CN1609341A - 高架桥梁架设施工工艺 - Google Patents

高架桥梁架设施工工艺 Download PDF

Info

Publication number
CN1609341A
CN1609341A CN 200310108096 CN200310108096A CN1609341A CN 1609341 A CN1609341 A CN 1609341A CN 200310108096 CN200310108096 CN 200310108096 CN 200310108096 A CN200310108096 A CN 200310108096A CN 1609341 A CN1609341 A CN 1609341A
Authority
CN
China
Prior art keywords
beam sections
sections
formation machine
collapses
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200310108096
Other languages
English (en)
Inventor
金仁兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOUNDATION ENGINEERING Co OF SHANGHAI CITY
Original Assignee
FOUNDATION ENGINEERING Co OF SHANGHAI CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOUNDATION ENGINEERING Co OF SHANGHAI CITY filed Critical FOUNDATION ENGINEERING Co OF SHANGHAI CITY
Priority to CN 200310108096 priority Critical patent/CN1609341A/zh
Publication of CN1609341A publication Critical patent/CN1609341A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种高架桥梁架设施工工艺,该工艺包括如下步骤:(a)安装上行式架桥机;(b)将整垮节段梁按一定的次序悬挂于主桁架上;(c)在各个节段梁拼接面上涂粘结剂,利用起重机小车移动节段梁以缩小梁间缝隙并张拉临时预应力,调整悬吊杆以确保所有节段梁垂直,并对节段梁穿预应力钢丝索、安装锚具、垫片、夹具;(d)松开悬吊杆降低支撑千斤顶使整垮节段梁支撑在临时支座上;经过上述工艺步骤,预应力节段梁结构体系转换得以完成,形成简支结构,高架桥节段梁的架设基本完成。应用本发明进行施工,占地小,人工成本低、效率高。同时,也便于施工管理人员对施工安全和施工质量更好的控制。

Description

高架桥梁架设施工工艺
                            技术领域
本发明涉及一种专用于架设或装配桥梁的方法,特别是涉及一种采用上行式架桥机对高架桥梁进行逐跨拼装架设的施工工艺。
目前国内城市高架桥梁架设中普遍采用满堂支架现浇的施工工艺或者采用吊机进行预制梁吊装的施工工艺。上述两种施工方法都需要较大的施工场地、大量的劳务人员和大吨位的起重吊机,施工过程中会占用较大的施工场地,给城市交通带来很大的不便。现有的高架桥梁架设施工工艺还存在施工周期长、成本高,对周边城市环境和居民生活影响大等缺点,因此亟待改进。
                            发明内容
本发明的目的在于克服现有高架桥梁架设施工工艺存在的施工周期长,成本高,对交通影响大等相关缺点,提供一种经过改进的高架桥梁架设施工工艺。
为了实现上述目的,本发明采取的技术方案:一种高架桥梁架设施工工艺,所述工艺包括如下步骤:
(a)在已经完成的桥墩上安装上行式架桥机,使架桥机纵向、横向正确就位,调制好架桥机的标高和纵坡;
(b)通过运梁车将节段梁运至架桥机正下方,吊架(1)吊住节段梁,前后移动起重机小车(4)来调整节段梁的位置,将整垮节段梁按一定的次序悬挂于主桁架(5)上,第一块节段梁和最后一块节段梁必须同时落在临时支座上;
(c)将第一块节段梁固定后,调整节段梁之间间隙,在各个节段梁拼接面上涂粘结剂,利用起重机小车(4)移动节段梁以缩小梁间缝隙并张拉临时预应力,调整悬吊杆以确保所有节段梁垂直,对所有节段梁拼接面完成粘结剂处理后,穿预应力钢丝索、安装锚具、垫片、夹具;
(d)张拉千斤顶,使整个跨度的节段梁荷载都支撑在千斤顶上,当整垮节段梁形成简支结构后,松开悬吊杆降低支撑千斤顶使整垮节段梁支撑在临时支座上;
通过上述工艺步骤,预应力节段梁结构体系转换得以完成,形成简支结构。
所述步骤(b)中起吊第一块节段梁应使其尽量靠近后支腿(3),整垮节段梁的起吊顺序是先两边后中间对称进行,第一块节段梁和第二块节段梁之间的间隙为30cm,其余的节段梁之间间隙为10cm。
本发明的有益效果在于,采用本发明进行高架桥梁架设,施工占地小,几乎不会影响施工现场的地面交通,施工中需要的工人数量少,只需要较少的工人就可完成整栋桥梁的架设,降低了施工的人工成本。本发明效率高,施工速度较快,工人熟悉施工操作以后,每六天就可完成一跨架设。本发明仪器设备简单在施工中操作方便,施工管理人员容易控制施工安全和施工质量。采用本发明进行节段拼装的施工环境比较整洁,对城市卫生和周边环境的影响都较以往的施工方法大大降低。
                             附图说明
图1是所述上行式架桥机立面示意图;
图2是所述上行式架桥机节段梁拼装图一;
图3是所述上行式架桥机节段梁拼装图二。
                           具体实施方式
下面结合附图1、2、3,对本发明进一步详细描述:如图1所示,一种高架桥梁架设施工工艺,步骤包括:(a)整跨节段粱在预制厂采用定型钢模板预制制作,在已经完成的桥墩上安装上行式架桥机,使架桥机纵向、横向正确就位,调制好架桥机的标高和纵坡,架桥机的安装顺序是安装墩顶牛腿、安装前支腿2和后支腿3、安装架桥机支腿小横梁、安装主桁架5、安装台车、安装双机台吊主桁架、安装起重机小车4;(b)通过运梁车将节段梁运至架桥机正下方,吊架1吊住节段梁,前后移动起重机小车4来调整节段梁的位置,将整垮节段梁按一定的次序悬挂于主桁架5上,第一块节段梁和最后一块节段梁必须同时落在临时支座上;(c)第一块节段是整跨节段梁的基准,必须精确定位并与前一跨梁临时固定,将第一块节段梁固定后调整各节段梁之间间隙,在各个节段梁拼接面上涂粘结剂,利用起重机小车4移动节段梁以缩小梁间缝隙并张拉临时预应力,调整悬吊杆以确保所有节段梁垂直,对所有节段梁拼接面完成粘结剂处理后,穿预应力钢丝索、安装锚具、垫片、夹具;(d)张拉千斤顶,使整个跨度的荷载都支撑在千斤顶上,当整垮节段梁形成简支结构后,松开悬吊杆降低支撑千斤顶使整垮节段梁支撑在临时支座上;通过上述工艺步骤,预应力节段梁结构体系转换得以完成,形成简支结构,如图3所示。所述步骤(b)中起吊第一块节段梁应使其尽量靠近后支腿3(距墩中心线),整垮节段梁的起吊顺序是先两边后中间对称进行,如有十一块节段梁则按照2#、11#、10#、4#、9#、5#、8#、7#、最后6#的顺序依次将所有节段梁吊起,第一块节段梁和第二块节段梁之间的间隙为30cm,其余的节段梁之间间隙为10cm,如图2所示。
本发明所述高架桥梁架设施工工艺在具体施工中应注意以下几个方面:
一是架桥机的施工,包括架桥机的行走、架桥机的固定就位、节段的固定、节段的调整、节段的粘结和预应力筋的张拉这些步骤,每一个步骤,均须谨慎操作:仔细检查,以保证作业安全。
二是施工顺序应严格遵守质量控制和监测方案,一项检查合格以后才能开展下一个项目的安装工作,以达到质量和安全的双重保障。

Claims (2)

1.一种高架桥梁架设施工工艺,其特征在于所述工艺包括如下步骤:
(a)在已经完成的桥墩上安装上行式架桥机,使架桥机纵向、横向正确就位,调制好架桥机的标高和纵坡;
(b)通过运梁车将节段梁运至架桥机正下方,吊架(1)吊住节段梁,前后移动起重机小车(4)来调整节段梁的位置,将整垮节段梁按一定的次序悬挂于主桁架(5)上,第一块节段梁和最后一块节段梁必须同时落在临时支座上;
(c)将第一块节段梁固定后,调整节段梁之间间隙,在各个节段梁拼接面上涂粘结剂,利用起重机小车(4)移动节段梁以缩小梁间缝隙并张拉临时预应力,调整悬吊杆以确保所有节段梁垂直,对所有节段梁拼接面完成粘结剂处理后,穿预应力钢丝索、安装锚具、垫片、夹具;
(d)张拉千斤顶,使整个跨度的节段梁荷载都支撑在千斤顶上,当整垮节段梁形成简支结构后,松开悬吊杆降低支撑千斤顶使整垮节段梁支撑在临时支座上;
通过上述工艺步骤,预应力节段梁结构体系转换得以完成,形成简支结构。
2.根据权利要求1所述的一种高架桥梁架设施工工艺,其特征在于所述步骤(b)中起吊第一块节段梁应使其尽量靠近后支腿(3),整垮节段梁的起吊顺序是先两边后中间对称进行,第一块节段梁和第二块节段梁之间的间隙为30cm,其余的节段梁之间间隙为10cm。
CN 200310108096 2003-10-22 2003-10-22 高架桥梁架设施工工艺 Pending CN1609341A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200310108096 CN1609341A (zh) 2003-10-22 2003-10-22 高架桥梁架设施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200310108096 CN1609341A (zh) 2003-10-22 2003-10-22 高架桥梁架设施工工艺

Publications (1)

Publication Number Publication Date
CN1609341A true CN1609341A (zh) 2005-04-27

Family

ID=34758462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200310108096 Pending CN1609341A (zh) 2003-10-22 2003-10-22 高架桥梁架设施工工艺

Country Status (1)

Country Link
CN (1) CN1609341A (zh)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101798875A (zh) * 2010-03-16 2010-08-11 南通华荣建设集团有限公司 单侧张拉有粘接预应力高跨大梁施工方法
CN101338683B (zh) * 2007-07-04 2010-09-15 祐彬营造股份有限公司 逐跨逆打桥梁工法
CN101230560B (zh) * 2007-01-24 2010-12-08 董兰田 液压升降塔斜拉龙门桥梁吊装车
CN102877419A (zh) * 2012-11-01 2013-01-16 河北益铁机电科技有限公司 预应力施工系统
CN103031811A (zh) * 2012-12-28 2013-04-10 中铁十一局集团有限公司 适用于极小曲线半径桥梁架设的节段拼装架桥机
CN101535571B (zh) * 2006-08-23 2013-05-29 科雷格有限责任公司 桥翻转方法
CN105780667A (zh) * 2016-05-16 2016-07-20 贵州路桥集团有限公司 空心板专用轻型架桥机
CN106759909A (zh) * 2016-12-15 2017-05-31 中建城市建设发展有限公司 一种下挂上承结构体系及其施工方法
CN106760572A (zh) * 2016-12-29 2017-05-31 上海建工五建集团有限公司 预制水平构件与叠合梁连接处快速定位调整工装及方法
CN107313358A (zh) * 2017-08-30 2017-11-03 中国建筑第五工程局有限公司 用于大纵坡工况下的架梁方法及架桥机
CN108149588A (zh) * 2017-12-27 2018-06-12 福建聚云科技股份有限公司 一种适应小曲线半径桥梁的节段拼装架桥机
CN108330842A (zh) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 一种大跨度钢混组合梁架设施工的架桥机及施工方法
CN108453132A (zh) * 2017-12-28 2018-08-28 上海二十冶建设有限公司 一种超薄带生产线热箱模块化安装方法
CN109537454A (zh) * 2018-11-01 2019-03-29 上海市政工程设计研究总院(集团)有限公司 一种预制节段拼装箱梁双幅同步施工方法
CN110093862A (zh) * 2019-05-31 2019-08-06 浙江省交通规划设计研究院有限公司 可实现纵横向拼装的三工作面架桥机及盖梁无便道节段拼装工法
CN111236077A (zh) * 2020-02-13 2020-06-05 中国水利水电第十一工程局有限公司 一种钢箱梁卸载施工方法
CN112030772A (zh) * 2020-09-14 2020-12-04 河南省交通规划设计研究院股份有限公司 连续刚构桥的快速施工方法

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101535571B (zh) * 2006-08-23 2013-05-29 科雷格有限责任公司 桥翻转方法
CN101230560B (zh) * 2007-01-24 2010-12-08 董兰田 液压升降塔斜拉龙门桥梁吊装车
CN101338683B (zh) * 2007-07-04 2010-09-15 祐彬营造股份有限公司 逐跨逆打桥梁工法
CN101798875B (zh) * 2010-03-16 2011-04-13 南通华荣建设集团有限公司 单侧张拉有粘接预应力高跨大梁施工方法
CN101798875A (zh) * 2010-03-16 2010-08-11 南通华荣建设集团有限公司 单侧张拉有粘接预应力高跨大梁施工方法
CN102877419A (zh) * 2012-11-01 2013-01-16 河北益铁机电科技有限公司 预应力施工系统
CN102877419B (zh) * 2012-11-01 2014-07-16 河北益铁机电科技有限公司 预应力施工系统
CN103031811A (zh) * 2012-12-28 2013-04-10 中铁十一局集团有限公司 适用于极小曲线半径桥梁架设的节段拼装架桥机
CN105780667B (zh) * 2016-05-16 2017-08-25 贵州路桥集团有限公司 空心板专用轻型架桥机
CN105780667A (zh) * 2016-05-16 2016-07-20 贵州路桥集团有限公司 空心板专用轻型架桥机
CN106759909B (zh) * 2016-12-15 2019-05-31 中建城市建设发展有限公司 一种下挂上承结构体系及其施工方法
CN106759909A (zh) * 2016-12-15 2017-05-31 中建城市建设发展有限公司 一种下挂上承结构体系及其施工方法
CN106760572A (zh) * 2016-12-29 2017-05-31 上海建工五建集团有限公司 预制水平构件与叠合梁连接处快速定位调整工装及方法
CN107313358A (zh) * 2017-08-30 2017-11-03 中国建筑第五工程局有限公司 用于大纵坡工况下的架梁方法及架桥机
CN107313358B (zh) * 2017-08-30 2019-01-04 中国建筑第五工程局有限公司 用于大纵坡工况下的架梁方法及架桥机
CN108149588A (zh) * 2017-12-27 2018-06-12 福建聚云科技股份有限公司 一种适应小曲线半径桥梁的节段拼装架桥机
CN108453132B (zh) * 2017-12-28 2020-10-02 上海二十冶建设有限公司 一种超薄带生产线热箱模块化安装方法
CN108453132A (zh) * 2017-12-28 2018-08-28 上海二十冶建设有限公司 一种超薄带生产线热箱模块化安装方法
CN108330842A (zh) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 一种大跨度钢混组合梁架设施工的架桥机及施工方法
CN108330842B (zh) * 2018-04-19 2024-04-26 郑州新大方重工科技有限公司 一种大跨度钢混组合梁架设施工的架桥机及施工方法
CN109537454A (zh) * 2018-11-01 2019-03-29 上海市政工程设计研究总院(集团)有限公司 一种预制节段拼装箱梁双幅同步施工方法
CN110093862B (zh) * 2019-05-31 2024-04-05 浙江数智交院科技股份有限公司 可实现纵横向拼装的三工作面架桥机及盖梁无便道节段拼装工法
CN110093862A (zh) * 2019-05-31 2019-08-06 浙江省交通规划设计研究院有限公司 可实现纵横向拼装的三工作面架桥机及盖梁无便道节段拼装工法
CN111236077A (zh) * 2020-02-13 2020-06-05 中国水利水电第十一工程局有限公司 一种钢箱梁卸载施工方法
CN112030772A (zh) * 2020-09-14 2020-12-04 河南省交通规划设计研究院股份有限公司 连续刚构桥的快速施工方法

Similar Documents

Publication Publication Date Title
CN1609341A (zh) 高架桥梁架设施工工艺
CN201826525U (zh) 建筑爬升模板体系装置
CN103290784B (zh) 拱梁结合桥吊装施工方法
CN107905111A (zh) 一种刚构连续梁边跨施工工艺
CN1908335A (zh) 悬浮架施工方法
JP2967876B1 (ja) コンクリート床版の形成方法及び上路式吊構造橋の構築方法
CN111622126B (zh) 高山岩区高空垂直载人通道的施工方法
JP3110985B2 (ja) 張出架設桁橋の柱頭部の施工方法
CN2816164Y (zh) 现浇钢筋砼空中连廊
CN100542944C (zh) 两台千斤顶串联下放超重结构的方法
JPH09317183A (ja) 建造物構築方法
CN114892813B (zh) 一种大跨度建筑主体支撑钢结构及施工方法
CN115182269A (zh) 一种超高墩大截面重型液压爬模分次拼装方法
CN114370008A (zh) 一种快速提升桥梁承载能力的加固系统及其施工方法
CN109205475B (zh) 隧洞内桁架联系梁式门机装拆装置及方法
CN206801589U (zh) 隧道锚段二衬混凝土施工无拆卸台车
CN206769198U (zh) 分离组合式钢筋混凝土预制块锚固端支撑结构
CN111549688A (zh) 一种整跨拆除连续桥梁梁体的静力提吊装置及施工方法
CN105507160B (zh) 现浇箱梁移动式贝雷梁操作平台施工方法
CN215714720U (zh) 一种快速提升桥梁承载能力的加固系统
CN210798994U (zh) 混凝土结构墙体单侧模板结构
CN219604164U (zh) 变截面异形钢塔冠安装装置
CN216766824U (zh) 一种预制板吊拉杆
CN219032955U (zh) 一种桥梁防撞墙模板施工作业平台
CN204000639U (zh) 一种大型墩柱混凝土钢筋整体吊装机械对接装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication