CN201284654Y - Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method - Google Patents

Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method Download PDF

Info

Publication number
CN201284654Y
CN201284654Y CNU2008201495177U CN200820149517U CN201284654Y CN 201284654 Y CN201284654 Y CN 201284654Y CN U2008201495177 U CNU2008201495177 U CN U2008201495177U CN 200820149517 U CN200820149517 U CN 200820149517U CN 201284654 Y CN201284654 Y CN 201284654Y
Authority
CN
China
Prior art keywords
belt conveyor
tunnel
steel form
plate trolley
form chassis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008201495177U
Other languages
Chinese (zh)
Inventor
李建斌
张宁川
康宝生
董丹阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CNU2008201495177U priority Critical patent/CN201284654Y/en
Application granted granted Critical
Publication of CN201284654Y publication Critical patent/CN201284654Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model belongs to the technology of lining and mucking of tunnel construction, and provides an arrangement structure for a steel molding plate trolley and a belt conveyor in tunnel construction with the drilling and blasting method. The front end of the belt conveyor (7) is positioned at an excavating work area and suspended at the top of a tunnel through a suspension rope (25) from the excavating work area to the steel molding plate trolley; the steel molding plate trolley (2) is positioned at the rear part of a mobile trestle construction area and positioned on a track in self cycling forward connection; the belt conveyor (7) positioned at the rear part of the movable trestle construction area and in front of the steel molding plate trolley is led downwards to the ground to be positioned on a cast-in-place inverted arch foundation, and the belt conveyor (7) is positioned at one side of the gantry of the steel molding plate trolley when passing through the steel molding plate trolley (2); and the belt conveyor (7) at the rear part of the steel molding plate trolley (2) is suspended at the top of the tunnel through the suspension rope (25). The utility model can effectively solve the space interference problem existing in mucking of the belt conveyor and synchronous lining and transportation operation of the molding plate trolley along with the tunnel excavation in tunnel construction.

Description

The arrangement of steel form chassis and belt conveyor in the drilling and blasting method constructing tunnel
Technical field
The utility model belongs to the lining cutting and the muck removal technology of drilling and blasting method constructing tunnel, relates generally to the arrangement of steel form chassis and belt conveyor in a kind of drilling and blasting method constructing tunnel.
Background technology
Worker's method that tunnel construction is at present adopted mainly contains drilling and blasting method (Mine Method), (tunnel tunnel bore creeps into the machine machine to the TBM method, be called for short TBM, be used for hard rock driving and be called TBM, be used for the soft rock driving and be called the shield structure, be large-scale full bore tunnel construction equipment), three kinds of shallow burial hidden diggings etc.No matter any worker's method, its excavation is abandoned the quarrel transportation can adopt automobile transportation, rail transport, long apart from three kinds of modes such as continuous belt transportation any.In three kinds of construction means of transportation, belt transportation is effective and the most economic a kind of of long-distance transportation, so more and more trend towards employing in the constructing tunnel of growing up at present.
The tunnel is built except section excavation is shaped also needs to carry out permanent supporting, the mode of the permanent supporting in tunnel generally has 3 kinds of precast concrete pipe loop supporting (being mainly the TBM method), concrete pouring supporting (lining cutting) and fibrous concrete ejection supportings, preceding two kinds of support patterns adopt at most.Need shaping and the braced structures of steel form chassis when adopting the concrete pouring support pattern as contoured surface in the supporting and protection structure.And the steel form chassis is a kind of large-scale steel work, occupy sizable space at tunnel internal, when therefore lining cutting is adopted in the tunnel excavation construction as permanent supporting, the TBM tunnel of less cross section diameter particularly, generally all after finishing, tunnel excavation carries out the lining cutting operation again, to avoid excavating the mutual interference mutually of transportation operation and lining cutting operation.But total duration that the tunnel is built can prolong.
In order to shorten total duration that the tunnel is built, the circle, tunnel proposed synchronization lining worker method very early, i.e. tunnel excavation and lining cutting carried out synchronously, and this kind worker method is achieved in tunnel big section, that reach employing track and automobile transportation is built.But in the tunnel that adopts conveyer belt as the transportation of quarrel soil, particularly build than the tunnel of minor diameter, synchronization lining also had never been realized, reason is that conveyer belt apparatus need pass the steel form chassis, and the steel form chassis needs a circulation to connect moving forward of a circulation, but conveyer belt apparatus is fixed, and to the installation accuracy sensitivity, has the position to change slightly and promptly cause belt deviation.Therefore in the synchronization lining technical field, the long transportation with the mutual interference problem of steel form chassis apart from continuous belt fails to solve always.
Except the interference of belt transportation with steel form chassis itself, when adopting the belt transportation to abandon quarrel, also need to dispose car assisted or rail transport is used to transport the required other materials of constructing tunnel, therefore also need to keep the transport channel of automobile or track, under narrow tunnel space condition, promptly to solve the interference of belt transportation and steel form chassis itself, reserve the transport channel of automobile or track again, make the synchronization lining problem when adopting length to transport more complicated apart from continuous belt.Past was designed the multiple technical scheme that makes conveyer belt apparatus pass the steel form chassis, because of not possessing feasibility in practice, thereby all actual the employing.
Summary of the invention
The utility model proposes the arrangement of steel form chassis and belt conveyor in a kind of drilling and blasting method constructing tunnel, its main purpose just is to realize that continuous muck removal of belt conveyor in the constructing tunnel and formwork jumbo with the tunnel excavation synchronization lining, also can make the required facility of automobile or rail transport mechanical transport constructing tunnel and other material.
The following technical proposals of taking the utility model realizes its goal of the invention: the arrangement of Schaltisch and belt conveyor in a kind of drilling and blasting method constructing tunnel, the belt conveyor front end of abandoning quarrel in order to continuous conveying excavation is positioned at the excavation working region, belt conveyor by excavation working region to formwork jumbo lining cutting zone is suspended on the top in tunnel by hoist cable, and is parallel with the air chimney of constructing tunnel; The steel form chassis that carries out permanent supporting lining cutting is positioned at movable trestle construction area rear portion and is positioned on the track that connects before circulation of both sides, tunnel itself; After being positioned at the movable trestle construction area, be that the belt conveyor in the place ahead, lining cutting zone is caused ground downwards and is positioned on the cast-in-place inverted arch basis before the steel form chassis, belt conveyor is positioned at a side of formwork jumbo door frame and be arranged in parallel with transport channel by the steel form chassis time; The belt conveyor at steel form chassis rear portion is suspended on the top in tunnel by hoist cable.
The space interference problem that belt conveyor muck removal when the arrangement of steel form chassis and belt conveyor can effectively solve constructing tunnel in the drilling and blasting method constructing tunnel that the utility model proposes, formwork jumbo exist with tunnel excavation synchronization lining and hauling operation, the continuous muck removal of belt conveyor, formwork jumbo are achieved with tunnel excavation synchronization lining, vehicle borne operation simultaneously, thereby improve the efficient of constructing tunnel, shorten the constructing tunnel cycle.
Description of drawings
Fig. 1 is that belt conveyor and steel form chassis are arranged schematic diagram.
Schematic diagram when Fig. 2 is positioned at the steel form chassis for belt conveyor.
Fig. 3 is that the anterior movable trestle of belt conveyor and steel form chassis is arranged schematic diagram.
Among the figure, 1, air chimney, 2, the steel form chassis, 3, lining concrete, 4, steel form chassis door frame, 5, the abutment wall basis, 6, cast-in-place inverted arch basis, 7, belt conveyor, 8, rail vehicle, 23, movable trestle, 25, hoist cable, 26, the inverted arch basis of pouring into a mould.
The specific embodiment
In conjunction with the accompanying drawings the utility model is illustrated:
Signal when Fig. 2 represents that belt conveyor passes through the steel form chassis, the drilling and blasting method tunnel cross-section is the shape of a hoof, and the inverted arch basis is cast-in-place, and the steel form chassis is positioned on the track that connects before itself circulation, and belt conveyor 7 is positioned at a side of steel form chassis door frame 4 inside.Fig. 3 has provided the signal of belt conveyor, movable trestle locus in the tunnel when adopting drill bursting construction, as shown in Figure 3, the length that rest on the ground at the regional belt conveyor 7 of excavation is 100~200 meters, the back is by causing tunnel top in hoist cable 25 suspentions, conveyer belt is 100~200m in last length of drawing slope section placement, and it is parallel with the air chimney 1 of constructing tunnel that its rear portion is suspended in tunnel top by hoist cable 25; The below of conveyer utilizes movable trestle 23 to carry out the cast-in-place making in basis of tunnel bottom inverted arch, and 26 for pouring into a mould the inverted arch basis of making, with belt conveyor space interference do not take place, and haulage vehicle passes through from movable trestle.In conjunction with Fig. 1, space interference does not take place with the lining cutting cycle operation of steel form chassis in belt conveyor 7 after by the movable trestle construction area, by being placed to before the steel form chassis 2 on the cast-in-place inverted arch basis of making 6 by steel form chassis 2; In steel form chassis lining cutting zone, the length that conveyer belt once is placed on the inverted arch base surface is about 300~400 meters, and the length that moves ahead once with the every circulation of lining cutting steel form chassis is consistent.Conveyer belt is by behind the steel form chassis 2, still belt conveyor 7 usefulness hoist cables 25 is suspended on tunnel top carrying out concrete-lined zone, so as keep transportation, can vehicle passage in, make the tunnel facilities such as gutter of the basic both sides of inverted arch.

Claims (1)

1, the arrangement of steel form chassis and belt conveyor in a kind of drilling and blasting method constructing tunnel, it is characterized in that: belt conveyor (7) front end of abandoning quarrel in order to continuous conveying excavation is positioned at the excavation working region, belt conveyor (7) by excavation working region to steel form chassis lining cutting zone is suspended on the top in tunnel by hoist cable (25), and is parallel with the air chimney (1) of constructing tunnel; The steel form chassis (2) that carries out permanent supporting lining cutting is positioned at movable trestle construction area rear portion and is positioned on the track that connects before circulation of both sides, tunnel itself; After being positioned at the movable trestle construction area, be that the belt conveyor (7) in the place ahead, lining cutting zone is caused ground downwards and is positioned on the cast-in-place inverted arch basis before the steel form chassis, belt conveyor (7) is positioned at a side of steel form chassis car door frame and be arranged in parallel with transport channel by steel form chassis (2) time; The belt conveyor (7) at steel form chassis (2) rear portion is suspended on the top in tunnel by hoist cable (25).
CNU2008201495177U 2008-10-06 2008-10-06 Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method Expired - Lifetime CN201284654Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201495177U CN201284654Y (en) 2008-10-06 2008-10-06 Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201495177U CN201284654Y (en) 2008-10-06 2008-10-06 Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method

Publications (1)

Publication Number Publication Date
CN201284654Y true CN201284654Y (en) 2009-08-05

Family

ID=40949639

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201495177U Expired - Lifetime CN201284654Y (en) 2008-10-06 2008-10-06 Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method

Country Status (1)

Country Link
CN (1) CN201284654Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383856A (en) * 2011-07-12 2012-03-21 中铁隧道集团二处有限公司 Transportation method for large-slope parallel adit construction
CN105378222A (en) * 2013-05-09 2016-03-02 Hyun工程建设株式会社 Method for reinforcing pillar part of adjacently constructed parallel tunnels with reinforcing rods and excavation method
CN106321116B (en) * 2015-06-15 2018-06-15 中国葛洲坝集团国际工程有限公司 A kind of tunnel is dug and the construction method of lining concrete parallel operations

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383856A (en) * 2011-07-12 2012-03-21 中铁隧道集团二处有限公司 Transportation method for large-slope parallel adit construction
CN105378222A (en) * 2013-05-09 2016-03-02 Hyun工程建设株式会社 Method for reinforcing pillar part of adjacently constructed parallel tunnels with reinforcing rods and excavation method
CN105378222B (en) * 2013-05-09 2017-03-22 Hyun工程建设株式会社 Method for reinforcing pillar part of adjacently constructed parallel tunnels with reinforcing rods and excavation method
CN106321116B (en) * 2015-06-15 2018-06-15 中国葛洲坝集团国际工程有限公司 A kind of tunnel is dug and the construction method of lining concrete parallel operations

Similar Documents

Publication Publication Date Title
CN101403305B (en) Construction method for tunnel continuous mucking, lining and excavation synchronization
CN101929341B (en) Construction method for TBM synchronization lining
CN201236704Y (en) Coal drift drill shipping and anchoring integrated machine
CN104213831B (en) A kind of roofboltier collecting colliery digging, supporting and transporting parallel sharp work
CN106437741B (en) A kind of New Austrian Tunneling Method rock tunnel(ling) machine
CN102493823B (en) Mine recyclable steel cylinder packing pier column and construction method thereof and method for gob-side entry retaining
CN104747199B (en) A kind of open type TBM with section of jurisdiction installation function
CN101769158A (en) Excavating, supporting and bolting integrated self-contained machine
CN201560771U (en) TBM (Tunnel Boring Machine) synchronous lining mould plate trolley and bench
CN204311971U (en) A kind ofly collect colliery digging, supporting and transport the roofboltier of parallel sharp work
CN207063985U (en) Open-type full-face rock ripper support system
CN107060795A (en) A kind of underground mine TBM assembly construction methods
CN201284653Y (en) Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by TBM method
CN109595022B (en) Thirteen-arm tunneling and anchoring integrated machine tunneling system for coal mine stoping roadway
CN101403302A (en) Pedrail type liftable anchor bar anchor cable construction drill rig and double-lane fast digging technique
CN112343617A (en) Automatic mine roadway tunneling system
CN103628893A (en) Drilling and blasting shield machine
CN201284654Y (en) Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by drilling explosion method
CN101302933A (en) Method for developing rock lane comprehensive mechanization developing operation
CN106437734B (en) The shape of a hoof shield excavating device and tunnel excavation method of anhydrous soft soil tunnel
CN101302932A (en) Method for underground chamber digging and laneway opening digging
CN110778320A (en) Synchronous excavation supporting construction method for three-step inverted arch of weak surrounding rock tunnel
CN112065492B (en) Synchronous operation rack for tunnel excavation construction and synchronous construction method
CN211648172U (en) Ten-arm tunneling and tracing machine
CN202810858U (en) Roadway heading machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20090805