CN201144528Y - Configuration structure of anode calcination shop and carbon block storeroom - Google Patents

Configuration structure of anode calcination shop and carbon block storeroom Download PDF

Info

Publication number
CN201144528Y
CN201144528Y CNU2007200156994U CN200720015699U CN201144528Y CN 201144528 Y CN201144528 Y CN 201144528Y CN U2007200156994 U CNU2007200156994 U CN U2007200156994U CN 200720015699 U CN200720015699 U CN 200720015699U CN 201144528 Y CN201144528 Y CN 201144528Y
Authority
CN
China
Prior art keywords
charcoal piece
anode
configuration structure
storehouse
carbon block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007200156994U
Other languages
Chinese (zh)
Inventor
明文雪
崔银河
梁和奎
尹良明
周生太
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Aluminum and Magnesium Engineering and Research Institute Co Ltd
Original Assignee
Shenyang Aluminum and Magnesium Engineering and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Aluminum and Magnesium Engineering and Research Institute Co Ltd filed Critical Shenyang Aluminum and Magnesium Engineering and Research Institute Co Ltd
Priority to CNU2007200156994U priority Critical patent/CN201144528Y/en
Application granted granted Critical
Publication of CN201144528Y publication Critical patent/CN201144528Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Solid Fuels And Fuel-Associated Substances (AREA)

Abstract

The utility model discloses a configuration structure for an anode calcining plant and a carbon block warehouse, in particular to a configuration structure for large-production anode calcining plant and carbon block warehouse. The configuration structure is as follows: the anode calcining plant and the carbon block warehouse are arranged in parallel; two calcining furnaces are arranged in a plant; the middle of the plant is provided with a corridor and the corridor is connected with the carbon block warehouse. At the same time, the corridor is provided with a transfer crane for clipping carbon blocks; the end part of the corridor is provided with a carbon block classifying device and a carbon block cleaning device; the calcining plant is provided with a multi-functional crane; the carbon block warehouse is provided with a stowing crane and other equipment. The utility model reduces the land use, saves the investment and ensures a more reasonable production layout.

Description

The configuration structure in anode-baking workshop and charcoal piece storehouse
Technical field
The utility model relates to the configuration structure in anode-baking workshop and charcoal piece storehouse, relates in particular to the configuration structure in a kind of big production capacity anode-baking workshop and charcoal piece storehouse.
Background technology
At present because the continuous increase of electrolytic aluminium factory production capacity, require the corresponding raising of production capacity of supporting anode factory.Along with the raising of anode factory production capacity, need to increase the quantity of anode-baking furnace and the storage area in charcoal piece storehouse, therefore need reasonable disposition anode-baking workshop and charcoal piece storehouse.Traditional approach is roasting workshop and vertical placement the in charcoal piece storehouse, and this kind configuration structure floor space is big, the equipment investment height, and production distribution is unreasonable.
The utility model content
Technical problem to be solved in the utility model provides the configuration structure in anode-baking workshop and charcoal piece storehouse, and purpose is to reduce land used, saves investment, and production distribution is rationalized more.
In order to achieve the above object, the utility model is achieved in that the configuration structure in anode-baking workshop and charcoal piece storehouse, and roasting workshop and charcoal piece storehouse are arranged in parallel, and two calcinating kilns are placed in the factory building, establish vestibule in the middle of the factory building of roasting workshop, vestibule links to each other with charcoal piece storehouse.
Charcoal piece waggon is set at described vestibule middle part and the transhipment overhead traveling crane carries out the gripping of charcoal piece.
Charcoal piece marshalling unit and charcoal piece cleaning unit are set in described vestibule end.
The quantity of described marshalling unit and cleaning unit is the 1-10 cover.
Described roasting workshop is provided with the roasting multifunction crane.
Described charcoal piece is provided with charcoal piece conveyer and stacking overhead travelling crane in the storehouse.
The quantity in described roasting workshop is 1-20.
Advantage of the present utility model and effect are as follows:
Owing to adopted above-mentioned allocation plan, the utility model has reduced land used, saves investment, and production distribution is rationalized more.
Description of drawings
Fig. 1 is the configuration structure schematic diagram in utility model anode-baking workshop and charcoal piece storehouse.
Among the figure, 1, the roasting workshop, 2, calcinating kiln, 3, charcoal piece storehouse, 4, vestibule, 5, stacking overhead travelling crane, 6, charcoal piece conveyer, 7, charcoal piece marshalling unit, 8, the transhipment overhead traveling crane, 9, charcoal piece waggon, 10, the roasting multifunction crane, 11, charcoal piece cleaning unit.
The specific embodiment
Below embodiment of the present utility model is described in detail in conjunction with the accompanying drawings, Figure 1 shows that the configuration structure in 4 anode-baking furnaces and charcoal piece storehouse, but protection domain of the present utility model is not limit by embodiment.
As shown in Figure 1, the configuration structure in anode-baking workshop and charcoal piece storehouse is as follows: roasting workshop 1 is arranged in parallel with charcoal piece storehouse 3, two calcinating kilns 2 are placed in the factory building, vestibule 4 is established in the centre, vestibule 4 links to each other with charcoal piece storehouse 3, charcoal piece waggon 9 is set in the vestibule 4 simultaneously, transhipment overhead traveling crane 8 carries out the transhipment of charcoal piece, and charcoal piece marshalling unit 7 and charcoal piece cleaning unit 11 are set in vestibule 4 ends; Be provided with roasting multifunction crane 10 in the roasting workshop 1; Establish equipment such as charcoal piece conveyer 6, stacking overhead travelling crane 5 in the charcoal piece storehouse 3.
The quantity of above-mentioned marshalling unit and cleaning unit is the 1-10 cover.The quantity in roasting workshop is 1-20.
Operational process of craft is as follows: give birth to the charcoal piece and put to charcoal piece conveyer 6 after by stacking overhead travelling crane 5 grippings, sending into charcoal piece marshalling unit 7 organizes into groups, charcoal piece marshalling back is put into the charcoal piece on the charcoal piece waggon 9 by transhipment overhead traveling crane 8, the charcoal piece is sent into roasting workshop 1 by charcoal piece waggon 9 and is carried out roasting, and the stove operation that takes on of charcoal piece is finished by roasting multifunction crane 10.Burning back charcoal piece is transported on the charcoal piece waggon 9 by multifunction crane 10, deliver to vestibule 4 ends, the charcoal piece that the charcoal piece is transported to is cleared up on the unit 11, carry out the cleaning of charcoal piece by transhipment overhead traveling crane 8, charcoal piece cleaning back is transported in the charcoal piece storehouse 3 by charcoal piece conveyer 6, carries out stacking by stacking overhead travelling crane 5 then and stores.

Claims (8)

1. the configuration structure in anode-baking workshop and charcoal piece storehouse, it is characterized in that roasting workshop (1) and charcoal piece storehouse (3) are arranged in parallel, two calcinating kilns (2) are placed in the factory building, establish vestibule (4) in the middle of the factory building of roasting workshop (1), and vestibule (4) links to each other with charcoal piece storehouse (3).
2, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse is characterized in that described vestibule (4) middle part is provided with charcoal piece waggon (9).
3, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse is characterized in that described vestibule (4) middle part is provided with transhipment overhead traveling crane (8) and carries out the gripping of charcoal piece.
4, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse is characterized in that in the end of described vestibule (4) charcoal piece marshalling unit (7) and charcoal piece being set clears up unit (11).
5, the configuration structure in anode-baking workshop according to claim 4 and charcoal piece storehouse, the quantity that it is characterized in that described marshalling unit (7) and cleaning unit (11) are the 1-10 cover.
6, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse, its feature is provided with roasting multifunction crane (10) in described roasting workshop (1).
7, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse is provided with charcoal piece conveyer (6), stacking overhead travelling crane (5) in the described charcoal piece of its feature storehouse (3).
8, the configuration structure in anode-baking workshop according to claim 1 and charcoal piece storehouse, the quantity that it is characterized in that described roasting workshop (1) are 1-20.
CNU2007200156994U 2007-11-06 2007-11-06 Configuration structure of anode calcination shop and carbon block storeroom Expired - Lifetime CN201144528Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200156994U CN201144528Y (en) 2007-11-06 2007-11-06 Configuration structure of anode calcination shop and carbon block storeroom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200156994U CN201144528Y (en) 2007-11-06 2007-11-06 Configuration structure of anode calcination shop and carbon block storeroom

Publications (1)

Publication Number Publication Date
CN201144528Y true CN201144528Y (en) 2008-11-05

Family

ID=40081402

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200156994U Expired - Lifetime CN201144528Y (en) 2007-11-06 2007-11-06 Configuration structure of anode calcination shop and carbon block storeroom

Country Status (1)

Country Link
CN (1) CN201144528Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102955443A (en) * 2011-08-30 2013-03-06 沈阳铝镁设计研究院有限公司 Interlocking system and interlocking control method of anode transport vehicle and roasting crown block
CN106315169A (en) * 2015-06-24 2017-01-11 沈阳铝镁设计研究院有限公司 An anode carbon block suspended chain conveying system
CN106315116A (en) * 2015-06-24 2017-01-11 沈阳铝镁设计研究院有限公司 Method for conveying anode carbon blocks used for aluminum
CN115573602A (en) * 2022-11-21 2023-01-06 河北鸿科碳素有限公司 Carbon anode roasting system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102955443A (en) * 2011-08-30 2013-03-06 沈阳铝镁设计研究院有限公司 Interlocking system and interlocking control method of anode transport vehicle and roasting crown block
CN102955443B (en) * 2011-08-30 2015-07-22 沈阳铝镁设计研究院有限公司 Interlocking system and interlocking control method of anode transport vehicle and roasting crown block
CN106315169A (en) * 2015-06-24 2017-01-11 沈阳铝镁设计研究院有限公司 An anode carbon block suspended chain conveying system
CN106315116A (en) * 2015-06-24 2017-01-11 沈阳铝镁设计研究院有限公司 Method for conveying anode carbon blocks used for aluminum
CN106315169B (en) * 2015-06-24 2018-11-27 沈阳铝镁设计研究院有限公司 A kind of anode carbon block Cantenary suspension conveying system
CN106315116B (en) * 2015-06-24 2019-01-15 沈阳铝镁设计研究院有限公司 A kind of method of aluminium anode carbon block conveying
CN115573602A (en) * 2022-11-21 2023-01-06 河北鸿科碳素有限公司 Carbon anode roasting system

Similar Documents

Publication Publication Date Title
CN201144528Y (en) Configuration structure of anode calcination shop and carbon block storeroom
CN105509465B (en) A kind of roller kilns automatically transporting materials device
CN203048134U (en) Multiple flower basket feeding and blanking table
CN107188165B (en) Large-scale portable graphitization system
CN205837011U (en) A kind of abandoned car disassembles line
CN205998631U (en) Automatically kiln mechanical hand is unloaded in loading of kiln
CN204844171U (en) Aluminum alloy ingot casting pile machinery hand
CN202245929U (en) Hoister
CN207877812U (en) A kind of aluminium alloy secondary time effect heat treatment system
CN202380029U (en) Logistics system for charging of electric furnace in electric furnace smelting
CN202864836U (en) Heat preservation building block carrying trolley
CN101397680A (en) Arrangement mode for anode roasting workshop and carbon block room
CN207026864U (en) Pipeline
CN2931675Y (en) Disposition structure of workshop for producing anode used for electrolyzing aluminum
CN104228905B (en) A kind of round table transport trolley
CN207433529U (en) A kind of ceramic blank dries kiln car
CN206300469U (en) A kind of submerged arc furnace system
CN204823273U (en) Aluminum alloy ingot casting pile sideslip device
CN206478986U (en) A kind of utilization sheet billet continuous casting waste heat dries the device of iron scale
CN207932968U (en) A kind of architectural engineering brick lifting device
CN206244714U (en) A kind of suspension type charcoal continuous firing system for being easy to transport
CN207226925U (en) A kind of iris type ball hydraulic elevating platform
CN207468039U (en) Complete non-maintaining simple and easy hoisting system manually
CN206064847U (en) A kind of online pipeline visual inspection sorting line
CN207417861U (en) A kind of strength unloads brick clamp disk

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jinan Haichuan Investment Group Co., Ltd.

Assignor: Shenyang Aluminium and Magnesium Design Institute

Contract record no.: 2010370000281

Denomination of utility model: Configuration structure of anode calcination shop and carbon block storeroom

Granted publication date: 20081105

License type: Exclusive License

Record date: 20100521

C56 Change in the name or address of the patentee

Owner name: SHENYANG ALUMINUM + MAGNESIUM ENGINEERING + RESEAR

Free format text: FORMER NAME: SHENYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP01 Change in the name or title of a patent holder

Address after: 110001 Heping Street, Heping District, Liaoning, Shenyang, No. 184

Patentee after: Shenyang Aluminum & Magnesium Engineering & Research Institute Co., Ltd.

Address before: 110001 Heping Street, Heping District, Liaoning, Shenyang, No. 184

Patentee before: Shenyang Aluminium and Magnesium Design Institute

CX01 Expiry of patent term