CN1542231A CNA2003101113494A CN200310111349A CN1542231A CN 1542231 A CN1542231 A CN 1542231A CN A2003101113494 A CNA2003101113494 A CN A2003101113494A CN 200310111349 A CN200310111349 A CN 200310111349A CN 1542231 A CN1542231 A CN 1542231A
Authority
CN
China
Prior art keywords
reinforcing bar
crevasse
bar
carrying
reinforcement frames
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2003101113494A
Other languages
Chinese (zh)
Inventor
周力平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University WHU
Original Assignee
Wuhan University WHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University WHU filed Critical Wuhan University WHU
Priority to CNA2003101113494A priority Critical patent/CN1542231A/en
Publication of CN1542231A publication Critical patent/CN1542231A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The present invention belongs to the field of flood prevention engineering, and is one emergency burst closing method. The burst closing method includes preparing 4 figure-shaped reinforcing steel bar trusses with empty oil tanks fixed to the bottom; drawing barge and several rows of reinforcing steel bar trusses with tug boat to near the burst; fixing the barge in front of the burst and controlling the drift of the reinforcing steel bar trusses to the burst, breaking the ropes fixing the empty oil tanks to make the trusses sink to the burst; and throwing blocking material from two sides of the burst. The present invention has high burst closing speed.

Description

A kind of method of the shutoff crevasse of speedily carrying out rescue work
Technical field
The invention belongs to the emergency flood fighting field of engineering technology, after particularly a kind of river dike crevasse, the method for the shutoff crevasse of speedily carrying out rescue work fast.
Background technology
At present, when the crevasse of burst dyke, standing in the hydroelectric project commonly used blocked up or flat blocking method shutoff crevasse both at home and abroad.Wherein, upright stifled method is on the crevasse both sides, with artificial or machinery plugging material is thrown and be filled to the embankment crevasse, and the material of piling fixed sealing burst-stopping, shutoff crevasse gradually; Flat stifled method is at the embankment dam breach position, encloses several barges, throws toward dam breach position from the barge and fills out plugging material, in case of necessity at the heavy barge of dam breach position, throws toward dam breach position simultaneously and fills out plugging material, Jiujiang embankment crevasse in 1998, the crevasse of having adopted this method shutoff exactly.Above-mentioned two kinds of methods, the former is on narrow and small embankment, carries out every work of shutoff crevasse in the short period of time with high construction intensity, and the material of jettisoninging in embankment crevasse both sides is very dangerous, cause crevasse to continue to cave in probably, the personnel that speedily carry out rescue work are poured torrent; The latter's construction intensity is big, and the transport of materials difficulty of shutoff, cost are also very high.Both all have quite a few plugging material to be washed away by high-velocity flow, form alluvial in embankment, work such as also need finish desilting after flood season, slag tap.
Summary of the invention
Purpose of the present invention is exactly the deficiency at above-mentioned situation, and a kind of employing control device that provides, the 4 font reinforcement frames that will have the interception function accurately sink to the dam breach position of embankment, before the plugging material that throwing is filled out is intercepted at reinforcement frame, and the method for quick blocking crevasse.
The present invention realizes in the following manner: before arriving flood season, the 4 font reinforcement frames that are prepared in advance, and on the bottom reinforcement bars of framework fixed a plurality of empty oil tubes, 4 font reinforcement frames can be floated on the surface.When burst embankment crevasse incident, with tugboat barge and number are arranged 4 font reinforcement frames and be transported near the crevasse.The fixing barge in embankment crevasse dead ahead, the personnel that speedily carry out rescue work control the drift of 4 font reinforcement frames with cable and move to the embankment dam breach position on barge, enable control device then and disconnect fixed empty oil tube rope, remove the buoyancy of 4 font reinforcement frames, make 4 font reinforcement frames dash the heavy crevasse that enters with current.The plugging material of jettisoninging in embankment crevasse both sides then and since the material that is thrown into crevasse by 4 font reinforcement frames effectively interception before reinforcement frame, stopped the plugging material washout, thereby reached the purpose of quick blocking embankment crevasse.
The invention solves the construction plant of speedily carrying out rescue work on embankment crevasse both sides little, throw contradictions such as the easy washout of underfill material, rescue intensity are big, and after can controlling plugging material and sinking to crevasse, tackled by 4 font reinforcement frames, can significantly reduce simultaneously the use amount of shutoff dam breach position material, avoid plugging material by high-velocity flow wash away the excavation, the desilting that form alluvial and increase, later stage engineering quantity such as slag tap.The present invention has improved the speed of shutoff embankment crevasse greatly, for the quality time is won in the crevasse of quick blocking embankment, thereby reduces the economic loss that flood brings.
Description of drawings
Fig. 1 is the structure chart of 4 font reinforcing bars.
Fig. 2 is the stereogram of a row 4 font reinforcement frame structures among Fig. 1.
Fig. 3 is the sectional drawing with the present invention one row 4 font reinforcement frame structural traps embankment crevasses.
The specific embodiment
Below in conjunction with Figure of description and embodiment the present invention is further described:
By illustrated in figures 1 and 2,1 for the interception reinforcing bar, is used to tackle the plugging material of jettisoninging.2 is anchor bar, is used to insert dam breach position, plays anchorage effect.3 for the carrying reinforcing bar, is used to carry the plugging material of jettisoninging, and also can play the effect of reinforcing 4 font reinforcement frames simultaneously.4 is bearing bar, is used to support the suffered pressure of interception reinforcing bar.5 for supporting steel bar stress, and 6 is fixed reinforcing bar, with several fixed reinforcing bars, a plurality of 4 font reinforcing bars is welded together at a certain distance, forms a structural frame.By shown in Figure 3,7 expression water (flow) directions, 8 is water surface curve, and 9 is the plugging material of jettisoninging, and 10 is embankment.
4 font reinforcement frames are welded a plurality of 4 font reinforcing bars by several fixed reinforcing bars 6 every 10-200cm, interception reinforcing bar 1 is vertical with support steel bar stress 5 with carrying reinforcing bar 3 with anchor bar 2, interception reinforcing bar 1 is positioned at carrying reinforcing bar 3 and supports the top of steel bar stress 5, anchor bar 2 is positioned at carrying reinforcing bar 3 and supports the below of steel bar stress 5, weld mutually with interception reinforcing bar 1 and support steel bar stress 5 respectively at the two ends of bearing bar 4, between interception reinforcing bar 1 and the interception reinforcing bar 1, between carrying reinforcing bar 3 and the carrying reinforcing bar 3, support between steel bar stress 5 and the support steel bar stress 5 and weld mutually by fixed reinforcing bar 6.
Before flood season, be cemented in a plurality of empty oil drums on the bottom carrying reinforcing bar 3 of 4 font reinforcement frames, 4 font reinforcement frames can be floated on the surface.When burst embankment crevasse incident, with tugboat barge and number are arranged 4 font reinforcement frames and be transported near the crevasse.Fix a barge in embankment 10 crevasse dead aheads, the personnel that speedily carry out rescue work move to the embankment dam breach position with the drift of cable control one row 4 font reinforcement frames on barge, enable control device then, disconnect fixed empty oil tube rope as several different methods such as line traffic control, remote control or ignition, remove its buoyancy, make 4 font reinforcement frames dash to sink and enter crevasse with current, the bearing bar 4 of 4 font reinforcement frames and water (flow) direction 7 relative (as shown in Figure 3), and be anchored at dam breach position.Then in embankment crevasse both sides to carrying reinforcing bar 3 places of the 4 font reinforcement frames plugging material 9 of jettisoninging, also available ZL00230474.0 chain type buoying device web material and ZL 00114576.2 float the stream method of intercepting, on barge, control the 4 font reinforcement frame places that the chain type buoying device web material that is loaded with plugging material drifts to crevasse with cable, before plugging material is discharged into framework, shutoff dam breach position current gradually.Effectively tackled before reinforcement frame by 4 font reinforcement frames owing to be thrown into the material of crevasse, stopped the plugging material washout, thereby reached the purpose of quick blocking embankment crevasse.

Claims (2)

1. method of shutoff crevasse of speedily carrying out rescue work is characterized in that: the 4 font reinforcement frames that are prepared in advance, and go up fixed a plurality of empty oil tube at the bottom carrying reinforcing bar (3) of 4 font reinforcement frames; With tugboat barge and number row's 4 font reinforcement frames are transported near the crevasse, the fixing barge in embankment crevasse dead ahead, on barge, control the drift of 4 font reinforcement frames and move to the embankment dam breach position with cable, enable control device then and disconnect fixed empty oil tube rope, 4 font reinforcement frames dash the heavy crevasse that enters with current; The plugging material of jettisoninging in embankment crevasse both sides then.
2. the method for a kind of shutoff crevasse of speedily carrying out rescue work according to claim 1, it is characterized in that: described 4 font reinforcement frames are welded a plurality of 4 font reinforcing bars by several fixed reinforcing bars (6) every 10-200cm, interception reinforcing bar (1) is vertical with support steel bar stress (5) with carrying reinforcing bar (3) with anchor bar (2), interception reinforcing bar (1) is positioned at carrying reinforcing bar (3) and supports the top of steel bar stress (5), anchor bar (2) is positioned at carrying reinforcing bar (3) and supports the below of steel bar stress (5), weld mutually with interception reinforcing bar (1) and support steel bar stress (5) respectively at the two ends of bearing bar (4), between interception reinforcing bar (1) and the interception reinforcing bar (1), between carrying reinforcing bar (3) and the carrying reinforcing bar (3), support between steel bar stress (5) and the support steel bar stress (5) and weld mutually by fixed reinforcing bar (6).
CNA2003101113494A 2003-11-07 2003-11-07 Emergency blockage method for levee breach Pending CN1542231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2003101113494A CN1542231A (en) 2003-11-07 2003-11-07 Emergency blockage method for levee breach

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2003101113494A CN1542231A (en) 2003-11-07 2003-11-07 Emergency blockage method for levee breach

Publications (1)

Publication Number Publication Date
CN1542231A true CN1542231A (en) 2004-11-03

Family

ID=34336045

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2003101113494A Pending CN1542231A (en) 2003-11-07 2003-11-07 Emergency blockage method for levee breach

Country Status (1)

Country Link
CN (1) CN1542231A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101974893A (en) * 2010-09-28 2011-02-16 张照华 Tripod plug cage for river closure of flood-resisting buster and watercourse
CN102182161A (en) * 2011-03-20 2011-09-14 胡洪新 Device for blocking dike breach

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101974893A (en) * 2010-09-28 2011-02-16 张照华 Tripod plug cage for river closure of flood-resisting buster and watercourse
CN102182161A (en) * 2011-03-20 2011-09-14 胡洪新 Device for blocking dike breach

Similar Documents

Publication Publication Date Title
US10669684B2 (en) Wave suppressor and sediment collection system
CN101666073B (en) Method for constructing river and lake levee breach closure with steel sheet pile
CN104372803B (en) Dyke reinforcement assembled moving cofferdam
IL219127A (en) Wave suppressor and sediment collection system
CN200982053Y (en) Reinforcing steel bar frame for plugging dam burst and dealing with emergency
CN111424716B (en) Oblique-pulling anchorage type suspension tunnel structure with relay extension of artificial island
CN1069718C (en) Construction method while river cut-off dam closured
CN203174558U (en) Conduit and floating pipe multilayer combined type wave-dissipation wall
CN101463594A (en) End dumping flow guiding and stopping method
CN109881634A (en) A kind of flood season dike breach rapid rescue method shut off using geosynthetics
CN103114556B (en) Wave dissipating wall with multi-layer combined pipes and floating hoses
CN1542231A (en) Emergency blockage method for levee breach
RU144821U1 (en) OPERATIONAL WATER DISCHARGE (OPTIONS)
CN113931135A (en) Column cage stone pile supporting cage type flashboard for blocking breach and burst and rapid emergency rescue method
CN110004959A (en) Concrete cofferdam rapid constructing method and template under circumstance of flowing water
CN1125902C (en) Floating and choking river-damming method
CN204238233U (en) Dyke reinforcement assembled moving cofferdam
CN105603942A (en) Dam over-standard flood diversion siphon belt
JP5669189B2 (en) Construction method of transmission type sea area control structure
CN106337397B (en) A kind of method of quickly blocking up of dykes and dams crevasse
CN115125902B (en) Method for rapidly blocking river breach based on blocking self-closing
CN115030090B (en) Quick blockage system for river breach based on blocking self-closing
CN206143718U (en) System of blocking up fast of dykes and dams crevasse
CN2455772Y (en) Chain connected float cylinder
CN108914955A (en) The method of irrigation sand pocket and the construction of steel frame combined cofferdam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication