CN201024366Y - Reinforced concrete pavement component - Google Patents

Reinforced concrete pavement component Download PDF

Info

Publication number
CN201024366Y
CN201024366Y CNU2006201174459U CN200620117445U CN201024366Y CN 201024366 Y CN201024366 Y CN 201024366Y CN U2006201174459 U CNU2006201174459 U CN U2006201174459U CN 200620117445 U CN200620117445 U CN 200620117445U CN 201024366 Y CN201024366 Y CN 201024366Y
Authority
CN
China
Prior art keywords
concrete
pavement
concrete block
component
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2006201174459U
Other languages
Chinese (zh)
Inventor
马俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2006201174459U priority Critical patent/CN201024366Y/en
Application granted granted Critical
Publication of CN201024366Y publication Critical patent/CN201024366Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

A reinforced concrete pavement component comprises square or rectangular concrete blocks with a prepared width below six-meter, which can be paved, combined and extends into a pavement. The utility model is characterized in that: the component also comprises a removable lifting device, a concrete saving device, an anti-displacement device, a fill-joints device and a rainwater collecting device; the component has the advantages of strong self strength, long service life, flat pavement, smooth water discharge, convenient maintenance and replacement, and resources saving. The component transfers the construction of pavement from road site to a preparation site, so the pavement can pass through immediately after being paved, and the sinking and displacement of component caused by sunk road bases can be timely repaired and the damaged components can be timely replaced, thus shortening the working period of road construction and maintenance, furthermore, the components with exploitation value can also be repeatedly used. The utility model is very suitable for paving urban roads and squares with underground pipes and floors of large buildings, thus fully developing the advantages of durability of reinforced concrete.

Description

A kind of reinforced concrete pavement member
Affiliated technical field
The utility model relates to a kind of reinforced concrete pavement member that is used for road, and the laying that also can be used for ground in square and the building is used.
Background technology
At present, employed road concrete road surface, most with plain concrete (or carry out steel reinforcing to the part) cast in situs, use and maintenance process in, have following deficiency: the one, construct (maintenance), the maintenance time is long.During build at the scene the rigid pavement, except that getting the raw materials ready, building, also must after certain maintenance time, just can be delivered for use; In to the maintenance process that well damage road surfaces such as fracture, fragmentation, depression, faulting of slab ends occur, need to remove the road surface damaged, get the raw materials ready and build, same, need still that the maintenance time of length could recover to pass through.The 2nd, the plain concrete road surface is damaged easily.Because its flexural tensile strength of plain concrete is far below compressive strength, in actual use, be difficult to bear because of basic unit, bed course and roadbed variation (generation differential settlement) with from the multiple factors such as weight in the vehicle pass-through, cause the road surface fracture, fragmentation, depression, faulting of slab ends etc. to occur and damage phenomenon, especially the weakness of plain concrete is not overcome in pavement construction, improve the intensity on road surface by thickness and the raising strength grade of concrete that increases the plain concrete road surface, once damage, will be bigger waste.The 3rd, the plain concrete road surface can not be reused.After build at the scene on the plain concrete road surface, can only disposablely use, particularly road change its course or pavement of road under engineering (sewer, underground pipeline) when construction, the way of repairing again after have to discarding or excavate, can not repeat to continue to use to intact rigid pavement, not only increase difficulty of construction and expense, and produced more building waste.The 4th, the easy ponding in the road surface in city makes troubles for driving, pedestrian.In the cast in situs of the rigid pavement in city,, when rainy, always form ponding not of uniform size between two catch-basins though be provided with catch-basin at regular intervals.
In addition, also useful plain concrete prefabricated section is made the top course on sub-district road and sidewalk, but the insufficient strength of whole factor concrete precast block and basic unit cannot stand travelling, parking of rainwater and vehicle, just occurs damaged after use soon.
Summary of the invention
The utility model is exactly in order to overcome the deficiency on existing road plain concrete road surface, provide that a kind of quality is good, long service life, evenness of road surface, can Fast Installation lay, can economize on resources again, reduce cost and can in time change, reusable reinforced concrete pavement member.
The technical scheme that its technical problem that solves the utility model adopts is: a kind of reinforced concrete pavement member, comprise the square or rectangle concrete block of width prefabricated below 6m, described concrete block tiles one by one to make up and extends into the road surface, it is characterized in that: further comprising dismountable hanging apparatus, saving concrete device, non-displacement device, seam filling device and rain collector
Described dismountable hanging apparatus: at the conical bore that is provided with " up-small and down-big " on the concrete block;
Described saving concrete device: by two-layer reinforcing bar up and down, described saving concrete device is to be arranged with concrete round cavity of a plurality of vertical savings and header between the two-layer reinforcing bar up and down at concrete block in the described concrete block;
Described non-displacement device: be two or more cone lug bosses to be arranged in the concrete block bottom;
Described seam filling device: described reinforced concrete pavement member also comprises the liner that thin type metal or nonmetals are made, and described concrete block is provided with the breach of lug boss in splicing place suitable for reading, and described liner places the slit between the concrete block;
Described rain collector: on the surface layer of member, be pressed with the circular arc or the square or V-arrangement catch basin that are no more than the 10mm degree of depth, and a plurality of above diameters gully-hole and header perforation between 2-50mm are arranged.
The beneficial effects of the utility model are: this member has that self intensity height, long service life, evenness of road surface, draining are unobstructed, convenient maintenance and replacement, the characteristics that economize on resources; This member is with the construction of supercrust, transferring to precasting yard by the road scene carries out, realized current while laying, and can in time repair Yin Luji basic unit and phenomenon such as member depression, faulting of slab ends occur making and change impaired member, road construction and maintenance duration have been shortened, and can also utilize the member that is worth to reuse to having, particularly suitable has the laying on ground in underground pipeline urban road and square and the building to use, and has given full play to the long-lived speciality of steel concrete.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is a schematic diagram of the present utility model.
Fig. 2 is the sectional structural map of the utility model A-A.
Fig. 3 is the sectional structural map of the utility model B-B.
Fig. 4 is the sectional structural map of the detachable hanging apparatus of the utility model.
Fig. 5 is the schematic diagram of detachable hanging apparatus of the present utility model " 7 " font cushion block.
Fig. 6 is a scheme of installation of the present utility model.
Fig. 7 is an embodiment schematic diagram of the present utility model.
Fig. 8 is another embodiment schematic diagram that the utility model changes drainage pattern.
Among the figure 1, concrete bodies, 2, two-layer up and down reinforcing bar, 3, the conical bore of " up-small and down-big ", 4, the suspension rod that has suspension hook (or suspension ring) " up-small and down-big ", 5, suspension rod tightening gong line, 6, suspension rod tightening Luo, 7, " 7 " font cushion block, 8, the breach that has lug boss, 9, the liner that thin type metal or nonmetals are made, 10, joint sealing material, 11, filler under the lifting hole(eyelet), 12, filler on the lifting hole(eyelet), 13, save concrete circle cavity, 14, the cone lug boss, 15, catch basin, 16, gully-hole, 17, header, 18, building, 19, the sidewalk, 20, kerbstone, 21, this member, 22, base course, 23, storm sewer, 24, greenbelt and lighting, R are the established angle between two members.
The specific embodiment
Requirement according to the construction road surface; square or the rectangle reinforced concrete pavement member of width prefabricated below 6m; on surface layer, be provided with many degree of depth and be not more than 10mm; spacing is not more than the cross-current tank of 20mm; the size of pressing member is reserved the conical bore 3 of 1-4 " up-small and down-big "; in vertical arrangement a plurality of diameters are set and are not more than member levels rebar spacing from the concrete circle of the saving of the difference that subtracts reinforcement cover cavity 13; the breach 8 that has lug boss is reserved on 1-4 suitable for reading limit at member; at the default two or more cone lug bosses 14 in member bottom; when estimating that two members are not or not same plane, establish established angle R between two members at a member or two members.
Add rain collector predetermined by in the element precast in roadside, in a side by the roadside, reserve vertical its diameter and be equal to or less than the header 17 of saving concrete circle cavity 13, on the surface layer of member, be pressed with the circular arc or the square or V-arrangement catch basin 15 that are no more than the 10mm degree of depth, and have a plurality of diameters gully-hole 16 between 2-50mm to connect with header 17.
Handling, installation.The 1-4 root is made the suspension rod 4 that has suspension hook (or suspension ring) " up-small and down-big " with iron and steel, insert respectively in the conical bore 3 of 1-4 " up-small and down-big " on the member body, " 7 " font cushion block 5 that the 1-4 pair is made by 2 blocks of above iron and steel inserts the conical bore 3 of " up-small and down-big " in the member bodies and has between the suspension rod 4 of suspension hook (or suspension ring) " up-small and down-big ", at most with degree of being inserted as again, and the suspension rod 4 that will have suspension hook (or suspension ring) " up-small and down-big " upwards lifts, suspension rod tightening Luo 6 rotates on suspension rod tightening gong line 5, make the suspension rod 4 that has suspension hook (or suspension ring) " up-small and down-big ", conical bore 3 threes of " up-small and down-big " on " 7 " font cushion block 5 and the member body tightening that coincide, upward use hawser at suspension hook (or suspension ring), member is placed on the transport vehicle of chock by crane; After transportation puts in place, by crane member being hung onto predetermined lateral has on the base course 22 of certain slope, its cone lug boss 14 enters the basic unit of base course under the effect of own wt, unscrew suspension rod tightening Luo 6 then, take out " 7 " font cushion block 5 and up-small and down-big " suspension rod 4; and under the conical bore 3 of " up-small and down-big " adds based on the lifting hole(eyelet) of sandstone filler 11, add after the tamping to the similar concrete lifting hole(eyelet) of member surface layer color and luster on filler 12, till putting down with the road surface.
In installing, the following mouth of a river of member header 17 is communicated with storm sewer 23 interfaces that are preset in base course 22 by the roadside member.
Extend into the road surface in the combination of tiling one by one of a plurality of members, the liner 9 that to make with thin type metal or nonmetals again, described liner 9 places the slit between the concrete block, also can put into the breach 8 that respectively carries lug boss by two members and be combined to form big up and down, a middle little breach, the joint sealing material 10 of filling pitch class with the road surface flat till.
In the embodiment of Fig. 7, be as the criterion with existing urban road, the utility model is used on the track in the middle of both sides building 18 and the sidewalk of both sides, when rainy, the rainwater on the middle track and the ground, sidewalk of both sides, by being located at many cross-current tanks on the utility model surface layer, import catch basin 15 respectively, flow at storm sewer 23 by the roadside through gully-hole 16 and header 17.
In another embodiment of the change drainage pattern of Fig. 8, at both sides building 18 inboard the utility model that directly use, by graticule division track (motor vehicle, bicycle and sidewalk), greenbelt and lighting 24 are established in the centre; When rainy, the rainwater on ground in the middle of road, by being located at many cross-current tanks on the utility model surface layer, flow to storm sewer 23 by building 18.This embodiment has and both makes things convenient for road construction, can more effectively utilize path resource again, guarantees that traffic is unobstructed.

Claims (1)

1. reinforced concrete pavement member, comprise the square or rectangle concrete block of width prefabricated below 6m, described concrete block tiles one by one to make up and extends into the road surface, it is characterized in that: further comprising dismountable hanging apparatus, saving concrete device, non-displacement device, seam filling device and rain collector
Described dismountable hanging apparatus: in the conical bore that is provided with " up-small and down-big " on the concrete block (3);
Described saving concrete device: by two-layer reinforcing bar up and down, described saving concrete device is to be arranged with the concrete circle of a plurality of vertical savings cavity (13) and header (17) up and down between the two-layer reinforcing bar at concrete block in the described concrete block;
Described non-displacement device: be two or more cone lug bosses (14) to be arranged in the concrete block bottom;
Described seam filling device: described reinforced concrete pavement member also comprises the liner (9) that thin type metal or nonmetals are made, described concrete block is provided with the breach (8) of lug boss in splicing place suitable for reading, and described liner (9) places the slit between the concrete block;
Described rain collector: on the surface layer of member, be pressed with the circular arc or the square or V-arrangement catch basin (15) that are no more than the 10mm degree of depth, and have a plurality of above diameters gully-hole (16) between 2-50mm to connect with header (17).
CNU2006201174459U 2006-06-02 2006-06-02 Reinforced concrete pavement component Expired - Fee Related CN201024366Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2006201174459U CN201024366Y (en) 2006-06-02 2006-06-02 Reinforced concrete pavement component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2006201174459U CN201024366Y (en) 2006-06-02 2006-06-02 Reinforced concrete pavement component

Publications (1)

Publication Number Publication Date
CN201024366Y true CN201024366Y (en) 2008-02-20

Family

ID=39098220

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2006201174459U Expired - Fee Related CN201024366Y (en) 2006-06-02 2006-06-02 Reinforced concrete pavement component

Country Status (1)

Country Link
CN (1) CN201024366Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102242537A (en) * 2010-11-29 2011-11-16 有利华建材(惠州)有限公司 Cyclically used temporary pavement platen, and method for paving temporary pavement therewith
CN104088207A (en) * 2014-06-27 2014-10-08 黑龙江省龙建路桥第四工程有限公司 Highway with shock absorption function and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102242537A (en) * 2010-11-29 2011-11-16 有利华建材(惠州)有限公司 Cyclically used temporary pavement platen, and method for paving temporary pavement therewith
CN104088207A (en) * 2014-06-27 2014-10-08 黑龙江省龙建路桥第四工程有限公司 Highway with shock absorption function and construction method thereof

Similar Documents

Publication Publication Date Title
CN100501004C (en) Reinforced concrete pavement member
CN109972659B (en) Novel municipal inspection well structure and construction method
CN103924525B (en) Urban interchange industrialization short-term precast assembly construction method
CN106567410A (en) New construction method of municipal road inspection well
CN105421571A (en) Sewer well and rainwater well construction process
CN111827149A (en) Bridge widening hinge structure and construction method
CN110438914A (en) Water tank culvert and its construction method are crossed on soft soil foundation
CN112228631A (en) Pipeline reinforcing system
LU501207B1 (en) Structure and method for reinforcing manhole cover anchored with existing road surface foundation by means of dowel bars
CN201024366Y (en) Reinforced concrete pavement component
CN201411713Y (en) Manhole of various kinds of pipe networks for urban roads having hole mouth reinforcing mechanism
CN212247917U (en) Combined box culvert for drainage of building site
CN205662948U (en) Cold area road surface manhole cover
CN110144784A (en) The town road and its construction method constructed based on prestressed concrete plate stake
CN214738600U (en) Bypass type drainage pipeline inspection well structure
CN214500241U (en) Pipeline reinforcing system
CN212128696U (en) Road bridge links up mixed light dirt road bed structure of section bubble
CN211522720U (en) Prefabricated pavement restoration modular structure
CN210657846U (en) Precast concrete road capable of collecting and draining water
CN210238174U (en) Old way transformation deep disease combined type micro pile reinforced structure
CN114592396A (en) Rapid permeable pavement
CN209636573U (en) A kind of assembled self-balancing channel design system
CN210163739U (en) Town road constructed based on prestressed concrete sheet piles
CN112095394A (en) Composite pavement with excellent drainage function and construction method thereof
CN217869790U (en) Precast block capable of quickly repairing pavement

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080220