CN103174165A - Full diameter embedded bolt positioning method - Google Patents

Full diameter embedded bolt positioning method Download PDF

Info

Publication number
CN103174165A
CN103174165A CN2013100827503A CN201310082750A CN103174165A CN 103174165 A CN103174165 A CN 103174165A CN 2013100827503 A CN2013100827503 A CN 2013100827503A CN 201310082750 A CN201310082750 A CN 201310082750A CN 103174165 A CN103174165 A CN 103174165A
Authority
CN
China
Prior art keywords
fixed mount
bolt
embedded bolt
bridging
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100827503A
Other languages
Chinese (zh)
Inventor
房政
施光涛
李永
吴晴冬
林涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN2013100827503A priority Critical patent/CN103174165A/en
Publication of CN103174165A publication Critical patent/CN103174165A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a full diameter embedded bolt positioning method which includes the steps of arranging an embedded piece in a concrete surface of a foundation slab according to the position of a stand column and the position of an inclined bridging of a bolt fixing frame when foundation concrete is poured in a hot blast heater, then manufacturing the bolt fixing frame which is composed of the stand column, bottom layer horizontal bridging, an upper layer horizontal bridging, a cross bridging and the inclined bridging, well adjusting the center and the elevation of an embedded bolt, finally manufacturing a flange which is placed on and firmly welded with the embedded bolt, and then conducting overall reinforcement by arranging the cross bridging and the inclined bridging on the bolt fixing frame. The full diameter embedded bolt positioning method has the advantages of being simple in operation, convenient to construct, high in positioning accuracy, and capable of greatly reducing displacement of the bolt when the concrete is poured and vibrated, and creating advantages for structural installation.

Description

A kind of major diameter pre-embedded bolt localization method
Technical field
The present invention relates to metallurgical Installation Technology of Steel Structure field, relate in particular to a kind of major diameter pre-embedded bolt localization method, be applicable to the installation of hot-blast stove, the contour macrostructure major diameter of granulation tower pre-embedded bolt.
Background technology
In existing metallurgical construction; often can run into the location as major diameter pre-embedded bolts such as hot-blast stoves; the tradition localization method is to carry out reinforcement of weld by foundation main reinforcement and pre-embedded anchoring bolts to locate; often building concrete when vibrating; easily produce displacement; affected the structure installation, installed to structure and bring inconvenience.
Summary of the invention
Purpose of the present invention is exactly the above-mentioned shortcoming that exists for prior art, and a kind of major diameter pre-embedded bolt localization method is provided, and improves the positioning accuracy of pre-embedded bolt, reduces pre-embedded bolt and builds the displacement that produces when vibrating because of concrete.
The object of the present invention is achieved like this: a kind of major diameter pre-embedded bolt localization method is characterized in that: built-in fitting first is set, then makes the bolt fixed mount, last manufacturing flange also adds the fixing bolt fixed mount.
The described built-in fitting that arranges is when the hot-blast stove foundation concrete is built, and according to bolt fixed mount column and bearing diagonal position, establishes built-in fitting at sole plate concrete face, when being used for fixed mount and installing with column, bearing diagonal and built-in fitting firm welding.
Described making bolt fixed mount be fixed mount by column, bottom horizontal brace, upper water support, bridging, bearing diagonal form, column is selected the 12# channel-section steel, all the other all use 75 * 5 angle steel making, make it form the annular stereo fixed mount of independent system, with transit, the pre-embedded bolt center line is thrown and surveyed to fixed mount, according to adjustment pre-embedded bolt center, the center on fixed mount.Fixed mount bottom horizontal brace absolute altitude is surveyed according to the accurate instrument of pre-embedded bolt design high water usage and is established, and pre-embedded bolt is placed on the bottom horizontal brace, and the pre-embedded bolt verticality supports by the fixed mount upper water and regulates.
Described manufacturing flange and to add the fixing bolt fixed mount be after pre-embedded bolt center, absolute altitude are adjusted is made annular flange with the steel plate of 6mm, and flange is placed in firm welding on pre-embedded bolt, then to bolt fixedly set up bridging, bearing diagonal carries out integral reinforcing.
Compared with prior art, the advantage of major diameter pre-embedded bolt localization method of the present invention is: simple to operate, easy construction, positioning accuracy is high, has greatly reduced bolt and has built the displacement that occurs when vibrating because of concrete, installs for structure and has created advantage.
Description of drawings
Fig. 1: major diameter pre-embedded bolt localization method front view.
Fig. 2: major diameter pre-embedded bolt localization method top view.
In figure: 1, built-in fitting 2, column 3, bottom horizontal brace 4, upper water support 5, pre-embedded bolt 6, flange 7, bridging 8, bearing diagonal.
The specific embodiment
For further describing the present invention, the invention will be further described below in conjunction with embodiment and accompanying drawing.
As shown in the figure, described major diameter pre-embedded bolt localization method is characterized in that: built-in fitting first is set, then makes the bolt fixed mount, last manufacturing flange also adds the fixing bolt fixed mount.
The described built-in fitting that arranges is when the hot-blast stove foundation concrete is built, and according to bolt fixed mount column 2 and bearing diagonal 8 positions, establishes built-in fitting 1 at sole plate concrete face, when being used for fixed mount and installing with column 2, bearing diagonal 8 and built-in fitting 1 firm welding.
Described making bolt fixed mount be fixed mount by column 2, bottom horizontal brace 3, upper water support 4, bridging 7, bearing diagonal 8 form, column 2 is selected the 12# channel-section steel, all the other all use 75 * 5 angle steel making, make it form the annular stereo fixed mount of independent system, with transit, pre-embedded bolt 5 center lines are thrown and surveyed to fixed mount, according to adjustment pre-embedded bolt 5 centers, the center on fixed mount.Fixed mount bottom horizontal brace 3 absolute altitudes are surveyed according to the pre-embedded bolt 5 accurate instrument of design high water usage and are established, and pre-embedded bolt 5 is placed on bottom horizontal brace 3, and pre-embedded bolt 5 verticality support 4 by the fixed mount upper water and regulate.
Described manufacturing flange and to add the fixing bolt fixed mount be after pre-embedded bolt 5 centers, absolute altitude are adjusted, steel plate with 6mm is made annular flange 6, flange 6 is placed in firm welding on pre-embedded bolt 5, then to bolt fixedly set up bridging 7, bearing diagonal 8 carries out integral reinforcing.

Claims (4)

1. major diameter pre-embedded bolt localization method is characterized in that: built-in fitting first is set, then makes the bolt fixed mount, last manufacturing flange also adds the fixing bolt fixed mount.
2. the described a kind of major diameter pre-embedded bolt localization method of claim 1, it is characterized in that: the described built-in fitting that arranges is when the hot-blast stove foundation concrete is built, according to bolt fixed mount column (2) and bearing diagonal (8) position, establish built-in fitting (1) at sole plate concrete face, when being used for fixed mount and installing with column (2), bearing diagonal (8) and built-in fitting (1) firm welding.
3. the described a kind of major diameter pre-embedded bolt localization method of claim 1, it is characterized in that: described making bolt fixed mount be fixed mount by column (2), bottom horizontal brace (3), upper water support (4), bridging (7), bearing diagonal (8) forms, column (2) is selected the 12# channel-section steel, all the other all use 75 * 5 angle steel making, make it form the annular stereo fixed mount of independent system, with transit, pre-embedded bolt (5) center line is thrown and surveyed to fixed mount, according to adjustment pre-embedded bolt (5) center, the center on fixed mount; Fixed mount bottom horizontal brace (3) absolute altitude is surveyed according to the accurate instrument of pre-embedded bolt (5) design high water usage and is established, pre-embedded bolt (5) is placed on bottom horizontal brace (3), and pre-embedded bolt (5) verticality supports (4) by the fixed mount upper water and regulates.
4. the described a kind of major diameter pre-embedded bolt localization method of claim 1, it is characterized in that: described manufacturing flange and to add the fixing bolt fixed mount be after pre-embedded bolt (5) center, absolute altitude are adjusted, steel plate with 6mm is made annular flange (6), flange (6) is placed in the upper firm welding of pre-embedded bolt (5), then to bolt fixedly set up bridging (7), bearing diagonal (8) carries out integral reinforcing.
CN2013100827503A 2013-03-15 2013-03-15 Full diameter embedded bolt positioning method Pending CN103174165A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100827503A CN103174165A (en) 2013-03-15 2013-03-15 Full diameter embedded bolt positioning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100827503A CN103174165A (en) 2013-03-15 2013-03-15 Full diameter embedded bolt positioning method

Publications (1)

Publication Number Publication Date
CN103174165A true CN103174165A (en) 2013-06-26

Family

ID=48634320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100827503A Pending CN103174165A (en) 2013-03-15 2013-03-15 Full diameter embedded bolt positioning method

Country Status (1)

Country Link
CN (1) CN103174165A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107267165A (en) * 2017-07-28 2017-10-20 马鞍山钢铁建设集团有限公司 A kind of dry coke quenching body of heater is circular layout pre-embedded bolt fixed structure and installation method
CN108589766A (en) * 2018-05-09 2018-09-28 五冶集团上海有限公司 Bolt location structure and di rect-buried bolt accuracy control method
CN110130390A (en) * 2019-05-31 2019-08-16 中国五冶集团有限公司 Raft foundation bolt embedment structure and installation method
CN111254968A (en) * 2020-01-19 2020-06-09 中国十七冶集团有限公司 Installation device and installation method for large-diameter embedded bolt of large-scale equipment foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0827813A (en) * 1994-07-13 1996-01-30 Mitsubishi Heavy Ind Ltd Installation foundation holder for machine of every kind
CN201277861Y (en) * 2008-10-30 2009-07-22 中冶京唐建设有限公司 Equipment foundation built-in anchor bolt installation measurement control platform
JP2009299419A (en) * 2008-06-17 2009-12-24 Hitachi Ltd Construction method for preventing displacement of form, and installment tool
CN101666100A (en) * 2009-09-15 2010-03-10 中冶实久建设有限公司 Method for accurately installing large foundation bolt of industrial equipment foundation
CN202170636U (en) * 2011-07-14 2012-03-21 中建八局第四建设有限公司 Mould for pre-embedded foundation bolt of steel structural foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0827813A (en) * 1994-07-13 1996-01-30 Mitsubishi Heavy Ind Ltd Installation foundation holder for machine of every kind
JP2009299419A (en) * 2008-06-17 2009-12-24 Hitachi Ltd Construction method for preventing displacement of form, and installment tool
CN201277861Y (en) * 2008-10-30 2009-07-22 中冶京唐建设有限公司 Equipment foundation built-in anchor bolt installation measurement control platform
CN101666100A (en) * 2009-09-15 2010-03-10 中冶实久建设有限公司 Method for accurately installing large foundation bolt of industrial equipment foundation
CN202170636U (en) * 2011-07-14 2012-03-21 中建八局第四建设有限公司 Mould for pre-embedded foundation bolt of steel structural foundation

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107267165A (en) * 2017-07-28 2017-10-20 马鞍山钢铁建设集团有限公司 A kind of dry coke quenching body of heater is circular layout pre-embedded bolt fixed structure and installation method
CN107267165B (en) * 2017-07-28 2019-10-11 马鞍山钢铁建设集团有限公司 A kind of dry coke quenching furnace body is circular layout pre-embedded bolt fixed structure and installation method
CN108589766A (en) * 2018-05-09 2018-09-28 五冶集团上海有限公司 Bolt location structure and di rect-buried bolt accuracy control method
CN110130390A (en) * 2019-05-31 2019-08-16 中国五冶集团有限公司 Raft foundation bolt embedment structure and installation method
CN111254968A (en) * 2020-01-19 2020-06-09 中国十七冶集团有限公司 Installation device and installation method for large-diameter embedded bolt of large-scale equipment foundation

Similar Documents

Publication Publication Date Title
CN104234385B (en) Construction method of installation after a kind of terrace heavy steel plate built-in fitting
CN204040056U (en) A kind of location and installation support of pre-embedded anchoring bolts
CN202194244U (en) Positioning support for embedding of ultra-high steel-work pedestals
CN105350654B (en) A kind of construction method for adjusting pre-embedded steel slab and reaching design and construction precision
CN103174165A (en) Full diameter embedded bolt positioning method
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN201850669U (en) Spatial accurate positioning support of vibration isolating device
CN103088840B (en) Axis type foundation bolt high-precision fast locator and locating method thereof
CN103485539B (en) The construction control method of large-scale direct burial steel anchor fluke built-in fitting
CN201546322U (en) Integral locating steel frame used in light steel buildings
CN102518300B (en) Embedded conical bearing joint type steel structural support and construction method thereof
CN203809870U (en) Supporting and fixing tool for level pump pipe on concrete floor
CN101538858B (en) Method and device for jointing reinforcement and vibration readjustment construction of pre-embedded bolt
CN203429564U (en) Accurate installation and construction structure for bridge support
CN106836829B (en) A kind of mounting structure and its installation method of ring crane corbel
CN201891172U (en) Fixing bracket with fine-adjusting function for embedding anchor bolts
CN103452098A (en) Opposite supporting embedded part construction method for underground continuous wall
CN203881339U (en) Detachable monitoring pier
CN103061454A (en) Locating method of installing concrete filled steel tubular column in underground deep hole
CN202884252U (en) High-low horizontal adjusting seat
CN203879041U (en) Embedded plate positioning support frame
CN205476528U (en) Precast pile device of taking one's place fast
CN205444228U (en) Framework column base rag bolt of transformer substation
CN103161311B (en) Large diameter reinforced concrete pipe road crosses the construction method of abutment
CN202381269U (en) Adjusting device of mounting levelness of basic ring of wind driven generator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130626