CN201715188U - Base plate for equipment installation of nitrogen press - Google Patents
Base plate for equipment installation of nitrogen press Download PDFInfo
- Publication number
- CN201715188U CN201715188U CN2010202445948U CN201020244594U CN201715188U CN 201715188 U CN201715188 U CN 201715188U CN 2010202445948 U CN2010202445948 U CN 2010202445948U CN 201020244594 U CN201020244594 U CN 201020244594U CN 201715188 U CN201715188 U CN 201715188U
- Authority
- CN
- China
- Prior art keywords
- backing plate
- equipment installation
- base plate
- equipment
- nitrogen press
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model relates to equipment installation, in particular to the equipment installation of a nitrogen press. In the base plate for the equipment installation of the nitrogen press, the base plate is arranged in a foundation pit and is reserved with a mounting hole of an adjustable bolt. The utility model does not need to reserve a foundation bolt in building projects, and completes the equipment installation through the special base plate.
Description
Technical field
The utility model equipment is installed, and relates in particular to a kind of nitrogen compressor equipment and installs.
Background technique
Usually some equipment are installed all needs civil works backup land foot bolt, places plain cushion on ground, by back-grouting equipment is fixed then behind levelling, the centering.Yet do not stay in civil engineering under the situation of stone bolt, equipment just can't locate, fixing, so has only under the situation foundation of civil work destroyed and implements secondary and do over again, so not only troublesome poeration and time-consumingly take a lot of work that Safety performance is very poor simultaneously.We do not stay in civil engineering and study under the situation of stone bolt and tackle key problems for this reason, and having invented does not need civil works backup land foot bolt and carry out the special-purpose backing plate setting that equipment is installed.
Summary of the invention
The utility model is intended to address the aforementioned drawbacks, and provides a kind of nitrogen compressor equipment that backing plate is installed.The utility model does not need civil works backup land foot bolt, finishes equipment by special-purpose backing plate and installs.
The utility model is achieved in that a kind of nitrogen compressor equipment installation backing plate, and described backing plate is arranged in the foundation ditch and is reserved with the adjusting bolt mounting holes.
Described a kind of nitrogen compressor equipment is installed backing plate, is fixed by grout blanket around the described backing plate.
The utility model does not need civil works backup land foot bolt and carries out equipment and install, and is simple in structure, easy to use, improves Security.
Description of drawings
Below, further specify embodiment of the present utility model in conjunction with the accompanying drawings:
Embodiment
As shown in Figure 1,, process the backing plate of respective numbers more separately, vacate a position on the backing plate 1 simultaneously so that install and adjust bolt 2 according to on-the-spot actual size.Less during site operation owing to the foundation ditch inside dimension, be merely able to place manufactured backing plate, specially made some support beams for this reason during site operation again, earlier device support has been put backing plate 1 again with firmlying, simultaneously equipment has been connected on basic 3 by connecting bolt 2, in order to resist pipe arrangement pressure, in two positions that will provide backing plate below, consider thermal expansion, the balance of backing plate allows freely to float, because pedestal freely expands, so these backing plates 1 that do not allow to be in the milk.Re-use pad guarantee between the pre-basis of plant bottom case firm connection, care should be used to when shimming and connecting bolt does not twist base.After backing plate placed, the preparation machine adjustment was aimed at.The integral device adjustment finish and by inspection after, just remaining space gap in the foundation ditch is filled up it by back-grouting.
Claims (2)
1. a nitrogen compressor equipment is installed backing plate, it is characterized in that, described backing plate is arranged in the foundation ditch and is reserved with the adjusting bolt mounting holes.
2. a kind of nitrogen compressor equipment according to claim 1 is installed backing plate, it is characterized in that, is fixed by grout blanket around the described backing plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010202445948U CN201715188U (en) | 2010-06-29 | 2010-06-29 | Base plate for equipment installation of nitrogen press |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010202445948U CN201715188U (en) | 2010-06-29 | 2010-06-29 | Base plate for equipment installation of nitrogen press |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201715188U true CN201715188U (en) | 2011-01-19 |
Family
ID=43461187
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010202445948U Expired - Fee Related CN201715188U (en) | 2010-06-29 | 2010-06-29 | Base plate for equipment installation of nitrogen press |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201715188U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103016412A (en) * | 2012-12-27 | 2013-04-03 | 陕西化建工程有限责任公司 | Installation method for embedded base plate of axial flow compressor |
CN107780433A (en) * | 2016-08-27 | 2018-03-09 | 上海宝冶集团有限公司 | The flow grouting construction method of backing plate |
-
2010
- 2010-06-29 CN CN2010202445948U patent/CN201715188U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103016412A (en) * | 2012-12-27 | 2013-04-03 | 陕西化建工程有限责任公司 | Installation method for embedded base plate of axial flow compressor |
CN107780433A (en) * | 2016-08-27 | 2018-03-09 | 上海宝冶集团有限公司 | The flow grouting construction method of backing plate |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101343879B (en) | Secondary grouting construction method of machine setting | |
CN201865121U (en) | Intergraded profile steel positioning bracket device for embedding overlong foundation anchor bolts | |
CN202194244U (en) | Positioning support for embedding of ultra-high steel-work pedestals | |
CN103114604B (en) | Prestressed concrete tubular type wind generating set foundation | |
CN103967058A (en) | Method for in-hole guiding deviation rectification and steel pipe column straightening based on one-column-one-pile back insertion method | |
CN201715188U (en) | Base plate for equipment installation of nitrogen press | |
CN105544762A (en) | Method for installing seismic isolation layer | |
CN104120802B (en) | Simple method for mounting and locating seismic isolation support | |
CN104404882A (en) | Assistant mounting die for support and construction method thereof | |
CN104234074A (en) | Positioning device for pre-embedded anchoring bolt | |
CN203429564U (en) | Accurate installation and construction structure for bridge support | |
CN201794088U (en) | Foundation bolt positioner | |
CN101985824A (en) | Embedded part mounting device for bridge bearing | |
CN103148316B (en) | Base supporting system of secondary reheating steam turbine generator unit | |
CN202510932U (en) | Fastening means | |
CN204920263U (en) | But height-adjusting's guardrail | |
CN204252023U (en) | Installation mold assisted by a kind of bearing | |
CN202884252U (en) | High-low horizontal adjusting seat | |
CN103184743B (en) | Template flange | |
CN103174165A (en) | Full diameter embedded bolt positioning method | |
CN203346897U (en) | Foundation raft embedded steel column positioning support | |
CN205896396U (en) | Modular fast -assembling pipeline bracket | |
CN106051307A (en) | Combined fast-assembly pipeline support and mounting method thereof | |
CN205776305U (en) | A kind of three pipe tower sill anchor positioners | |
CN204326613U (en) | A kind of 110kV transformer station installation component |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110119 Termination date: 20120629 |