CN201599158U - Multi-pile steel frame offshore wind turbine foundation structure with central pile - Google Patents

Multi-pile steel frame offshore wind turbine foundation structure with central pile Download PDF

Info

Publication number
CN201599158U
CN201599158U CN2009202919621U CN200920291962U CN201599158U CN 201599158 U CN201599158 U CN 201599158U CN 2009202919621 U CN2009202919621 U CN 2009202919621U CN 200920291962 U CN200920291962 U CN 200920291962U CN 201599158 U CN201599158 U CN 201599158U
Authority
CN
China
Prior art keywords
steel pipe
steel
offshore wind
pile
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202919621U
Other languages
Chinese (zh)
Inventor
郑永明
周永
孙杏建
姜贞强
张春生
方滔
贾献林
郇彩云
俞华锋
罗金平
高礼洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2009202919621U priority Critical patent/CN201599158U/en
Application granted granted Critical
Publication of CN201599158U publication Critical patent/CN201599158U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Foundations (AREA)
  • Revetment (AREA)

Abstract

The utility model relates to a multi-stake steel framework maritime wind turbine infrastructure with a central stake. In order to solve technical problems, the utility model provides the multi-stake steel framework maritime wind turbine infrastructure with the central stake, which is suitable for offshore and intertidal belt sea area, and has the characteristics of cheapness, reliability, quick-speed construction and simplity and convenience. In order to solve the technical problems, the utility model adopts the technical scheme that the infrastructure adopts an integral steel framework with four to seven stakes, and comprises peripheral steel bushing pipes vertically arranged and a central connection section steel pipe; the steel pipe stake is fixedly connected inside the steel bushing pipes; a steel pipe stake is also fixedly connected to the bottom of the connection section steel pipe; the lower end of the steel pipe stake stretches into a bearing stratum below the sea bed; and the steel bushing pipes are connected with the connection section steel pipe through an oblique upper steel pipe and a horizontal lower steel pipe; in addition, the horizontal steel pipe is connected among the steel bushing pipes in the horizontal direction, and the upper end of the connection section steel pipe is fixedly connected with a stepped drum through a flange. The utility model can be used for maritime wind power generation.

Description

具有中心桩的多桩钢构架海上风电机组基础结构 Multi-pile steel frame offshore wind turbine foundation structure with central pile

技术领域technical field

本实用新型涉及一种具有中心桩的多桩钢构架海上风电机组基础结构,属于海上风力发电行业土木工程技术领域。The utility model relates to a foundation structure of a multi-pile steel frame offshore wind power unit with central piles, and belongs to the technical field of civil engineering in the offshore wind power generation industry.

背景技术Background technique

在我国,风力发电行业是一个新兴的行业。上世纪八十年代起,我国引进国外技术逐步在国内建设风力发电场,2000年以后,由于国家鼓励对可再生能源的开发和利用,使国内风力发电行业得到迅速发展。In my country, the wind power industry is a new industry. Since the 1980s, my country has introduced foreign technology and gradually built wind power plants in China. After 2000, the domestic wind power industry has developed rapidly due to the country's encouragement of the development and utilization of renewable energy.

到目前为止,我国已经在内蒙古、新疆、河北及东部沿海地区建成了一大批陆上风电场。但随着风电产业的大规模发展,土地资源紧张、与当地其它产业的予盾等问题已日渐显现,而我国拥有漫长的海岸线,海域蕴藏有丰富的风能资源,近年来,海上风电得到快速的发展。So far, my country has built a large number of onshore wind farms in Inner Mongolia, Xinjiang, Hebei and the eastern coastal areas. However, with the large-scale development of the wind power industry, problems such as shortage of land resources and conflicts with other local industries have gradually emerged. my country has a long coastline, and the sea area is rich in wind energy resources. In recent years, offshore wind power has been rapidly developed. develop.

由于海上自然环境的特殊性,普通的陆上施工机械和施工方法将不能使用,陆上常规的风电机组基础结构不便于用在海上。海上的风电机组基础要解决防潮水、防海浪、软弱地基、海水腐蚀、快速施工等一系列问题。因为目前缺乏海上风电场的建设经验,尚没有找到一种廉价、可靠的基础解决方案,常规的混凝土承台浇筑方式海上施工作业量大,受天气影响大,施工周期长。尤其对于东南沿海潮间带海域,传统的陆上和海上设备较难进场,海床面潮汐涨落频繁,可供施工作业的时间更短。Due to the particularity of the natural environment at sea, ordinary land construction machinery and construction methods cannot be used, and the foundation structure of conventional land wind turbines is not convenient for use at sea. The foundation of offshore wind turbines needs to solve a series of problems such as tide-proof, anti-wave, weak foundation, seawater corrosion, and rapid construction. Due to the lack of experience in the construction of offshore wind farms, a cheap and reliable foundation solution has not yet been found. The conventional concrete cap pouring method requires a lot of offshore construction work, is greatly affected by the weather, and has a long construction period. Especially for the intertidal sea area along the southeast coast, it is difficult for traditional land and offshore equipment to enter the site, and the seabed surface has frequent tidal fluctuations, and the time available for construction operations is shorter.

发明内容Contents of the invention

本实用新型要解决的技术问题是:基于我国沿海的近海及潮间带环境条件,提供一种适合于近海及潮间带海域的具有中心桩的多桩钢构架海上风电机组基础结构,具有廉价、可靠、施工快速、简便的特点。The technical problem to be solved by the utility model is: based on the coastal and intertidal environmental conditions of our country, to provide a multi-pile steel frame offshore wind turbine foundation structure with central piles suitable for offshore and intertidal sea areas, with low cost , Reliable, fast and easy construction.

本实用新型所采用的技术方案是:具有中心桩的多桩钢构架海上风电机组基础结构,其特征在于:所述基础结构为4~7桩整体钢构架结构,包括竖直设置的外围的钢套管和中央的连接段钢管,所述钢套管内固结连接钢管桩,连接段钢管底部也固定连接1根钢管桩,钢管桩下端伸入至海床以下持力层;钢套管通过斜向的上部钢管和水平向的下部钢管与连接段钢管相连,此外,钢套管之间在水平方向连有水平钢管;所述连接段钢管的上端通过法兰与塔筒固定连接。The technical scheme adopted by the utility model is: the foundation structure of the multi-pile steel frame offshore wind turbine with central piles, which is characterized in that: the foundation structure is an integral steel frame structure of 4 to 7 piles, including vertically arranged peripheral steel structures. The casing and the steel pipe in the central connection section, the steel casing is consolidated and connected to the steel pipe pile, and the bottom of the steel pipe in the connection section is also fixedly connected to a steel pipe pile, and the lower end of the steel pipe pile extends into the bearing layer below the seabed; the steel casing The pipe is connected to the steel pipe in the connection section through the oblique upper steel pipe and the horizontal lower steel pipe. In addition, a horizontal steel pipe is connected in the horizontal direction between the steel sleeves; the upper end of the steel pipe in the connection section is fixedly connected to the tower through a flange.

所述钢套管与钢管桩之间由灌浆材料粘结固定。The steel casing and the steel pipe pile are bonded and fixed by grouting material.

所述连接段钢管可按等管径或变管径设计,直径为4000~5000mm,其顶面高于最高潮位。连接段钢管的顶部设置检修平台。The steel pipes of the connecting section can be designed according to equal pipe diameter or variable pipe diameter, and the diameter is 4000~5000mm, the top surface is higher than the highest tide level. An inspection platform is arranged on the top of the steel pipe of the connecting section.

所述钢管桩的直径为

Figure G2009202919621D00022
800~2700mm;上部钢管的直径为
Figure G2009202919621D00023
600~2200mm;The diameter of the steel pipe pile is
Figure G2009202919621D00022
800~2700mm; the diameter of the upper steel pipe is
Figure G2009202919621D00023
600~2200mm;

下部钢管的直径为

Figure G2009202919621D00024
500~1600mm;水平钢管的直径为
Figure G2009202919621D00025
400~1400mm。The diameter of the lower steel tube is
Figure G2009202919621D00024
500~1600mm; the diameter of the horizontal steel pipe is
Figure G2009202919621D00025
400~1400mm.

本实用新型的有益效果是:(1)钢构架在工厂预制,质量易保证,并采用整体安装,海上作业量小、作业时间短;(2)单个基础打入4~7根钢管桩,呈中央和外围相结合布置,受力均匀,稳定性好,并利用国内现有设备沉桩,施工工艺成熟;(3)钢构架均为圆形钢管组成,波浪力较小,尤其对近海海域,钢构架位于水下,波浪荷载较大的区域仅为单根钢管,可较大限度的减少浪压力的作用;(4)钢管桩与连接段间采用灌浆材料连接,施工简便,并且可以适应现场施工误差;(5)基础为全钢结构,结合牺牲阳极的阴极保护与涂层防护的防腐蚀措施,施工工艺成熟,质量易保证。The beneficial effects of the utility model are: (1) the steel frame is prefabricated in the factory, the quality is easy to guarantee, and the overall installation is adopted, the offshore operation is small and the operation time is short; (2) 4 to 7 steel pipe piles are driven into a single foundation, It is arranged in a combination of the center and the periphery, with uniform force and good stability. The existing domestic equipment is used for pile sinking, and the construction technology is mature; (3) The steel structure is composed of circular steel pipes, and the wave force is small, especially for offshore waters , the steel frame is located underwater, and the area with a large wave load is only a single steel pipe, which can greatly reduce the effect of wave pressure; (4) The steel pipe pile and the connecting section are connected by grouting materials, which is easy to construct and can Adapt to on-site construction errors; (5) The foundation is an all-steel structure, combined with sacrificial anode cathodic protection and coating protection anti-corrosion measures, the construction technology is mature, and the quality is easy to guarantee.

附图说明Description of drawings

图1是本实用新型应用于近海或潮间带海域的立面图。Fig. 1 is the elevation view that the utility model is applied in offshore or intertidal zone sea area.

图2是本实用新型实施例1(4桩)应用于近海或潮间带海域的平面图。Fig. 2 is the plan view that embodiment 1 (4 piles) of the present invention is applied to offshore or intertidal zone sea area.

图3是本实用新型实施例2(5桩)应用于近海或潮间带海域的平面图。Fig. 3 is the plan view that the utility model embodiment 2 (5 piles) is applied in offshore or intertidal zone sea area.

图4是本实用新型实施例3(6桩)应用于近海或潮间带海域的平面图。Fig. 4 is the plan view that embodiment 3 (6 piles) of the present invention is applied in offshore or intertidal zone sea area.

图5是本实用新型实施例4(7桩)应用于近海或潮间带海域的平面图。Fig. 5 is a plan view of application of embodiment 4 (7 piles) of the present utility model in offshore or intertidal sea areas.

具体实施方式Detailed ways

(1)实施例1:(1) Embodiment 1:

如图1、图2所示,本例为应用于海上风电机组的4桩钢构架基础结构,它包括3根竖直的钢套管2,呈等边三角形排列,相邻套管间距为18000mm,其内是与钢套管通过灌浆材料粘结固定的钢管桩1。该基础结构的中央是一竖直设置的等管径或变管径的连接段钢管6,其底部也固定连接1根钢管桩1,连接方式包括螺栓连接、灌浆连接或焊接等,如果采用大直径等管径的连接段钢管,则在连接位置还必须设置加强固定的部件。本例钢管桩1的直径均为

Figure G2009202919621D00031
2100mm,钢管桩下端打入至海床以下持力层,桩长需根据风电机组基础所处的地质与水文条件、风电机组的大小而定。钢套管2与连接段钢管6之间,焊有3根直径为1600mm的斜撑的上部钢管3,并焊有3根直径为
Figure G2009202919621D00033
1300mm的下部钢管4,下部钢管4可根据需要设置为斜撑或水平向,本例按水平向设计。此外,钢套管2之间有3根直径为
Figure G2009202919621D00034
1000mm的水平钢管5焊接相连。下部钢管4和上部钢管3的里端均与中间竖直的连接段钢管6焊接固定,连接段钢管的上端通过法兰与塔筒8固定连接。As shown in Figure 1 and Figure 2, this example is a 4-pile steel frame foundation structure applied to offshore wind turbines, which includes 3 vertical steel casings 2 arranged in an equilateral triangle, and the distance between adjacent casings is 18000mm , which is a steel pipe pile 1 that is bonded and fixed with the steel casing through grouting materials. In the center of the foundation structure is a vertically arranged steel pipe 6 of equal or variable diameter connecting section, the bottom of which is also fixedly connected to a steel pipe pile 1, and the connection methods include bolt connection, grouting connection or welding, etc. For steel pipes with large diameters and equal diameters, strengthening and fixing parts must be installed at the connection position. The diameter of steel pipe pile 1 in this example is
Figure G2009202919621D00031
2100mm, the lower end of the steel pipe pile is driven into the bearing layer below the seabed. The pile length needs to be determined according to the geological and hydrological conditions of the wind turbine foundation and the size of the wind turbine. Between the steel casing 2 and the connecting section steel pipe 6, there are 3 diameters welded The upper steel pipe 3 of the 1600mm diagonal bracing is welded with 3 steel pipes with a diameter of
Figure G2009202919621D00033
The lower steel pipe 4 of 1300mm, the lower steel pipe 4 can be set as a diagonal brace or a horizontal direction as required, and this example is designed according to the horizontal direction. In addition, there are 3 diameters between the steel sleeves 2
Figure G2009202919621D00034
1000mm horizontal steel pipes 5 are connected by welding. The inner ends of the lower steel pipe 4 and the upper steel pipe 3 are welded and fixed with the vertical connection section steel pipe 6 in the middle, and the upper end of the connection section steel pipe is fixedly connected with the tower tube 8 by the flange.

图1是按等管径设计的大直径连接段管钢6,直径

Figure G2009202919621D00035
4300,连接段钢管的顶面应高于最高潮位,以保证风电机组的电气设备不受海浪影响。连接段钢管的顶部设置检修平台7,检修平台用于运行期维护和检修。Figure 1 is a large-diameter connecting section of pipe steel 6 designed according to equal pipe diameters.
Figure G2009202919621D00035
4300, the top surface of the steel pipe in the connecting section should be higher than the highest tide level to ensure that the electrical equipment of the wind turbine is not affected by the waves. An overhaul platform 7 is arranged on the top of the steel pipe in the connecting section, and the overhaul platform is used for maintenance and overhaul during operation.

本实施例的钢构架及钢管桩1分别在工厂整体加工制作,运到现场后钢构架由起重设备整体安装,钢管桩由打桩船打桩。根据水深情况,可先安装钢构架,调平完毕后,沿钢套管位置进行打桩;也可先打桩,之后将钢构架整体套接在钢管桩上,再进行调平。钢套管与钢管桩间的间隙采用灌注灌浆材料,灌浆材料固化后即钢管桩和连接筒牢固的粘接在一起。The steel frame and the steel pipe pile 1 of this embodiment are processed and manufactured in a factory as a whole, and after being transported to the site, the steel frame is integrally installed by lifting equipment, and the steel pipe pile is driven by a piling ship. According to the water depth, the steel frame can be installed first, and after the leveling is completed, piles can be driven along the position of the steel casing; the piles can also be driven first, and then the steel frame is integrally socketed on the steel pipe pile, and then leveled. The gap between the steel casing and the steel pipe pile is filled with grouting material. After the grouting material is solidified, the steel pipe pile and the connecting cylinder are firmly bonded together.

(2)实施例2:(2) Embodiment 2:

如图1、图3所示,本例为应用于海上风电机组的5桩钢构架基础结构,它包括4根竖直的钢套管2,呈正方形排列,相邻套管间距为15000mm,外围4根钢套管内通过灌浆材料粘结固定钢管桩1,基础结构中央的连接段钢管6底部也通过螺栓、灌浆或焊接等固定连接1根钢管桩,钢管桩的直径为1700mm,钢管桩下端打入至海床以下持力层。钢套管2与连接段钢管6之间,焊有4根直径为

Figure G2009202919621D00037
1400mm的斜撑的上部钢管3,并焊有4根直径为
Figure G2009202919621D00038
1200mm的水平的下部钢管4。钢套管2之间有4根直径为
Figure G2009202919621D00039
800mm的水平钢管5焊接相连。As shown in Figure 1 and Figure 3, this example is a 5-pile steel frame foundation structure applied to offshore wind turbines, which includes 4 vertical steel casings 2 arranged in a square, with a distance of The steel pipe pile 1 is bonded and fixed by grouting materials in the four steel sleeves, and the bottom of the steel pipe 6 in the connecting section in the center of the foundation structure is also fixedly connected to a steel pipe pile by bolts, grouting or welding. The diameter of the steel pipe pile is 1700mm, the lower end of the steel pipe pile is driven into the bearing layer below the seabed. Between the steel casing 2 and the connecting section steel pipe 6, there are 4 diameters welded
Figure G2009202919621D00037
The upper steel pipe 3 of the 1400mm diagonal bracing is welded with 4 steel pipes with a diameter of
Figure G2009202919621D00038
1200mm horizontal lower steel pipe 4. There are 4 diameters between the steel sleeves 2
Figure G2009202919621D00039
The horizontal steel pipe 5 of 800mm is connected by welding.

其余结构及施工方式和例1相同,不再重复描述。The rest of the structure and construction methods are the same as in Example 1, and will not be described again.

(3)实施例3:(3) Embodiment 3:

如图1、图4所示,本例为应用于海上风电机组的6桩钢构架基础结构,呈五边形排列,外围有5根竖直的钢套管2,相邻套管间距为12000mm,每个钢套管内通过灌浆材料粘结固定钢管桩1,在基础结构中央的连接段钢管6底部也固结连接1根钢管桩,钢管桩的直径为

Figure G2009202919621D00041
1300mm,钢管桩下端打入至海床以下持力层。钢套管2与连接段钢管6之间,焊有5根直径为
Figure G2009202919621D00042
1200mm的上部钢管3,并焊有5根直径为
Figure G2009202919621D00043
1000mm的下部钢管4。钢套管2之间有5根直径为700mm的水平钢管5焊接相连。As shown in Figure 1 and Figure 4, this example is a 6-pile steel frame foundation structure applied to offshore wind turbines, arranged in a pentagonal shape, with 5 vertical steel casings 2 on the periphery, and the distance between adjacent casings is 12000mm , the steel pipe pile 1 is bonded and fixed by grouting material in each steel casing, and a steel pipe pile is also consolidated and connected to the bottom of the steel pipe 6 in the central connection section of the foundation structure. The diameter of the steel pipe pile is
Figure G2009202919621D00041
1300mm, the lower end of the steel pipe pile is driven into the bearing layer below the seabed. Between the steel casing 2 and the connecting section steel pipe 6, 5 diameters are welded
Figure G2009202919621D00042
1200mm upper steel pipe 3, and welded with 5 diameters
Figure G2009202919621D00043
The lower steel pipe 4 of 1000mm. There are 5 diameters between the steel sleeves 2 The horizontal steel pipe 5 of 700mm is connected by welding.

其余结构及施工方式和例1相同,不再重复描述。The rest of the structure and construction methods are the same as in Example 1, and will not be described again.

(4)实施例4(4) Embodiment 4

如图1、图5所示,本例为应用于海上风电机组的7桩钢构架基础结构,呈六边形排列,外围有6根竖直的钢套管2,相邻套管间距为10000mm,每根钢套管通过灌浆材料粘结固定钢管桩1,在基础结构中央的连接段钢管6底部也固结连接1根钢管桩,钢管桩的直径为1100mm,钢管桩下端打入至海床以下持力层。钢套管2与连接段钢管6之间,焊有6根直径为

Figure G2009202919621D00046
900mm的上部钢管3,并焊有6根直径为
Figure G2009202919621D00047
700mm的下部钢管4。钢套管2之间有6根直径为
Figure G2009202919621D00048
600mm的水平钢管5焊接相连。As shown in Figure 1 and Figure 5, this example is a 7-pile steel frame foundation structure applied to offshore wind turbines, arranged in a hexagonal shape, with 6 vertical steel casings 2 on the periphery, and the distance between adjacent casings is 10000mm , each steel casing is bonded and fixed to the steel pipe pile 1 by grouting material, and a steel pipe pile is also consolidated and connected to the bottom of the steel pipe 6 in the central connection section of the foundation structure. The diameter of the steel pipe pile is 1100mm, the lower end of the steel pipe pile is driven into the bearing layer below the seabed. Between the steel casing 2 and the connecting section steel pipe 6, there are 6 steel tubes with a diameter of
Figure G2009202919621D00046
900mm upper steel pipe 3, and welded with 6 diameters
Figure G2009202919621D00047
700mm lower steel pipe 4. There are 6 diameters between the steel sleeves 2
Figure G2009202919621D00048
The horizontal steel pipe 5 of 600mm is connected by welding.

其余结构及施工方式和例1相同,不再重复描述。The rest of the structure and construction methods are the same as in Example 1, and will not be described again.

本实用新型用于单机容量为1.5~6.0MW的海上风电机组基础结构,上述四个实施例重点针对2.0MW风电机组荷载情况提出,其相关尺寸还可根据实际海床地质、海洋水文条件、施工能力等有所调整。采用本结构后,风电机组基础可适应0~30m深度的海上环境,基础不均匀沉降和水平位移都可以得到有效控制,且海上施工作业量小,受天气影响小,施工质量易保证,造价较低,施工工期较短。The utility model is used for the basic structure of offshore wind turbines with a unit capacity of 1.5-6.0MW. The above four embodiments are mainly proposed for the load of 2.0MW wind turbines. The relevant dimensions can also be based on actual seabed geology, ocean hydrology conditions, and construction. Ability etc. have been adjusted. After adopting this structure, the wind turbine foundation can adapt to the sea environment at a depth of 0-30m, the uneven settlement and horizontal displacement of the foundation can be effectively controlled, and the offshore construction workload is small, the weather is less affected, the construction quality is easy to guarantee, and the cost is relatively low. Low and short construction period.

Claims (8)

1. many steel framework offshore wind farm unit fondational structures with Center stake, it is characterized in that: described fondational structure is 4~7 whole steel frame constructions, comprise the Steel Sleeve (2) of the periphery of vertical setting and the linkage section steel pipe (6) of central authorities, fixed connection steel pipe pile (1) in the described Steel Sleeve (2), linkage section steel pipe (6) bottom also fixedly connected 1 steel pipe pile (1), the steel pipe pile lower end stretches to the following supporting course of sea bed; Steel Sleeve (2) by oblique top steel pipe (3) and level to bottom steel pipe (4) link to each other with linkage section steel pipe (6), in addition, be connected with horizontal steel tube (5) between the Steel Sleeve (2) in the horizontal direction; Fixedly connected with tower tube (8) by flange in the upper end of described linkage section steel pipe (6).
2. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 is characterized in that: fixing by the grouting material bonding between described Steel Sleeve (2) and the steel pipe pile (1).
3. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 is characterized in that: described linkage section steel pipe (6) is for waiting caliber or becoming caliber, and diameter is
Figure F2009202919621C00011
4000~5000mm, its end face is higher than highest water level.
4. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 3, it is characterized in that: the top of described linkage section steel pipe (6) is provided with inspection platform (7).
5. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 and 2, it is characterized in that: the diameter of described steel pipe pile (1) is
Figure F2009202919621C00012
800~2700mm.
6. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 and 2, it is characterized in that: the diameter of described top steel pipe (3) is
Figure F2009202919621C00013
600~2200mm.
7. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 and 2, it is characterized in that: the diameter of described bottom steel pipe (4) is
Figure F2009202919621C00014
500~1600mm.
8. many steel framework offshore wind farm unit fondational structures with Center stake according to claim 1 and 2, it is characterized in that: the diameter of described horizontal steel tube (5) is
Figure F2009202919621C00015
400~1400mm.
CN2009202919621U 2009-09-29 2009-12-09 Multi-pile steel frame offshore wind turbine foundation structure with central pile Expired - Fee Related CN201599158U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202919621U CN201599158U (en) 2009-09-29 2009-12-09 Multi-pile steel frame offshore wind turbine foundation structure with central pile

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN200920198227.6 2009-09-29
CN2009202919621U CN201599158U (en) 2009-09-29 2009-12-09 Multi-pile steel frame offshore wind turbine foundation structure with central pile

Publications (1)

Publication Number Publication Date
CN201599158U true CN201599158U (en) 2010-10-06

Family

ID=42810211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202919621U Expired - Fee Related CN201599158U (en) 2009-09-29 2009-12-09 Multi-pile steel frame offshore wind turbine foundation structure with central pile

Country Status (1)

Country Link
CN (1) CN201599158U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103352474A (en) * 2013-06-27 2013-10-16 天津大学 High-rise pile cap offshore wind power foundation combining vertical single pile and multiple raking piles
CN104088292A (en) * 2014-08-05 2014-10-08 熊翱 Axis single-pile multi-tripod foundation and construction method thereof
CN105297696A (en) * 2014-07-16 2016-02-03 中国海洋石油总公司 Six-leg wellhead platform jacket
CN109403368A (en) * 2018-09-06 2019-03-01 李敬 A kind of load basis and its design method
CN113250235A (en) * 2021-05-24 2021-08-13 江苏科技大学 Truss type single pile based on offshore wind turbine
CN114108672A (en) * 2021-11-16 2022-03-01 安徽省公路桥梁工程有限公司 Tower crane foundation and bottom plate superposition integrated structure and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103352474A (en) * 2013-06-27 2013-10-16 天津大学 High-rise pile cap offshore wind power foundation combining vertical single pile and multiple raking piles
CN105297696A (en) * 2014-07-16 2016-02-03 中国海洋石油总公司 Six-leg wellhead platform jacket
CN104088292A (en) * 2014-08-05 2014-10-08 熊翱 Axis single-pile multi-tripod foundation and construction method thereof
CN109403368A (en) * 2018-09-06 2019-03-01 李敬 A kind of load basis and its design method
CN113250235A (en) * 2021-05-24 2021-08-13 江苏科技大学 Truss type single pile based on offshore wind turbine
CN114108672A (en) * 2021-11-16 2022-03-01 安徽省公路桥梁工程有限公司 Tower crane foundation and bottom plate superposition integrated structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN201649118U (en) Foundation structure of jacket-type offshore wind turbine
CN201513303U (en) Offshore wind turbine generator foundation structure with multi-pile steel frame
CN101768978B (en) At-sea wind generation unit foundation formed by barrel type foundation and mooring rope anchor
CN201538971U (en) High pile cap type offshore wind turbine foundation structure
CN204610156U (en) Offshore wind turbine single-pile foundation integrated form accessory structure
CN110984214B (en) Offshore wind power monopile-wing plate-rockfill composite foundation and construction method thereof
CN201526424U (en) Monopile Offshore Wind Turbine Foundation Structure
CN101545462B (en) A steel-concrete combined weight type offshore wind fan foundation structure
CN101798815A (en) Marine wind turbine foundation for steel-concrete combined structure
CN106245671B (en) A kind of combined type offshore wind power foundation and its construction method
CN201599158U (en) Multi-pile steel frame offshore wind turbine foundation structure with central pile
CN102777333A (en) Truss type wind turbine structure
CN209603168U (en) A kind of offshore wind farm combination foundation
CN109853609A (en) A kind of offshore wind farm combination foundation
CN106381881B (en) A kind of gravity type single-pile foundation
CN201599157U (en) Offshore wind turbine infrastructure with multi-pile steel framework and without peripheral connecting pipes
CN110158637A (en) Offshore wind farm bucket foundation constructing structure and construction method
CN204825949U (en) Marine fan basis connection structure of pipe posture of driving piles in advance
CN201502064U (en) Offshore wind turbine steel structure foundation
CN202247928U (en) Multi-pile portal frame type offshore wind generating set foundation structure
CN204645074U (en) A kind of single pile-gravity associating offshore wind power foundation
CN103243732A (en) Installing method of marine anemometer tower base structure
CN201704699U (en) Steel structure foundation system of offshore fan
CN201953582U (en) Offshore wind turbine foundation with levelling structure
CN207749529U (en) A kind of offshore wind farm combined type single-pile foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101006

Termination date: 20181209

CF01 Termination of patent right due to non-payment of annual fee