CN201722615U - Spanning type construction system with large-span box girder - Google Patents

Spanning type construction system with large-span box girder Download PDF

Info

Publication number
CN201722615U
CN201722615U CN2010202106489U CN201020210648U CN201722615U CN 201722615 U CN201722615 U CN 201722615U CN 2010202106489 U CN2010202106489 U CN 2010202106489U CN 201020210648 U CN201020210648 U CN 201020210648U CN 201722615 U CN201722615 U CN 201722615U
Authority
CN
China
Prior art keywords
military
pier
piers
construction system
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202106489U
Other languages
Chinese (zh)
Inventor
邓寿军
陈延军
张立军
刘洪亮
林斌
闫学永
李永红
白子斌
董志彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Si Engineering Co Ltd Of Middle Iron Er Shierju Group
China Railway 22nd Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Original Assignee
Si Engineering Co Ltd Of Middle Iron Er Shierju Group
China Railway 22nd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Si Engineering Co Ltd Of Middle Iron Er Shierju Group, China Railway 22nd Bureau Group Co Ltd filed Critical Si Engineering Co Ltd Of Middle Iron Er Shierju Group
Priority to CN2010202106489U priority Critical patent/CN201722615U/en
Application granted granted Critical
Publication of CN201722615U publication Critical patent/CN201722615U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Revetment (AREA)

Abstract

The utility model discloses a spanning type construction system with a large-span box girder, which comprises a plurality of temporary piers, two military piers and movable die carriers. A concrete support foundation is arranged at the lower part of the temporary pier; a cushion cap and a plurality of pile foundations positioned below the cushion cap are arranged at the lower part of the military pier; the two military piers are respectively arranged in positions close to two sides of an object to be spanned; the temporary piers are symmetrically distributed on two sides of the temporary piers; and the movable die carriers are supported at the upper parts of the temporary piers or the military piers. By adopting the spanning type construction system as a supporting system for the construction of a continuous girder support, not only the limitation to the traditional door opening method by span can be prevented, but also supporting and fencing can be integrated into a whole, therefore, the complexity that two systems are required to be respectively considered originally is avoided; moreover, the adoption of a movable die carrier method as a supporting and fencing system for spanning is easy to be accepted by a spanned property right unit, and provides convenience for the examination and approval of various procedures; and the system is very beneficial to popularization and application.

Description

The great-leap-forward construction system of wide-span case beam
Technical field
The utility model relates to a kind of construction field of wide-span case beam, particularly relates to a kind of great-leap-forward construction system of wide-span case beam.
Background technology
Often run into Construction of continuous beam in present stage railway, the construction of the highway and cross over the situation of existing railway, highway, if adopt traditional door opening method construction, not only be subjected to the restriction of span, also can influence the operation of existing railway and highway, need to coordinate relevant departments' coordinated time, involve examining of some formalities, and construction speed also is subjected to the restriction of existing railway, road travel, very inconvenient.
The utility model content
The purpose of this utility model is at the problems referred to above, proposes a kind of great-leap-forward construction system of wide-span case beam.
The technical solution of the utility model is: a kind of great-leap-forward construction system of wide-span case beam, comprise several interim piers, two military piers and mobile formwork, and described interim pedestal is the concrete brace foundation; Described military pedestal is provided with cushion cap and is positioned at several pile foundations below the cushion cap, and near the dual-side setting of being crossed over thing, described interim pier is symmetrically distributed in the both sides of military pier to described two military piers respectively; Described mobile formwork is supported on interim pier or military socle.
Described mobile formwork comprises girder and the bed die truss that is fixedly installed togather in length and breadth, is provided with bed die on the bed die truss; Be provided with mobile device below described girder, this mobile device is installed in interim pier and military pier upper end.
The front end of described girder is provided with the girder nose girder of certain-length.
Described mobile device comprises pumping plant, vertical jack, displacement chassis, vertical shift mechanism, transverse-moving mechanism, hook, carriage.
The top of described interim pier and military pier is provided with the two-layer bearing beam of going up of crisscross setting, and the described bearing beam top of going up is provided with crossbeam, and described mobile formwork is installed in crossbeam top; The bottom of described interim pier and military pier is provided with the two-layer down bearing beam of crisscross setting, and described bearing beam down is positioned on the concrete brace foundation or on the cushion cap.
The beneficial effects of the utility model
Adopt the support system of great-leap-forward construction system of the present utility model, both can prevent that traditional door opening method is subjected to the restriction of span as the continuous beam rack construction; Can also support, protection is as one, saved loaded down with trivial details that original two kinds of systems consider respectively; In addition, adopt the mobile formwork method as the supporting protection system of crossing over, the property right unit of being crossed over is acceptant, is the condition of providing convenience of examining of various formalities.
Description of drawings
Fig. 1 is the structural representation of facing of this great-leap-forward construction system
Fig. 2 is the structural representation of facing of the mobile formwork among Fig. 1
Fig. 3 is the plan structure schematic diagram of Fig. 2
Fig. 4 is a military pier place cross-sectional structure schematic diagram among Fig. 1
Fig. 5 is the local enlarged diagram of mounting structure between mobile formwork and the military pier
Fig. 6 is the left TV structure schematic diagram of Fig. 5
Fig. 7 is the structural representation of facing of interim pier or military pier
Fig. 8 is the left TV structure schematic diagram of Fig. 7
Fig. 9 is the structural representation of facing of this great-leap-forward construction system of mobile formwork after putting in place
The specific embodiment
Referring to Fig. 1-Fig. 9,1. wide-span case beams among the figure, 2. mobile formwork, 3. crossed over thing, 4. military pier, 5. cushion cap, 6. pile foundation, 7. interim pier, 8. the concrete brace foundation, 9. descend bearing beam, 10. go up bearing beam, 11. crossbeams, wherein 2-1. girder, 2-2. bed die truss, 2-3. girder nose girder, 2-4. mobile device, 2-5. bed die.
Embodiment: a kind of great-leap-forward construction system of wide-span case beam, comprise several interim piers, two military piers and mobile formwork, described interim pedestal is the concrete brace foundation; Described military pedestal is provided with cushion cap and is positioned at several pile foundations below the cushion cap, and near the dual-side setting of being crossed over thing, described interim pier is symmetrically distributed in the both sides of military pier to described two military piers respectively; Described mobile formwork is supported on interim pier or military socle.
Described mobile formwork comprises girder and the bed die truss that is fixedly installed togather in length and breadth, is provided with bed die on the bed die truss; Be provided with mobile device below described girder, this mobile device is installed in interim pier and military pier upper end.
The front end of described girder is provided with the girder nose girder of certain-length.
Described mobile device comprises pumping plant, vertical jack, displacement chassis, vertical shift mechanism, transverse-moving mechanism, hook, carriage.
The top of described interim pier and military pier is provided with the two-layer bearing beam of going up of crisscross setting, and the described bearing beam top of going up is provided with crossbeam, and described mobile formwork is installed in crossbeam top; The bottom of described interim pier and military pier is provided with the two-layer down bearing beam of crisscross setting, and described bearing beam down is positioned on the concrete brace foundation or on the cushion cap.
The construction initial stage is handled concrete brace foundation and pile foundation earlier, and cushion cap, interim pier and military pier are installed then, then the mobile formwork after the assembly unit is lifted on the top of interim pier and military pier, after the leveling, start this mobile formwork of mobile device translation, after the girder of mobile formwork crosses by the leap thing fully, locate.

Claims (5)

1. the great-leap-forward construction system of a wide-span case beam comprises several interim piers, two military piers and mobile formwork, and it is characterized in that: described interim pedestal is the concrete brace foundation; Described military pedestal is provided with cushion cap and is positioned at several pile foundations below the cushion cap, and near the dual-side setting of being crossed over thing, described interim pier is symmetrically distributed in the both sides of military pier to described two military piers respectively; Described mobile formwork is supported on interim pier or military socle.
2. the great-leap-forward construction system of wide-span case beam according to claim 1, it is characterized in that: described mobile formwork comprises girder and the bed die truss that is fixedly installed togather in length and breadth, is provided with bed die on the bed die truss; Be provided with mobile device below described girder, this mobile device is installed in interim pier and military pier upper end.
3. the great-leap-forward construction system of wide-span case beam according to claim 2, it is characterized in that: the front end of described girder is provided with the girder nose girder of certain-length.
4. the great-leap-forward construction system of wide-span case beam according to claim 2 is characterized in that: described mobile device comprises pumping plant, vertical jack, displacement chassis, vertical shift mechanism, transverse-moving mechanism, hook, carriage.
5. the great-leap-forward construction system of wide-span case beam according to claim 1, it is characterized in that: the top of described interim pier and military pier is provided with the two-layer bearing beam of going up of crisscross setting, the described bearing beam top of going up is provided with crossbeam, and described mobile formwork is installed in crossbeam top; The bottom of described interim pier and military pier is provided with the two-layer down bearing beam of crisscross setting, and described bearing beam down is positioned on the concrete brace foundation or on the cushion cap.
CN2010202106489U 2010-06-01 2010-06-01 Spanning type construction system with large-span box girder Expired - Fee Related CN201722615U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202106489U CN201722615U (en) 2010-06-01 2010-06-01 Spanning type construction system with large-span box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202106489U CN201722615U (en) 2010-06-01 2010-06-01 Spanning type construction system with large-span box girder

Publications (1)

Publication Number Publication Date
CN201722615U true CN201722615U (en) 2011-01-26

Family

ID=43490930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202106489U Expired - Fee Related CN201722615U (en) 2010-06-01 2010-06-01 Spanning type construction system with large-span box girder

Country Status (1)

Country Link
CN (1) CN201722615U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321159A (en) * 2013-07-09 2013-09-25 中铁十五局集团第六工程有限公司 Construction method capable of improving girder erection speed of large double-track T-girder bridge
CN105133497A (en) * 2015-07-21 2015-12-09 杭州江润科技有限公司 Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system
CN105908629A (en) * 2016-04-27 2016-08-31 中铁大桥局集团有限公司 Descending movable framework for highway box girder at highway and railway combined construction section and application method of descending movable framework
CN107245953A (en) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 The bent device and crossed construction method of a kind of multilayer bridge structure
CN107841953A (en) * 2017-11-30 2018-03-27 中铁二十局集团第工程有限公司 Across the cast-in-place section construction support in high-altitude obliquely-intersected beams abrupt slope side and construction method
CN111021251A (en) * 2019-12-04 2020-04-17 中铁上海工程局集团有限公司 Construction method for assembling steel box girder above tramcar
CN112746564A (en) * 2020-12-31 2021-05-04 中铁二十局集团第六工程有限公司 Movable formwork assembling method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321159A (en) * 2013-07-09 2013-09-25 中铁十五局集团第六工程有限公司 Construction method capable of improving girder erection speed of large double-track T-girder bridge
CN103321159B (en) * 2013-07-09 2015-03-18 中铁十五局集团有限公司 Construction method capable of improving girder erection speed of large double-track T-girder bridge
CN105133497A (en) * 2015-07-21 2015-12-09 杭州江润科技有限公司 Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system
CN105908629A (en) * 2016-04-27 2016-08-31 中铁大桥局集团有限公司 Descending movable framework for highway box girder at highway and railway combined construction section and application method of descending movable framework
CN105908629B (en) * 2016-04-27 2018-03-30 中铁大桥局集团有限公司 Downlink movable mould frame and its application method for combined highway and metro section highway box beam
CN107245953A (en) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 The bent device and crossed construction method of a kind of multilayer bridge structure
CN107245953B (en) * 2017-07-14 2018-12-28 北京市市政一建设工程有限责任公司 A kind of crossed construction method of multilayer bridge structure
CN107841953A (en) * 2017-11-30 2018-03-27 中铁二十局集团第工程有限公司 Across the cast-in-place section construction support in high-altitude obliquely-intersected beams abrupt slope side and construction method
CN107841953B (en) * 2017-11-30 2024-02-27 中铁二十局集团第一工程有限公司 High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method
CN111021251A (en) * 2019-12-04 2020-04-17 中铁上海工程局集团有限公司 Construction method for assembling steel box girder above tramcar
CN111021251B (en) * 2019-12-04 2021-11-16 中铁上海工程局集团有限公司 Construction method for assembling steel box girder above tramcar
CN112746564A (en) * 2020-12-31 2021-05-04 中铁二十局集团第六工程有限公司 Movable formwork assembling method

Similar Documents

Publication Publication Date Title
CN201722615U (en) Spanning type construction system with large-span box girder
CN203256761U (en) Tower crane foundation arranged on top plate of basement
CN107044090A (en) A kind of construction method of dual deck bridge
CN206513104U (en) A kind of only pillar overhead station structure of urban track traffic
CN105386411A (en) Multifunctional portal device of suspension bridge pillar top
CN102249137B (en) Renewal method of elevator
CN103437304B (en) A kind of method increasing pier section replacing pot bearing
CN103485280B (en) Quick constructing method of cross-line bridge
JP4796411B2 (en) Bridge removal method
CN104775363B (en) The spelling method of upper king-post strut reinforcing bar sections
CN207714155U (en) A kind of bent cap holder
CN205741942U (en) A kind of great cantilever chooses arm pier cap beam segmental timbering
CN206800220U (en) One kind is used for across highway old bridge removal Fast Installation adjustable support
CN107724247B (en) A kind of box bridge tunnel face changes the outfit technique
CN202899639U (en) Concrete column structure
CN206034271U (en) Novel shelter bridge concrete foundation structure
CN204343701U (en) A kind of special-shaped leg post supports installation structure
CN105970988B (en) The construction method of elevator sidewall reinforcing bar is installed in raft foundation
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
CN210104781U (en) Tower crane foundation and structure of supporting sharing stand pile that links to each other
CN104314316B (en) A kind of special-shaped leg post supports construction method of installation
CN202848875U (en) Portal crane main beam structure
CN202388183U (en) Lifting equipment for H-shaped steel numerical control cutting machine
CN107237251B (en) A kind of access bridge flat stacking sets up the construction method of interim steel bridge
CN205382428U (en) Whole cast -in -place roof beam formwork support frame of falling triangle in hole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110126

Termination date: 20190601