CN1851151A - Internal-tamping immersed tube bored concrete tamping-extending pile construction method - Google Patents
Internal-tamping immersed tube bored concrete tamping-extending pile construction method Download PDFInfo
- Publication number
- CN1851151A CN1851151A CN 200610039707 CN200610039707A CN1851151A CN 1851151 A CN1851151 A CN 1851151A CN 200610039707 CN200610039707 CN 200610039707 CN 200610039707 A CN200610039707 A CN 200610039707A CN 1851151 A CN1851151 A CN 1851151A
- Authority
- CN
- China
- Prior art keywords
- outer tube
- tamping
- tube
- soil body
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title abstract description 10
- 238000000465 moulding Methods 0.000 claims abstract description 15
- 239000002689 soil Substances 0.000 claims description 21
- 238000000034 method Methods 0.000 claims description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 238000009792 diffusion process Methods 0.000 claims description 4
- 230000005484 gravity Effects 0.000 claims description 3
- 238000004080 punching Methods 0.000 claims description 3
- 230000007613 environmental effect Effects 0.000 abstract description 4
- 238000005516 engineering process Methods 0.000 description 2
- 238000005056 compaction Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses an inner-tamping, pipe-immersing poured and tamp-expanded pile construction method, comprising the steps of moving and spotting machine, forming by tamp-expansion, pouring molding, pipe drawing forming, etc. And it has characters of low construction noise, little environmental influence, good environmental protectiveness, reliable construction quality and good pile body quality.
Description
Technical field:
The present invention relates to a kind of job practices.
Background technology:
The form that the construction technology of existing tube-sinking cast-in-situ pile, compaction pile generally adopts diesel hammer or vibrating hammer directly to hit the outer tube inner tamping tube, its construction noise is big, and vibration is big, and is bigger to the influence of surrounding environment, has some undesirable parts.
Summary of the invention:
The object of the present invention is to provide a kind of construction noise little, little to ambient influnence, the feature of environmental protection is good, the job practices of the internal-tamping immersed tube bored concrete tamping-extending pile of reliable construction quality.
Technical solution of the present invention is:
A kind of job practices of internal-tamping immersed tube bored concrete tamping-extending pile is characterized in that: comprise the following steps:
(1) telephone-moving is in place: mobile device is located in outer tube on the setting stake position;
(2) immersed tube: outer tube is sunk down into set depth;
(3) ram to expand moulding: on carry interior hammer ram in the outer tube, once throw in the outer tube by the setting height H that feeds intake, on pull out outer tube certain altitude h, interior hammer ram is rammed inserts repeatedly and is formed enlarged footing, by adjusting size, the shape that shape factor α=h/H wherein adjusts tamper diffusion head, α value (0,1) wherein;
(4) build moulding: on carry interior hammer ram, build pile body or transfer precast pile;
(5) tube drawing moulding: extract outer tube, forming pile.
Immersed tube method in the step (2) is:
(a) ram the soil body in: the interior hammer ram in the outer tube is mentioned do the movement of falling object, the soil body under the punching outer tube forms soil body sheared edge;
(b) outer tube sinks: outer tube adopts one of following method to sink at least: 1. under the outer tube deadweight, outer tube sinks from gravity along soil body sheared edge; 2. start the water booster system on the outer tube, outer tube sinks along the pressurization of soil body sheared edge; 3. start the vibrating device on the outer tube, outer tube is along soil body sheared edge vibration-sunk; 4. start vibration and water booster system on the outer tube simultaneously, outer tube along soil body sheared edge shake depress heavy;
(c) mutual (a) and (b) step sinks down into set depth until outer tube.
Immersed tube method in the step (2) is: bury shoe underground in the outer tube bottom, adopt external force that outer tube is sunk down into set depth simultaneously.
Construction noise of the present invention is little, little to ambient influnence, and the feature of environmental protection is good, reliable construction quality, and pile quality is good.
The invention will be further described below in conjunction with embodiment.
The specific embodiment:
Embodiment 1:
A kind of job practices of internal-tamping immersed tube bored concrete tamping-extending pile comprises the following steps:
(1) telephone-moving is in place: mobile device is located in outer tube on the setting stake position;
(2) immersed tube: outer tube is sunk down into set depth, and concrete grammar is:
(a) ram the soil body in: the interior hammer ram in the outer tube is mentioned do the movement of falling object, the soil body under the punching outer tube forms soil body sheared edge;
(b) outer tube sinks: outer tube adopts one of following method to sink at least: 1. under the outer tube deadweight, outer tube sinks from gravity along soil body sheared edge; 2. start the water booster system on the outer tube, outer tube sinks along the pressurization of soil body sheared edge; 3. start the vibrating device on the outer tube, outer tube is along soil body sheared edge vibration-sunk; 4. start vibration and water booster system on the outer tube simultaneously, outer tube along soil body sheared edge shake depress heavy;
(c) mutual (a) and (b) step sinks down into set depth until outer tube.
(3) ram to expand moulding: on carry interior hammer ram in the outer tube, once throw in the outer tube by the setting height H that feeds intake, on pull out outer tube certain altitude h, interior hammer ram is rammed inserts repeatedly and is formed enlarged footing, by adjusting size, the shape that shape factor α=h/H wherein adjusts tamper diffusion head, α value (0,1) wherein;
(4) build moulding: on carry interior hammer ram, build pile body or transfer precast pile;
(5) tube drawing moulding: directly tube drawing moulding.
Embodiment 2:
A kind of job practices of internal-tamping immersed tube bored concrete tamping-extending pile comprises the following steps:
(1) telephone-moving is in place: mobile device is located in outer tube on the setting stake position;
(2) immersed tube: outer tube is sunk down into set depth, and concrete grammar is:
Bury shoe underground in the outer tube bottom, adopt external force that outer tube is sunk down into set depth simultaneously.
(3) ram to expand moulding: on carry interior hammer ram in the outer tube, once throw in the outer tube by the setting height H that feeds intake, on pull out outer tube certain altitude h, interior hammer ram is rammed inserts repeatedly and is formed enlarged footing, by adjusting size, the shape that shape factor α=h/H wherein adjusts tamper diffusion head, α value (0,1) wherein;
(4) build moulding: on carry interior hammer ram, build pile body or transfer precast pile;
(5) tube drawing moulding: the mode that adopts direct tube drawing and vibration pipe-drawing to carry out alternately, tube drawing moulding.
Claims (3)
1, a kind of job practices of internal-tamping immersed tube bored concrete tamping-extending pile is characterized in that: comprise the following steps:
(1) telephone-moving is in place: mobile device is located in outer tube on the setting stake position;
(2) immersed tube: outer tube is sunk down into set depth;
(3) ram to expand moulding: on carry interior hammer ram in the outer tube, once throw in the outer tube by the setting height H that feeds intake, on pull out outer tube certain altitude h, interior hammer ram is rammed inserts repeatedly and is formed enlarged footing, by adjusting size, the shape that shape factor α=h/H wherein adjusts tamper diffusion head, α value (0,1) wherein;
(4) build moulding: on carry interior hammer ram, build pile body or transfer precast pile;
(5) tube drawing moulding: extract outer tube, forming pile.
2, the job practices of internal-tamping immersed tube bored concrete tamping-extending pile according to claim 1 is characterized in that: the immersed tube method in the step (2) is:
(a) ram the soil body in: the interior hammer ram in the outer tube is mentioned do the movement of falling object, the soil body under the punching outer tube forms soil body sheared edge;
(b) outer tube sinks: outer tube adopts one of following method to sink at least: 1. under the outer tube deadweight, outer tube sinks from gravity along soil body sheared edge; 2. start the water booster system on the outer tube, outer tube sinks along the pressurization of soil body sheared edge; 3. start the vibrating device on the outer tube, outer tube is along soil body sheared edge vibration-sunk; 4. start vibration and water booster system on the outer tube simultaneously, outer tube along soil body sheared edge shake depress heavy;
(c) mutual (a) and (b) step sinks down into set depth until outer tube.
3, the job practices of internal-tamping immersed tube bored concrete tamping-extending pile according to claim 1 is characterized in that: the immersed tube method in the step (2) is: bury shoe underground in the outer tube bottom, adopt external force that outer tube is sunk down into set depth simultaneously.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100397079A CN100480474C (en) | 2006-04-06 | 2006-04-06 | Internal-tamping immersed tube bored concrete tamping-extending pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100397079A CN100480474C (en) | 2006-04-06 | 2006-04-06 | Internal-tamping immersed tube bored concrete tamping-extending pile construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1851151A true CN1851151A (en) | 2006-10-25 |
CN100480474C CN100480474C (en) | 2009-04-22 |
Family
ID=37132652
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006100397079A Expired - Fee Related CN100480474C (en) | 2006-04-06 | 2006-04-06 | Internal-tamping immersed tube bored concrete tamping-extending pile construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100480474C (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102400461A (en) * | 2010-09-17 | 2012-04-04 | 张卫国 | Static pressure immersed tube free drop hammer concrete expanded bore pile tamping process |
CN102444122A (en) * | 2011-04-25 | 2012-05-09 | 朱建新 | Construction method of pile |
CN103821138A (en) * | 2012-07-02 | 2014-05-28 | 朱建新 | Composite pile construction method |
WO2020211285A1 (en) * | 2019-04-17 | 2020-10-22 | 朱建新 | Inspection and construction method for composite cement-soil pile |
WO2020211286A1 (en) * | 2019-04-17 | 2020-10-22 | 朱建新 | Method for constructing full-casing full-rotary internal-ramming pile |
CN112502137A (en) * | 2020-11-30 | 2021-03-16 | 陈远 | Construction method of pile and special equipment |
-
2006
- 2006-04-06 CN CNB2006100397079A patent/CN100480474C/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102400461A (en) * | 2010-09-17 | 2012-04-04 | 张卫国 | Static pressure immersed tube free drop hammer concrete expanded bore pile tamping process |
CN102444122A (en) * | 2011-04-25 | 2012-05-09 | 朱建新 | Construction method of pile |
CN103821138A (en) * | 2012-07-02 | 2014-05-28 | 朱建新 | Composite pile construction method |
CN103821138B (en) * | 2012-07-02 | 2016-09-07 | 朱建新 | The construction method of composite pile |
WO2020211285A1 (en) * | 2019-04-17 | 2020-10-22 | 朱建新 | Inspection and construction method for composite cement-soil pile |
WO2020211286A1 (en) * | 2019-04-17 | 2020-10-22 | 朱建新 | Method for constructing full-casing full-rotary internal-ramming pile |
CN112502137A (en) * | 2020-11-30 | 2021-03-16 | 陈远 | Construction method of pile and special equipment |
Also Published As
Publication number | Publication date |
---|---|
CN100480474C (en) | 2009-04-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1851151A (en) | Internal-tamping immersed tube bored concrete tamping-extending pile construction method | |
CN102226341A (en) | Construction method for piles | |
CN101798809B (en) | Non-borrow composite underreamed pile constructing method | |
CN105350525A (en) | Construction method for piles | |
CN102733377B (en) | Method for constructing concrete pile | |
CN106049465B (en) | A kind of construction method of | |
CN1603522A (en) | Composite pile foundation construction method | |
CN105839638A (en) | Convenient and efficient construction method for piles | |
CN101298772A (en) | Static pressure sunken tube pedestal concrete pile construction method | |
CN106192999A (en) | The construction method of uplift pile | |
CN1052284C (en) | Method for construction of concrete pile | |
CN1434174A (en) | Cross thin wall pipe-sinking device for vibration pipe-sinking pile-dilling machine and pile-filling method thereof | |
EP1857597A3 (en) | Method and pile-driving device for inserting foundation piles into the ground | |
RU2466239C1 (en) | Method to manufacture cast-in-place piles | |
CN106049464A (en) | Construction method for pile | |
CN101936004A (en) | Precast expanding pile as well as construction method and construction mechanical equipment thereof | |
CN1182301C (en) | Technology for boring and prefabricating cast piles for foundation of building | |
CN106013093B (en) | A kind of pile construction method | |
CN102345287A (en) | Construction method of large-diameter cast-in-situ thin-wall concrete composite pile and special hole forming device | |
CN1214158C (en) | Method for construction of cast-in-place concrete anchor pile | |
CN112240022A (en) | Construction method and construction equipment for static pressure immersed tube pile | |
CN106088085B (en) | Pile construction method | |
CN1851144A (en) | Column-hammer strong-tamper displacing base kit supporting construction method | |
CN1279248C (en) | Static force top pressing cast-in-place pile device and construction method | |
FR2909395B1 (en) | METHOD FOR REINFORCING FOUNDATIONS COMPRISING A SLAB IN THE SOIL, IN PARTICULAR FOUNDATIONS FOR PYLâNES, AND STRUCTURE OBTAINED |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090422 |