate cement floor pipe perforation, and this joint filling bed die is convenient to operation, can reduce labour intensity greatly, increases work efficiency.
The technical solution of the utility model is: a kind of joint filling bed die of cement floor pipe perforation, it is characterized in that: comprise the garter spring that is used to locate clamping pipe, the upper end of described garter spring is connected with bearing plate, described bearing plate is provided with the pipeline through hole with the same center of circle of garter spring, described garter spring and bearing plate are all by the halved body be combined into, the joint of the halved body both sides of described garter spring is respectively equipped with lug, and the lug of joint is connected respectively.
The lug of described joint is connected through bolt and nut respectively.
The joint of the halved body both sides of described bearing plate is respectively equipped with the flight that staggers mutually and cooperate.
The outer, upper end of described garter spring is provided with and is used to strengthen the reinforcing ring that garter spring is connected with bearing plate.
Described garter spring and bearing plate are made into one.
Described bearing plate is a quadrangle, and described garter spring is positioned at middle part or angle of bearing plate.
Described bearing plate is circular, and described garter spring is positioned at the middle part of bearing plate.
Compared with prior art, the utlity model has following advantage: (1) is simple in structure, and manufacturing materials is few, and cost is low; (2) easy to operate, can reduce labour intensity, easy accessibility can be increased work efficiency; (3) reusable edible, relatively environmental protection.
Description of drawings
Fig. 1 is the schematic top plan view of the utility model first embodiment.
Fig. 2 is the elevational schematic view of the utility model first embodiment.
Fig. 3 looks schematic diagram for the master of the utility model first embodiment.
Fig. 4 is the perspective view of a halfbody among the utility model first embodiment.
Fig. 5 is the elevational schematic view of the utility model second embodiment.
Fig. 6 is the work schematic diagram of the utility model second embodiment.
The specific embodiment
With reference to figure 1 ~ 6, a kind of joint filling bed die of cement floor pipe perforation, it is characterized in that: comprise the garter spring 1 that is used to locate clamping pipe A, the upper end of described garter spring 1 is connected with bearing plate 2, described bearing plate 2 is provided with the pipeline through hole 2-1 with the garter spring 1 same center of circle, described garter spring 1 and bearing plate 2 are all by the halved body be combined into, Fig. 4 is the structural representation of a halfbody in the halved body, the joint of the halved body both sides of described garter spring 1 is respectively equipped with lug 3, and the lug 3 of joint is connected respectively.
The lug 3 of above-mentioned joint is connected through bolt and nut respectively, also can adopt the connected mode of other buckles and so on.
Be connected with bearing plate 2 in order to strengthen garter spring 1, the outer, upper end of above-mentioned garter spring 1 is provided with reinforcing ring 4.
In order to make the halved body of bearing plate 2 directly cooperate preferably, the joint of the halved body both sides of above-mentioned bearing plate 2 is respectively equipped with the flight B that staggers mutually and cooperate, even the diameter of pipeline A some size difference a little like this, after lug 3 connects, bearing plate 2 is butt joint fully not, but flight B staggers mutually and still can block perforation fully, and mud can not leak when caulking joint yet.
In order to reduce manufacturing process, above-mentioned garter spring 1 can be made into one with bearing plate 2.
Bearing plate 2 is a quadrangle among first embodiment of the present utility model, and described garter spring 1 is positioned at an angle of bearing plate 2, shown in Fig. 1 ~ 4, is applicable to when pipeline A is positioned at floor wall angle; Bearing plate 2 is circular among second embodiment of the present utility model, and described garter spring 1 is positioned at the middle part of bearing plate 2, as shown in Figure 5, be applicable to pipeline A be positioned at floor broader local time; Fig. 6 is the work schematic diagram of second embodiment, and A is a pipeline among the figure, and C is a floor plates, and D is the cement of caulking joint.
The course of work of the present utility model is as follows: after floor plates C boring and installing pipeline A, the joint filling bed die is installed again; Earlier a halfbody of bearing plate 2 is propped up lower floor's ceiling of floor, another halfbody of preliminary mounting support base plate 2 is again locked the lug 3 of the halved body both sides of garter spring 1 again; At the upper floor of floor casting cement in the slit of perforation, after waiting to the cement solidifies, unclamp bolt, pull down the caulking joint bed die.
It needs to be noted that the garter spring in the utility model and the material of bearing plate can be rigid plastics or metal material.
The above only is preferred embodiment of the present utility model, and all equalizations of being done according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.

Claims (7)

1. the joint filling bed die of a cement floor pipe perforation, it is characterized in that: comprise the garter spring that is used to locate clamping pipe, the upper end of described garter spring is connected with bearing plate, described bearing plate is provided with the pipeline through hole with the same center of circle of garter spring, described garter spring and bearing plate are all by the halved body be combined into, the joint of the halved body both sides of described garter spring is respectively equipped with lug, and the lug of joint is connected respectively.
2. the joint filling bed die of cement floor pipe perforation according to claim 1 is characterized in that: the lug of described joint is connected through bolt and nut respectively.
3. the joint filling bed die of cement floor pipe perforation according to claim 1 and 2 is characterized in that: the joint of the halved body both sides of described bearing plate is respectively equipped with the flight that staggers mutually and cooperate.
4. the joint filling bed die of cement floor pipe perforation according to claim 1 and 2 is characterized in that: the outer, upper end of described garter spring is provided with and is used to strengthen the reinforcing ring that garter spring is connected with bearing plate.
5. the joint filling bed die of cement floor pipe perforation according to claim 1 and 2 is characterized in that: described garter spring and bearing plate are made into one.
6. the joint filling bed die of cement floor pipe perforation according to claim 1 and 2 is characterized in that: described bearing plate is a quadrangle, and described garter spring is positioned at middle part or angle of bearing plate.
7. the joint filling bed die of cement floor pipe perforation according to claim 1 and 2 is characterized in that: described bearing plate is for circular, and described garter spring is positioned at the middle part of bearing plate.
CN2010205999669U 2010-11-10 2010-11-10 Bottom die for jointing penetrable hole of pipeline of cement floors Expired - Fee Related CN201843338U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010205999669U CN201843338U (en) 2010-11-10 2010-11-10 Bottom die for jointing penetrable hole of pipeline of cement floors

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010205999669U CN201843338U (en) 2010-11-10 2010-11-10 Bottom die for jointing penetrable hole of pipeline of cement floors

Publications (1)

Publication Number Publication Date
CN201843338U true CN201843338U (en) 2011-05-25

Family

ID=44038231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010205999669U Expired - Fee Related CN201843338U (en) 2010-11-10 2010-11-10 Bottom die for jointing penetrable hole of pipeline of cement floors

Country Status (1)

Country Link
CN (1) CN201843338U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817472A (en) * 2012-08-17 2012-12-12 中国十七冶集团有限公司 Shoring moldboard for preventing edge of pipeline from seeping

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817472A (en) * 2012-08-17 2012-12-12 中国十七冶集团有限公司 Shoring moldboard for preventing edge of pipeline from seeping

Similar Documents

Publication Publication Date Title
CN103498523B (en) Floor system
CN202000380U (en) Basement outer wall post-pouring belt backfill protective plate
CN201843338U (en) Bottom die for jointing penetrable hole of pipeline of cement floors
CN209066873U (en) A kind of pipeline hangs hole mold
CN201704954U (en) Formwork opposite-pulling device for pouring waterproof walls
CN101603330A (en) Steel-Solderless node connector for steel-concrete composite structure
CN207277389U (en) A kind of end template structure of deformation joint
CN201843336U (en) Pipeline through pore concrete-pouring template for pipeline installation and construction
CN202248862U (en) Pipe holder for plugging gap
CN102400440B (en) Outer template
CN210500792U (en) Double-tube type steel bar connecting structure between precast concrete components
CN202672735U (en) Construction site pump pipe-reinforcing auxiliary tool
CN202430986U (en) Device for lengthening steel pipe
CN211114133U (en) Connecting joint
CN204435421U (en) A kind of assembling manhole
CN203716477U (en) Connecting tube for building exterior wall scaffold
CN203699741U (en) Assembled type wall attaching device of tower crane
CN202299353U (en) Building scaffold
CN206903189U (en) A kind of connecting structure of wall of dual-raw external scaffold
CN203145122U (en) Drain pipe pre-embedding base
CN109594559B (en) Detachable counterforce anchor rod assembly and application method thereof
CN204326250U (en) Direct type steel column syndeton on a kind of reinforced concrete post
CN203322510U (en) Bidirectional petroleum platform pipeline fixing device
CN205230603U (en) Lantern ring support
CN204342322U (en) The counterbalanced weight structure of arm tower crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110525