CN207877812U - A kind of aluminium alloy secondary time effect heat treatment system - Google Patents

A kind of aluminium alloy secondary time effect heat treatment system Download PDF

Info

Publication number
CN207877812U
CN207877812U CN201820124309.5U CN201820124309U CN207877812U CN 207877812 U CN207877812 U CN 207877812U CN 201820124309 U CN201820124309 U CN 201820124309U CN 207877812 U CN207877812 U CN 207877812U
Authority
CN
China
Prior art keywords
aging
aging furnace
furnace
heat treatment
flat car
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820124309.5U
Other languages
Chinese (zh)
Inventor
吴先志
王东明
何木生
周景兰
周友斌
吴隆
刘瑰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHIZHOU JIUHUA MINGKUN ALUMINUM INDUSTRY Co Ltd
Original Assignee
CHIZHOU JIUHUA MINGKUN ALUMINUM INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHIZHOU JIUHUA MINGKUN ALUMINUM INDUSTRY Co Ltd filed Critical CHIZHOU JIUHUA MINGKUN ALUMINUM INDUSTRY Co Ltd
Priority to CN201820124309.5U priority Critical patent/CN207877812U/en
Application granted granted Critical
Publication of CN207877812U publication Critical patent/CN207877812U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat Treatments In General, Especially Conveying And Cooling (AREA)

Abstract

本实用新型属于铝型材热处理设备技术领域,具体涉及一种铝合金二级时效热处理系统,包括设置在地面上的并排设置的第一时效炉和第二时效炉,第一时效炉入口正对设置有备料台,第二时效炉入口正对设置有冷却台,平车滑轨横向布置在地面上,位于第一时效炉与备料台之间位置,平车滑轨设置有电动平车,电动平车能够沿着平车滑轨横向移动,从而切换与第一时效炉、第二时效炉、备料台和冷却台之间的对接;第一时效炉的炉腔底面、第二时效炉的炉腔底面、电动平车上表面、备料台和冷却台上均设置有纵向设置的小车滑轨,输送小车能够在小车滑轨上移动,本实用新型能够实现快捷方便地二级时效处理。

The utility model belongs to the technical field of heat treatment equipment for aluminum profiles, and in particular relates to a secondary aging heat treatment system for aluminum alloys, which includes a first aging furnace and a second aging furnace arranged side by side on the ground, and the entrance of the first aging furnace is set directly opposite There is a material preparation platform, and a cooling platform is installed directly opposite the entrance of the second aging furnace. The car can move laterally along the slide rail of the flat car to switch the docking with the first aging furnace, the second aging furnace, the preparation table and the cooling table; the bottom surface of the furnace cavity of the first aging furnace and the furnace cavity of the second aging furnace The bottom surface, the upper surface of the electric flat car, the material preparation platform and the cooling platform are all provided with longitudinally arranged trolley slide rails, and the conveying trolley can move on the trolley slide rails. The utility model can realize quick and convenient secondary aging treatment.

Description

一种铝合金二级时效热处理系统A secondary aging heat treatment system for aluminum alloy

技术领域technical field

本实用新型属于铝型材热处理设备技术领域,具体涉及一种铝合金二级时效热处理系统。The utility model belongs to the technical field of heat treatment equipment for aluminum profiles, in particular to a secondary aging heat treatment system for aluminum alloys.

背景技术Background technique

现有技术中,铝型材的时效处理往往是一级时效,其只需要一个时效炉即可,但是针对部分需要二级时效的铝型材,单个时效炉处理起来不便,一次时效后不仅要等待铝型材冷却才能进行二次时效,另外,两次时效条件不同,还得调节多种参数,这样就降低了时效的效率;虽然分开用两个时效炉能够提高效率,但铝型材的转运比较麻烦。In the prior art, the aging treatment of aluminum profiles is usually primary aging, which only requires one aging furnace. However, for some aluminum profiles that require secondary aging, it is inconvenient to handle with a single aging furnace. The secondary aging can only be carried out after the profile is cooled. In addition, the two aging conditions are different, and various parameters have to be adjusted, which reduces the efficiency of aging; although the efficiency can be improved by using two aging furnaces separately, the transfer of aluminum profiles is more troublesome.

实用新型内容Utility model content

本实用新型所要解决的技术问题是,如何能够方便快捷地实现铝型材的二级时效处理。The technical problem to be solved by the utility model is how to conveniently and quickly realize the secondary aging treatment of aluminum profiles.

本实用新型所采取的技术方案是:一种铝合金二级时效热处理系统,包括设置在地面上的并排设置的第一时效炉和第二时效炉,第一时效炉入口正对设置有备料台,第二时效炉入口正对设置有冷却台,平车滑轨横向布置在地面上,位于第一时效炉与备料台之间位置,平车滑轨设置有电动平车,电动平车能够沿着平车滑轨横向移动,从而切换与第一时效炉、第二时效炉、备料台和冷却台之间的对接;第一时效炉的炉腔底面、第二时效炉的炉腔底面、电动平车上表面、备料台和冷却台上均设置有纵向设置的小车滑轨,输送小车能够在小车滑轨上移动。The technical solution adopted by the utility model is: a secondary aging heat treatment system for aluminum alloy, including the first aging furnace and the second aging furnace arranged side by side on the ground, and the entrance of the first aging furnace is directly opposite to the material preparation platform , the entrance of the second aging furnace is directly opposite to the cooling platform, and the flat car slide rail is arranged horizontally on the ground, between the first aging furnace and the material preparation platform, and the flat car slide rail is equipped with an electric flat car, which can move along the The slide rail of the flat car moves horizontally, so as to switch the docking with the first aging furnace, the second aging furnace, the preparation table and the cooling table; the bottom surface of the furnace cavity of the first aging furnace, the bottom surface of the second aging furnace, the electric The upper surface of the flat car, the material preparation platform and the cooling platform are all provided with longitudinally arranged trolley slide rails, and the conveying trolley can move on the trolley slide rails.

进一步地,所述的第一时效炉与第二时效炉结构相同,其入口设置有升降门,其入口上部设置有用于承重升降门的冂形架,冂形架两侧固定有油缸,油缸的活塞杆末端连接升降门上的连接板。Further, the structure of the first aging furnace and the second aging furnace is the same, its entrance is provided with a lifting door, and the upper part of the entrance is provided with a vertical frame for bearing the lifting door, and oil cylinders are fixed on both sides of the vertical frame. The end of the piston rod is connected to the connecting plate on the lift gate.

进一步地,所述的升降门的底部设置有与第一时效炉内小车滑轨截面相同的缺口,升降门下降时,缺口与小车滑轨配合。Further, the bottom of the lifting door is provided with a gap having the same section as the trolley slide rail in the first aging furnace. When the lifting door descends, the gap matches the trolley slide rail.

进一步地,所述的冷却台上部设置有抽风装置。Further, a ventilation device is provided on the upper part of the cooling platform.

进一步地,所述的输送小车为电控的,其电机连接PLC控制器,电动平车、油缸的电磁阀均连接PLC控制器。Further, the conveying trolley is electronically controlled, its motor is connected to a PLC controller, and the solenoid valves of the electric flat car and the oil cylinder are all connected to the PLC controller.

本实用新型的有益效果是:本实用新型所述一种铝合金二级时效热处理系统,能够实现铝型材在各时效炉之间以及在时效炉与冷却台之间快速的运转,当通过PLC控制时,能够实现半自动化,节省人力,提高效率。The beneficial effects of the utility model are: the secondary aging heat treatment system for aluminum alloy described in the utility model can realize the rapid operation of aluminum profiles between aging furnaces and between aging furnaces and cooling platforms. At the same time, it can realize semi-automation, save manpower and improve efficiency.

附图说明Description of drawings

图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;

图2为第一时效炉升降门结构示意图。Fig. 2 is a structural schematic diagram of the lift door of the first aging furnace.

具体实施方式Detailed ways

下面结合附图对本实用新型的具体实施方式进行详细说明。The specific embodiment of the utility model will be described in detail below in conjunction with the accompanying drawings.

如图1和图2所示的一种铝合金二级时效热处理系统,包括设置在地面1上的并排设置的第一时效炉21和第二时效炉22,第一时效炉21入口正对设置有备料台51,第二时效炉22入口正对设置有冷却台52,平车滑轨31横向布置在地面上,位于第一时效炉21与备料台51之间位置,平车滑轨31设置有电动平车32,电动平车32能够沿着平车滑轨31横向移动,从而切换与第一时效炉21、第二时效炉22、备料台51和冷却台52之间的对接;第一时效炉21的炉腔底面、第二时效炉22的炉腔底面、电动平车32上表面、备料台51和冷却台52上均设置有纵向设置的小车滑轨,输送小车4能够在小车滑轨上移动。A secondary aging heat treatment system for aluminum alloys as shown in Figures 1 and 2, includes a first aging furnace 21 and a second aging furnace 22 arranged side by side on the ground 1, and the entrance of the first aging furnace 21 is arranged opposite There is a material preparation platform 51, and a cooling platform 52 is provided facing the entrance of the second aging furnace 22. The flat car slide rail 31 is arranged horizontally on the ground, and is located between the first aging furnace 21 and the material preparation platform 51. The flat car slide rail 31 is set There is an electric flat car 32, and the electric flat car 32 can move laterally along the flat car slide rail 31, thereby switching between the first aging furnace 21, the second aging furnace 22, the stock preparation platform 51 and the cooling platform 52; the first The furnace cavity bottom surface of the aging furnace 21, the furnace cavity bottom surface of the second aging furnace 22, the upper surface of the electric flat car 32, the material preparation platform 51 and the cooling platform 52 are all provided with vertically arranged trolley slide rails, and the conveying trolley 4 can slide on the trolley. move on rails.

所述的第一时效炉21和第二时效炉22可以为电加热或是燃气加热,其加热方案、循环方案采用现有技术中的技术即可;电动平车32和输送小车4采用现有技术中即可,其中电动平车属于成熟的技术,应用广泛;而输送小车4可以看做是电动平车设置有供铝型材堆放的架体构成。The first aging furnace 21 and the second aging furnace 22 can be electric heating or gas heating, and its heating scheme and circulation scheme can adopt the technology in the prior art; The electric flat car is a mature technology and widely used; and the conveying trolley 4 can be regarded as an electric flat car equipped with a frame for stacking aluminum profiles.

所述的第一时效炉21与第二时效炉22结构相同,其入口设置有升降门23,其入口上部设置有用于承重升降门23的冂形架25,冂形架25两侧固定有油缸24,油缸24的活塞杆末端连接升降门23上的连接板231。The first aging furnace 21 has the same structure as the second aging furnace 22, and its entrance is provided with a lifting door 23, and the upper part of the entrance is provided with a vertical frame 25 for the load-bearing lifting door 23, and oil cylinders are fixed on both sides of the vertical frame 25 24. The end of the piston rod of the oil cylinder 24 is connected to the connecting plate 231 on the lifting door 23.

所述的升降门23的底部设置有与第一时效炉21内小车滑轨211截面相同的缺口,升降门23下降时,缺口与小车滑轨211配合。The bottom of the lift gate 23 is provided with a gap that has the same section as the trolley slide rail 211 in the first aging furnace 21, and when the lift gate 23 descends, the gap matches the trolley slide rail 211.

所述的冷却台52上部设置有抽风装置522。The upper part of the cooling table 52 is provided with a draft device 522 .

所述的输送小车4为电控的,其电机连接PLC控制器,电动平车32、油缸24的电磁阀均连接PLC控制器。The conveying trolley 4 is electronically controlled, its motor is connected to the PLC controller, and the solenoid valves of the electric flat car 32 and the oil cylinder 24 are all connected to the PLC controller.

本实用新型工作时,输送小车4首先在备料台51上备料,将需要进行时效处理的铝型材放置在输送小车4,完毕后,电动平车32移动至第一时效炉21与备料台51之间,备料台小车滑轨511、电动平车小车滑轨321和第一时效炉小车滑轨211共线,输送小车4通过小车滑轨可以移动至第一时效炉21中;在第一时效炉21中完成预时效后,打开升降门23,输送小车4转移至冷却冷却台52处冷却,当电动平车32移动至第二时效炉22与冷却台52之间时,第二时效炉小车滑轨221、电动平车小车滑轨321与冷却台小车滑轨521共线;当冷却完毕后且第二时效炉22完成上一次处理后,输送小车4转移至第二时效炉22,完成二级时效后,转移至冷却台52冷却,冷却后卸料或运至他处。When the utility model works, the conveying trolley 4 first prepares materials on the material preparation platform 51, and the aluminum profiles that need aging treatment are placed on the conveying trolley 4. After the completion, the electric flat car 32 moves to between the first aging furnace 21 and the material preparation platform 51. During the period, the trolley slide rail 511 of the preparation platform, the trolley slide rail 321 of the electric flat car and the trolley slide rail 211 of the first aging furnace are collinear, and the conveying trolley 4 can be moved to the first aging furnace 21 through the trolley slide rail; in the first aging furnace After completing the pre-aging in 21, open the lifting door 23, and transfer the conveying trolley 4 to the cooling stage 52 for cooling. When the electric flat car 32 moves between the second aging furnace 22 and the cooling stage 52, the second aging furnace trolley slides Rail 221, electric flat car trolley slide rail 321 and cooling table trolley slide rail 521 are collinear; After cooling is completed and after the second aging furnace 22 finishes the last treatment, the conveying trolley 4 is transferred to the second aging furnace 22 to complete the secondary aging furnace 22. After aging, it is transferred to the cooling table 52 for cooling, and then unloaded or transported to other places after cooling.

以上显示和描述了本实用新型的基本原理、主要特征和本实用新型的优点。本实用新型不受上述实施例的限制,上述实施例和说明书中描述的只是说明本实用新型的原理,在不脱离本实用新型精神和范围的前提下本实用新型还会有各种变化和改进,这些变化和改进都落入要求保护的本实用新型的范围内。本实用新型要求保护范围由所附的权利要求书及其等同物界定。The basic principles, main features and advantages of the present utility model have been shown and described above. The utility model is not limited by the above-mentioned embodiments, and what is described in the above-mentioned embodiments and the description only illustrates the principle of the utility model, and the utility model also has various changes and improvements without departing from the spirit and scope of the utility model , these changes and improvements all fall within the scope of the claimed utility model. The scope of protection required by the utility model is defined by the appended claims and their equivalents.

Claims (5)

1.一种铝合金二级时效热处理系统,其特征在于,包括设置在地面(1)上的并排设置的第一时效炉(21)和第二时效炉(22),第一时效炉(21)入口正对设置有备料台(51),第二时效炉(22)入口正对设置有冷却台(52),平车滑轨(31)横向布置在地面上,位于第一时效炉(21)与备料台(51)之间位置,平车滑轨(31)设置有电动平车(32),电动平车(32)能够沿着平车滑轨(31)横向移动,从而切换与第一时效炉(21)、第二时效炉(22)、备料台(51)和冷却台(52)之间的对接;第一时效炉(21)的炉腔底面、第二时效炉(22)的炉腔底面、电动平车(32)上表面、备料台(51)和冷却台(52)上均设置有纵向设置的小车滑轨,输送小车(4)能够在小车滑轨上移动。1. A secondary aging heat treatment system for aluminum alloy, characterized in that it comprises a first aging furnace (21) and a second aging furnace (22) arranged side by side on the ground (1), the first aging furnace (21 ) is provided with a material preparation platform (51) opposite to the entrance, and a cooling platform (52) is provided directly opposite to the entrance of the second aging furnace (22). ) and the material preparation platform (51), the flat car slide rail (31) is provided with an electric flat car (32), and the electric flat car (32) can move laterally along the flat car slide rail (31), thereby switching to the first The docking between the first aging furnace (21), the second aging furnace (22), the material preparation table (51) and the cooling table (52); the bottom surface of the first aging furnace (21), the second aging furnace (22) The bottom surface of the furnace cavity, the upper surface of the electric flat car (32), the material preparation platform (51) and the cooling platform (52) are all provided with vertically arranged dolly slide rails, and the conveying trolley (4) can move on the dolly slide rails. 2.如权利要求1所述的一种铝合金二级时效热处理系统,其特征在于,所述的第一时效炉(21)与第二时效炉(22)结构相同,其入口设置有升降门(23),其入口上部设置有用于承重升降门(23)的冂形架(25),冂形架(25)两侧固定有油缸(24),油缸(24)的活塞杆末端连接升降门(23)上的连接板(231)。2. A secondary aging heat treatment system for aluminum alloy according to claim 1, characterized in that, the first aging furnace (21) has the same structure as the second aging furnace (22), and the entrance is provided with a lifting door (23), the upper part of the entrance is provided with a vertical frame (25) for the load-bearing lifting door (23), and an oil cylinder (24) is fixed on both sides of the vertical frame (25), and the end of the piston rod of the oil cylinder (24) is connected to the lifting door Connecting plate (231) on (23). 3.如权利要求2所述的一种铝合金二级时效热处理系统,其特征在于,所述的升降门(23)的底部设置有与第一时效炉(21)内小车滑轨(211)截面相同的缺口,升降门(23)下降时,缺口与小车滑轨(211)配合。3. A secondary aging heat treatment system for aluminum alloy according to claim 2, characterized in that, the bottom of the lifting door (23) is provided with a slide rail (211) that is connected to the trolley in the first aging furnace (21) For the same gap in section, when the lift gate (23) descends, the gap cooperates with the dolly slide rail (211). 4.如权利要求1所述的一种铝合金二级时效热处理系统,其特征在于,所述的冷却台(52)上部设置有抽风装置(522)。4 . The secondary aging heat treatment system for aluminum alloy according to claim 1 , characterized in that, an exhaust device ( 522 ) is arranged on the upper part of the cooling table ( 52 ). 5.如权利要求1所述的一种铝合金二级时效热处理系统,其特征在于,所述的输送小车(4)为电控的,其电机连接PLC控制器,电动平车(32)、油缸(24)的电磁阀均连接PLC控制器。5. A two-stage aging heat treatment system for aluminum alloy according to claim 1, characterized in that, the conveying trolley (4) is electronically controlled, its motor is connected to a PLC controller, and the electric flat trolley (32), The solenoid valves of the oil cylinders (24) are all connected to the PLC controller.
CN201820124309.5U 2018-01-25 2018-01-25 A kind of aluminium alloy secondary time effect heat treatment system Expired - Fee Related CN207877812U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820124309.5U CN207877812U (en) 2018-01-25 2018-01-25 A kind of aluminium alloy secondary time effect heat treatment system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820124309.5U CN207877812U (en) 2018-01-25 2018-01-25 A kind of aluminium alloy secondary time effect heat treatment system

Publications (1)

Publication Number Publication Date
CN207877812U true CN207877812U (en) 2018-09-18

Family

ID=63508353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820124309.5U Expired - Fee Related CN207877812U (en) 2018-01-25 2018-01-25 A kind of aluminium alloy secondary time effect heat treatment system

Country Status (1)

Country Link
CN (1) CN207877812U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108103294A (en) * 2018-01-25 2018-06-01 池州市九华明坤铝业有限公司 A kind of aluminium alloy secondary time effect heat treatment system
CN112725565A (en) * 2020-12-28 2021-04-30 云南爱家铝业有限公司 High-strength aluminum alloy heat treatment aging furnace and treatment method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108103294A (en) * 2018-01-25 2018-06-01 池州市九华明坤铝业有限公司 A kind of aluminium alloy secondary time effect heat treatment system
CN112725565A (en) * 2020-12-28 2021-04-30 云南爱家铝业有限公司 High-strength aluminum alloy heat treatment aging furnace and treatment method

Similar Documents

Publication Publication Date Title
CN104513890B (en) Circulating efficient Q-tempering equipment
CN206447906U (en) Between a kind of portable slow cooling
CN105499476A (en) A vacuum insulation induction heating furnace for forging
CN108103294A (en) A kind of aluminium alloy secondary time effect heat treatment system
CN206763644U (en) A kind of roller flatteningl roller levelling device
CN218876352U (en) Autoclave efficiency lifting mechanism
CN205192224U (en) Balanced stable form platform truck resistance furnace of low temperature
CN211142094U (en) Single-frame hot rolling continuous pickling annealing device
CN103642993A (en) Improved aluminium profile aging furnace
CN105506243B (en) An online quenching system and process
CN211254100U (en) Compound lifting feeding system
CN205481002U (en) Lifting double kang surface cremation machine
CN209906839U (en) Vacuum furnace for processing die-casting die
CN205341797U (en) A vacuum insulation induction heating furnace for forging
CN203429216U (en) Suspension type hub quenching furnace
CN208038491U (en) Metal casting solid-solution and aging heat treatment device
CN203112868U (en) After-heat-usable roller-type quick cooling furnace
CN207347620U (en) A kind of energy-efficient Whole fiber car-type vacuum annealing furnace of automatic intelligent
CN210692336U (en) Table top for automatic stacking of ultra-high voltage iron cores
CN211147316U (en) Hydrogen Annealing Furnace
CN211712951U (en) A kind of aviation transparent material thermal processing molding equipment
CN211218044U (en) A device for stacking intermediate billets in continuous strip rolling line
CN207525290U (en) A kind of annealing furnace aluminium handler
CN206635232U (en) A kind of vacuum glass is vertical to vacuumize furnace apparatus
CN209619416U (en) A solid melting furnace for the production of aluminum alloy parts

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Two-stage aging heat treatment system for aluminum alloy

Effective date of registration: 20190710

Granted publication date: 20180918

Pledgee: Chizhou Jiuhua Rural Commercial Bank Co.,Ltd.

Pledgor: CHIZHOU JIUHUA MINGKUN ALUMINUM Co.,Ltd.

Registration number: 2019340000382

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20200528

Granted publication date: 20180918

Pledgee: Chizhou Jiuhua Rural Commercial Bank Co.,Ltd.

Pledgor: CHIZHOU JIUHUA MINGKUN ALUMINUM Co.,Ltd.

Registration number: 2019340000382

PC01 Cancellation of the registration of the contract for pledge of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180918

CF01 Termination of patent right due to non-payment of annual fee