CN201730106U CN2010201277199U CN201020127719U CN201730106U CN 201730106 U CN201730106 U CN 201730106U CN 2010201277199 U CN2010201277199 U CN 2010201277199U CN 201020127719 U CN201020127719 U CN 201020127719U CN 201730106 U CN201730106 U CN 201730106U
Authority
CN
China
Prior art keywords
steel
foundation
power transmission
iron tower
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010201277199U
Other languages
Chinese (zh)
Inventor
吴锁平
安增军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Electric Power Design Institute
Original Assignee
Jiangsu Electric Power Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Electric Power Design Institute filed Critical Jiangsu Electric Power Design Institute
Priority to CN2010201277199U priority Critical patent/CN201730106U/en
Application granted granted Critical
Publication of CN201730106U publication Critical patent/CN201730106U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)
  • Foundations (AREA)

Abstract

The utility model discloses a power transmission tower composite foundation, which is characterized by comprising a section steel metal foundation and a reinforced concrete foundation. The section steel metal foundation is directly laid on a foundation of a pit, the upper portion is connected with a tower, and the reinforced concrete foundation covers the outside of the section steel metal foundation. By combining the section steel metal foundation with the reinforced concrete foundation, the power transmission tower composite foundation saves the time of waiting for concrete curing before assembly of large-sized tower in construction of power transmission lines, is favorable for shortening rescue time for the power transmission lines, and reduces affection of power failure to production and daily life.

Description

A kind of composite foundation of power transmission line iron tower
Technical field
The utility model relates to the basis that a kind of iron tower of power transmission line uses, and belongs to the civil engineering technical field.
Background technology
There are the concrete foundation of cast in situs and two kinds of forms of assembling type base of precognition in the basis of iron tower of power transmission line.Concrete is because self properties of materials needs certain curing time after the foundation construction, and concrete strength just can be born load after increasing.The assembling type base construction is fast, constructed and can bear load immediately, but the supporting capacity of assembling type base is low, can only be used for small-sized iron tower.
Itself all adopts assembling type steel structure large-scale iron tower, the field-installed time is very short, the basic pattern that present 220kV and above large-scale iron tower adopt nearly all is a reinforced concrete foundation, between foundation construction and the iron tower assembling is arranged one period free time, waits for concrete gain in strength.
Current social industrial production and people's lives are very high to the degree of dependence of electric power, and the time of the speedily carrying out rescue work control after the iron tower of power transmission line accident is collapsed is very important, and concrete maintenance has restricted the time that transmission line of electricity is speedily carried out rescue work in large-scale iron tower.
The utility model content
It is simple that technical problem to be solved in the utility model provides a kind of construction, do not influence a kind of iron tower of power transmission line basis of upright tower, stringing engineering time.
For solving the problems of the technologies described above, the utility model provides a kind of composite foundation of power transmission line iron tower, it is characterized in that, the shaped steel metal basis and the reinforced concrete foundation that comprise self-organizing system, described shaped steel metal basis directly is placed on the ground of foundation ditch, top links to each other with iron tower, shaped steel metal basis is assembled to finish in foundation ditch and just can be begun to assemble iron tower on the ground, reinforced concrete foundation is coated on the outside on shaped steel metal basis, can in the assembling iron tower, construct, also can construct earlier and assemble iron tower again, but not need extra curing time.
The load of assembling iron tower can be born in shaped steel metal basis, and concrete maintenance utilizes the engineering time of iron tower assembling, and the final composite foundation that forms can be born the load of later stage line construction and operation.
Aforesaid composite foundation of power transmission line iron tower is characterized in that: described shaped steel metal basis comprises basic steel cap, column, girder and floor from top to bottom successively, and connects by bolt each other.
Aforesaid composite foundation of power transmission line iron tower is characterized in that: the basic steel cap that reinforced concrete foundation is coated on shaped steel metal basis reaches with the lower part.Concrete is until concordant with steel plate three, and final steel plate three also can be built a layer concrete after having assembled iron tower, steel are all wrapped in the concrete.Concrete had both been born the pressure of a part of iron tower in whole basis, play the effect of steel corrosion-resistant again.
Described floor comprises that the some H shaped steel one that are parallel to each other reach and the steel plate one of putting more energy into of its welding, and is connected with girder.
Described girder is arranged on the floor, and with the H shaped steel one perpendicular layout of floor, comprise two H shaped steel two and and its steel plate two of putting more energy into that welds mutually.
Described column comprises four angle steel one and four angle steel two that directly are arranged at the floor top that are arranged at H shaped steel two tops, described angle steel one, angle steel two weld with steel plate one respectively, H shaped steel two and steel plate one link to each other by bolt, floor is connected by bolt with steel plate, is provided with the angle steel three of many levels and the angle steel four of many inclinations between described four angle steel one and the angle steel two.
Described basic steel cap comprises four blocks of steel plates two all around that are welded into the steel plate three of " returning " font and are vertically installed in steel plate three that are horizontally placed on column top, and be welded to each other together, described steel plate two is connected with four angle steel two with four angle steel one of column by bolt.
The beneficial effect that the utility model reached:
The utility model is by combining shaped steel metal basis and reinforced concrete foundation, saved the medium-and-large-sized preceding time of waiting for concrete curing of iron tower assembling of transmission line construction, help shortening the time that transmission line of electricity is speedily carried out rescue work, reduce the influence that has a power failure to producing and living.
Description of drawings
Fig. 1 is chassis, the shaped steel metal basis schematic diagram of a kind of embodiment of composite foundation of power transmission line iron tower of the present utility model;
Fig. 2 is the shaped steel metal basis elevational schematic view of a kind of embodiment of composite foundation of power transmission line iron tower of the present utility model;
Fig. 3 is a composite foundation of power transmission line iron tower of the present utility model basis steel cap portion vertical view.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is further described.
In Fig. 1 and Fig. 2, shaped steel metal basis comprises basic steel cap, column, girder and floor from top to bottom successively, and connects by bolt each other.
Steel plate 2 14, steel plate 31 weld together, common formation base steel cap; Steel plate 1 welds with angle steel 1, angle steel 22 respectively, as the bolt junction plate of column angle steel end; Angle steel 35, angle steel 4 11 are the upright supports part; The H shaped steel 27 and the steel plate 2 10 of putting more energy into weld together, the girder of common formation base; The H shaped steel 1 and the steel plate 1 of putting more energy into weld together, the floor of common formation base; Connect the main stress frame of formation base by bolt between basis steel cap, column, girder, the floor; Template support 4 is connected by bolt with the column angle steel.
The utility model is mainly used in speedily carrying out rescue work of 220kV and the large-scale iron tower of 500kV transmission line of electricity.
Metal shaped steel, concrete composite foundation design procedure are as follows:
1) according to iron tower quality, place geological conditions, the wind speed of construction period design metal assembling type base;
2) size and the arrangement of reinforcement of concrete foundation calculated in the meteorological combination of the least favorable of the lead wire and earth wire parameter that adopts according to transmission line of electricity, stringing construction method, circuit run duration;
3) take all factors into consideration the structure of metal mold base steel plinth and concrete foundation, the bearing carrier that cancellation repeats to be provided with, the position of the member of coordinating to influence each other;
4) suitable concrete strength and the Admixture of selection of time that assembles according to iron tower.
Metal shaped steel, concrete composite foundation method for designing are exemplified below:
As certain 500kV power transmission sequence, 58.8 tons of iron tower deadweights, iron tower assembly process maximum design wind speed 10m/s, circuit run duration maximum design wind speed 30m/s, foundation soil is the silty clay of soft-plastic state, and bearing capacity of foundation soil 70kPa stablizes groundwater level 0.5m throughout the year.
1) according to the iron tower load of construction period, the width of metal assembling type base is defined as 3.65m, and foundation bed adopts 11 H shaped steel that width is 0.25m.
2) according to the load of stringing construction and circuit run duration, the width of concrete foundation is 5.9m, buried depth 2.5m, basis arrangement of reinforcement 30 at the end φ14.
3) metal shaped steel in the basic column and reinforcing bar merge, and promptly increase the area of shaped steel, cancellation column arrangement of reinforcement, and the position of coordinating sole plate reinforcing bar and H shaped steel, reserved steel bar passes through the hole.
4) in metal mold base steel plinth, add auxiliary accessories or the installing hole that foundation construction is used.
5) concrete foundation adopts C35 early strength concrete 12, curing time 2~3 days.
Above embodiment limits the utility model never in any form, and every other improvement and application that above embodiment is made in the equivalent transformation mode all belongs to protection domain of the present utility model.

Claims (7)

1. composite foundation of power transmission line iron tower, it is characterized in that: the shaped steel metal basis and the reinforced concrete foundation that comprise self-organizing system, described shaped steel metal basis directly is placed on the ground of foundation ditch, and top links to each other with iron tower, and reinforced concrete foundation is coated on the outside on shaped steel metal basis.
2. composite foundation of power transmission line iron tower according to claim 1 is characterized in that: described shaped steel metal basis comprises basic steel cap, column, girder and floor from top to bottom successively, and connects by bolt each other.
3. composite foundation of power transmission line iron tower according to claim 1 and 2 is characterized in that: the basic steel cap that reinforced concrete foundation is coated on shaped steel metal basis reaches with the lower part.
4. composite foundation of power transmission line iron tower according to claim 2 is characterized in that: described floor comprises that the some H shaped steel one (8) that are parallel to each other reach and the steel plate one (9) of putting more energy into of its welding.
5. composite foundation of power transmission line iron tower according to claim 2 is characterized in that: described girder is arranged on the floor, and with H shaped steel one (8) perpendicular layout, comprise two H shaped steel two (7) and and its steel plate two (10) of putting more energy into that welds mutually.
6. composite foundation of power transmission line iron tower according to claim 2, it is characterized in that: described column comprises that one (3) and four in four angle steel that are arranged at H shaped steel two (7) tops directly are arranged at the angle steel two (2) of floor top, described angle steel one (3), angle steel two (2) welds with steel plate one (6) respectively, H shaped steel two (7) links to each other with bolt by steel plate (6) with angle steel one (3), floor is connected with bolt by steel plate (6) with angle steel two (2), is provided with the angle steel three (5) of many levels and the angle steel four (11) of many inclinations between described four angle steel one (3) and the angle steel two (2).
7. composite foundation of power transmission line iron tower according to claim 2, it is characterized in that: described basic steel cap comprises four blocks of steel plates two (14) all around that are welded into the steel plate three (1) of " returning " font and are vertically installed in steel plate three (1) that are horizontally placed on column top, and be welded to each other together, described steel plate two (14) is connected with four angle steel two (2) with four angle steel one (3) of column by bolt.
CN2010201277199U 2010-03-10 2010-03-10 Power transmission tower composite foundation Expired - Lifetime CN201730106U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201277199U CN201730106U (en) 2010-03-10 2010-03-10 Power transmission tower composite foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201277199U CN201730106U (en) 2010-03-10 2010-03-10 Power transmission tower composite foundation

Publications (1)

Publication Number Publication Date
CN201730106U true CN201730106U (en) 2011-02-02

Family

ID=43521263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201277199U Expired - Lifetime CN201730106U (en) 2010-03-10 2010-03-10 Power transmission tower composite foundation

Country Status (1)

Country Link
CN (1) CN201730106U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775813A (en) * 2010-03-10 2010-07-14 江苏省电力设计院 Composite foundation of power transmission line iron tower
CN103469807A (en) * 2013-08-06 2013-12-25 安徽华电工程咨询设计有限公司 Distribution type rapid assembly method for new and old foundations for power transmission line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775813A (en) * 2010-03-10 2010-07-14 江苏省电力设计院 Composite foundation of power transmission line iron tower
CN103469807A (en) * 2013-08-06 2013-12-25 安徽华电工程咨询设计有限公司 Distribution type rapid assembly method for new and old foundations for power transmission line

Similar Documents

Publication Publication Date Title
CN101775813B (en) Composite foundation of power transmission line iron tower
CN202323978U (en) Base components for offshore wind power set installation
CN105179183A (en) Prestressed concrete wind power tower system and construction method thereof
CN111236294A (en) Combined cylinder structure fan foundation
CN201826325U (en) Foundation structure of tower crane
CN112412707B (en) Circular section concrete supporting structure of assembled wind turbine generator system
CN204898706U (en) Steel pipe pile foundation communication tower structure
CN103161174A (en) Offshore wind turbine generator set installation fundamental assembly
CN102852156A (en) Composite pile foundation structure
CN201599157U (en) Offshore wind turbine infrastructure with multi-pile steel framework and without peripheral connecting pipes
CN201599158U (en) Multi-stake steel framework maritime wind turbine infrastructure with central stake
CN201730106U (en) Power transmission tower composite foundation
CN206562827U (en) A kind of modularization steel-frame structure for tower equipment
CN201730109U (en) Novel fan foundation for intertidal zone wind farm
CN102852154A (en) Composite pile foundation
CN105756077B (en) Foundation ring Rock Bolt Foundation
CN103726505A (en) Offshore wind plant wind turbine foundation
CN204491567U (en) Prefabricated steel pipe pile wind power generation platform
CN216194894U (en) Cylindrical structure fan foundation with inverted convex bearing platform structure and wind turbine generator
WO2012146447A1 (en) A wind turbine tower made of wood and a method of erection thereof
CN202755368U (en) Long span pre-stressing force fish-belly beam used for retaining and protecting foundation pit
CN211898511U (en) Combined cylinder structure fan foundation
CN202031370U (en) Concrete-steel structure composite wind power tower
CN205036512U (en) Prestressed concrete wind -powered electricity generation pylon system
CN201588413U (en) Reinforcing structure for concrete bracket in original workshop

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20110202

Effective date of abandoning: 20110831