CN201525995U - Cloverleaf intersection scheme for urban intersections - Google Patents

Cloverleaf intersection scheme for urban intersections Download PDF

Info

Publication number
CN201525995U
CN201525995U CN2009201368960U CN200920136896U CN201525995U CN 201525995 U CN201525995 U CN 201525995U CN 2009201368960 U CN2009201368960 U CN 2009201368960U CN 200920136896 U CN200920136896 U CN 200920136896U CN 201525995 U CN201525995 U CN 201525995U
Authority
CN
China
Prior art keywords
intersection
bridge
vehicles
vehicle
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009201368960U
Other languages
Chinese (zh)
Inventor
朱立新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2009201368960U priority Critical patent/CN201525995U/en
Application granted granted Critical
Publication of CN201525995U publication Critical patent/CN201525995U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a cloverleaf intersection scheme for urban intersections, relating to an intersection which does not occupy large urban land or space, and separates pedestrians from vehicles. The cloverleaf intersection scheme is as follows: vehicles on a flyover are reasonably separated according to straight moving 2, left turn 3 and right turn 4, thus leading the vehicles to travel into individual lane without interference; as for the separated vehicles, vehicles which travel straight forward and vehicles which turn left converge close to the center of the intersection, then pass the cross bridge and travel to a ground-level inner-side ramp bridge 1, then travel away from the flyover along the ground-level road, and converge with vehicles which turn right from an outer-side ramp bridge 5, then the vehicles travel away from the intersection together. By utilizing the majority of remaining ground-level space, pedestrians and non-motor vehicles exchange roads by an middle passage and a central movement region, therefore, pedestrians and vehicles are separated, thus guaranteeing traffic safety, and shortening the time for a motor vehicle passing the intersection due to reasonable convergence of vehicles.

Description

A kind of grade separation scheme of city intersection
Technical field:
The utility model belongs to the graded crossing of intersection in the road dealings by scheme, the particularly overpass bridge of medium and small intersection, city.
Background technology:
Along with the raising of constant development of economy and living standards of the people, the automobile particularly quantity of car rapidly increases, and it is crowded that this has caused for traffic, particularly urban traffic, and especially blocking up of the intersection of down town given prominence to especially.These are local owing to be subjected to the restriction of urban development and the influence of people's action need, can't build large-scale overpass bridge and solve congested in traffic problem.Therefore need to adopt a kind of neither excessive urban land and space of taking, can effectively pedestrian and motor vehicle be separated again, can be convenient for people to movable scheme simultaneously to greatest extent.
Summary of the invention:
The purpose of this utility model is to build a kind of neither excessive urban land and locus of taking in the intersection of down town, the overpass bridge that again can be effectively pedestrian and motor vehicle be separated, the problem of solution down town traffic congestion.
The implementing method of this utility model scheme is: this programme is to build a single-deck stereo cross bridge in the intersection (no matter being crossroad or fork in the road), the descending people of the up vehicle bridge of bridge.Vehicle shunting and confluxing on bridge, that avoids that intersection brings blocks up.When vehicle drives towards the intersection, reach bridge floor along approach ramp, the ramp access bridge with the rising of pontic road to the right ground be the direction broadening on bicycle and sidewalk, make that vehicle is told craspedodrome, left-hand bend on ramp bridge, three the guiding tracks (fork in the road is as long as turn left and two tracks of leading of turning right) of turning right.When motor vehicle was passed by the intersection on bridge, sailing out of overpass bridge had two passes, Yi Tiaolu be near the center, intersection for keeping straight on and the left-hand bend vehicle is walked the inboard ramp bridge that pontic is sailed down ground after confluxing, sail out of the intersection along ground level road behind the following bridge; Another road be by the roadside from overpass bridge for the right-hand bend vehicle sail out of the intersection at present bridge remove the outside ramp bridge of row, Liang Tiaodao (bridge) is confluxing at a distance from the intersection on the road.After supplying craspedodrome and left-hand bend vehicle to conflux, sail out of the ground level road of intersection the remaining ground level road and the above ground portion at center, intersection, the center-aisle and the central movable zone that are the pedestrian and non motorized vehicle intersection and evacuate to all directions.Article two, motor vehicle sails out of in road (bridge) road of overpass bridge, remove the outside ramp bridge of row for bridge under the right-hand bend vehicle from overpass bridge by the roadside, last passage that sails out of overpass bridge also had supplementary function, when near the center, intersection for keeping straight on and the left-hand bend vehicle walks that pontic is sailed down the inboard ramp bridge on ground or the ground level road generation traffic accident or when meeting traffic jam of moving ahead after confluxing, can utilize the outside ramp bridge that supplies the right-hand bend vehicle to sail out of the intersection to evacuate.Bus station is set up on the ground level road side of sailing out of the intersection after confession right-hand bend vehicle is sailing out of under the outside ramp bridge of intersection, supplying craspedodrome and left-hand bend vehicle to conflux, can more effectively improve the efficient of intersection, traffic that is convenient for people to and activity.Under normal circumstances, when motor vehicle reaches overpass bridge along approach ramp, according to separately whereabouts respectively according to the reasonable shunting of keeping straight on, turning left, turning right, through vehicles and left-hand bend vehicle conflux on overpass bridge earlier, along overpass bridge under the inboard ramp bridge, move ahead along ground level road, sail out of the intersection after the right-hand bend vehicle that gets off with outside ramp bridge confluxes a long way off; Pedestrian and non motorized vehicle is realized changing of intersection by the center-aisle and the central active region on ground.
This programme has following characteristics:
1, the complete separated running of pedestrian and motor vehicle is eliminated people's car hidden peril of accident, prevents the generation of major traffic accidents effectively.This grade separation scheme is with the motor-driven vehicle going bridge floor, it is main mode that pedestrian and non motorized vehicle is walked the road under bridge face, and pedestrian and motor vehicle are separated fully, makes pedestrian's the unordered cruising that does not influence motor vehicle, so both improve road speed, avoided the generation of traffic accident again.
2, the handling capacity of vehicle is greatly improved in the shunting in advance of motor vehicle and do not have staggered confluxing.This grade separation scheme is divided into three with regard to the vehicle that will drive towards the intersection in advance and removes line direction on access bridge, reasonably arrange vehicle to go using Correct Lane of line direction along difference; By in the intersection,, steal the intersection of vehicle with confluxing of twice other vehicle ' that are independent of each other, make motor vehicle the time by the intersection, can keep certain travel speed, shorten the time of vehicle, improve the vehicle handling capacity of intersection by the intersection.
3, be very easy to the pedestrian, hommization is stronger.This grade separation scheme allows pedestrian and non motorized vehicle walk the road under bridge face, the pedestrian has been removed pick up from the painstaking and inconvenient of rank climbing, has made things convenient for the pedestrian who passes by on one's way on the one hand, has given up people on the other hand and has schemed facility and cross the thought of walking motorway.The pontic of motorway can also be pedestrian's sun-shading rain-proof on road surface simultaneously.Not only eliminate hidden peril of accident, also embodied the humanity concept that people-oriented from the source.
4, floor space is little, and is easy to implement.The bridge floor of the overpass bridge in this grade separation scheme only supplies motor-driven vehicle going, and pontic extends by the aerial expansion to nonmotorized vehicle lane and sidewalk, reaches the vehicle shunting requirement of bridge floor.Therefore not high to the width requirement of original ground level road, as long as generally there is Four-Lane Road above, this is the situation of the busy road in most of city.The ground resource of these intersections is in short supply, can't build large-scale overpass bridge, and this programme can remedy not enough around here, helps implementing.
5, the bus station is located at the intersection, helps pedestrian's the convenience and the prosperity of down town.This grade separation scheme brings great convenience for citizen and the visitor who passes by on one's way in the set-point, bus stop that each corner of intersection is reserved.The intersection is exactly people's traffic distribution centre originally, allows people transfer to bus here up and down, can improve people's travel efficiency to greatest extent, and such convenience must be subjected to everybody welcome, is the potential of the bustling upgrading in this intersection.
6, leave the traffic jam prediction scheme, guarantee The coast is clear.Two motor vehicles sail out of in road (bridge) road of overpass bridge in this grade separation scheme, supply the descending outside ramp bridge of right-hand bend vehicle by the roadside from overpass bridge, another passage that sails out of overpass bridge also had supplementary function, walk after confluxing that pontic is sailed down the inboard ramp bridge on ground or the ground level road generation traffic accident or when meeting traffic jam of moving ahead, can utilize the outside ramp bridge that confession right-hand bend vehicle sails out of the intersection to evacuate near the craspedodrome of center, intersection confession and left-hand bend vehicle.Guaranteed the unimpeded of road well.
Description of drawings:
Fig. 1 is the schematic perspective view of this grade separation scheme.
Fig. 2 is this grade separation scheme schematic top plan view.
Fig. 3 is shunting on the motor-driven vehicle bridge of this grade separation scheme, confluxes and the travel direction schematic diagram.
Fig. 4 is this grade separation scheme pedestrian and non motorized vehicle center-aisle and central movable zone schematic diagram.
Mark 1 among the figure for walking the inboard ramp bridge that pontic is sailed down ground near buying car in installments of center, intersection; 2 is bridge craspedodrome guiding track on the vehicle; 3 is bridge left-hand bend guiding track on the vehicle; 4 is bridge right-hand bend guiding track on the vehicle; 5 for vehicle turn right the back down bridge remove the outside ramp bridge of row; 6 is the road that vehicle carries out the transition to ground under the overpass bridge; The trade road is gone on 7 ground of sailing out of the intersection for vehicle; 8 is the placement, bus stop; 9 is sidewalk, roadside and nonmotorized vehicle lane; 10 center-aisles for pedestrian and non motorized vehicle remittance intersection central active region.
The specific embodiment:
The schematic perspective view of Fig. 1 has shown each bar runway of bridge floor and has bought car in installments near the center and passed that bridge removes capable outside ramp bridge under inboard ramp bridge that pontic arrives ground level road and the right-hand bend vehicle.The vehicle that leaves for the intersection is before arriving the overpass bridge top, sail the guiding track of craspedodrome 2, left- hand bend 3,4 three directions of turning right respectively into, after the left-hand bend vehicle in the through vehicles in track 2 and track 3 confluxes, along inboard ramp bridge track 1 through the track 1 and track 6 pass pontic and arrive ground, 7 leave for line direction along the track; The right-hand bend vehicle is turned right and to be left for line direction along ramp bridge track, the outside 5 after entering guiding track 4, and the vehicle that comes with track 7 a long way off confluxes and sails out of the intersection.
Pedestrian and non motorized vehicle imports central active region in the sidewalk and nonmotorized vehicle lane 9 walkings at turning, roadside, intersection via center-aisle 10, according to the line direction that goes of oneself, selects corresponding center-aisle 10 to leave away in central active region.In 8 relevant positions the bus stop is set, can greatly makes things convenient for the pedestrian.

Claims (1)

1. in the grade separation scheme of a city intersection, it is characterized in that have on the overpass bridge buy car in installments before arriving the bridge top on bridge the ramp bridge that is divided into three tracks, the bent bridge that travels for the left-hand bend vehicle, for keeping straight on and the left-hand bend vehicle is walked pontic after confluxing and sailed the inboard ramp bridge at the center, close intersection on ground and the outside ramp bridge that leans on the roadside that sails out of the intersection for the right-hand bend vehicle down; On the ground ground level road part under the bridge that sails out of the intersection after supplying craspedodrome and left-hand bend vehicle to conflux and cross in the centre of intersection walking for pedestrian and non motorized vehicle passage and central active region are partly separated.
CN2009201368960U 2009-03-03 2009-03-03 Cloverleaf intersection scheme for urban intersections Expired - Fee Related CN201525995U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201368960U CN201525995U (en) 2009-03-03 2009-03-03 Cloverleaf intersection scheme for urban intersections

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201368960U CN201525995U (en) 2009-03-03 2009-03-03 Cloverleaf intersection scheme for urban intersections

Publications (1)

Publication Number Publication Date
CN201525995U true CN201525995U (en) 2010-07-14

Family

ID=42517285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201368960U Expired - Fee Related CN201525995U (en) 2009-03-03 2009-03-03 Cloverleaf intersection scheme for urban intersections

Country Status (1)

Country Link
CN (1) CN201525995U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102277816A (en) * 2010-07-19 2011-12-14 易晓俊 Traffic system suitable for access
CN103161105A (en) * 2011-12-12 2013-06-19 洛阳丰兴机械科技有限公司 Crossroad unblocked bridge
CN104294724A (en) * 2014-11-04 2015-01-21 吴小平 Designing scheme for loop intersections with primary and secondary phase positions
CN105369705A (en) * 2015-11-27 2016-03-02 于明禧 Interchange
CN112176801A (en) * 2020-09-14 2021-01-05 朱立新 Overpass for urban road crossroad

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102277816A (en) * 2010-07-19 2011-12-14 易晓俊 Traffic system suitable for access
CN103161105A (en) * 2011-12-12 2013-06-19 洛阳丰兴机械科技有限公司 Crossroad unblocked bridge
CN104294724A (en) * 2014-11-04 2015-01-21 吴小平 Designing scheme for loop intersections with primary and secondary phase positions
CN105369705A (en) * 2015-11-27 2016-03-02 于明禧 Interchange
CN112176801A (en) * 2020-09-14 2021-01-05 朱立新 Overpass for urban road crossroad

Similar Documents

Publication Publication Date Title
CN201634978U (en) Road intersection system of T-shaped junction
CN201525995U (en) Cloverleaf intersection scheme for urban intersections
CN101792993A (en) Three-layered complete interchange system at crossroad
CN202705838U (en) Three-bridge combined crossroad achieving complete interchange
CN101255674A (en) Method and road structure for run of road junction without block
CN201634980U (en) Complete interchange three-layer intersection system of cross road
CN200985480Y (en) Non-obstacle crossroad road structure
CN202017171U (en) Three-layer flyover for urban roads
CN201027293Y (en) High speed road for city district floor
CN100383340C (en) One-way gallop bridge
CN103572677B (en) Left-turn-free flyover
CN110158510A (en) A kind of pedestrains safety crossing facilities and control method
CN204530358U (en) Track, crossroad is without intersection current traffic system continuously
CN204417943U (en) A kind of crossroad short overpass bridge
CN202865713U (en) Downtown overpass
CN203200625U (en) Bridge on junction of three roads
CN101792994A (en) Multifunctional tunnel grade separation hub bridge
CN112176801A (en) Overpass for urban road crossroad
CN204509921U (en) Track, T-shaped road junction is without intersection current traffic system continuously
CN109778624A (en) Intersection to current mode of going together and its passing method from all directions
CN101487214A (en) Humanized multifunctional intersection for urban crossroad
CN104480820A (en) City fast traffic track system and traffic control method thereof
CN101177927A (en) Rapid passing road system
CN200949198Y (en) Bar-bell type all-interchange overpass
CN104612012B (en) Track, crossroad is without intersecting the most current traffic system and control method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100714