CN201695398U - Stepped top-down pit excavation trestle - Google Patents

Stepped top-down pit excavation trestle Download PDF

Info

Publication number
CN201695398U
CN201695398U CN201020167744XU CN201020167744U CN201695398U CN 201695398 U CN201695398 U CN 201695398U CN 201020167744X U CN201020167744X U CN 201020167744XU CN 201020167744 U CN201020167744 U CN 201020167744U CN 201695398 U CN201695398 U CN 201695398U
Authority
CN
China
Prior art keywords
trestle
contrary
shoveling
excavation
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201020167744XU
Other languages
Chinese (zh)
Inventor
周臻全
姜峰
于成杰
朱毅敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai First Construction Co Ltd
Original Assignee
Shanghai First Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai First Construction Co Ltd filed Critical Shanghai First Construction Co Ltd
Priority to CN201020167744XU priority Critical patent/CN201695398U/en
Application granted granted Critical
Publication of CN201695398U publication Critical patent/CN201695398U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a stepped top-down pit excavation trestle, which is arranged in a top-down foundation pit, surrounding top-down structural beam slabs are enlarged layer by layer from the top down, and are formed into a stepped structure, and each excavation trestle is connected with the end of the upper layer of top-down structural beam slab and the end of the opposite lower layer of top-down structural beam slab. By arranging the pit excavation trestle, a construction passage is built from the ground into the pit, so that earthmoving machines can directly get into the pit to excavate and transport earth, consequently, the efficiency of earth-excavating construction is increased, and the earth excavation speed can be more than two times as high as the earth excavation speed of conventional top-down construction.

Description

The contrary hole shoveling trestle down of doing of stepping type
Technical field
The utility model relates to building underground engineering construction technical field, particularly a kind of shoveling trestle, the contrary hole shoveling trestle down of doing of specifically a kind of stepping type.
Background technology
Little digging machine level was lightered to soil outlet or foundation ditch limit under the contrary do shoveling of current base pit engineering mostly was and cheats, excavate by ground long-armed digging machine or grab bucket again, it is too much that the problem of this shoveling mode is cubic metre of earth to dig out to the process on ground the transportation by lighter number of times down via the hole, the construction machinery loss is bigger, so that the inefficiency of cutting the earth, performance is particularly evident in ultra-large type base pit engineering adverse construction method.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of can reduce cubic metre of earth a transportation by lighter number of times and a construction machinery loss, improves the contrary hole shoveling trestle down of doing of stepping type of excavation and construction work efficiency, to overcome the above-mentioned defective that prior art exists.
The technical scheme of the utility model technical solution problem is as follows:
The contrary hole shoveling trestle down of doing of a kind of stepping type, it is arranged on contrary the work in the foundation ditch, the contrary structure beam slab of doing of periphery successively strengthens from top to bottom, be the stepping type structure, it is characterized in that described shoveling trestle is connected in contrary contrary the work between the structure beam slab end of lower floor of making the relative side with it in structure beam slab end in upper strata.
By above disclosed technical scheme as can be known, the utility model stepping type is contrary, and to make hole shoveling trestle down be to connect the levels contrary a kind of trestle form of making structure contrary work of periphery under the form that structure successively increases from top to bottom.By shoveling trestle in hole is set down, set up by ground and led to the interior construction passage in hole, earth moving plant can directly be cheated down carry out excavation and construction and hauling operation.Adopt the contrary work of the utility model stepping type to cheat the shoveling trestle down and improve the soil excavation efficiency of construction, unearthed speed can reach conventional adverse construction method more than 2 times.
Description of drawings
Fig. 1 is the contrary hole shoveling trestle structural representation down of doing of the utility model stepping type.
The specific embodiment
Further specify the utility model below in conjunction with accompanying drawing.
As shown in Figure 1, the contrary hole shoveling trestle down of doing of the utility model stepping type, it is arranged on contrary the work in the foundation ditch, the contrary structure beam slab 2 of doing of periphery successively strengthens from top to bottom, be the stepping type structure, described shoveling trestle 1 is connected in contrary contrary the work between the structure beam slab 2 ' end of lower floor of making the relative side with it in structure beam slab 2 ends in upper strata.
Described shoveling trestle 1 is the steel concrete trestle.
Because shoveling trestle in hole mainly is arranged on contrary the work between the structure of upper and lower layer periphery down, satisfies the current requirement of upper and lower layer earth moving plant, the trestle gradient is unsuitable excessive when being provided with.Relatively Shi Yi trestle gradient scope is for being not more than 1: 8.

Claims (3)

1. cheat the shoveling trestle under contrary work of stepping type, it is arranged on contrary the work in the foundation ditch, the contrary structure beam slab (2) of doing of periphery successively strengthens from top to bottom, be the stepping type structure, it is characterized in that described shoveling trestle (1) is connected in contrary contrary the work between structure beam slab (the 2 ') end of lower floor of making the relative side with it in structure beam slab (2) end in upper strata.
2. the contrary hole shoveling trestle down of doing of stepping type according to claim 1 is characterized in that described shoveling trestle (1) is the steel concrete trestle.
3. the contrary hole shoveling trestle down of doing of stepping type according to claim 1 is characterized in that, described shoveling trestle (1) in easy flights in 1: 8.
CN201020167744XU 2010-04-22 2010-04-22 Stepped top-down pit excavation trestle Expired - Fee Related CN201695398U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201020167744XU CN201695398U (en) 2010-04-22 2010-04-22 Stepped top-down pit excavation trestle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201020167744XU CN201695398U (en) 2010-04-22 2010-04-22 Stepped top-down pit excavation trestle

Publications (1)

Publication Number Publication Date
CN201695398U true CN201695398U (en) 2011-01-05

Family

ID=43396638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201020167744XU Expired - Fee Related CN201695398U (en) 2010-04-22 2010-04-22 Stepped top-down pit excavation trestle

Country Status (1)

Country Link
CN (1) CN201695398U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005571A (en) * 2014-06-17 2014-08-27 浙江华展工程研究设计院有限公司 Slanting construction trestle combined with internal supporting system
CN104131565A (en) * 2014-06-18 2014-11-05 中国建筑第四工程局有限公司 Construction method of using down-top method for excavating earthworks in top-down construction
CN104452575A (en) * 2014-10-22 2015-03-25 中国建筑第四工程局有限公司 Inclined trestle structure for reverse construction method excavation construction and earth excavation method
CN110004936A (en) * 2019-05-20 2019-07-12 中建四局土木工程有限公司 A kind of unearthed ramp and construction method based on deep foundation pit supporting structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005571A (en) * 2014-06-17 2014-08-27 浙江华展工程研究设计院有限公司 Slanting construction trestle combined with internal supporting system
CN104131565A (en) * 2014-06-18 2014-11-05 中国建筑第四工程局有限公司 Construction method of using down-top method for excavating earthworks in top-down construction
CN104131565B (en) * 2014-06-18 2016-06-22 中国建筑第四工程局有限公司 A kind of against making the construction method that the earthwork is just made to excavate
CN104452575A (en) * 2014-10-22 2015-03-25 中国建筑第四工程局有限公司 Inclined trestle structure for reverse construction method excavation construction and earth excavation method
CN110004936A (en) * 2019-05-20 2019-07-12 中建四局土木工程有限公司 A kind of unearthed ramp and construction method based on deep foundation pit supporting structure

Similar Documents

Publication Publication Date Title
CN102677695B (en) Mutually-embedded ecological building block retaining wall and construction method thereof
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN103711135B (en) Anti-slide pile of jointed arch structure
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN102535474A (en) Construction method for deep-foundation pit excavation
CN201695398U (en) Stepped top-down pit excavation trestle
CN102116028B (en) Method and structure for excavating soil in core tube region based on raft pile supporting
CN103290847A (en) Inner oblique beam supporting structure for oversized-area deep foundation pit and construction method
CN109930608A (en) A kind of pit earthwork excavation method of peat matter weak soil
CN110984133A (en) Construction method for foundation of deep-water shallow-covering-layer trestle
CN101845955A (en) Underground tunnel formation infrastructure establishment method
CN104695445A (en) Basement earth excavation method adopting reverse construction method
CN101705685B (en) Stepped top-down construction method for peripheral beam slabs of underground structure
CN103061767B (en) Lower to horizontal slice Dry-placed fill mining
CN201695657U (en) Excavation platform in step type top-down pit
CN104594371A (en) Reinforcing structure of existing foundation bottom plate and construction method thereof
CN206368375U (en) A kind of electric power pylon basis
CN201495571U (en) Special soil lifting device for topdown construction method underground excavation engineering
CN204608826U (en) Tunneling boring stirs cutting and makes wall telephone
CN112942377A (en) Novel support shear-resistant structure and construction method thereof
CN206338070U (en) A kind of super-large diameter deep shaft simple shield device
CN201695397U (en) Reverse construction stepped excavation trestle
CN111677512A (en) Shaft type diversion tunnel excavation method
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110105

Termination date: 20110422