CN1858364A - Secondary pouring method for preventing broken pile accident in pile pouring construction - Google Patents

Secondary pouring method for preventing broken pile accident in pile pouring construction Download PDF

Info

Publication number
CN1858364A
CN1858364A CN 200510067997 CN200510067997A CN1858364A CN 1858364 A CN1858364 A CN 1858364A CN 200510067997 CN200510067997 CN 200510067997 CN 200510067997 A CN200510067997 A CN 200510067997A CN 1858364 A CN1858364 A CN 1858364A
Authority
CN
China
Prior art keywords
pouring
concrete
secondary pouring
pile
wellhole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200510067997
Other languages
Chinese (zh)
Inventor
宋亚非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200510067997 priority Critical patent/CN1858364A/en
Publication of CN1858364A publication Critical patent/CN1858364A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The twice pouring method for preventing broken pile accident in pile pouring construction includes the following steps: 1. setting one first pouring guide pipe and one second pouring guide pipe in the construction site; 2. hoisting the blocked first pouring guide pipe immediately outside the pile pouring well; 3. measuring the distance between the concrete surface inside the pouring well to the work plane, inserting the second pouring guide pipe to below the concrete surface for the second pouring; 4. filling the hopper with the first batch of concrete; 5. opening the valve of the hopper for the second pouring, and lowering the second pouring guide pipe by 0.5-1 m for further pouring; and 6. further pouring until reaching the required design elevation.

Description

A kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction
Technical field
The present invention relates to a kind of method that prevents that fracture accident takes place in the filling pile construction, this method can solve plugging, pipe laying and card pipe fault, prevents that fracture accident from taking place, and simple to operate, cost is lower.
Background technology
Chinese patent 98116992.9 discloses a kind of castinplace pile, this castinplace pile is the concrete enlarged footing that forms hole enlargement on the different depth position of isometrical steel concrete solid pile, also can be provided with at least two grout pipes that insert the grout pipe of soil layer at the bottom of directing reach and direct reach each concrete enlarged footing bottom, and form the permeation enhanced net of grouting along stake week, its job practices is to form stake hole and enlarged footing hole from top to bottom piecemeal with drill bit and reaming bit, reinforcing cage and grout pipe are set again, behind the concrete perfusion pile, through grout pipe high pressure injection from bottom to top cement grout, above-mentioned concrete enlarged footing and reinforcement net have improved the bearing capacity of stake, can be by reducing the stake footpath, high and the stake number of stake reduces construction cost.Because this castinplace pile adopts the construction of underwater grouting method, tends to run into the phenomenon of plugging, pipe laying and card pipe in the process of concrete under priming petock, and causes taking place fracture accident thus.
The measure of in the past handling plugging is to adopt to carry conduit up and down, and form vibrator or stock are inserted the method for smashing and dredged.When the more serious plugging situation that takes place to get rid of, conduit must be proposed a stake hole and clear up, and then insert heavily and irritate, heavily usually cause the generation of fracture accident in the process of Guaning.Therefore, need to propose a kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction.
Summary of the invention
The object of the present invention is to provide a kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction, this method can solve the plugging fault, prevents that fracture accident from taking place, and simple to operate, cost is lower.
The objective of the invention is to be realized by following technical proposals: a kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction is characterized in that:
A, a perfusion cannula of a cover and a cover secondary pouring conduit are set at the filling pile construction scene;
B, when a perfusion cannula generation plugging, immediately this perfusion cannula is lifted out outside the castinplace pile wellhole;
Concrete face in C, the measurement castinplace pile wellhole is determined the secondary pouring catheter length to the distance of work plane according to this distance, and described secondary pouring catheter length l should meet calculating formula l=l 1+ l 2+ l 3Then the secondary pouring conduit is installed in the castinplace pile wellhole and prepares secondary pouring, following 0.5~1 meter of the interior concrete face of described wellhole should be inserted in described secondary pouring conduit bottom;
D, put into first batch of concrete in hopper, the volume of described first batch of concrete should meet calculating formula:
V≥πD 2/4*(H 1+H 2)+πd 2/4*h 1+πd 2/4;
E, open hopper valve and carry out first batch of concrete pouring in the secondary pouring operation,, immediately the secondary pouring conduit is reduced by 0.5~1 meter downwards, continue the continous pouring concrete then when first batch of concrete falls behind down;
F, stop perfusion when high when the perfusion concrete reaches a top mark, described stake top mark height should be higher than design elevation.
Compared with the prior art the present invention has following advantage:
1,, prevents that fracture accident from taking place because the present invention is provided with the secondary pouring conduit at the filling pile construction scene, and the plugging fault that can get rid of a filling process immediately enters the secondary pouring operation.
2, method of the present invention is simple to operate, and cost is lower.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples.
Fig. 1, secondary pouring conduit scheme of installation of the present invention
Fig. 2, first batch of concrete quantity of the present invention are calculated reference diagram
The specific embodiment
Embodiment one:
A kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction, the concrete operations step is:
A, a perfusion cannula of a cover and a cover secondary pouring conduit are set at the filling pile construction scene; Described perfusion cannula is conventional conduit.Use a perfusion cannula during pouring construction earlier.
B, when a perfusion cannula generation plugging, can use conventional mode to handle the plugging section, in the time can not getting rid of the plugging segment fault, immediately this perfusion cannula is lifted out outside the castinplace pile wellhole;
C, the conventional measurement means of use are measured the distance of the interior concrete face of castinplace pile wellhole to work plane, and according to the length of the definite secondary pouring conduit of this distance, described secondary pouring catheter length l should meet calculating formula l=l 1+ l 2+ l 3Then the secondary pouring conduit is installed in the castinplace pile wellhole and prepares secondary pouring, following 0.5~1 meter of the interior concrete face of described wellhole should be inserted in described secondary pouring conduit bottom.Referring to Fig. 1, in the present embodiment, l 1Be the spacing of work plane 3 to secondary pouring conduit 2 tops, i.e. length in reserve, 0.5~1 meter of span.l 2Be the spacing (concrete face 6 is meant the concrete face position when the plugging fault takes place) of the concrete face 6 of work plane to castinplace pile wellhole 4, adopt actual measured value, long measure rice.L 3Be the spacing (conduit bottom 7 residing positions be meant secondary pouring conduit for the first time insert the position of concrete face) of the interior concrete face of castinplace pile wellhole to secondary pouring conduit bottom 7,0.5~1 meter of span.
D, put into first batch of concrete in hopper 1, the volume of described first batch of concrete should meet calculating formula:
V≥πD 2/4*(H 1+H 2)+πd 2/4*h 1+πd 2/4;
Referring to Fig. 2, in the present embodiment, D is the castinplace pile well diameter, H 1Be castinplace pile wellhole bottom surface to secondary pouring conduit bottom spacing, value is 0 in this formula, H 2Be the following degree of depth of the embedding first concrete face in secondary pouring conduit bottom, value is 0.5 meter (this degree of depth does not comprise the L among Fig. 1 in this formula 3), d is the secondary pouring catheter diameter.h 1Be that concrete reaches buried depth H in the castinplace pile wellhole 2The time, the required height of concrete column equilibration conduit external pressure in the conduit, i.e. h 1=H Wγ W/ γ CIn addition, the concrete post height in the secondary pouring conduit should increase by 1 meter.The volume of first batch of concrete also can calculate with reference to the 6.5.4 formula of the 44th page of highway bridge and culvert construction technique normalizing JTJ041-2000, about H W, γ W, γ CImplication can not be described in detail at this with reference to the 43rd page of related content of highway bridge and culvert construction technique normalizing JTJ041-2000 yet.
E, open hopper valve and carry out first batch of concrete pouring in the secondary pouring operation, when first batch of concrete falls behind down, concrete face in the castinplace pile wellhole reaches rising the position of concrete face 5, reduce by 0.5~1 meter downwards with secondary pouring conduit (in original position) this moment immediately, this moment, in-position, conduit bottom 8 was continued the continous pouring concrete then; This perfusion is to adopt conventional reperfusion mode to carry out.
F, stop perfusion when high when the perfusion concrete reaches a top mark, described stake top mark height should be higher than design elevation.
Referring to Fig. 1, in the present embodiment, the span that stake top mark height can not be routinely, and should be greater than l 3+ l 4+ l 5Summation, l wherein 3, l 40.5~1 meter of span, l 50.5 meter of value.
In the present embodiment, the quality of perfusion concrete should satisfy the pertinent regulations among the highway bridge and culvert construction technique normalizing JTJ041-2000, and in the filling process, the minimum buried depth in secondary pouring conduit bottom should be greater than l 3+ l 4+ l 5+ 0.5 meter.Super filling concrete height should be greater than l 3+ l 4+ l 5
Embodiment two:
Present embodiment is the improvement project on the basis of embodiment one, in the present embodiment, when a perfusion cannula generation plugging, immediately this perfusion cannula is lifted out outside the castinplace pile wellhole, plugging section to perfusion cannula is removed, if the plugging segment fault of this perfusion cannula is got rid of, this perfusion cannula can be used as the secondary pouring conduit.Remaining step and embodiment one are identical.

Claims (2)

1, a kind of secondary pouring method that prevents that fracture accident takes place in the filling pile construction is characterized in that:
A, a perfusion cannula of a cover and a cover secondary pouring conduit are set at the filling pile construction scene;
B, when a perfusion cannula generation plugging, immediately this perfusion cannula is lifted out outside the castinplace pile wellhole;
Concrete face in C, the measurement castinplace pile wellhole is determined the secondary pouring catheter length to the distance of work plane according to this distance, and described secondary pouring catheter length l should meet calculating formula l=l 1+ l 2+ l 3Then the secondary pouring conduit is installed in the castinplace pile wellhole and prepares secondary pouring, following 0.5~1 meter of the interior concrete face of described wellhole should be inserted in described secondary pouring conduit bottom;
D, put into first batch of concrete in hopper, the volume of described first batch of concrete should meet calculating formula:
V≥πD 2/4*(H 1+H 2)+πd 2/4*h 1+πd 2/4;
E, open hopper valve and carry out first batch of concrete pouring in the secondary pouring operation,, immediately the secondary pouring conduit is reduced by 0.5~1 meter downwards, continue the continous pouring concrete then when first batch of concrete falls behind down;
F, stop perfusion when high when the perfusion concrete reaches a top mark, described stake top mark height should be higher than design elevation.
2, secondary pouring method according to claim 1, it is characterized in that: when a perfusion cannula generation plugging, immediately this perfusion cannula is lifted out outside the castinplace pile wellhole, plugging section to perfusion cannula is removed, if the plugging segment fault of this perfusion cannula is got rid of, this perfusion cannula can be used as the secondary pouring conduit.
CN 200510067997 2005-05-08 2005-05-08 Secondary pouring method for preventing broken pile accident in pile pouring construction Pending CN1858364A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200510067997 CN1858364A (en) 2005-05-08 2005-05-08 Secondary pouring method for preventing broken pile accident in pile pouring construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200510067997 CN1858364A (en) 2005-05-08 2005-05-08 Secondary pouring method for preventing broken pile accident in pile pouring construction

Publications (1)

Publication Number Publication Date
CN1858364A true CN1858364A (en) 2006-11-08

Family

ID=37297315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200510067997 Pending CN1858364A (en) 2005-05-08 2005-05-08 Secondary pouring method for preventing broken pile accident in pile pouring construction

Country Status (1)

Country Link
CN (1) CN1858364A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871211A (en) * 2010-07-13 2010-10-27 武汉一冶交通工程有限责任公司 Wet pile extension method for cast-in place pile
CN102561355A (en) * 2012-02-16 2012-07-11 广东省六建集团有限公司 Method for treating burst and jam of bored pile guide pipe
CN104153361A (en) * 2014-08-25 2014-11-19 中国十七冶集团有限公司 Underground pile splicing construction method of prestressed concrete pipe pile
CN105986577A (en) * 2015-02-02 2016-10-05 山东宇通路桥集团有限公司 Plugging device for secondary underwater concrete pipe insertion
CN111733823A (en) * 2020-06-15 2020-10-02 中冶地集团西北岩土工程有限公司 Grouting pipe burying structure and broken pile processing method in cast-in-situ bored pile pouring process
CN112962583A (en) * 2021-01-27 2021-06-15 中国建筑一局(集团)有限公司 Method for quickly connecting broken pile of rotary drilling cast-in-place pile

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871211A (en) * 2010-07-13 2010-10-27 武汉一冶交通工程有限责任公司 Wet pile extension method for cast-in place pile
CN101871211B (en) * 2010-07-13 2011-09-21 中国一冶集团有限公司 Wet pile extension method for cast-in place pile
CN102561355A (en) * 2012-02-16 2012-07-11 广东省六建集团有限公司 Method for treating burst and jam of bored pile guide pipe
CN104153361A (en) * 2014-08-25 2014-11-19 中国十七冶集团有限公司 Underground pile splicing construction method of prestressed concrete pipe pile
CN105986577A (en) * 2015-02-02 2016-10-05 山东宇通路桥集团有限公司 Plugging device for secondary underwater concrete pipe insertion
CN105986577B (en) * 2015-02-02 2017-12-29 山东宇通路桥集团有限公司 The secondary intubation plugging device of underwater concrete
CN111733823A (en) * 2020-06-15 2020-10-02 中冶地集团西北岩土工程有限公司 Grouting pipe burying structure and broken pile processing method in cast-in-situ bored pile pouring process
CN112962583A (en) * 2021-01-27 2021-06-15 中国建筑一局(集团)有限公司 Method for quickly connecting broken pile of rotary drilling cast-in-place pile

Similar Documents

Publication Publication Date Title
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN101413266B (en) Processing method of interlayer defect injection concrete of drill filling pile
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN108797587A (en) A kind of novel sinking construction technology of static pressed pile
CN1858364A (en) Secondary pouring method for preventing broken pile accident in pile pouring construction
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN106320333B (en) Combined drainage type water filling pile device and construction method
CN104532813A (en) Overwater building construction platform and erecting method and use method thereof
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN110158582A (en) A method of trestle steel pipe pile is set on intectate riverbed
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN113174961B (en) Foundation pit slope supporting method
CN1654749A (en) Lean correcting and foundation consolidating method for building by filling water
CN104631438A (en) Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN1288308C (en) Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre
CN1861914A (en) Installing method for rail beam structure of magnetic suspension tunnel shoreside section
CN1676761A (en) Long-spiral post-joint-bar bored concrete pile construction method
CN1313681C (en) Binding anti-slide pile structure and construction method
CN1196426A (en) Construction method for inversion underground continuous wall
CN211312225U (en) Pile-column integrated structure based on bridge transformed from existing road surface
CN113756290A (en) Sand-pebble geological variable-section screw pile construction process
CN1461857A (en) Construction method and its use
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication