CN1570927A - Die developing management system and method - Google Patents

Die developing management system and method Download PDF

Info

Publication number
CN1570927A
CN1570927A CN 03139913 CN03139913A CN1570927A CN 1570927 A CN1570927 A CN 1570927A CN 03139913 CN03139913 CN 03139913 CN 03139913 A CN03139913 A CN 03139913A CN 1570927 A CN1570927 A CN 1570927A
Authority
CN
China
Prior art keywords
mould
design
server
computing machine
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 03139913
Other languages
Chinese (zh)
Inventor
罗圣淇
黄迎春
武子勇
严俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongfujin Precision Industry Shenzhen Co Ltd
Hon Hai Precision Industry Co Ltd
Original Assignee
Hongfujin Precision Industry Shenzhen Co Ltd
Hon Hai Precision Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongfujin Precision Industry Shenzhen Co Ltd, Hon Hai Precision Industry Co Ltd filed Critical Hongfujin Precision Industry Shenzhen Co Ltd
Priority to CN 03139913 priority Critical patent/CN1570927A/en
Publication of CN1570927A publication Critical patent/CN1570927A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This invention relates to a kind of model developing management method. It can receive the model design demand information from client, and monitor each phase of model developing. It comprises the following steps: receiving the model design demand information from different clients, designing model and producing model design plan according to the above mentioned model design demand information. Arranging the model machining time according to the above mentioned model design plan, and recording the machining condition of model. Testing the model, and recording the testing result of model. Delivering the model and settlement, recording the delivery and settlement condition. The model developing management system is used for implementing the above mentioned method, which comprising a server and several client-end computers, design-end computers, model machining-end computers, model testing-end computers and client service-end computers linked to server through network.

Description

Mould development management system and method
[technical field]
The present invention discloses a kind of mould development management system and method, relates in particular to a kind of mould co-development management system and method for comprehensive management and control mould development.
[background technology]
Economic globalization brings infinite commercial opportunities to enterprise, brings the increasing pressure also for simultaneously the manufacturing of enterprise.On the one hand, customer personalized requirement is more and more higher, and is also more and more stricter to the requirement at quality, delivery date.On the other hand, the production of cross-region and business activities have brought great challenge to management again.Enterprise must adopt new technology, develops new product, and the compressed products life cycle is raised labour productivity, and reduces cost.
Product development process includes product design, mould design, Mould Machining, test manufacture, test and volume production different phase.In the traditional product development process, enterprise is responsible for all processes from the product design to the volume production.For different enterprises, each enterprise all has different technical advantages.For example, one enterprise has certain technical advantage aspect product design, yet it is in the advantage that do not possess skills aspect mould design, Mould Machining or the test, if this enterprise is in the performance history of new product, be responsible for all processes, this not only can increase the Products Development time, also can increase the input of product development, thereby increase the cost of product, and the quality of product also can't guarantee.
Along with, the reinforcement of interfirm cooperation different enterprises occurred and has carried out the product collaborative exploitation according to the technical advantage of oneself, and promptly each enterprise only is responsible for the stage of its advantage that possesses skills, and this has shortened the Products Development time greatly, has also reduced the input of product development.Yet, in the process of product collaborative exploitation, still rely on traditional mode to link up between different enterprises, after designing product design figure shelves (or data) when the enterprise that is responsible for product design, to scheme shelves (or data) and give mould development enterprise with manual type, mould development enterprise gives mould test enterprise (or department) with the mould design figure file (or data) that designs with manual type again and carries out the mould test, this has increased the Products Development time equally, and can't really embody the advantage of Collaborative Product Developing.
Along with computer technology and development of internet technology, can utilize network to transmit designed graphic document (or data) between different enterprises, so, shorten the activity duration of product development greatly.For example Wise property office in Taiwan is 525076 patent in the notification number of on March 21st, 2003 bulletin, and this patent name is " listing system for making network mask of multiple supply chains ".This patent has disclosed a kind of system that utilizes network to carry out the light shield co-development, and the listing system for making network mask of this multiple supply chains comprises: integrated circuit (IC) design side's computing machine; One design service side computing machine; One light shield supplier computing machine; An and network, be used for connecting this integrated circuit (IC) design side's computing machine, this design service side computing machine and this light shield supplier computing machine, wherein this integrated circuit (IC) design side's computing machine is to provide a component design data and a product light shield data to this design service side computing machine via this network; This component design data that this design service side computing machine can be provided this integrated circuit (IC) design side's computing machine and this product light shield data are carried out a treatment step and a data, and to converge synchronizing rapid, and a product light shield manufacture data, and send this light shield supplier's computing machine and this integrated circuit (IC) design side computing machine to via this network; And this light shield supplier computing machine can become light shield according to this product light shield manufacture data make.
The existing deficiency of aforesaid patent is that it only is processing and the transmission of carrying out product related data between different enterprises, yet it has not disclosed how to carry out mould development according to received product design data, and mould development includes each stage such as mould design, Mould Machining, die trial and mould transfer, aforesaid patent is not also carried out effective management and control to each stage of aforesaid mould development, thereby the work compound of the embodiment product development that aforesaid patent also can't be real.
[summary of the invention]
Therefore, at the existing deficiency of prior art, fundamental purpose of the present invention is to provide a kind of mould development management system and method, and it can receive client's mould design requirement information, utilize different departments to carry out the co-development of mould, and each stage of mould development is monitored.
The invention provides a kind of mould development management system, it comprises: a server reaches a plurality of client computers, design end computing machine, Mould Machining end computing machine, mould test lead computing machine and the customer service end computing machine that connects this server by network, wherein server includes: a customer demand receiver module, and it is used to be received from the mould design requirement information of different clients computing machine; One assessment operation module, design end computer log server can obtain aforesaid mould design requirement information, and assesses operation, and it is single to generate assessment; One engineering data is built and is put module, design end computer log server, and build by engineering data and to put the relevant information that module can be set the mould engineering data; One mould design figure file receiver module, the design end computing machine that it is used to receive is according to the mould design figure file of aforementioned mould design requirement information through design; One neck material operation module is used for Mould Machining end computing machine and leads the material operation according to aforesaid mould design figure file, the disposition of record neck material operation; One worker's single job module, it is used for the process time that Mould Machining end computing machine is arranged mould according to aforesaid mould design figure file, the processing disposition of record mould; One die trial operation module, it is used for the disposition of mould test lead computing machine record mould test; One mould is transferred module, and it is used for customer service end computing machine and carries out mould transfer operation and clearing operation, and the record mould is transferred situation and clearing situation.
The invention provides a kind of mould development management method, it includes following steps: the mould design requirement information that receives different clients; Obtain aforesaid mould design requirement information, carry out the mould design evaluation, it is single to generate assessment, will assess single transmit and give respective client, receives client's receipt; Formulate the relevant information of engineering data; Carry out the mould design according to aforementioned mould design requirement information, generate mould design figure file; Lead the material operation, the process time that the disposition of record neck material operation is arranged mould according to aforesaid mould design figure file, the processing disposition of record mould; Carry out the mould assembly operation, the disposition of record mould assembly process; Carry out the die trial operation, the disposition of record mould test; Carry out mould and transfer operation and clearing operation, the record mould is transferred situation and clearing situation.
[description of drawings]
Fig. 1 is the Organization Chart of mould development management system of the present invention.
Fig. 2 is the functional block diagram of mould development Tomcat-AdminPortal of the present invention.
Fig. 3 is the mould design requirement assessment operation process chart of mould development management method of the present invention.
Fig. 4 is the mould development operation process chart of mould development management method of the present invention.
[embodiment]
Consult shown in Figure 1ly, be the Organization Chart of mould development management system of the present invention.It adopts B/S (Browser/Server) framework mould development management system of the present invention, the management platform of one mould development is provided, be used to receive a plurality of clients' mould design requirement information, receive design evaluation and the mould design figure file of mould design department to aforementioned mould design requirement information, and the overall process of management and control mould development.Described mould development management system is formed by a server 2 and by a plurality of client computers 4 and design end computing machine 5, Mould Machining end computing machine 6, mould test lead computing machine 7 and customer service end computing machine 10 that network 3 is connected to server 2.
Wherein client computer 4 its place mould design requirement information side, it moves a series of softwares such as Enterprise Resources Planning software, E-mail software, database management language, figure shelves process software and other instrument general under business environment, can be connected to the mould design requirement information that server 2 of the present invention provides mould design requirement information side by network 3, this mould design requirement information includes name of product, product type and product design figure shelves.Described client can be the external client of enterprise or the different product production division of enterprises.
Server 2 has comprised core and business logic mutability (planning, How It Works, management mode etc.) in the enterprise information system, its function is to receive mould design requirement information that client computer 4 sends, receives mould design evaluation and the mould design figure file of mould design department to aforementioned mould design requirement information, and the overall process transferred of supervision molding design, Mould Machining, mould assembly, die trial and mould.Described mould design is meant that mould design department designs a plurality of mould design figure file of producing this product according to client's product design figure shelves, and each product mold designed graphic document can include a total mould and constitute the designed graphic document of a plurality of submodule tools of this total mould.Mould Machining is meant according to each mould design figure file and processes each submodule tool.Mould assembly is meant that each the submodule tool according to product is assembled into a total mould.Die trial is meant according to total mould and test-manufactures that specimen is unqualified to judge that mould goes out.The mould transfer is meant total mould is consigned to relative clients, and settles accounts.
Server 2 also is connected with a database 9 by linking 8 by it.Linking 8 is a database connections, as the open type data storehouse link (Open Database Connectivity, ODBC), or the Java database connections (Java Database Connectivity, JDBC).Database 9 stores the related data of mould development management system of the present invention, as mould design requirement information, mould design figure file, mould engineering data and mould development progress management and control table 92.Wherein the mould engineering data is noted down the related data of mould, and it includes name of product, type, total pattern number and each sub-pattern number.Mould development progress management and control table 92 is used to note down the related data that mould is developed each stage, and the related data in each stage includes official in charge, start time, concluding time and disposition, and wherein disposition is noted down the detailed process situation in each stage.
In the present invention, design end computing machine 5 places mould design department, it can be desktop PC or portable computer, it can receive client's product design figure shelves, the designer can utilize this design end computing machine 5 designing moulds, and sends the mould design figure file that generates to server 2.Mould Machining end computing machine 6 places Mould Machining department, and it can receive mould design figure file, and Mould Machining personnel are connected to server 2 by this Mould Machining end computing machine 6, the related data of record Mould Machining.Mould test lead computing machine 7 places mould test organization, and mould examination tester is connected to server 2 by this mould test lead computing machine 7 and can carries out the die trial operation, the die trial situation of record mould.Customer service end computing machine 10 places Customer Service Department, and the customer service personnel are connected to server 2 by this customer service end computing machine 10 can carry out mould transfer and clearing operation, the related data that the record mould is transferred and settled accounts.Network 3 can be intranet (Intranet), Internet (Internet) or the network system of other type.
It is described to consult Fig. 2, is the functional block diagram of mould development Tomcat-AdminPortal of the present invention.This server 2 includes a customer demand receiver module 21, an assessment operation module 22, an engineering data and builds and put module 23, a mould design figure file receiver module 24, a neck material operation module 25, worker's single job module 26, a mould assembly module 27, a die trial operation module 28 and a mould and transfer module 29.Wherein customer demand receiver module 21 is used to be received from the mould design requirement information of different clients computing machine 4, and this mould design requirement information includes name of product, product type and product design figure shelves, and it is stored in the database 9.Assessment operation module 22 provides an interface to be used for the mould designer and obtains aforesaid product design figure shelves, and receive mould designer input carry out the result of mould design evaluation according to product design figure shelves, this assessment result includes information such as name of product, product type, die needed quantity and price, and assessment result sent to corresponding client computer 4, and receive the receipt that client computer 4 sends.Engineering data is built and is put module 23 and be used to set the relevant information of mould engineering data and generate a new mould development progress management and control table 92.Mould design figure file receiver module 24 is used to receive the mould design figure file that the mould designer designs, it is stored in the database 9, and the situation that the design of record mould is finished in mould development progress management and control table 92, this mould design performance comprises information such as mould designer title, start time and deadline, and mould design figure file is associated by total pattern number and each sub-pattern number with mould development progress management and control table 92.Neck material operation module 25 is used for the Mould Machining personnel and leads the material operation according to aforesaid mould design figure file, generate material requistion, and this leads the disposition of material operation in the record of mould development progress management and control table 92.Worker's single job module 26 is used for the process time that the Mould Machining personnel arrange each submodule tool and total mould according to aforesaid mould design figure file, and notes down the processing disposition of each submodule tool and total mould in mould development progress management and control table 92.Mould assembly module 27 is used for the disposition of Mould Machining personnel at mould assembly process record mould assembly, and the disposition of this mould assembly is stored in the mould development progress management and control table 92.Die trial operation module 28 is used for the disposition of mould tester in the test of mould test process record mould, the disposition of mould test includes tester's title, start time, concluding time and test status, test status comprises qualified and defective two kinds, and the disposition of this mould test is stored in the mould development progress management and control table 92.Mould is transferred module 29 and is used for the customer service personnel transfer the client to by customer service end computing machine 10 logon servers 2 record moulds situation, and record and client's clearing situation, aforesaid mould is transferred and the clearing situation is embedded in the mould development progress management and control table 92.
It is described to consult Fig. 3, is the mould design requirement assessment operation process chart of mould development management method of the present invention.Server 2 is received from the mould design requirement information of different clients computing machine 4, and this mould design requirement information includes name of product, product type and product design figure shelves, and it is stored in (step S310) in the database 9.The mould designer is by design end computing machine 5 logon servers 2, obtain aforesaid product design figure shelves, and by the mould design evaluation result of assessment operation module 22 inputs according to aforesaid product design figure shelves, this mould design evaluation result is stored in (step S320) in the database 9.It is single that assessment operation module 22 generates assessment according to aforesaid assessment result, and should assess single transmit and give corresponding client computer 4 (step S330).It is single that the client receives assessment, can consider, and judges whether to accept this assessment result (step S340).When not accepting this assessment result, finish All Jobs.When the client accepted aforesaid assessment result, client computer 4 can produce a receipt, and this receipt is sent to server 2 (step S350).The assessment operation module 22 of server 2 receives aforesaid receipt, and it is stored in (step S360) in the database 9.The mould designer utilizes engineering data to build and puts the relevant information (step S370) that module 23 is set the mould engineering data by design end computing machine 5 logon servers 2.Engineering data is built and is put module 23 generations one mould development progress management and control table 92 (step S380).After above-mentioned step is finished, carry out flow process A (please refer to the narration of Fig. 4).
It is described to consult Fig. 4, is the mould development operation process chart of mould development management method of the present invention.The mould designer obtains product design figure shelves by design end computing machine 5 logon servers 2, and according to this product design figure shelves designing mould designed graphic document, and sends mould design figure file to server 2 (step S410).Mould design figure file receiver module 24 receives aforesaid mould design figure file, and it is stored in (step S420) in the database 2.Mould Machining personnel are by Mould Machining end computing machine 6 logon servers 2, obtain mould design figure file, the process time of arranging each submodule tool and total mould by worker's single job module 26, and in mould development progress management and control table 92 the processing disposition (step S430) of each each submodule tool of record and total mould.Lead the material operation by neck material operation module 25, record neck material situation generates material requistion (step S440).By mould assembly module 27, Mould Machining personnel note down the disposition (step S450) of mould assembly.In the mould test process, note down the test case (step S460) of mould by die trial operation module 28 mould testers.Judge mould whether qualified (step S470) according to the disposition of mould test.When the test result of mould test when being defective, can carry out step S410 again.When the mould test passes, the customer service personnel are by customer service end computing machine 10 logon servers 2, carry out mould transfer and clearing operation by transferring the operation mould, the record mould is transferred client's situation to, and record and client's clearing situation (step S480).

Claims (15)

1. mould development management system, it is characterized in that, it comprises: a server reaches a plurality of client computers, design end computing machine, Mould Machining end computing machine, mould test lead computing machine and the customer service end computing machine that connects this server by network, and wherein server includes:
One customer demand receiver module, it is used to be received from the mould design requirement information of different clients computing machine;
One mould design figure file receiver module, the design end computing machine that it is used to receive is according to the mould design figure file of aforementioned mould design requirement information through design;
One worker's single job module, it is used for the process time that Mould Machining end computing machine is arranged mould according to aforesaid mould design figure file, the processing disposition of record mould;
One die trial operation module, it is used for the test case of mould test lead computing machine record mould;
One mould is transferred module, and it is used for customer service end computing machine and carries out mould transfer operation and clearing operation, and the record mould is transferred situation and clearing situation.
2. mould development management system as claimed in claim 1, it is characterized in that, server also links a database, this database storing has a mould development progress management and control table, and this mould development progress management and control table is stored test case, the mould of aforesaid Mould Machining disposition, mould and transferred situation and clearing situation.
3. mould development management system as claimed in claim 1 is characterized in that, wherein server also includes an assessment operation module, and design end computer log server can obtain aforesaid mould design requirement information, and assesses operation, and it is single to generate assessment.
4. mould development management system as claimed in claim 1 is characterized in that, wherein server also includes an engineering data and builds and put module, and design end computer log server is built by engineering data and put the relevant information that module can be set the mould engineering data.
5. mould development management system as claimed in claim 1 is characterized in that, wherein server also includes a neck material operation module, is used for Mould Machining end computing machine and leads the material operation according to aforesaid mould design figure file, the disposition of record neck material operation.
6. mould development management system as claimed in claim 5 is characterized in that, wherein server also includes a mould assembly module, is used for the disposition of Mould Machining end computing machine record mould assembly process.
7. mould development management method is characterized in that it includes following steps:
Receive different clients' mould design requirement information;
Carry out the mould design according to aforementioned mould design requirement information, generate mould design figure file;
According to the process time that aforesaid mould design figure file is arranged mould, the processing disposition of record mould;
Carry out the die trial operation, the disposition of record mould test;
Carry out mould and transfer operation and clearing operation, the record mould is transferred situation and clearing situation.
8. mould development management method as claimed in claim 7 is characterized in that, wherein mould design requirement information includes name of product, product type and product design figure shelves.
9. mould development management method as claimed in claim 7 is characterized in that, also includes the assessment operation before the mould design procedure, obtains aforesaid mould design requirement information, carries out the mould design evaluation, and it is single to generate assessment.
10. mould development management method as claimed in claim 9 is characterized in that, also includes the step of the assessment single transmit being given respective client.
11. mould development management method as claimed in claim 10 is characterized in that, also includes the step that receives client's receipt.
12. mould development management method as claimed in claim 7 is characterized in that, also includes engineering data and builds and put step, it can formulate the relevant information of engineering data.
13. mould development management method as claimed in claim 7 is characterized in that, the preceding neck material job step that also includes of Mould Machining step, the disposition of record neck material operation.
14. mould development management method as claimed in claim 7 is characterized in that, the preceding step of carrying out mould assembly that also includes of die trial job step, the disposition of record mould assembly process.
15. a mould development management system, it comprises that a server reaches a plurality of client computers that connect this server by network, is characterized in that wherein server includes:
One customer demand receiver module, it is used to be received from the mould design requirement information of different clients computing machine;
One mould design figure file receiver module, it is used to receive the mould design figure file according to aforementioned mould design requirement information design;
One worker's single job module, it is used for arranging according to aforesaid mould design figure file the process time of mould, the processing disposition of record mould;
One die trial operation module, it is used to note down the test case of mould;
One mould is transferred module, and it is used to carry out mould and transfers operation and clearing operation, and the record mould is transferred situation and clearing situation;
Server also links a database, and this database storing has a mould development progress management and control table, and this mould development progress management and control table is stored test case, the mould of aforesaid Mould Machining disposition, mould and transferred situation and clearing situation.
CN 03139913 2003-07-19 2003-07-19 Die developing management system and method Pending CN1570927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 03139913 CN1570927A (en) 2003-07-19 2003-07-19 Die developing management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 03139913 CN1570927A (en) 2003-07-19 2003-07-19 Die developing management system and method

Publications (1)

Publication Number Publication Date
CN1570927A true CN1570927A (en) 2005-01-26

Family

ID=34470771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 03139913 Pending CN1570927A (en) 2003-07-19 2003-07-19 Die developing management system and method

Country Status (1)

Country Link
CN (1) CN1570927A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100454289C (en) * 2005-09-29 2009-01-21 鸿富锦精密工业(深圳)有限公司 System and method for merging homogeneous hole in workpiece image files
CN101419639B (en) * 2007-10-22 2010-11-10 鸿富锦精密工业(深圳)有限公司 Mold design graph monitoring system and method
CN108764627A (en) * 2018-04-20 2018-11-06 昆山行恰软件科技有限公司 Intelligent die manages system and method
CN109262962A (en) * 2018-09-27 2019-01-25 南京塑维网络科技有限公司 A kind of system and method that injection molding work order generates
CN109977007A (en) * 2019-02-20 2019-07-05 精英制模实业(深圳)有限公司 A kind of PLM mold test and management method and its system
CN110119906A (en) * 2019-05-23 2019-08-13 合肥联宝信息技术有限公司 A kind of method and apparatus of management product quality
CN110264167A (en) * 2019-07-19 2019-09-20 宋岳 A kind of mold intelligence manufacture method and platform

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100454289C (en) * 2005-09-29 2009-01-21 鸿富锦精密工业(深圳)有限公司 System and method for merging homogeneous hole in workpiece image files
CN101419639B (en) * 2007-10-22 2010-11-10 鸿富锦精密工业(深圳)有限公司 Mold design graph monitoring system and method
CN108764627A (en) * 2018-04-20 2018-11-06 昆山行恰软件科技有限公司 Intelligent die manages system and method
CN109262962A (en) * 2018-09-27 2019-01-25 南京塑维网络科技有限公司 A kind of system and method that injection molding work order generates
CN109977007A (en) * 2019-02-20 2019-07-05 精英制模实业(深圳)有限公司 A kind of PLM mold test and management method and its system
CN110119906A (en) * 2019-05-23 2019-08-13 合肥联宝信息技术有限公司 A kind of method and apparatus of management product quality
CN110119906B (en) * 2019-05-23 2022-03-25 合肥联宝信息技术有限公司 Method and device for managing product quality
CN110264167A (en) * 2019-07-19 2019-09-20 宋岳 A kind of mold intelligence manufacture method and platform

Similar Documents

Publication Publication Date Title
CN110599103B (en) Production management subsystem based on intelligent manufacturing MES system
Huang et al. Manufacturing system modeling for productivity improvement
CN104808639B (en) Pharmaceutical product manufacturing execution system and method
CN110580026A (en) intelligent manufacturing MES system
Gunasekaran et al. Agile manufacturing: a taxonomy of strategic and technological imperatives
Lu et al. An IoT-enabled simulation approach for process planning and analysis: a case from engine re-manufacturing industry
KR100971009B1 (en) A product recovery management system
KR20090032049A (en) Quality control system, quality control program, and client device
US20020138317A1 (en) System for implementing an exchange
CN113657730B (en) Integrated execution platform for digital manufacturing
CN112116364A (en) Production and manufacturing tracing system and platform
CN111915167A (en) Intelligent manufacturing virtual shipyard information model construction method
CN112418540A (en) Intelligent MES real-time data analysis system
CN1570927A (en) Die developing management system and method
CN1661606A (en) Product pricing system and method
TWI338262B (en) A system and method for managing module development
CN116859834A (en) Digital control system of microwave assembly full-flow process and workshop data network
CN110826926A (en) Intelligent manufacturing execution system for surface assembly production line
Senthilkumar et al. Implementation of DMAIC methodology in supply chains to reduce customer end-rejections: a case study in an Indian SME
JP3390663B2 (en) Production control method
Rambabu et al. Gap analysis and optimization of process involved in product design and development by integrating enterprise resource planning & product lifecycle management
CN110675112A (en) E-commerce system based on supply chain management
RU2813554C1 (en) Hardware and software system for selection of equipment maintenance and servicing means in machine building
CN1542661A (en) Production field management information system
Jaimes Carvajal Lean Philosophies in a Logistic Operation of tool parts in Forging Process of Oil Filters-A Case Study

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication