CN112962583A - Method for quickly connecting broken pile of rotary drilling cast-in-place pile - Google Patents

Method for quickly connecting broken pile of rotary drilling cast-in-place pile Download PDF

Info

Publication number
CN112962583A
CN112962583A CN202110112493.8A CN202110112493A CN112962583A CN 112962583 A CN112962583 A CN 112962583A CN 202110112493 A CN202110112493 A CN 202110112493A CN 112962583 A CN112962583 A CN 112962583A
Authority
CN
China
Prior art keywords
pile
concrete
slurry
broken
guide pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110112493.8A
Other languages
Chinese (zh)
Inventor
张廷安
李焕军
杨勇
李泽彪
缪应璟
唐子森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202110112493.8A priority Critical patent/CN112962583A/en
Publication of CN112962583A publication Critical patent/CN112962583A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/64Repairing piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a method for quickly connecting broken piles of a rotary drilling cast-in-place pile, which comprises the following steps: firstly, when the cast-in-place pile is found to be broken due to pipe blockage and other reasons during concrete pouring, pulling out a guide pipe and cleaning; the blocking pipe is a conduit poured by concrete; step two: measuring the depth of the broken pile position; step three: placing the cleaned guide pipe into a position with the depth of 500mm-1000mm away from the broken pile, pouring concrete, removing slurry in the guide pipe, and extruding a mixture at the joint of the concrete and the slurry out of the original concrete pouring surface; step four: the conduit was inserted 4-5m below the concrete and slurry mixture. The method is scientific and reasonable, and convenient and fast to construct; the pile splicing is simple and comprehensive, the pile is spliced by the 'rescue' method after the pile is actually broken, and the integrity of the pile body meets the relevant standard requirements after the ultrasonic detection.

Description

Method for quickly connecting broken pile of rotary drilling cast-in-place pile
Technical Field
The invention relates to the field of building construction, in particular to a method for quickly connecting broken piles of a rotary drilling cast-in-place pile.
Background
The rotary drilling bored concrete pile can be constructed in strata such as higher water level, removed areas, mucky soil, clay, sandy soil, pebble beds and the like, has the advantages of high automation degree, high hole forming speed, high quality and the like, and is widely applied to various pile foundation engineering.
Due to the influence of a plurality of factors such as geological conditions, field factors, construction management and the like, pile breakage of the rotary drilling cast-in-place pile during pouring sometimes occurs, and the mode of treating the pile breakage of the rotary drilling cast-in-place pile is commonly used: 1. in-situ pile replacement: the broken pile detected by ultrasonic waves is found in time in the construction process, and a new pile is poured in situ after the pile is thoroughly cleaned, so that the pile is thoroughly treated. The method has the advantages of good effect, high difficulty, long period and high cost, and can be selected and adopted according to factors such as the importance of engineering, geological conditions, the number of defects and the like.
2. Pile splicing manually: determining a pile splicing scheme, determining well point dewatering-excavation-20 # plain concrete according to geological data provided by design to perform wall protection, reinforcing the interior of the wall protection by using a steel bar hoop, excavating to a qualified position, performing manual roughening, and pouring concrete according to a concrete construction method of a hole excavation method.
3. Pile core sinking method: the method is easy to make, namely, a well with the diameter of 80cm is dug in the center of a defective pile by using an air pick while water is lowered, the depth at least exceeds the defective part, then the sediment is sealed and cleaned, a steel reinforcement cage is placed, and the expanded concrete is poured by using a hole digging concrete construction method. The method is slow in daily progress, and if the water treatment of individual piles is poor and cannot be reduced, the method is difficult and serious, and the quality, the construction period and the economy are seriously lost.
Disclosure of Invention
The invention aims to provide a method for quickly connecting broken piles of cast-in-place piles by rotary drilling, and aims to solve the technical problems of complex construction, high maintenance cost, uncertain construction period, low safety and the like after the broken piles of the cast-in-place piles are broken.
In order to achieve the purpose, the invention adopts the following technical scheme: the invention provides a method for quickly connecting broken piles of a rotary drilling cast-in-place pile, which comprises the following steps:
firstly, when the cast-in-place pile is found to be broken due to pipe blockage and other reasons during concrete pouring, pulling out a guide pipe and cleaning; the blocking pipe is a conduit poured by concrete;
step two: measuring the depth of the broken pile position;
step three: placing the cleaned guide pipe into a position with the depth of 500mm-1000mm away from the broken pile, pouring concrete, removing slurry in the guide pipe, and extruding a mixture at the joint of the concrete and the slurry out of the original concrete pouring surface;
step four: inserting a conduit 4-5m below the mixture of concrete and slurry;
fifthly, performing broken pile concrete pouring by using the guide pipe again, and returning the slurry and the mixture upwards by using the concrete compactness until the pouring of the cast-in-place pile is finished; the broken pile must be available before the initial setting of the broken pile concrete.
And further, measuring the depth of the pile breaking position by using a measuring rope.
Further, the concrete steps of measuring the depth of the broken pile position are as follows:
s1, moving the measuring rope to the hole edge;
s2, slowly placing the hammer at the end of the measuring rope into the hole;
s3, slowly loosening the measuring rope until the measuring hammer reaches the pile breaking position;
and s4, keeping the measuring rope vertical, and checking the measuring rope scale at the same horizontal position with the hole edge, namely the depth of the pile breaking position.
Further, in step four, the lower portion of the conduit is at least 4-5m below the concrete and slurry mixture.
The compactness is referred to herein without specific parameters, and is expressed by the formula: (ρ 0/ρ) × 100% (ρ 0: bulk density; ρ: bulk density); the expression is mainly intended to mean that the density of the concrete is greater than that of the slurry and the mixture, and the slurry and the mixture are automatically returned when the concrete is poured by using the principle.
Further, the diameter of the catheter was 260 mm.
Furthermore, the distance between the bottom end of the guide pipe and the top surface of the hole bottom elevation is 500mm, and the distance between the top end of the guide pipe and the ground is at least 500 mm; the funnel is arranged at the top end of the catheter.
Further, when the rotary excavating machine drills, slurry is injected while forming holes, so that the lateral pressure of a soil body is offset to prevent hole collapse; when the concrete is poured, the density of the concrete is different from that of the slurry, the concrete sinks below the slurry to form a layer, but the concrete and the slurry form a mixed liquid at the junction of the slurry and the concrete.
And further, the method also comprises a sixth step of confirming the integrity of the pile body by using ultrasonic detection.
The invention has the beneficial effects that:
the invention provides a method for quickly connecting broken piles of a rotary drilling cast-in-place pile, which is scientific and reasonable and is convenient to construct; the pile splicing is simple and comprehensive, the pile is spliced by the 'rescue' method after the pile is actually broken, and the integrity of the pile body meets the relevant standard requirements after the ultrasonic detection.
2, the method has no influence on the quality of the whole rotary drilling cast-in-place pile, and has the advantages of short construction period, low cost, high safety and convenience in use, and a large amount of labor consumption is avoided.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by the practice of the invention. The primary objects and other advantages of the invention may be realized and attained by the instrumentalities particularly pointed out in the specification.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
FIG. 1 is a schematic view showing that in step one, when a pile is broken due to pipe blockage and the like, a guide pipe is pulled out for cleaning and the depth of the broken pile is measured;
FIG. 2 is a schematic view of the present invention placing a cleaned catheter 50cm to 100cm above the concrete placement surface;
FIG. 3 is a schematic view of the present invention in which concrete is poured through a pipe and the infiltration mud is removed from the pipe;
FIG. 4 is a schematic illustration of the invention after concrete placement through the conduit, cleaning the mixture of the concrete and slurry junction;
FIG. 5 is a schematic representation of the present invention in which the pipe is lowered 4-5m below the concrete and mud mixture for pile placement;
FIG. 6 is a schematic view of the invention with the gradual extraction of the catheter just prior to completion of the concrete pour;
fig. 7 is a schematic view of the invention for the completion of the integral casting.
Reference numerals: 1-guide pipe, 2-slurry, 3-concrete, 4-concrete and slurry mixture.
Detailed Description
The technical solutions of the present invention are described in detail below by examples, and the following examples are only exemplary and can be used only for explaining and illustrating the technical solutions of the present invention, but not construed as limiting the technical solutions of the present invention.
Examples
Referring to fig. 1-7 in detail, the invention provides a method for quickly connecting broken piles of a rotary drilling cast-in-place pile, which comprises the following steps:
step one, when the cast-in-place pile is found to be broken due to pipe blockage and other reasons during concrete pouring, pulling out the guide pipe 1 and cleaning; the pipe blockage refers to a concrete poured conduit 1;
step two: measuring the depth of the broken pile position; the concrete steps of measuring the depth of the broken pile position are as follows:
s1, moving the measuring rope to the hole edge;
s2, slowly placing the hammer at the end of the measuring rope into the hole;
s3, slowly loosening the measuring rope until the measuring hammer reaches the pile breaking position;
and s4, keeping the measuring rope vertical, and checking the measuring rope scale at the same horizontal position with the hole edge, namely the depth of the pile breaking position. Depth position measurement is performed using a measuring line.
Step three: placing the cleaned guide pipe 1 at a position with a depth of 500mm-1000mm away from the broken pile, pouring concrete 3, removing slurry 2 in the guide pipe 1, and extruding a mixture at the joint of the concrete 3 and the slurry 2 out of the original concrete pouring surface;
step four: inserting the guide pipe 1 into the mixture of the concrete 3 and the slurry 2 for 4-5m below; the lower part of the conduit 1 is at least 4-5m below the mixture of concrete 3 and slurry 2.
Fifthly, the broken pile concrete is poured by using the guide pipe 1 again, and the mud 2 and the mixture are returned upwards by using the compactness of the concrete 3 until the pouring of the cast-in-place pile is finished; the broken pile must be available before the initial setting of the broken pile concrete 3. The catheter 1 has a diameter of 260 mm. The lower part of the bottom end of the guide pipe 1 is 500mm away from the top surface of the hole bottom elevation, and the distance from the top end of the guide pipe 1 to the ground is at least 500 mm; the funnel is mounted on the top end of the catheter 1.
And step six, using ultrasonic detection to confirm the integrity of the pile body.
The compactness is expressed by the formula: ρ 0/ρ × 100% ρ 0: bulk density: ρ: bulk density; the expression is mainly intended to mean that the concrete 3 is more compact than the slurry 2 and the mixture, and the slurry 2 and the mixture are automatically returned when the concrete is poured by using the principle.
When the rotary drilling machine drills, the mud 2 is injected while forming holes, and the side pressure of a soil body is offset to prevent hole collapse; when the concrete 3 is poured, the density of the concrete 3 is different from that of the slurry 2, the concrete 3 sinks below the slurry 2 to form a layer, and the concrete 3 and the slurry 2 form a mixed liquid at the boundary of the slurry 2 and the concrete 3.
The invention provides a method for quickly connecting broken piles of a rotary drilling cast-in-place pile, which is equivalent to a remedial measure that the rotary drilling cast-in-place pile cannot be subjected to one-time concrete pouring due to pipe blockage or other reasons during concrete pouring.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that may be made by those skilled in the art within the technical scope of the present invention will be covered by the scope of the present invention.

Claims (8)

1. A method for quickly connecting broken piles of cast-in-place piles by rotary drilling is characterized by comprising the following steps: the method comprises the following steps:
step one, when the cast-in-place pile is found to be broken due to pipe blockage and other reasons during concrete pouring, pulling out the guide pipe (1) and cleaning; the pipe plugging refers to a concrete pouring guide pipe (1);
step two: measuring the depth of the broken pile position;
step three: placing the cleaned guide pipe (1) into a place with the depth of 500mm-1000mm away from the broken pile to pour concrete (3), discharging slurry (2) in the guide pipe (1), and extruding a mixture at the joint of the concrete (3) and the slurry (2) out of the original concrete pouring surface;
step four: inserting the conduit (1) below the mixture of concrete (3) and slurry (2);
fifthly, performing broken pile concrete pouring by using the guide pipe (1) again, and returning the slurry (2) and the mixture upwards by using the compactness of the concrete (3) until the pouring of the cast-in-place pile is finished; the broken pile and the pile must be available before the initial setting of the broken pile concrete (3).
2. A pile splicing method according to claim 1, wherein in the second step, the depth measurement of the pile breaking position is performed by using a measuring rope.
3. A pile extension method according to claim 2, characterized in that the depth measurement of the pile-breaking position comprises the following specific steps:
s1, moving the measuring rope to the hole edge;
s2, slowly placing the hammer at the end of the measuring rope into the hole;
s3, slowly loosening the measuring rope until the measuring hammer reaches the pile breaking position;
and s4, keeping the measuring rope vertical, and checking the measuring rope scale at the same horizontal position with the hole edge, namely the depth of the pile breaking position.
4. A method according to claim 1, characterised in that in step four the lower part of the pipe (1) is at least 4-5m below the mixture of concrete (3) and slurry (2).
5. A pile splicing method according to claim 1, characterised in that the conduit (1) has a diameter of 260 mm.
6. A pile extension method according to claim 1, characterized in that the bottom end of the guide pipe (1) is 500mm below the top surface of the hole bottom elevation, and the top end of the guide pipe (1) is at least 500mm above the ground; the funnel is arranged at the top end of the catheter (1).
7. A pile extension method according to claim 1, characterized in that when the rotary excavating machine drills, mud (2) is injected while forming a hole to counteract the side pressure of the soil body to prevent hole collapse; when the concrete (3) is poured, the density of the concrete (3) is different from that of the slurry (2), the concrete (3) sinks to be positioned at the lower part of the slurry (2) to form layering, and part of the concrete (3) at the junction of the slurry (2) and the concrete (3) and the slurry (2) form mixed liquid.
8. A pile splicing method according to claim 1, further comprising a sixth step of further confirming the integrity of the pile body using ultrasonic testing.
CN202110112493.8A 2021-01-27 2021-01-27 Method for quickly connecting broken pile of rotary drilling cast-in-place pile Pending CN112962583A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110112493.8A CN112962583A (en) 2021-01-27 2021-01-27 Method for quickly connecting broken pile of rotary drilling cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110112493.8A CN112962583A (en) 2021-01-27 2021-01-27 Method for quickly connecting broken pile of rotary drilling cast-in-place pile

Publications (1)

Publication Number Publication Date
CN112962583A true CN112962583A (en) 2021-06-15

Family

ID=76273186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110112493.8A Pending CN112962583A (en) 2021-01-27 2021-01-27 Method for quickly connecting broken pile of rotary drilling cast-in-place pile

Country Status (1)

Country Link
CN (1) CN112962583A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1858364A (en) * 2005-05-08 2006-11-08 宋亚非 Secondary pouring method for preventing broken pile accident in pile pouring construction
JP2007138470A (en) * 2005-11-16 2007-06-07 Tekken Constr Co Ltd Reinforcing cage, construction method of cast-in-place concrete pile, and cast-in-place concrete pile
CN101871211A (en) * 2010-07-13 2010-10-27 武汉一冶交通工程有限责任公司 Wet pile extension method for cast-in place pile
CN110004925A (en) * 2019-04-04 2019-07-12 中国葛洲坝集团第一工程有限公司 Breakage of cast-in-place bored pile processing unit and construction method
CN111733823A (en) * 2020-06-15 2020-10-02 中冶地集团西北岩土工程有限公司 Grouting pipe burying structure and broken pile processing method in cast-in-situ bored pile pouring process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1858364A (en) * 2005-05-08 2006-11-08 宋亚非 Secondary pouring method for preventing broken pile accident in pile pouring construction
JP2007138470A (en) * 2005-11-16 2007-06-07 Tekken Constr Co Ltd Reinforcing cage, construction method of cast-in-place concrete pile, and cast-in-place concrete pile
CN101871211A (en) * 2010-07-13 2010-10-27 武汉一冶交通工程有限责任公司 Wet pile extension method for cast-in place pile
CN110004925A (en) * 2019-04-04 2019-07-12 中国葛洲坝集团第一工程有限公司 Breakage of cast-in-place bored pile processing unit and construction method
CN111733823A (en) * 2020-06-15 2020-10-02 中冶地集团西北岩土工程有限公司 Grouting pipe burying structure and broken pile processing method in cast-in-situ bored pile pouring process

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
余刚: "浅谈桥梁钻孔灌注桩断桩处理及预防措施", 《广东建材》 *
彭成锦: "浅谈桥梁工程灌注桩施工中导管堵塞的处理方法", 《民营科技》 *

Similar Documents

Publication Publication Date Title
CN108560541B (en) Rotary drilling full-casing follow-up rock face drilling construction method
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN105239563A (en) Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method
CN108797569A (en) A kind of control method that drilled pile novel energy-conserving pile crown is superfilled
CN104110028B (en) A kind of dry operation boring is without the cast-in-place pile construction method of water law concrete perfusion
CN111236216A (en) Construction method of bridge drilled pile
CN112482372A (en) Defect repairing method for cast-in-place pile
CN110805029A (en) Subway underground-excavated station drilling and grouting fender post construction method
CN112609690A (en) Construction method of rotary drilling cast-in-place pile in sea-filling geological complex area
CN110306536A (en) A kind of mud off pore-creating filling pile construction technology
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN114808923B (en) Cave grouting construction treatment method
CN111236214A (en) Construction method for constructing secant pile by lengthening protective cylinder of rotary drilling rig
CN112962583A (en) Method for quickly connecting broken pile of rotary drilling cast-in-place pile
CN110714459A (en) Construction method of cast-in-situ bored pile
CN115030142A (en) Pile foundation engineering construction method
CN112302039A (en) Tunnel portal shallow-buried slope collapse volume treatment construction method
CN211735404U (en) Anti-over-irrigation system for long spiral bored pile
CN113404042A (en) Bridge pile position construction method
CN110485413B (en) Combined type protection rapid hole forming method for pile foundation of viaduct adjacent to subway
CN111691426A (en) Comprehensive construction method for non-occluded water stop pile of deep foundation pit drilling support structure
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile
CN112647492A (en) Dry hole forming construction method for rotary-excavated cast-in-place pile under high-fill geological condition
CN110805052A (en) Comprehensive treatment method for sudden surge of ultra-deep foundation pit
CN115404845B (en) Soil dissolving hole treatment construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210615

RJ01 Rejection of invention patent application after publication