CN201326524Y CNU2008202338332U CN200820233833U CN201326524Y CN 201326524 Y CN201326524 Y CN 201326524Y CN U2008202338332 U CNU2008202338332 U CN U2008202338332U CN 200820233833 U CN200820233833 U CN 200820233833U CN 201326524 Y CN201326524 Y CN 201326524Y
Authority
CN
China
Prior art keywords
reinforced concrete
changeover portion
power generating
wind power
cylindrical shell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008202338332U
Other languages
English (en)
Inventor
张芹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinovel Wind Group Co Ltd
Original Assignee
SINOVEL WIND CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SINOVEL WIND CO Ltd filed Critical SINOVEL WIND CO Ltd
Priority to CNU2008202338332U priority Critical patent/CN201326524Y/zh
Application granted granted Critical
Publication of CN201326524Y publication Critical patent/CN201326524Y/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Wind Motors (AREA)

Abstract

本实用新型公开了一种风力发电机组混合式塔筒,其包括有底段的钢筋混凝土筒体、钢制塔筒及用于连接所述钢筋混凝土筒体和所述钢制塔筒的过滤段,所述钢筋混凝土筒体直接浇注在风力发电机组基础上,所述过渡段的顶端与所述钢制塔筒的底端由法兰及螺栓固定连接,所述过渡段的底端与所述钢筋混凝土筒体的顶端由螺杆、螺母固定连接,并由与所述螺杆位于同一直径圆上的钢绞线提供预拉紧,同时在所述过渡段的底端设置有三个用于调平过渡段的调平螺栓。具有降低成本及减少安装、运输费用的优点。

Description

风力发电机组混合式塔筒
技术领域
本实用新型关于风力发电机组,更具体地说,关于一种风力发电机组的混合式塔筒。
背景技术
塔筒和基础是风力发电机组的主要承载部件。且随着风力发电机组容量的增加,高度增加,其重要性也愈来愈明显。目前国内兆瓦(MW)级以上风力发电机组的塔筒大多采用圆锥型钢制塔筒,具有成本高以及安装费用高的问题。
实用新型内容
本实用新型的目的在于提供一种混合式塔筒,以解决目前由于钢制塔筒成本高和安装费用高的问题。
本实用新型中的风力发电机组混合式塔筒包括有底段的钢筋混凝土筒体、钢制塔筒及用于连接所述钢筋混凝土筒体和所述钢制塔筒的过滤段,所述钢筋混凝土筒体直接浇注在风力发电机组基础上,所述过渡段的顶端与所述钢制塔筒的底端由法兰及螺栓固定连接,所述过渡段的底端与所述钢筋混凝土筒体的顶端由螺杆、螺母固定连接,并由与所述螺杆位于同一直径圆上的钢绞线提供预拉紧,同时在所述过渡段的底端设置有三个用于调平过渡段的调平螺栓。
所述钢绞线与所述螺杆呈交替均匀间隔设置。
所述过渡段底端与所述钢筋混凝土筒体的顶端在调平处理后形成的间隙处填入素混凝土。
所述过渡段底端的法兰上预留有防止填入素混凝土时形成气泡的通气孔。
所述钢绞线在提供预拉紧时穿过事先埋设在所述钢筋混凝土筒体顶端的长方形包螺管内,其中在一个包螺管内穿设有三根钢绞线,且所述钢绞线在穿设后的两端由铆具拉紧、固定。
所述三个调平螺栓沿圆周呈120度角分布在所述过渡段的法兰上。
本实用新型中的混合式塔筒在底端采用钢筋混凝土筒体,即在风场现场具体设计并施工钢筋混凝土塔筒底段,综合考虑了塔筒的经济性,既满足了运输的要求,同时也减少了塔筒的成本,混凝土成本大概是钢制塔筒的60%左右。
附图说明
图1为本实用新型中混合式塔筒的结构示意图;
图2为图1中所示塔筒沿A-A线的剖视示意图;
图3为图2中沿B-B线的剖视示意图;
图4为图2中沿C-C线的剖视示意图;
图5为图2中D所示部分的放大示意图。
具体实施方式
下面将结合附图对本实用新型中的具体实施例作进一步详细说明。
如图1所示,本实用新型中的混合式塔筒包括有底段的钢筋混凝土筒体2、钢制塔筒4及用于连接钢筋混凝土筒体2和钢制塔筒4的过滤段3。其中:
底段的钢筋混凝土筒体2采用在风力发电机组基础1上方现场浇注混凝土的方式来实现的,其中现场浇注混凝土的施工工艺是混凝土施工工程中的滑动模板施工工艺,该施工方法与常规的施工方法相比,具有施工速度快、机械化程度高,可节省支模和搭设脚手架所需要的工料、能较方便地将模板进行拆散和灵活组装并可重复使用。
钢制塔筒4根据具体的钢制塔筒高度分成2段或者3段,便于运输与吊装,每段之间采取法兰组对及高强度螺栓连接,该连接为现有技术,不再另行说明。
如图3和图4所示,过渡段3的顶端与钢制塔筒4的底端也通过法兰组对及高强度螺栓连接,因此不再另行说明。过渡段3的底端设置有法兰30,与钢筋混凝土筒体2顶端的凸缘20对接,并由螺杆5、螺母7固定连接,在由螺杆5、螺母7固定的同时由与螺杆5位于同一直径圆上的钢绞线6提供预拉紧。其中具体实施的方式是:在钢筋混凝土筒体2顶端凸缘20的同一直径圆上设有多个用于穿设螺杆5的螺杆孔,如图2和图5所示,及埋设的多个呈长方形的包螺管11,包螺管11与螺杆孔呈交错间隔均匀设置,同理,在过渡段3的法兰30上也设有多个呈交错间隔且距离相等、位于同一直径圆上的螺杆孔和钢绞线6的穿设孔。当过渡段3与钢筋混凝土筒体2结合时,螺杆5的两端经由螺母7旋紧固定,钢绞线6的两端通过铆具(图中未示出)固定、拉紧,其中往下延伸的一端直接拉伸到钢筋混凝土筒体2底端。
风力发电机组塔架的垂直度和法兰的水平度要求非常高,由于底部的钢筋混凝土筒体2的上表面较为粗糙,与过渡段3连接不能满足机组要求,因此在过渡段3的底端设置有三个按照圆周方向120度均布用于调平过渡段3的调平螺栓8,即调平螺栓8与过渡段的法兰30螺纹连接,由于在调平处理后会在过渡段3的下表面与钢筋混凝土筒体2上表面之间形成有不规则的缝隙,为了完美的处理这种接触不均匀的现象,在调整水平度合格后在预留的缝隙内填入素混凝土9,并在过渡段3底部法兰30上预留有通气孔10,防止在填入素混凝土9时形成汽包,在填入素混凝土9后在素混凝土9与过渡段3的过渡部分采用建筑用材料密封,防止雨水等的侵入。

Claims (6)

1、一种风力发电机组混合式塔筒,其特征在于,包括有底段的钢筋混凝土筒体(2)、钢制塔筒(4)及用于连接所述钢筋混凝土筒体(2)和所述钢制塔筒(4)的过滤段(3),所述钢筋混凝土筒体(2)直接浇注在风力发电机组基础(1)上,所述过渡段(3)的顶端与所述钢制塔筒(4)的底端由法兰及螺栓固定连接,所述过渡段(3)的底端与所述钢筋混凝土筒体(2)的顶端由螺杆(5)、螺母(7)固定连接,并由与所述螺杆(5)位于同一直径圆上的钢绞线(6)提供预拉紧,同时在所述过渡段(3)的底端设置有三个用于调平过渡段(3)的调平螺栓(8)。
2、根据权利要求1所述的风力发电机组混合式塔筒,其特征在于,所述钢绞线(6)与所述螺杆(5)呈交替均匀间隔设置。
3、根据权利要求1或2所述的风力发电机组混合式塔筒,其特征在于,所述过渡段(3)底端与所述钢筋混凝土筒体(2)的顶端在调平处理后形成的间隙处填入素混凝土(9)。
4、根据权利要求3所述的风力发电机组混合式塔筒,其特征在于,所述过渡段(3)底端的法兰上预留有防止填入素混凝土(9)时形成气泡的通气孔(10)。
5、根据权利要求1或2所述的风力发电机组混合式塔筒,其特征在于,所述钢绞线(6)在提供预拉紧时穿过事先埋设在所述钢筋混凝土筒体(2)顶端的长方形包螺管(11)内,其中在一个包螺管(11)内穿设有三根钢绞线(6),且所述钢绞线(6)在穿设后的两端由铆具拉紧、固定。
6、根据权利要求1或2所述的风力发电机组混合式塔筒,其特征在于,所述三个调平螺栓(8)沿圆周呈120度角分布在所述过渡段(3)的法兰(30)上。
CNU2008202338332U 2008-12-24 2008-12-24 风力发电机组混合式塔筒 Expired - Lifetime CN201326524Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008202338332U CN201326524Y (zh) 2008-12-24 2008-12-24 风力发电机组混合式塔筒

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008202338332U CN201326524Y (zh) 2008-12-24 2008-12-24 风力发电机组混合式塔筒

Publications (1)

Publication Number Publication Date
CN201326524Y true CN201326524Y (zh) 2009-10-14

Family

ID=41178497

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008202338332U Expired - Lifetime CN201326524Y (zh) 2008-12-24 2008-12-24 风力发电机组混合式塔筒

Country Status (1)

Country Link
CN (1) CN201326524Y (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011158095A2 (en) * 2010-06-16 2011-12-22 Cortina Innovations, S. A. De C. V. Flange for wind power generators
CN102720644A (zh) * 2012-05-03 2012-10-10 沈阳华创风能有限公司 一种塔筒结构
CN102777334A (zh) * 2012-07-21 2012-11-14 广东明阳风电产业集团有限公司 风力发电机组调平装置
CN102947524A (zh) * 2010-06-14 2013-02-27 马克斯·博格建筑两合公司 一种具有转接件的塔以及用于制造具有转接件的塔的方法
CN103423099A (zh) * 2012-05-21 2013-12-04 上海电气风能有限公司 一种可以用于大型陆上风力发电机组的混合塔架支撑结构
CN103573562A (zh) * 2013-11-07 2014-02-12 国电联合动力技术有限公司 一种混合式风机塔筒
CN103899499A (zh) * 2014-04-25 2014-07-02 湖南大学 一种风力发电机塔架
CN103899495A (zh) * 2012-12-27 2014-07-02 北京万源工业有限公司 一种风力发电机组混合塔架
CN104454393A (zh) * 2014-12-11 2015-03-25 华北电力大学(保定) 一种风力发电机塔架
CN105715463A (zh) * 2016-04-05 2016-06-29 大唐湖北新能源有限公司 一种钢混结构风机塔筒
CN107825563A (zh) * 2017-11-09 2018-03-23 北京金风科创风电设备有限公司 调平装置、塔筒段及其制造方法和塔筒及其制造方法
CN112796954A (zh) * 2021-02-02 2021-05-14 上海市机电设计研究院有限公司 风电机组混凝土塔筒和钢塔筒间隙调整方法
CN115354903A (zh) * 2022-08-24 2022-11-18 中国电建集团西北勘测设计研究院有限公司 一种混合塔筒转换段上法兰水平度测平、调节方法

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102947524A (zh) * 2010-06-14 2013-02-27 马克斯·博格建筑两合公司 一种具有转接件的塔以及用于制造具有转接件的塔的方法
CN102947524B (zh) * 2010-06-14 2016-10-12 马克斯·博格建筑两合公司 一种具有转接件的塔以及用于制造具有转接件的塔的方法
WO2011158095A3 (en) * 2010-06-16 2012-03-08 Cortina Innovations, S. A. De C. V. Flange for wind power generators
WO2011158095A2 (en) * 2010-06-16 2011-12-22 Cortina Innovations, S. A. De C. V. Flange for wind power generators
CN102720644A (zh) * 2012-05-03 2012-10-10 沈阳华创风能有限公司 一种塔筒结构
CN103423099A (zh) * 2012-05-21 2013-12-04 上海电气风能有限公司 一种可以用于大型陆上风力发电机组的混合塔架支撑结构
CN102777334A (zh) * 2012-07-21 2012-11-14 广东明阳风电产业集团有限公司 风力发电机组调平装置
CN103899495A (zh) * 2012-12-27 2014-07-02 北京万源工业有限公司 一种风力发电机组混合塔架
CN103573562A (zh) * 2013-11-07 2014-02-12 国电联合动力技术有限公司 一种混合式风机塔筒
CN103573562B (zh) * 2013-11-07 2017-03-22 国电联合动力技术有限公司 一种混合式风机塔筒
CN103899499A (zh) * 2014-04-25 2014-07-02 湖南大学 一种风力发电机塔架
CN104454393A (zh) * 2014-12-11 2015-03-25 华北电力大学(保定) 一种风力发电机塔架
CN104454393B (zh) * 2014-12-11 2017-12-26 华北电力大学(保定) 一种风力发电机塔架
CN105715463A (zh) * 2016-04-05 2016-06-29 大唐湖北新能源有限公司 一种钢混结构风机塔筒
CN105715463B (zh) * 2016-04-05 2017-10-24 大唐湖北新能源有限公司 一种钢混结构风机塔筒
CN107825563A (zh) * 2017-11-09 2018-03-23 北京金风科创风电设备有限公司 调平装置、塔筒段及其制造方法和塔筒及其制造方法
CN112796954A (zh) * 2021-02-02 2021-05-14 上海市机电设计研究院有限公司 风电机组混凝土塔筒和钢塔筒间隙调整方法
CN112796954B (zh) * 2021-02-02 2021-10-22 上海市机电设计研究院有限公司 风电机组混凝土塔筒和钢塔筒间隙调整方法
CN115354903A (zh) * 2022-08-24 2022-11-18 中国电建集团西北勘测设计研究院有限公司 一种混合塔筒转换段上法兰水平度测平、调节方法
CN115354903B (zh) * 2022-08-24 2024-04-09 中国电建集团西北勘测设计研究院有限公司 一种混合塔筒转换段上法兰水平度测平、调节方法

Similar Documents

Publication Publication Date Title
CN201326524Y (zh) 风力发电机组混合式塔筒
CN101063509B (zh) 塔连接装置、生产塔基的方法和塔基
CN102312799A (zh) 具有张紧缆索的塔架
CN103422512B (zh) 可更换预埋螺栓式风机组混凝土基础及其施工方法
CN104005569A (zh) 一种托梁拔柱施工方法
CN108223294B (zh) 混凝土塔筒高空用预应力穿筋及锚栓调平装置的使用方法
CN101885208B (zh) 一种新型高效、节能、环保离心混凝土桩制造系统
CN207747196U (zh) 一种预制风电塔架用模具装备
CN207047885U (zh) 一种体外预应力混凝土风机塔架空心基础
CN110863953A (zh) 圆环形钢管混凝土组合风电机组塔架结构
CN204139694U (zh) 内壁带加强结构的钢管塔柱
CN206987144U (zh) 一种底模可拆卸的钢筋桁架楼承板
CN214574622U (zh) 一种pc预制柱连接结构
CN205036512U (zh) 一种预应力混凝土风电塔架体系
CN210712562U (zh) 斜拉桥现浇塔柱施工塔吊体系
CN203452270U (zh) 钢筋保护层控制马凳
CN209469540U (zh) 混凝土塔筒的下塔筒段和具有其的混凝土塔筒
CN106438216A (zh) 分段直塔筒预应力混凝土风机塔架及其安装方法
CN207131088U (zh) 一种剪力墙支撑组件
CN204979712U (zh) 带门洞预制墙板专用辅助支撑杆组件
CN205502608U (zh) 钢管柱安装卡具
CN220621142U (zh) 一种地脚螺栓组固定结构
CN218623612U (zh) 混凝土电线杆的连接结构
CN220117405U (zh) 一种钢混组合梁连接结构
CN107882019A (zh) 工字型预应力钢筋混凝土板桩接桩结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SINOVEL WIND GROUP CO., LTD. I

Free format text: FORMER NAME: HUARUI WIND ELECTRICITY TECHNOLOGY CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 19 floor, building 59, Zhongguancun Avenue, Beijing, Haidian District, 100872

Patentee after: Sinovel Polytron Technologies Inc

Address before: 19 floor, building 59, Zhongguancun Avenue, Beijing, Haidian District, 100872

Patentee before: Sinovel Wind Co., Ltd.

C56 Change in the name or address of the patentee

Owner name: SINOVEL WIND GROUP CO., LTD.

Free format text: FORMER NAME: SINOVEL WIND CO., LTD.

CP03 Change of name, title or address

Address after: 100872, room 7, building 59, 705 Zhongguancun street, Haidian District, Beijing

Patentee after: Sinovel Wind Group Co., Ltd.

Address before: 100872, 19 floor, building 59, Zhongguancun Avenue, Beijing, Haidian District

Patentee before: Sinovel Polytron Technologies Inc

CX01 Expiry of patent term

Granted publication date: 20091014

CX01 Expiry of patent term