CN201459756U - 悬挂式施工顶管竖井 - Google Patents

悬挂式施工顶管竖井 Download PDF

Info

Publication number
CN201459756U
CN201459756U CN200920092488XU CN200920092488U CN201459756U CN 201459756 U CN201459756 U CN 201459756U CN 200920092488X U CN200920092488X U CN 200920092488XU CN 200920092488 U CN200920092488 U CN 200920092488U CN 201459756 U CN201459756 U CN 201459756U
Authority
CN
China
Prior art keywords
cast
side wall
type construction
vertical shaft
sidewall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920092488XU
Other languages
English (en)
Inventor
吴纪东
邹霄
罗付军
刘炜嶓
刘国强
王明远
刘勇
马军
郑亚男
郭伟
高振波
徐伟
杨艳
王松阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Municipal Engineering General Corp
Original Assignee
Zhengzhou Municipal Engineering General Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Municipal Engineering General Corp filed Critical Zhengzhou Municipal Engineering General Corp
Priority to CN200920092488XU priority Critical patent/CN201459756U/zh
Application granted granted Critical
Publication of CN201459756U publication Critical patent/CN201459756U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型公开了一种悬挂式施工顶管竖井,包括浇筑为一体的侧壁和底板,侧壁上设有洞口,所述侧壁包括上下相接并浇筑为一体的至少三个壁段,所述侧壁内竖向贯通浇筑有工程桩。本实用新型结构简单,制作简便,仅需在竖井所在位置向下根据侧壁的分段情况分层开挖并浇筑。所述侧壁内竖向贯通设置有工程桩,这样在自上而下浇筑侧壁时,工程桩将对已浇筑的上层侧壁起到支撑的作用,侧壁浇筑完成后,工程桩也将起到加强筋的作用,增强了本实用新型的强度。侧壁包括上下相接的三个以上的壁段,这样就可以自上而下分段浇筑,上段侧壁浇筑、凝固后将对井内空间起到支护作用。

Description

悬挂式施工顶管竖井
技术领域
本实用新型涉及一种悬挂式施工顶管竖井。
背景技术
顶管施工是城镇排水工程非开挖地下管线施工的重要施工方法,它不需要开挖面层,并且能够穿越公路、铁道、河川、地面建筑物、地下构筑物以及各种地下管线等。具有不污染环境、不影响交通、对地层结构破坏小、施工安全可靠、周期短、无需运输和堆放杂土、成本低、社会效益与经济效益显著等优点。顶管施工中必须要制作竖井(工作井、接收井等),现有的竖井结构都要求在测量放线、确定竖井位置后采用开挖基坑或采用沉井施工工艺的方法来施工制作,现有的竖井结构限制了施工方法只能是从下到上浇筑施工,而不能从上到下浇筑施工,同时必须开挖基坑,这就给竖井施工造成了如下的困难:1.竖井距建筑较近时,如无防护结构则对附近建筑的安全构成威胁(容易导致附近建筑地基出现下沉现象),如加设防护结构后施工,则需增加昂贵的防护结构成本,而防护结构在施工完毕后也不能取出重复利用,降低成本和确保建筑安全不可兼得。2.竖井位于道路上时,开挖基坑的施工方法施工所需的面积较大,需要关闭道路施工,来往车辆皆须绕行。3.现有竖井施工方法所制造出来的竖井具有易侧向变形的缺陷。4.开挖面积较大,施工周期较长。5.现有的竖井施工方法在施工时都是开挖好基坑后,由下至上浇筑井壁,没有由上至下逆向浇筑井壁的施工方法。
实用新型内容
本实用新型的目的在于提供一种悬挂式施工顶管竖井,其井体结构允许自上而下的浇筑施工,同时施工中无须开挖小型基坑,避免了现有井体结构给施工带来的困难。
为实现上述目的,本实用新型的悬挂式施工顶管竖井,包括浇筑为一体的侧壁和底板,侧壁上设有洞口,所述侧壁包括上下相接并浇筑为一体的至少三个壁段,所述侧壁内竖向贯通浇筑有工程桩。
所述壁段之间的接缝处浇筑有井壁扩大头。
所述工程桩沿所述侧壁的水平截面均匀设有至少四根。
所述工程桩为钢筋混凝土灌注桩或预制桩。
所述工程桩的底端伸出所述底壁的底端。
本实用新型具有如下的优点:
1.本实用新型结构简单,制作简便,仅需在竖井所在位置向下根据侧壁的分段情况分层开挖并浇筑.所述侧壁内竖向贯通设置有工程桩,这样在自上而下浇筑侧壁时,工程桩将对已浇筑的上层侧壁起到支撑的作用,侧壁浇筑完成后,工程桩也将起到加强筋的作用,增强了本实用新型的强度.侧壁包括上下相接的三个以上的壁段,这样就可以自上而下分段浇筑,上段侧壁浇筑、凝固后将对井内空间起到支护作用,施工人员可以在上段侧壁的支护下继续向下开挖并进行下段侧壁的浇筑,而无须另外设置支护结构,因此在附近有其它建筑的情况下,节省了大量的支护成本.施工中开挖面积小也缩短了工期.
2.所述壁段之间的接缝处浇筑有井壁扩大头,增强了接缝处的防水性。
3.所述工程桩沿所述侧壁的水平截面均匀设有多根,既能够对竖井施工起到足够的支撑和支护作用以及在施工完成后起到侧壁加强筋的作用,同时又避免了以往沿竖井周边设置密集的支护排桩带来的材料浪费。
4.所述工程桩为钢筋混凝土灌注桩或预制桩,成本较低,强度较高。
5.所述工程桩的底端伸出所述底壁的底端,便于在施工中获得足够的土体摩擦力以及桩顶力。
附图说明
图1是本实用新型的平面布置结构示意图;
图2是图1的A-A剖视图。
具体实施方式
如图1和图2所示,本实用新型的悬挂式施工顶管竖井包括井壁,井壁包括浇筑为一体的侧壁1和底板5,侧壁1上设有洞口4,洞口4在施工中作为机械出洞口,竖井施工完毕后作为管道连接口。所述侧壁包括上下相接并浇筑为一体的五个壁段,如图2所示所述的五个壁段由上至下分别为H1、H2、H3、H4、H5。所述侧壁1内竖向贯通浇筑有工程桩2,工程桩2的底端伸出所述底壁5的底端。如图1所示工程桩沿所述侧壁的水平截面均匀设有多根。如图2所示,所述壁段之间的接缝处浇筑有井壁扩大头3。其中,工程桩可以是钢筋混凝土灌注桩,也可以是预制桩。
当然,本实用新型包括但不限于本实施例,如本实用新型不仅可以是图1和图2所示的方形竖井,也可以是圆形或其它形状的竖井;所述侧壁壁段的数目可以是图2所示的五个,也可以是三个、四个、六个以及六个以上的其它数目;上述变换均落在本实用新型的保护范围之内。

Claims (5)

1.悬挂式施工顶管竖井,包括浇筑为一体的侧壁和底板,侧壁上设有洞口,其特征在于:所述侧壁包括上下相接并浇筑为一体的至少三个壁段,所述侧壁内竖向贯通浇筑有工程桩。
2.根据权利要求1所述的悬挂式施工顶管竖井,其特征在于:所述壁段之间的接缝处浇筑有井壁扩大头。
3.根据权利要求1或2所述的悬挂式施工顶管竖井,其特征在于:所述工程桩沿所述侧壁的水平截面均匀设有至少四根。
4.根据权利要求3所述的悬挂式施工顶管竖井,其特征在于:所述工程桩为钢筋混凝土灌注桩或预制桩。
5.根据权利要求4所述的悬挂式施工顶管竖井,其特征在于:所述工程桩的底端伸出所述底壁的底端。
CN200920092488XU 2009-08-19 2009-08-19 悬挂式施工顶管竖井 Expired - Fee Related CN201459756U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920092488XU CN201459756U (zh) 2009-08-19 2009-08-19 悬挂式施工顶管竖井

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920092488XU CN201459756U (zh) 2009-08-19 2009-08-19 悬挂式施工顶管竖井

Publications (1)

Publication Number Publication Date
CN201459756U true CN201459756U (zh) 2010-05-12

Family

ID=42387109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920092488XU Expired - Fee Related CN201459756U (zh) 2009-08-19 2009-08-19 悬挂式施工顶管竖井

Country Status (1)

Country Link
CN (1) CN201459756U (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155025A (zh) * 2011-03-23 2011-08-17 东南大学 后浇带型装配式顶管工作井
CN106917415A (zh) * 2017-04-10 2017-07-04 金陵科技学院 一种预制装配式地下结构及其施工方法
CN107975376A (zh) * 2017-10-24 2018-05-01 上海市基础工程集团有限公司 隧道盾构顶管与竖向管道连接结构及施工方法
CN108547628A (zh) * 2018-05-17 2018-09-18 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法
CN108661651A (zh) * 2018-05-17 2018-10-16 中冶建工集团有限公司 硬质岩层顶管工作井快速施工方法
CN108678755A (zh) * 2018-05-17 2018-10-19 中冶建工集团有限公司 松软岩层顶管工作井快速施工方法
CN113027463A (zh) * 2021-03-24 2021-06-25 山东建筑大学 一种悬挂式逆作墙工作井支护结构及施工方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155025A (zh) * 2011-03-23 2011-08-17 东南大学 后浇带型装配式顶管工作井
CN102155025B (zh) * 2011-03-23 2012-05-23 东南大学 后浇带型装配式顶管工作井
CN106917415A (zh) * 2017-04-10 2017-07-04 金陵科技学院 一种预制装配式地下结构及其施工方法
CN106917415B (zh) * 2017-04-10 2024-01-19 金陵科技学院 一种预制装配式地下结构及其施工方法
CN107975376A (zh) * 2017-10-24 2018-05-01 上海市基础工程集团有限公司 隧道盾构顶管与竖向管道连接结构及施工方法
CN107975376B (zh) * 2017-10-24 2020-09-01 上海市基础工程集团有限公司 隧道盾构顶管与竖向管道连接结构及施工方法
CN108547628A (zh) * 2018-05-17 2018-09-18 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法
CN108661651A (zh) * 2018-05-17 2018-10-16 中冶建工集团有限公司 硬质岩层顶管工作井快速施工方法
CN108678755A (zh) * 2018-05-17 2018-10-19 中冶建工集团有限公司 松软岩层顶管工作井快速施工方法
CN108547628B (zh) * 2018-05-17 2020-09-01 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法
CN113027463A (zh) * 2021-03-24 2021-06-25 山东建筑大学 一种悬挂式逆作墙工作井支护结构及施工方法
CN113027463B (zh) * 2021-03-24 2022-08-30 山东建筑大学 一种悬挂式逆作墙工作井支护结构及施工方法

Similar Documents

Publication Publication Date Title
CN201459756U (zh) 悬挂式施工顶管竖井
CN1837511B (zh) 一种双排围堰及其制作方法
CN105862910B (zh) 一种装配式立体地下车库的逆作式建造方法
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN200985518Y (zh) 门式抗浮结构
CN101418569B (zh) 预制拱片、支护与主体结构结合的优化复合拱墙
CN104947682A (zh) 一种基坑支护施工方法及其装置
CN202689031U (zh) 深基坑支护挡墙
CN203411993U (zh) 一种简单快捷式挡土墙
CN105064711B (zh) 一种在居民楼间施工地下车库的方法
CN202689009U (zh) 一种钢板桩与管桩组合基坑支护结构
CN206752667U (zh) 一种地下室挡墙结构
CN103397634A (zh) 一种锁扣钢管桩围堰的锚固施工方法
CN206428707U (zh) 一种基坑支护降水一体化管桩护壁结构
CN216041201U (zh) 一种先撑后挖双层斜向支撑基坑围护体系
CN102220764B (zh) 深基坑支护体系的施工方法
CN110241813A (zh) 一种输电线路钻埋式预制管桩
CN110939139B (zh) 基于桩后异型挡墙刚性接触的桩板墙结构及其构建方法
CN204059460U (zh) 电厂循环水系统的内河水取水口结构
CN112681376A (zh) 一种井筒式地下立体车库的施工方法
CN206128077U (zh) 一种深基坑支护的内支撑结构
CN110117959B (zh) 一种临近江河基坑支护施工方法
CN204715364U (zh) 一种基坑支护装置
CN104074234A (zh) 电厂循环水系统的内河水取水口结构及其施工方法
CN103410155B (zh) 一种可回收前置装配式支撑围护结构及其应用方法

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100512

Termination date: 20160819

CF01 Termination of patent right due to non-payment of annual fee