CN201695397U - Reverse construction stepped excavation trestle - Google Patents
Reverse construction stepped excavation trestle Download PDFInfo
- Publication number
- CN201695397U CN201695397U CN201020167737XU CN201020167737U CN201695397U CN 201695397 U CN201695397 U CN 201695397U CN 201020167737X U CN201020167737X U CN 201020167737XU CN 201020167737 U CN201020167737 U CN 201020167737U CN 201695397 U CN201695397 U CN 201695397U
- Authority
- CN
- China
- Prior art keywords
- trestle
- excavation
- layer
- shoveling
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a reverse construction stepped excavation trestle, which comprises a first layer of trestle and a multi-layered lower trestle below the first layer of trestle, which are arranged along the depth direction of a reverse construction area from up and down, wherein the first layer of trestle and the multi-layered lower trestle are extended towards the center of a reverse construction excavation area from up and down layer by layer, so a stepped structure is formed, and the lower layer of trestle is arranged on a beam and slab structure of a basement. The utility model utilizes the beam and slab structure of the basement, so the excavation trestle in the reverse construction presents in a stepped mode, the excavation construction has no limitation on layer height, only small-sized equipment is adopted to complete the excavation construction, and the excavation efficiency is high.
Description
Technical field
The utility model relates to building underground engineering construction technical field, particularly a kind of stepping type shoveling trestle that is used for adverse construction method.
Background technology
Conventional adverse construction method is owing to the restriction of underground structure floor height, and the shoveling trestle generally can only be chosen in the structure first floor, and the earthwork that cutting depth is bigger needs large-scale shoveling equipment, and excavation efficient is lower.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of shoveling efficient height, and goes for the adverse construction method stepping type shoveling trestle that whole underground structure is cut the earth to be needed, to overcome the above-mentioned defective that prior art exists.
The technical scheme of the utility model technical solution problem is as follows:
A kind of adverse construction method stepping type shoveling trestle, it is characterized in that, it comprises first floor trestle and the multilayer lower floor trestle that is arranged on first floor trestle below from top to down along the contrary regional depth of doing, successively stretch from top to bottom between the trestle of first floor trestle and multilayer lower floor to the contrary shoveling regional center of doing, form the stepping type structure, lower floor's trestle is arranged on the beam and slab structure of basement.
By above disclosed technical scheme as can be known, the utility model is by utilizing the beam and slab structure of basement, make the shoveling trestle in the adverse construction method be stepping type, the digging construction does not have the restriction of floor height, adopts small-sized shoveling equipment can finish digging construction, shoveling efficient height, adopt the utility model stepping type shoveling trestle, the shoveling efficient of conventional adverse construction method is improved more than 2 times, solved that trestle can only be positioned at the structure first floor in the conventional adverse construction method, the inefficient problem of cutting the earth.
Description of drawings
Fig. 1 is the utility model shoveling trestle structural representation.
The specific embodiment
Further specify the utility model below in conjunction with accompanying drawing.
As shown in Figure 1, the utility model adverse construction method stepping type shoveling trestle, it comprises first floor trestle 1 and the multilayer lower floor trestle 2 that is arranged on first floor trestle below from top to down along the contrary regional depth of doing, successively stretch from top to bottom between the trestle 2 of first floor trestle 1 and multilayer lower floor to the contrary shoveling regional center of doing, form the stepping type structure, lower floor's trestle 2 is arranged on the beam and slab structure 3 of basement.
The beam and slab structure at described lower floor trestle 2 places is provided with reinforcement.
Claims (2)
1. adverse construction method stepping type shoveling trestle, it is characterized in that, its edge is against making the multilayer lower floor trestle (2) that regional depth comprises first floor trestle (1) from top to down and is arranged on first floor trestle below, successively stretch from top to bottom between the trestle (2) of first floor trestle (1) and multilayer lower floor to the contrary shoveling regional center of doing, form the stepping type structure, lower floor's trestle (2) is arranged on the beam and slab structure (3) of basement.
2. adverse construction method stepping type shoveling trestle according to claim 1 is characterized in that the beam and slab structure that described lower floor trestle (2) is located is provided with reinforcement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201020167737XU CN201695397U (en) | 2010-04-22 | 2010-04-22 | Reverse construction stepped excavation trestle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201020167737XU CN201695397U (en) | 2010-04-22 | 2010-04-22 | Reverse construction stepped excavation trestle |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201695397U true CN201695397U (en) | 2011-01-05 |
Family
ID=43396637
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201020167737XU Expired - Fee Related CN201695397U (en) | 2010-04-22 | 2010-04-22 | Reverse construction stepped excavation trestle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201695397U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102691300A (en) * | 2012-04-18 | 2012-09-26 | 浙江省建工集团有限责任公司 | Construction method of foundation pit earthwork |
-
2010
- 2010-04-22 CN CN201020167737XU patent/CN201695397U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102691300A (en) * | 2012-04-18 | 2012-09-26 | 浙江省建工集团有限责任公司 | Construction method of foundation pit earthwork |
CN102691300B (en) * | 2012-04-18 | 2014-08-13 | 浙江省建工集团有限责任公司 | Construction method of foundation pit earthwork |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103277106B (en) | Highway tunnel three-step five-procedure excavation construction method | |
CN205662947U (en) | Coincide assembled underground pipe gallery system | |
CN103195085B (en) | Downward story-adding basement and construction method thereof | |
CN104963705B (en) | A kind of underground space tunneling construction method | |
CN102995643B (en) | Underground-space steel truss foundation pit supporting structure and construction method thereof | |
CN106351331A (en) | Multi-floor basement reverse and normal combined construction process | |
CN103290847A (en) | Inner oblique beam supporting structure for oversized-area deep foundation pit and construction method | |
CN1793527A (en) | Method for construction of underground continuous steel jacket box | |
CN209509554U (en) | Increase basement underpinning structure under existing building newly | |
CN101498133B (en) | Method and supporting construction for enlarging basement top-down method earth excavation space | |
CN104164878A (en) | Earth excavation technology for ultra-large type deep foundation pit | |
CN203238642U (en) | Supporting retaining wall of foundation pit | |
CN204608794U (en) | A kind of transhipment mound platform for deep-foundation pit excavation | |
CN201695397U (en) | Reverse construction stepped excavation trestle | |
CN201695398U (en) | Stepped top-down pit excavation trestle | |
CN202416324U (en) | Beam and slab structure superposed through top-down beam and down-top slab construction of foundation pit project | |
CN202925564U (en) | Tunnel shield receiving structure without working well of existing cellar structure | |
CN205688473U (en) | A kind of reverse construction machinery | |
CN202610677U (en) | Auxiliary tool for soft soil earthwork construction | |
CN102493488A (en) | Construction method for reverse beams and normal plates in foundation pit engineering | |
CN204849777U (en) | Tilting board double row pile supporting construction that bears down on one | |
CN202543946U (en) | Supporting structure for drainage type fender posts in soft soil area | |
CN201695657U (en) | Excavation platform in step type top-down pit | |
CN205188982U (en) | Removable system of strutting of rectangle work well | |
CN105887949B (en) | A kind of reverse construction mechanical device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110105 Termination date: 20110422 |