CN106567410A - New construction method of municipal road inspection well - Google Patents

New construction method of municipal road inspection well Download PDF

Info

Publication number
CN106567410A
CN106567410A CN201610976992.0A CN201610976992A CN106567410A CN 106567410 A CN106567410 A CN 106567410A CN 201610976992 A CN201610976992 A CN 201610976992A CN 106567410 A CN106567410 A CN 106567410A
Authority
CN
China
Prior art keywords
inspection shaft
well
construction method
layer
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610976992.0A
Other languages
Chinese (zh)
Inventor
叶建兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENZHOU XINGYE MUNICIPAL CONSTRUCTION Co Ltd
Original Assignee
WENZHOU XINGYE MUNICIPAL CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENZHOU XINGYE MUNICIPAL CONSTRUCTION Co Ltd filed Critical WENZHOU XINGYE MUNICIPAL CONSTRUCTION Co Ltd
Priority to CN201610976992.0A priority Critical patent/CN106567410A/en
Publication of CN106567410A publication Critical patent/CN106567410A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Abstract

The invention discloses a new construction method of a municipal road inspection well. The method is characterized by comprising the following steps: 1) foundation pit soil of the inspection well is excavated; 2) the foundation is treated; 3) widened parts around the inspection well and empty parts between pipe foundations are treated for compaction and leveling; 4) the inspection well is built; and a bearing stratum is filled; 5) a water stabilization basic layer is paved; 6) an opening of the inspection well is temporarily and tightly covered by a wood cover or a steel plate; 7) a bottom layer in asphalt concrete is paved, leveled and rolled; 8) the bottom layer of the asphalt concrete paved around the inspection well is excavated out; 9) a reinforced concrete structural layer is cast at the reverse excavated part in situ; 10) a prefabricated well ring and a well lid are mounted; 11) an asphalt concrete surface layer is cast in situ; and 12) a road basic layer is covered for maintenance. The construction method can effectively reinforce the manual compaction and surface reinforcing treatment of the road foundation around the well to prevent the well periphery sedimentation and the well lid damage so as to achieve the effects of safety and beauty.

Description

The newly-built construction method of town road inspection shaft
Technical field
The present invention relates to urban road construction technical field, more specifically, it relates to a kind of town road inspection shaft Newly-built construction method.
Background technology
When road structure layer is constructed, underground pipe network and all kinds of inspection shafts have been completed in advance, are carrying out road foundation backfill When, because road roller cannot be rolled closely near well Zhou Jinhang, cause well Zhou Luji relax leakiness, road be open to traffic one section when Between after, the mass defect for occurring therewith is depression around inspection shaft, and manhole cover protrudes and loosens, so develop into inspection shaft week Purse seine shape cracking, well lid loosen damaged, well week pavement structure and the disease such as release, due to the breakage of various degrees, shadow The sound comfortableness and security for more causing great potential safety hazard, have impact on driving attractive in appearance.
With urban highway traffic net gradually form with it is perfect, due to increasing sharply and various factors for vehicular load Destruction, old city thoroughfare and urban road far can not meet needs.To the improvement project of old road It is stepped up.Depression around inspection shaft is damaged, it has also become one of main quality common diseasess of current town road.
The means of science how are adopted, depression around inspection shaft is eliminated, it is ensured that the use function of road and the design of road Service life, it has also become be engaged in the emphasis brainstorm subject of town road construction enterprises now.
The content of the invention
In view of the shortcomings of the prior art, it is an object of the invention to provide a kind of the newly-built of town road inspection shaft is applied Work method, the construction method can effectively strengthen the hand compaction to well periphery roadbed and facial consolidation process, it is to avoid well week Sedimentation and well lid are damaged, and reach safety effect attractive in appearance.
For achieving the above object, the invention provides following technical scheme:A kind of newly-built construction of town road inspection shaft Method, including following construction procedure:
1), inspection shaft pit earthwork excavate;
2), based process, the soil layer weak to inspection shaft foundation bottom process;
3), neutral gear position is processed between the part widened of inspection shaft periphery and pipeline foundation, tamp smooth;
4), build inspection shaft by laying bricks or stones, when pit shaft often builds high about 40-60cm by laying bricks or stones, i.e., to well Zhou Jinhang back-fillings in layers and tamp, form holding force Layer;
5), pit shaft built by laying bricks or stones rise under roadbase, then carry out cement treated material and pave;
6), inspection shaft well head wooden cover or steel plate covered tightly temporarily, and carry out the interim sign for burying front position;
7), carry out on cement treated material paving, flatten, rolling for bottom in bitumen concrete;
8), bottom in inspection shaft the periphery bitumen concrete of making dug out, excavate in well week 0.8-1.6 rice radiuses, below road surface Bottom in bitumen concrete in the range of 40cm;
9), it is anti-around inspection shaft well head dig position cast-in-situ reinforced concrete structure layer, inspection shaft well head periphery is reinforced;
10), prefabricated walling crib, well lid are installed, acted as a planted agent using masonry of cement mortar under walling crib;
11), to inspection shaft around, cast-in-place bitumen concrete superficial layer on bottom in bitumen concrete, until under road surface;
12), roadbase cover health.
The present invention is further arranged to:Step 1)The spy of bottom land pricker is included after construction, to the soft, hard of inspection shaft foundation bottom Reconnoitred.
The present invention is further arranged to:Step 2)The debris for removing well week are also included, bottom land is flattened;And in construction step Rapid 4)During also include removing widen the loose soil body and useless fragment of brick.
The present invention is further arranged to:Step 4)Middle supporting course placement in layers, often fills about 20cm and uses electric rammer Or artificial ramming machine is rammed repeatedly.
The present invention is further arranged to:Step 5)Middle pit shaft is built by laying bricks or stones after rising under roadbase, carries out compactness inspection.
The present invention is further arranged to:Step 5)Construction paves before cement treated material, in the lateral surface depth 15cm model of pit shaft Enclose one layer of malthoid isolated material of laying, step 9)Construction pour before reinforced concrete structure layer, pit shaft top surface lay one layer of malthoid every From material so that reinforced concrete structure layer pours rear and pit shaft and forms separation layer.
The present invention is further arranged to:Step 9)In work progress, inspection shaft well head and around anti-position of digging carry out steel Muscle pricks weldering, and, as cushion block, installation site is accurate, centering for the framework of steel reinforcement basis rest concrete or stone of installation forming;It is right again The anti-reinforcing bar for digging position carries out steel external mold supporting;Last concrete is poured.
The present invention is further arranged to:Step 10)In when under walling crib crouch cement mortar thickness be less than 2cm when, walling crib Under only acted as a planted agent using masonry of cement mortar;When the thickness of the cement mortar that crouches under walling crib is more than 2cm, what is exceeded should be mixed using microlith Solidifying soil pad is sleeping.
The present invention is further arranged to:Step 10)After implementing 3 days, treat that the mortar crouched under walling crib has certain intensity, then pacify Row's step 11)Implement.
The present invention is further arranged to:Step 11)The first brush sticking layer oil on bottom in bitumen concrete before implementing, then using C30 Or more concrete poured, casting process keeps speed of perfusion uniform, vibrating leakage is shaken cross to shake of uniformly avoid.
In sum, the invention has the advantages that:1)Economic benefit:The reinforced concrete of walling crib periphery is reinforced, it is contemplated that About 300 yuan/well of increase expense, calculates according to per kilometer of 80 well, increases about 24000 yuan of expense, if not consolidation process, is open to traffic After a period of time, because subgrade settlement is damaged, well curb well lid is damaged soon by external force to be needed to change, often about 450 yuan of set crib lid/ Well, considers further that is abolished in the damaged road surface cutting of well week and carry out again road surface and repair, it is contemplated that every well also needs about 600 yuan, per of increase expense The later stage that well is caused repairs and is once accomplished by 1050 yuan/well, and total about 80*1050=84000 is first for expense;Walling crib is changed after repairing, Run through a period of time, repairing even multiple for the second time may be there is also, cause larger manpower and materials to waste, society Can affect also worse, so, disposably the economic benefit that walling crib consolidation process is received is also apparent from.2)Social benefit:It is newly-built Road was open to traffic after operation a period of time, and due to the reason such as vehicular load and road settlement, walling crib surrounding road occurs Different degrees of sedimentation or road surface radioactivity is ftractureed, and has both affected attractive in appearance, more cause driving to jump the unsafe factors such as car, by well The compacting of circle periphery roadbed and reinforce, it is to avoid above-mentioned common quality defect, receive good social benefit.
Description of the drawings
Fig. 1 is cast-in-situ reinforced concrete structure figure around inspection shaft.
Reference:1st, pit shaft;2nd, supporting course;3rd, roadbase;31st, bottom in bitumen concrete;32nd, bitumen concrete superficial layer; 4th, cement treated material;5th, reinforced concrete structure layer;6th, walling crib;7th, well lid.
Specific embodiment
With reference to the accompanying drawings and examples, the present invention is described in more detail.Wherein identical parts identical Reference is represented.It should be noted that word "front", "rear", "left", "right", the "up" and "down" used in describing below The direction in accompanying drawing is referred to, word " bottom surface " and " top surface ", " interior " and " outward " are referred respectively to towards or away from particular elements The direction of geometric center.
With reference to shown in Fig. 1, a kind of newly-built construction method of town road inspection shaft, its key points for operation are included:
1st, material prepares
Engineering material requested is got all the ready according to schedule substantially before construction, including Commercial Concrete is ordered, reinforcing bar is pricked and is welded into that type is standby, finished product Steel fibre crib lid and construction auxiliary material etc..
2nd, scene prepares
1)Job site water, with electrically connecting, while preparing night illumination facility;
2)Site road is unimpeded, and construction site answers smooth solid, to meet construction machinery job requirements.
3)Select the storage space of anti-digging up and filling in material.
4)Safe guardrail, security civilization warning sign, direction board, the night red light facility material such as warn is complete.
3rd, technical work prepares
Carry out technical annotation in construction in writing form to workmen and construction safety told somebody what one's real intentions are, specify construction method, quality standard, Environmental protection, safety operation points for attention etc..
4th, construction material is required
Job site Cast-in-situ Piles in Sand-filling, plain soil, slag, steady layer of water etc. will meet design requirement and use functional requirement;
1)Backfill element soil:Without debris such as rubbish, vegetation, humus in plain soil;
2)Backfill sand:Preferably adopt clean, hard thick, middle sand of the modulus of fineness more than 2.3.Clay content in sand should be less than 3%。
3)Slag is natural crystal exploitation, and within 20cm, clay content can not be more than 30% to size controlling, prevent weathered ore Material backfill.
4)Steady layer of water is formed using sand, artificial rubble, cement and water according to design proportion mixing, and cement content is more than 3%;
5)Reinforced concrete can live mixing, concrete water mud, sand, stone, additive, admixture, mixing water etc. must Jing Inspection is qualified can be used.Commercial Concrete may also be employed.
6)Concrete has to comply with design strength requirement, when such as design is not specified, strength grade of concrete being less than not C30。
7)Construction equipment prepares with equipment:According to Active workings and be backfilling and compacted used material and backfill thickness, choosing Select construction machinery and equipment.Preparing tamping apparatus has:Frog rammer, vibro-rammer, irony pier hammer, vibrating spear, spade, iron pick etc..
5th, construction procedure
1), inspection shaft pit earthwork excavate, being excavated to after projected depth the soil layer to bottom land carries out pricker spy, reconnoitres foundation bottom It is soft, hard.During such as soft base, invite in time geologic prospect, design, the relevant personnel of construction unit confirmed to scene and by Its requirement is processed, to guarantee that inspection shaft overall structure is not settled and deformed.
2), based process, the soil layer weak to inspection shaft foundation bottom is processed, and removes the debris in well week, leveling Bottom land;If it was found that foundation bottom is loose, it is necessary to processed, making foundation bottom solid, to ensure to check the overall work of well area Cheng Zhiliang, processing mode can be to continue to deep-cut, and then pouring reinforcement concrete forms base plate in foundation bottom;Or using compacting Mechanical work, makes real pressure coefficient be not less than 95%.
3), neutral gear position is processed between the part widened of inspection shaft periphery and pipeline foundation, tamp smooth;
4), build inspection shaft by laying bricks or stones, remove in building process and widen the debris such as the loose soil body and useless fragment of brick;And pit shaft 1 is often built When building high about 40-60cm, i.e., to well Zhou Jinhang back-fillings in layers and tamp, form supporting course 2;Carrying out the placement in layers of supporting course 2 When, require to carry out the compacting of human assistance mechanical delamination according to each structure sheaf job specfication of road smooth, often fill about 20cm and use Electric rammer or artificial ramming machine are rammed repeatedly, and reach design and the requirement of specification, make real pressure coefficient be not less than 92%.
5), pit shaft 1 built by laying bricks or stones rise under roadbase 3, compactness inspection need to be carried out to supporting course 2, overall supporting course 2 Press coefficient to be not less than 92% in fact, then carry out cement treated material 4 and pave;And before the cement treated material 4 that paves, in the lateral surface depth of pit shaft 1 Degree 15cm scopes lay the isolated materials such as one layer of malthoid so that the reinforced concrete structure layer 5 of later stage cast is formed with pit shaft 1 isolates Layer.
6), inspection shaft well head wooden cover or steel plate covered tightly temporarily, and the interim sign for burying front position is carried out, by surveying Amount personnel determine inspection shaft physical location, and are identified with red paint.
7), carry out on cement treated material 4 paving, flatten, rolling for bottom 31 in bitumen concrete;
8), inspection shaft periphery done using counter(Dig)Method, bottom 31 in the bitumen concrete of making is dug out, and excavates well week 0.8- In 1.6 meters of radiuses, bottom 31 in the bitumen concrete below road surface in the range of 40cm;
9), inspection shaft well head and around it is anti-dig position and carry out reinforcing bar prick weldering, according to the reinforcing bar rule of the framework of steel reinforcement of detail design Lattice and physical dimension, expect off field, weld and colligation shaping in steel bar meter, are integrally transported to job site using transport vehicle and are pacified Dress;The cushion block such as the framework of steel reinforcement basis rest concrete of installation forming or stone, installation site is accurate, centering, and reinforcing bar walling crib 6 is pacified Fill it is in place after, by quality testing, personnel are inspected for acceptance, then carry out steel external mold supporting to the anti-reinforcing bar for digging position, by measurement people Member checks template elevation using paired-line cross.Last cast-in-situ reinforced concrete structure layer 5, reinforces to inspection shaft well head periphery, makes Walling crib 6 forms entirety with pavement structure;In addition before reinforced concrete structure layer 5 is poured in construction, in the top surface of pit shaft 1 one layer of malthoid is laid Deng isolated material so that reinforced concrete structure layer 5 pours rear and pit shaft 1 and forms separation layer.Inspection shaft reinforced-concrete walling crib 6 is once Pour, the folding template that can freely dismantle is installed in pit shaft 1.Template first checks for the masonry quality of pit shaft 1 before installing, will fold Template is strutted along the inwall of pit shaft 1, and with paired-line cross template elevation is adjusted,(Design road surface elevation deducts well week and concrete reinforcing body It is high), framework of steel reinforcement is laid, the cushion blocks such as framework of steel reinforcement concrete are paved, it is ensured that thickness of protection tier.
10), prefabricated walling crib 6, well lid 7 are installed, acted as a planted agent using masonry of cement mortar under walling crib 6, to increase stablizing for walling crib 6 Property;When the thickness of the cement mortar that crouches under walling crib is less than 2cm, only acted as a planted agent using masonry of cement mortar under walling crib;When under walling crib When the thickness of sleeping cement mortar is more than 2cm, what is exceeded should be sleeping using pea gravel concreten pad, installs walling crib 6 and uses paired-line cross side Method, little line effective length is no less than 2m, and the direction in length and breadth of surface layer along road controls the vertical and horizontal gradient that walling crib 6 is installed.
11), after walling crib 6 was using masonry of cement mortar planted agent construction 3 days, treat that mortars that walling crib 6 time crouches have certain strong Degree, then to inspection shaft around, cast-in-place bitumen concrete superficial layer 32 on bottom 31 in bitumen concrete mainly makes walling crib 6 pave and roll During can keep enough stability, the rupture on the surrounding road surface of walling crib 6 for preventing well head circle unstable and causing.In the drip that paves Before blue or green concrete superficial layer 32, on-site cleanup work is carried out first, it is ensured that the surface of bottom 31 is clean, dry in bitumen concrete, and to reinforcing Inspection shaft elevation afterwards is checked, it is ensured that accurate, is paved before bitumen concrete superficial layer 32 within an hour to walling crib 6 weeks Enclose in bitumen concrete brush sticking layer oil on bottom 31, it is desirable to brush uniform, smear isolation oil on well lid 7, then to around inspection shaft and Cast-in-place bitumen concrete superficial layer 32 is carried out using C30 or more concrete on bottom 31 in bitumen concrete, is controlled in casting process mixed Coagulate the slump and speed of perfusion of soil, vibrating leakage is shaken cross to shake of uniformly avoid, until under road surface.The paving process of bitumen concrete superficial layer 32 It is middle to send special messenger that inspection shaft periphery is tamped with hammer ram, it is ensured that well lid 7 and road surface drop-over, flatness requirement meets road marking It is accurate.
12), the concrete of roadbase 3 cover in time after surviving and timely and appropriate discovery watering health, health 7 days, during health Must not trample or stack construction material.
After concrete reaches the 70% of design with foster test block, the folding punching block in manhole shaft 1 will be removed.It is first First dismantle the plate marked time at position, then lay down swelling nut and bolt, take out from walling crib 6 after finally template is folded.
6 quality controls
1)Excavation slope and substrate should be solid, smooth, stable.Side slope answer it is smooth and not suddenly in detail design require.
2)Foundation ditch backfill must not contain organic matter, frozen soil, the block more than 50mm, must not there is ponding during backfill in foundation ditch.
3)Bottom of foundation ditch soil must not backbreak, disturb, enduring cold, water logging.
4)Concrete surface should be smooth, straight suitable, free from flaw, without the phenomenon such as obvious voids and pits and dew muscle.
5)There must not be the defects such as crackle, disconnected wound and indentation after steel bar meter shaping.Rebar surface should be clean, must not there is rust The dirts such as erosion, oil stain.After reinforcement welding, commissure is removed without meat, crackle, slag inclusion, welding agent figure for shadow-play is stung.
6)Reinforcement installation position, the clear distance of protective layer meet design requirement.Side is bundled into type, and tying up silk should fasten, and must not have pine Move, fracture, the phenomenon such as displacement.
7)Model sheetinstallat and support firmly must must not have loosening, run mould, the phenomenon such as sinking.
8)Template and structure cohesion position piece must tight not spillage, template cleaning no-sundries.
9)The interleaving agent brushing of template brushing should be uniform, must not pollute reinforcing bar.
7 performance analyses:
1)Economic benefit:The reinforced concrete of walling crib periphery is reinforced, it is contemplated that increase about 300 yuan/well of expense, according to per kilometer of 80 well meters Calculate, increase about 24000 yuan of expense, if not consolidation process, after a period of time that is open to traffic, because subgrade settlement is damaged, well curb well lid is received External force is damaged soon to be needed to change, and often covers crib about 450 yuan/well of lid, and considering further that the damaged road surface cutting of well week is abolished is carried out again Repair on road surface, it is contemplated that every well also needs about 600 yuan of increase expense, the later stage that every well is caused repairs and is once accomplished by 1050 yuan/well, Total about 80*1050=84000 is first for expense;Walling crib is changed after repairing, and is run through a period of time, may there is also second Even multiple repairing, causes larger manpower and materials to waste, and social influence is also worse, so, disposably walling crib is reinforced The economic benefit that process is received is also apparent from.
2)Social benefit:Newly-built road is open to traffic after operation a period of time, due to the original such as vehicular load and road settlement Cause, walling crib surrounding road occurs different degrees of sedimentation or road surface radioactivity cracking, has both affected attractive in appearance, more cause driving to jump The unsafe factors such as car, by tamping to walling crib periphery roadbed and reinforcing, it is to avoid above-mentioned common quality defect, receive good society Benefit.
8 case histories
1)Dongtou County new city second phase Municipal Road Engineering(Binhai Road, five bridge blocks)Engineering, positioned at Wenzhou City Dongtou County new city Area(The phase of new city one)To the west of, scope is k0+41.33-k1+380m, and west connects 77 provincial highway traffic cycles, to the east of built landscape, 1.27km is always about, project content includes road, bridge, draining, feedwater, means of transportation and street lighting and afforestation project; Wherein road is had a lot of social connections 40 meters, is two-way six-lane, using asphalt concrete pavement;Engineering 78772677 yuan of cost of acceptance of the bid, the calendar of duration 720 My god, walling crib periphery is all reinforced using above-mentioned engineering method.
2)The construction contract section of Oujiangkou new district starting area municipal works the 11st, positioned at Wenzhou City Oujiangkou new district starting area. Into south-north direction, whole construction area is the area that reclaims fields from the sea, and physical features is flat, and original place level ground absolute altitude is about between 2.2 meters ~ 4.5 meters. Engineering is mainly road surface, lap slab of bridge along the line, platform post processing and bridge floor pitch, plumbing, the cable tube of the roads of Jing tetra- and Jing seven road Raceway groove, traffic marking and mark basis, traffic signal system pipe laying and basis, street lamp pipeline and streetlamp foundation etc..Engineering is always made 138654922 yuan of valency.The calendar day of duration 300, walling crib perimeter reinforcement is reinforced using reinforced concrete.
The above is only the preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-described embodiment, All technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art For those of ordinary skill, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (10)

1. a kind of newly-built construction method of town road inspection shaft, is characterized in that:Including following construction procedure:
1), inspection shaft pit earthwork excavate;
2), based process, the soil layer weak to inspection shaft foundation bottom process;
3), neutral gear position is processed between the part widened of inspection shaft periphery and pipeline foundation, tamp smooth;
4), build inspection shaft by laying bricks or stones, when pit shaft (1) often builds high about 40-60cm by laying bricks or stones, i.e., to well Zhou Jinhang back-fillings in layers and tamp, formed Supporting course (2);
5), pit shaft (1) built by laying bricks or stones rise under roadbase (3), then carry out cement treated material (4) and pave;
6), inspection shaft well head wooden cover or steel plate covered tightly temporarily, and carry out the interim sign for burying front position;
7), carry out on cement treated material (4) paving, flatten, rolling for bottom (31) in bitumen concrete;
8), bottom (31) in inspection shaft the periphery bitumen concrete of making dug out, excavate in well week 0.8-1.6 rice radiuses, road surface Bottom (31) in bitumen concrete in the range of following 40cm;
9), it is anti-around inspection shaft well head dig position cast-in-situ reinforced concrete structure layer (5), inspection shaft well head periphery is reinforced;
10), prefabricated walling crib (6), well lid (7) are installed, walling crib is acted as a planted agent under (6) using masonry of cement mortar;
11), to inspection shaft around, cast-in-place bitumen concrete superficial layer (32) on bottom (31) in bitumen concrete, until under road surface;
12), roadbase (3) cover health.
2. the newly-built construction method of town road inspection shaft according to claim 1, is characterized in that:Step 1)Wrap after construction Included bottom land pricker spy, to inspection shaft foundation bottom it is soft, reconnoitre firmly.
3. the newly-built construction method of town road inspection shaft according to claim 1 and 2, is characterized in that:Step 2)Also wrap The debris for removing well week are included, bottom land is flattened;And in construction procedure 4)During also include removing widen loose soil Body and useless fragment of brick.
4. the newly-built construction method of town road inspection shaft according to claim 3, is characterized in that:Step 4)Middle supporting course (2) placement in layers, often fills about 20cm and is rammed repeatedly with electric rammer or artificial ramming machine.
5. the newly-built construction method of town road inspection shaft according to claim 1, is characterized in that:Step 5)Middle pit shaft (1) build by laying bricks or stones after rising under roadbase (3), carry out compactness inspection.
6. the newly-built construction method of town road inspection shaft according to claim 5, is characterized in that:Step 5)Construction paves Before cement treated material (4), in the lateral surface depth 15cm scope of pit shaft (1) isolated materials such as one layer of malthoid, step 9 are laid)Construction Before pouring reinforced concrete structure layer (5), the isolated materials such as one layer of malthoid are laid in the top surface of pit shaft (1) so that reinforced concrete structure layer (5) Pour rear and pit shaft (1) and form separation layer.
7. the newly-built construction method of town road inspection shaft according to claim 6, is characterized in that:Step 9)Work progress In, inspection shaft well head and around it is anti-dig position and carry out reinforcing bar prick weldering, the framework of steel reinforcement basis rest concrete of installation forming or , as cushion block, installation site is accurate, centering for stone;Again steel external mold supporting is carried out to the anti-reinforcing bar for digging position;Last concrete enters Row is poured.
8. the newly-built construction method of town road inspection shaft according to claim 1, is characterized in that:Step 10)In work as well When the thickness of the cement mortar that crouches under circle (6) is less than 2cm, walling crib is only acted as a planted agent under (6) using masonry of cement mortar;When walling crib (6) When down the thickness of sleeping cement mortar is more than 2cm, what is exceeded should be sleeping using pea gravel concreten pad.
9. the newly-built construction method of town road inspection shaft according to claim 8, is characterized in that:Step 10)Implement 3 days Afterwards, treat that the mortar crouched under walling crib (6) has certain intensity, then arrange step 11)Implement.
10. the newly-built construction method of town road inspection shaft according to claim 9, is characterized in that:Step 11)Before enforcement The first brush sticking layer oil on bottom (31) in bitumen concrete, then poured using C30 or more concrete, casting process keeps pouring Speed is uniform, vibrating leakage is shaken cross to shake of uniformly avoid.
CN201610976992.0A 2016-11-07 2016-11-07 New construction method of municipal road inspection well Pending CN106567410A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610976992.0A CN106567410A (en) 2016-11-07 2016-11-07 New construction method of municipal road inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610976992.0A CN106567410A (en) 2016-11-07 2016-11-07 New construction method of municipal road inspection well

Publications (1)

Publication Number Publication Date
CN106567410A true CN106567410A (en) 2017-04-19

Family

ID=58541641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610976992.0A Pending CN106567410A (en) 2016-11-07 2016-11-07 New construction method of municipal road inspection well

Country Status (1)

Country Link
CN (1) CN106567410A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111268963A (en) * 2019-12-20 2020-06-12 漳州明威建材发展有限公司 Road inspection well and manufacturing process and construction method thereof
CN111321793A (en) * 2020-02-26 2020-06-23 中铁二院工程集团有限责任公司 Construction method of ballastless track railway roadbed water collecting well
CN111779030A (en) * 2020-06-28 2020-10-16 中国二十冶集团有限公司 Wellbore installation method
CN112227502A (en) * 2020-10-28 2021-01-15 中建七局安装工程有限公司 Drainage inspection well construction method
CN112647543A (en) * 2021-01-12 2021-04-13 荆州市路远市政工程有限公司 Rigid mounting construction method for manhole cover
CN114855536A (en) * 2022-05-31 2022-08-05 广州市交通设计研究院有限公司 Method for preventing and treating highway pipeline diseases
CN115030224A (en) * 2022-06-21 2022-09-09 青岛中润公用事业设计有限责任公司 Municipal road inspection well and construction method thereof
CN115075301A (en) * 2022-07-20 2022-09-20 中国二十二冶集团有限公司 Novel road pipeline well cover and well base and construction and installation method around well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831752A (en) * 2015-04-16 2015-08-12 北京市政路桥管理养护集团有限公司 Prefabricated inspection well and construction method thereof
CN204690528U (en) * 2015-06-02 2015-10-07 宏盛建业投资集团有限公司 Urban road pavement around inspection well Defects Treatment structure
CN204825969U (en) * 2015-07-06 2015-12-02 河南省路嘉路桥股份有限公司 Inspection shaft subsides prevents and treats structure
CN105569087A (en) * 2016-01-13 2016-05-11 中国十九冶集团有限公司 Construction method for inspection well

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831752A (en) * 2015-04-16 2015-08-12 北京市政路桥管理养护集团有限公司 Prefabricated inspection well and construction method thereof
CN204690528U (en) * 2015-06-02 2015-10-07 宏盛建业投资集团有限公司 Urban road pavement around inspection well Defects Treatment structure
CN204825969U (en) * 2015-07-06 2015-12-02 河南省路嘉路桥股份有限公司 Inspection shaft subsides prevents and treats structure
CN105569087A (en) * 2016-01-13 2016-05-11 中国十九冶集团有限公司 Construction method for inspection well

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱明安等: ""城市道路检查井沉陷原因分析及治理对策"", 《城市道桥与防洪》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111268963A (en) * 2019-12-20 2020-06-12 漳州明威建材发展有限公司 Road inspection well and manufacturing process and construction method thereof
CN111321793A (en) * 2020-02-26 2020-06-23 中铁二院工程集团有限责任公司 Construction method of ballastless track railway roadbed water collecting well
CN111779030A (en) * 2020-06-28 2020-10-16 中国二十冶集团有限公司 Wellbore installation method
CN111779030B (en) * 2020-06-28 2022-03-01 中国二十冶集团有限公司 Wellbore installation method
CN112227502A (en) * 2020-10-28 2021-01-15 中建七局安装工程有限公司 Drainage inspection well construction method
CN112647543A (en) * 2021-01-12 2021-04-13 荆州市路远市政工程有限公司 Rigid mounting construction method for manhole cover
CN114855536A (en) * 2022-05-31 2022-08-05 广州市交通设计研究院有限公司 Method for preventing and treating highway pipeline diseases
CN115030224A (en) * 2022-06-21 2022-09-09 青岛中润公用事业设计有限责任公司 Municipal road inspection well and construction method thereof
CN115075301A (en) * 2022-07-20 2022-09-20 中国二十二冶集团有限公司 Novel road pipeline well cover and well base and construction and installation method around well

Similar Documents

Publication Publication Date Title
CN106567410A (en) New construction method of municipal road inspection well
CN102644295A (en) Construction method for preventing peripheral and local sedimentation of road surface inspection well
CN103334357A (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN110144783B (en) Roadbed construction method
CN110080051B (en) Geotextile bag bridge type embankment structure and construction method thereof
CN101311418A (en) Exchange filling method for deep-foundation pit and large area equipment foundation
CN113774917B (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN101597888B (en) Construction method of municipal drainage culvert sinking trough
CN107460890A (en) A kind of city bituminous concrete pavement inspection shaft construction method
CN110295628A (en) A kind of pavement construction method with inspection shaft
CN101424063A (en) Interim and permanent roads single time construction method
CN107938456A (en) Fill out river road construction method
CN109706952A (en) Large-scale well-sinking construction method
CN108252176A (en) A kind of pavement engineering construction method equipped with inspection shaft
CN111778941A (en) High-standard farmland channel construction method and structure
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN111549599B (en) Construction structure and method suitable for roadbed filling and pavement restoration under complex conditions
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN201411713Y (en) Manhole of various kinds of pipe networks for urban roads having hole mouth reinforcing mechanism
CN112554167A (en) Novel poured large-particle-size aggregate UHPC soft soil road foundation pile
CN109082961B (en) Road construction method with steep slope
CN211142675U (en) Roadbed structure of expressway filled with muck type construction waste
Giffen Design and construction of a strengthened embankment for an intermodal transfer facility
Maher et al. MAT-758: Constructability Benefits of the Use of Lightweight Foamed Concrete Fill (LFCF) in Pavement Applications
CN104894942A (en) Drainage type recoverable combined construction road

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wu Chaohui

Inventor after: Zhang Xiaoyan

Inventor after: Ji Ruixue

Inventor after: Jiang Yuelin

Inventor before: Ye Jianxing

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170419