CN201705369U - Waterproof structure for tunnels in frozen soil on plateau - Google Patents

Waterproof structure for tunnels in frozen soil on plateau Download PDF

Info

Publication number
CN201705369U
CN201705369U CN2010202421125U CN201020242112U CN201705369U CN 201705369 U CN201705369 U CN 201705369U CN 2010202421125 U CN2010202421125 U CN 2010202421125U CN 201020242112 U CN201020242112 U CN 201020242112U CN 201705369 U CN201705369 U CN 201705369U
Authority
CN
China
Prior art keywords
waterproof
joint
construction
laid
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202421125U
Other languages
Chinese (zh)
Inventor
任少强
陈文珍
李培安
李景超
王永顺
吴应明
张永鸿
郭朋超
仲维玲
张爱玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 20th Bureau Group Corp
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 20th Bureau Group Corp filed Critical China Railway 20th Bureau Group Corp
Priority to CN2010202421125U priority Critical patent/CN201705369U/en
Application granted granted Critical
Publication of CN201705369U publication Critical patent/CN201705369U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a waterproof structure for tunnels in frozen soil on plateau, which comprises a full-ring waterproof structure, a circular joint waterproof structure, an expansion joint waterproof structure and a settlement joint waterproof structure which are arranged between a primary support system and a secondary lining of a constructed tunnel. The full-ring waterproof structure comprises a composite waterproof plate and a waterproof protective layer, the circular joint waterproof structure comprises a cement based interfacial agent protective layer uniformly coated in circular construction joints and a plurality of rubber waterstop strips I, the expansion joint waterproof structure comprises rubber waterstop strips II arranged in the middle of expansion joints, rubber waterstop strips III arranged at upper ends of the expansion joints and waterproof packing compactly filled in the expansion joints, and the structure of the settlement joint waterproof structure is identical to that of the expansion joint waterproof structure. The waterproof structure is simple in structure, reasonable in design, comprehensive in conception, convenient in construction and fine in waterproof effect, strengthens waterproof treatment to weak areas on the basis of integral waterproof treatment of the full-ring waterproof structure, and can thoroughly resolve the waterproof problem of tunnels in frozen soil on plateau.

Description

Plateau permafrost tunnel water proofing structure
Technical field
The utility model belongs to the tunnel construction technology field, especially relates to a kind of plateau permafrost tunnel water proofing structure.
Background technology
When the construction tunnel of Qinghai-Tibet innerland, because the rail level height above sea level in tunnel is very high, usually about 4,000 7 hundred meters, the barrel in its tunnel all is arranged in and freezes rock, the geological formations complexity, integrate badly geology such as full freezing soil, ice-rich permafrost, crack ice, mud sandstone, thereby when high height above sea level like this, high and cold, anoxic and Permafrost Area are built the tunnel, all do not have experience to use for reference both at home and abroad.There is very big difference in the construction technology in tunnel and Plain non-frozen soil area, and its construction is very difficult.How protecting frozen soil in the constructing tunnel process is the key problem in technology of construction, therefore, must study corresponding construction method and disturb problem with the heat that reduces to construct, and reduces the influence of construction blasting to frozen soil.Simultaneously, the validity of frozen soil tunnel waterproofing system is the assurance of whole construction of tunnel quality, it also is the key factor of control tunnel defect, therefore must research one cover corresponding construction method and corresponding tunnel internal construction, guarantee the construction quality and the endurance quality of frozen soil tunnel concrete lining and sprayed mortar under waterproof thermal-insulated system, the high and cold condition.
The utility model content
Technical problem to be solved in the utility model is at above-mentioned deficiency of the prior art, a kind of plateau permafrost tunnel water proofing structure is provided, it is simple in structure, reasonable in design, consider comprehensively and construction sequence is simple, easy construction, good water-proof effect, on the basis of loopful formula waterproof construction integral waterproofing, again waterproofing work is strengthened in weak area, make and isolate fully with the stratum in the hole, tunnel, can thoroughly solve the waterproof problem in plateau permafrost tunnel.
For solving the problems of the technologies described above; the technical solution adopted in the utility model is: a kind of plateau permafrost tunnel water proofing structure; it is characterized in that: comprise the preliminary bracing system that is laid in construction tunnel and the loopful formula waterproof construction between the secondary lining; be laid in the interior hoop seam waterproof construction of hoop constuction joint of construction tunnel; be laid in the dilatation joint waterproof structure in the shrinkage joint of construction tunnel and be laid in settlement joint waterproof construction in the settlement joint of construction tunnel; described loopful formula waterproof construction comprises compound water-proof that is laid on the preliminary bracing system and the fish tail and waterproof layer that is laid on the compound water-proof; described hoop seam waterproof construction comprises the cement based interfacial agents overcoat of even brushing in described hoop constuction joint and a plurality of rubber sealing rods one that are laid in the described hoop constuction joint; described dilatation joint waterproof structure comprises the rubber fastening band two that is laid in the middle part, shrinkage joint; be laid in the upper end, shrinkage joint and fill out waterproof filler in the shrinkage joint near the rubber sealing rod three of preliminary bracing system outer edge and closely knit plug, described settlement joint waterproof construction is identical with the structure of described dilatation joint waterproof structure.
A plurality of described rubber sealing rods one begin to lay to secondary lining one side from the outward flange of preliminary bracing system.
Described waterproof filler is residual oil hemp cut or immersion oil plank.
Described fish tail and waterproof layer is a splash guard.
Also comprise layer of non-woven fabric, described nonwoven is laid on the arch and the fish tail and waterproof layer at the bottom of the tunnel of construction tunnel.
Described nonwoven is that specification is greater than 300g/m 2Geotextiles.
Described loopful formula waterproof construction also comprises the insulating that is laid between compound water-proof and the fish tail and waterproof layer.
The utility model compared with prior art has the following advantages:
1, simple in structure, reasonable in design, consider comprehensively and construction sequence simple, easy construction, input cost is lower.
2, good water-proof effect, adopt loopful formula waterproof construction to carry out integral waterproofing to whole tunnel earlier, and on the basis of integral waterproofing, more special waterproofing work is carried out in weak area (comprising horizontal joint, hoop constuction joint, shrinkage joint, settlement joint etc.), thereby under the condition of dual tight waterproof, can thoroughly solve the waterproof problem in plateau permafrost tunnel, for construction brings very big facility.
3, practical value height, because the utility model has thoroughly solved the waterproof problem in plateau permafrost tunnel, and it is convenient to realize, thereby can effectively solve the safe construction and the safe operation problem in plateau permafrost tunnel, can prolong the application life in plateau permafrost tunnel greatly, reduce the maintenance cost in tunnel significantly.
4, popularizing application prospect is extensive, can promote to be suitable for to the relevant constructing tunnel that carries out waterproofing work such as Karst Tunnel.
In sum, the utility model is simple in structure, reasonable in design, consider comprehensively and construction sequence is simple, easy construction, good water-proof effect, on the basis of loopful formula waterproof construction integral waterproofing, again waterproofing work is further strengthened in weak area, make and isolate fully with the stratum in the hole, tunnel, thereby can thoroughly solve the waterproof problem in plateau permafrost tunnel.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Description of drawings
Fig. 1 is a user mode reference diagram of the present utility model.
Fig. 2 is the structural representation of the utility model hoop seam waterproof construction.
Fig. 3 is the structural representation of the utility model dilatation joint waterproof structure.
Description of reference numerals:
The 1-construction tunnel; 2-preliminary bracing system; 3-loopful formula waterproof construction;
The 3-1-compound water-proof; The 3-2-insulating; The 3-3-fish tail and waterproof layer;
The 4-secondary lining; 5-hoop seam waterproof construction; The 6-dilatation joint waterproof structure;
7-rubber sealing rod one; 8-rubber fastening band two; The 10-shrinkage joint;
11-rubber sealing rod three.
The specific embodiment
As Fig. 1, Fig. 2 and shown in Figure 3, the hoop seam waterproof construction 5 in the hoop constuction joint that the utility model comprises the preliminary bracing system 2 and the loopful formula waterproof construction 3 between the secondary lining 4 that are laid in construction tunnel 1, be laid in construction tunnel 1, be laid in the dilatation joint waterproof structure 6 in the shrinkage joint 10 of construction tunnel 1 and be laid in settlement joint waterproof construction in the settlement joint of construction tunnel 1.Described loopful formula waterproof construction 3 comprises compound water-proof 3-1 that is laid on the preliminary bracing system 2 and the fish tail and waterproof layer 3-3 that is laid on the compound water-proof 3-1, and described hoop seam waterproof construction 5 comprises the cement based interfacial agents overcoat of even brushing in described hoop constuction joint and a plurality of rubber sealing rods 1 that are laid in the described hoop constuction joint.Described dilatation joint waterproof structure 6 comprises the rubber fastening band 28 that is laid in 10 middle parts, shrinkage joint, be laid in 10 upper ends, shrinkage joint and fill out waterproof filler in shrinkage joint 10 near the rubber sealing rod 3 11 of preliminary bracing system 2 outer edge and closely knit plug, and described settlement joint waterproof construction is identical with the structure of described dilatation joint waterproof structure 6.Simultaneously, the method for waterproofing to the horizontal joint of construction tunnel 1 is identical with hoop seam waterproof construction 5 with formed horizontal joint waterproofing structure.
In the present embodiment, a plurality of described rubber sealing rods 1 begin to lay to secondary lining 4 one sides from the outward flange of preliminary bracing system 2.Described waterproof filler is residual oil hemp cut or immersion oil plank.Described fish tail and waterproof layer 3-3 is a splash guard.Simultaneously, the utility model also comprises layer of non-woven fabric, and described nonwoven is laid on the arch of construction tunnel 1 and the fish tail and waterproof layer 3-3 at the bottom of the tunnel, and it is greater than 300g/m that described nonwoven is specially specification 2Geotextiles.Described loopful formula waterproof construction 3 also comprises the insulating 3-2 that is laid between compound water-proof 3-1 and the fish tail and waterproof layer 3-3.
During practice of construction,, in horizontal joint or hoop constuction joint, arrange a plurality of rubber sealing rods 1 afterwards to the thick WJ interface cementing agent (being described cement based interfacial agents overcoat) of brush 2mm before horizontal joint and the hoop constuction joint employing newly placed concrete.And when the shrinkage joint 10 of secondary lining 4 inside and settlement joint carried out waterproofing work, be the rubber sealing rod 3 11 of 10cm laying length along the edge of secondary lining 4 earlier near preliminary bracing system 2 one sides, rubber fastening band 28 is laid at 10 middle parts at the shrinkage joint again, last described its complementary space in shrinkage joint 10 adopts residual oil hemp cut or the filling of immersion oil plank, the water-swellable sealing rod of selecting for use has slow expansion character, and the expansion rate of its 7d is not more than 50% of final expansion rate.
The above; it only is preferred embodiment of the present utility model; be not that the utility model is imposed any restrictions; everyly any simple modification that above embodiment did, change and equivalent structure are changed, all still belong in the protection domain of technical solutions of the utility model according to the utility model technical spirit.

Claims (7)

1. plateau permafrost tunnel water proofing structure; it is characterized in that: comprise the preliminary bracing system (2) that is laid in construction tunnel (1) and the loopful formula waterproof construction (3) between the secondary lining (4); be laid in the interior hoop seam waterproof construction (5) of hoop constuction joint of construction tunnel (1); be laid in the dilatation joint waterproof structure (6) in the shrinkage joint (10) of construction tunnel (1) and be laid in the interior settlement joint waterproof construction of settlement joint of construction tunnel (1); described loopful formula waterproof construction (3) comprises the compound water-proof (3-1) that is laid on the preliminary bracing system (2) and is laid in fish tail and waterproof layer (3-3) on the compound water-proof (3-1); described hoop seam waterproof construction (5) comprises the cement based interfacial agents overcoat of even brushing in described hoop constuction joint and a plurality of rubber sealing rods one (7) that are laid in the described hoop constuction joint; described dilatation joint waterproof structure (6) comprises the rubber fastening band two (8) that is laid in middle part, shrinkage joint (10); be laid in (10) upper end, shrinkage joint and fill out waterproof filler in shrinkage joint (10) near the rubber sealing rod three (11) of preliminary bracing system (2) outer edge and closely knit plug, described settlement joint waterproof construction is identical with the structure of described dilatation joint waterproof structure (6).
2. according to the described plateau permafrost tunnel water proofing of claim 1 structure, it is characterized in that: a plurality of described rubber sealing rods one (7) begin to lay to secondary lining (4) one sides from the outward flange of preliminary bracing system (2).
3. according to claim 1 or 2 described plateau permafrost tunnel water proofing structures, it is characterized in that: described waterproof filler is residual oil hemp cut or immersion oil plank.
4. according to claim 1 or 2 described plateau permafrost tunnel water proofing structures, it is characterized in that: described fish tail and waterproof layer (3-3) is a splash guard.
5. according to the described plateau permafrost tunnel water proofing of claim 4 structure, it is characterized in that: also comprise layer of non-woven fabric, described nonwoven is laid on the arch and the fish tail and waterproof layer at the bottom of the tunnel (3-3) of construction tunnel (1).
6. according to the described plateau permafrost tunnel water proofing of claim 5 structure, it is characterized in that: described nonwoven is that specification is greater than 300g/m 2Geotextiles.
7. according to claim 1 or 2 described plateau permafrost tunnel water proofing structures, it is characterized in that: described loopful formula waterproof construction (3) also comprises the insulating (3-2) that is laid between compound water-proof (3-1) and the fish tail and waterproof layer (3-3).
CN2010202421125U 2010-06-28 2010-06-28 Waterproof structure for tunnels in frozen soil on plateau Expired - Fee Related CN201705369U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202421125U CN201705369U (en) 2010-06-28 2010-06-28 Waterproof structure for tunnels in frozen soil on plateau

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202421125U CN201705369U (en) 2010-06-28 2010-06-28 Waterproof structure for tunnels in frozen soil on plateau

Publications (1)

Publication Number Publication Date
CN201705369U true CN201705369U (en) 2011-01-12

Family

ID=43442523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202421125U Expired - Fee Related CN201705369U (en) 2010-06-28 2010-06-28 Waterproof structure for tunnels in frozen soil on plateau

Country Status (1)

Country Link
CN (1) CN201705369U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032083A (en) * 2012-12-21 2013-04-10 中南大学 Reconstruction method for water-proof shell
CN104018858A (en) * 2014-06-11 2014-09-03 云南省交通规划设计研究院 Novel water stopping structure for tunneling seam in permafrost region
CN104695980A (en) * 2015-03-11 2015-06-10 中水北方勘测设计研究有限责任公司 Hydropower diversion tunnel lining structure applied to rock burst regions with high burial depth, high ground temperature and high ground stress
CN107587881A (en) * 2017-10-30 2018-01-16 中铁五局集团第五工程有限责任公司 A kind of composite lining structure and construction technology for permafrost tunnel
CN107605513A (en) * 2017-09-13 2018-01-19 中交公局桥隧工程有限公司 A kind of application process of tunnel longitudinal direction construction joint cement base crystalline waterproof material
CN108716404A (en) * 2018-05-17 2018-10-30 西安建筑科技大学 A kind of Frozen Area freezing damage in tunnel prevention device and installation method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032083A (en) * 2012-12-21 2013-04-10 中南大学 Reconstruction method for water-proof shell
CN104018858A (en) * 2014-06-11 2014-09-03 云南省交通规划设计研究院 Novel water stopping structure for tunneling seam in permafrost region
CN104695980A (en) * 2015-03-11 2015-06-10 中水北方勘测设计研究有限责任公司 Hydropower diversion tunnel lining structure applied to rock burst regions with high burial depth, high ground temperature and high ground stress
CN104695980B (en) * 2015-03-11 2017-03-15 中水北方勘测设计研究有限责任公司 For the regional Lining of Power Tunnel structure of high buried depth, High-geotemperature, high stress rock burst
CN107605513A (en) * 2017-09-13 2018-01-19 中交公局桥隧工程有限公司 A kind of application process of tunnel longitudinal direction construction joint cement base crystalline waterproof material
CN107587881A (en) * 2017-10-30 2018-01-16 中铁五局集团第五工程有限责任公司 A kind of composite lining structure and construction technology for permafrost tunnel
CN108716404A (en) * 2018-05-17 2018-10-30 西安建筑科技大学 A kind of Frozen Area freezing damage in tunnel prevention device and installation method

Similar Documents

Publication Publication Date Title
CN201705369U (en) Waterproof structure for tunnels in frozen soil on plateau
CN201810321U (en) Composite heat insulation lining structure of plateau frozen earth tunnel
CN106194218B (en) shield end soil body reinforcing system in high-water-head deep-thick sand layer area
CN103726425B (en) Foam lightweight soil construction method
CN101985882B (en) Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN109026064A (en) A kind of construction method that large span multiple-arch tunnel is hazy
CN202745937U (en) Hidden trench for concentrated seepage water guidance and drainage of existing tunnel in cold area
CN103046513A (en) Method for coating and sealing fracture of bed rock in uncovered heavy consolidation grouting
CN101749026A (en) Grid reinforcing method of shield receiving or starting end head and shield receiving method
CN2921279Y (en) Tunnel support structure
CN109184253A (en) A kind of method for repairing and mending of exterior wall leakage
CN210163948U (en) Construction system for pouring post-cast strip of basement roof
CN209179060U (en) The deformation joint structure of underground pipe gallery
CN205205598U (en) Foam light layer for road bed is widened to road
CN204492847U (en) A kind of supporting and protection structure of underground space reverse construction
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN109372558A (en) A kind of construction method of subway large section tunnel tunneling support replacement and main structure
CN106869169A (en) A kind of three-dimensional interval construction method of underground pipe gallery warehouse
CN203412598U (en) Cable-tunnel composite lining waterproof structure
CN103669746B (en) The construction method of inverted roof heat-insulation system
CN204252414U (en) Roof covering water-proof structure
CN203768925U (en) Seal device for dewatering well in foundation pit
US11821316B1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110112

Termination date: 20160628

CF01 Termination of patent right due to non-payment of annual fee