CN1499017A - Method for reconditioning road surface by using asphalt rubber - Google Patents

Method for reconditioning road surface by using asphalt rubber Download PDF

Info

Publication number
CN1499017A
CN1499017A CNA02146197XA CN02146197A CN1499017A CN 1499017 A CN1499017 A CN 1499017A CN A02146197X A CNA02146197X A CN A02146197XA CN 02146197 A CN02146197 A CN 02146197A CN 1499017 A CN1499017 A CN 1499017A
Authority
CN
China
Prior art keywords
rubber
asphalt
heated bitumen
sealing material
crack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA02146197XA
Other languages
Chinese (zh)
Other versions
CN100395409C (en
Inventor
罗尼・伦肖
罗尼·伦肖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Original Assignee
LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd filed Critical LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Priority to CNB02146197XA priority Critical patent/CN100395409C/en
Publication of CN1499017A publication Critical patent/CN1499017A/en
Application granted granted Critical
Publication of CN100395409C publication Critical patent/CN100395409C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Road Repair (AREA)

Abstract

A method for repairing the pavement with asphalt rubber includes cleaning the sracks, spraying hot asphalt rubber, adding the aggregate, and rolling by heavy road roller.

Description

Utilize the method on asphalt rubber finishing road surface
Technical field
The present invention relates to utilize the method on asphalt rubber finishing road surface, particularly utilize asphalt rubber to fill out the envelope crack again and spray the method on the road surface that needs finishing.
Background technology
Pitch and cement concrete pavement various cracks can occur through after a while use, and aging and disrepair phenomenon take place.At this moment, need road pavement to repair and safeguard, to guarantee evenness of road surface.
Usually, the flexible pavement of breakage is repaired the method that is adopted be, smash damaged flexible pavement earlier, more broken supercrust (pitch fragment) is removed this discontinuous method from the road surface and carry out lentamente.Then, aspect impaired under original blacktop is transformed and again compacting until meeting the requirements.In addition, at present the processing of damaged aspect is comprised that also cold bundle method removes damaged asphalt surface course.Said process is not only time-consuming, consumption wealth, and can produce the available old concrete that pile up like a mountain.
Summary of the invention
An object of the present invention is to provide a kind of new asphalt rubber that utilizes and fill out the method for road closure face.
A method according to the present present invention comprises the following steps: to remove dust and the foreign material in the crack that needs the flexible pavement repaired; Preparation asphalt rubber sealing/joint sealing material; Seal or fill up above-mentioned crack with heated bitumen rubber joint seal/joint sealing material.Described heated bitumen rubber seal/joint sealing material should be heated to correct temperature.Asphalt rubber extracts and processing with brand-new technology from pitch, oil plant and junked tire.
Another kind of method according to the present invention comprises the following steps: to utilize asphalt rubber crack sealer/joint sealing material sealing or fills asphalt pavement crack or the junction, rigid pavement that needs are repaired; The preparation asphalt rubber binder; Spray the road surface with the heated bitumen rubber binder for preparing; In the good heated bitumen rubber binder of above-mentioned sprinkling, add gathering materials with particle diameter; Roll with heavy air pressure road roller.If the Uneven road or the distortion of repairing before spraying heated bitumen rubber binder, are built a level surface with traditional bituminous concrete.Asphalt rubber extracts and processing with brand-new technology from pitch, oil plant and junked tire.But spraying mechanical system carries out.
Utilize method of the present invention, can prevent that sealing infiltrates old pavement crack, thereby prevent that supercrust from further damaging.Can save greatly simultaneously and transform damaged used time and the construction costs in road surface, reduce when utilizing the prior art transformation to repair damaged road surface the influence of traffic and the time of blocked road.In addition, keep road surface elasticity, greatly reduced the road surface ageing time, reduced maintenance number of times and time, saved cost greatly.
The specific embodiment
Use or other reason owing to long-time, various cracks usually appear in the supercrust that is made of pitch or cement concrete, take place damaged.
For the crack of flexible pavement or the junction of rigid pavement, at first to remove wherein dust or foreign material etc.Removing work can be by hand or mechanical mode carry out.Because size, the degree of depth and the out-of-shape in crack, the most handy mechanical system is finished.About 250 ℃ hot gas that can use instrument such as hot-air syringe to produce blows out the dust in the crack, rubble or foreign material etc.Also can use other known equipment or instrument to remove.
After dust out, the foreign material etc., seal or fill asphalt pavement crack or the junction, rigid pavement that needs repairing with a kind of special asphalt rubber crack sealer/joint sealing material.This asphalt rubber crack sealer/joint sealing material utilizes in pitch, oil plant and the junked tire and extracts and be processed into brand-new technology, has very high softening point.
When asphalt pavement crack or junction, rigid pavement filled bitumen rubber crack sealer/joint sealing material, asphalt rubber crack sealer/joint sealing material is reached or remain on correct temperature, promptly about 190 ℃-200 ℃, to guarantee to penetrate and fill the crack.High temperature can also guarantee the bonding of asphalt rubber crack sealer/joint sealing material and crack perisporium.For this reason, can adopt special-purpose mobile unit heating and storage asphalt rubber crack sealer/joint sealing material.Because the scrambling in crack, preferably asphalt rubber crack sealer/joint sealing material is placed in the mobile unit that can be heated correct temperature, be injected into crack or junction with hand-held gate spool, to reach the purpose that the crack is fully filled.
The Uneven road of Xiu Buing or deform if desired should be after above-mentioned filling be finished, with traditional bituminous concrete at above-mentioned Uneven road place or the place of deforming build a level surface so that the road surface keeps is smooth.
On level surface, spray special heated bitumen rubber binder then.This asphalt rubber binder is fully to be stirred by crumb and pitch to form.Stirring should at high temperature be carried out to guarantee its uniformity.
Sprinkling can utilize mechanical system to carry out.Should be between 195 ℃-210 ℃ during sprinkling with the temperature maintenance of asphalt rubber binder.
After spraying asphalt rubber binder on the road surface, directly in heated bitumen rubber binder, add single-sizeaggregat.Normally 6.7 millimeters of the sizes of gathering materials, 9.5 millimeters, 13.2 millimeters, 16.0 millimeters and 19.0 millimeters.The density of gathering materials is determined according to factors such as concrete road conditions, weathers.
Then, roll, make the road surface reach the use standard with heavy pneumatic road roller road pavement.
More than by embodiment the present invention has been described, but the present invention is not limited thereto.Those skilled in the art can make different modifications to the present invention under the situation that does not break away from spirit of the present invention.All modifications all falls within the scope of the present invention.

Claims (9)

1. method of utilizing asphalt rubber finishing road surface is characterized in that comprising the following steps: removing dust and foreign material in the crack of flexible pavement of needs repairing; Preparation asphalt rubber sealing/joint sealing material; Asphalt rubber joint seal/joint sealing material is heated to correct temperature; Seal or fill up above-mentioned crack with the heated bitumen rubber joint seal that remains on correct temperature/joint sealing material.
2. according to the process of claim 1 wherein that asphalt rubber extracts and processing with brand-new technology from pitch, oil plant and junked tire.
3. according to the process of claim 1 wherein that the temperature of described heated bitumen rubber seal/joint sealing material is 190 ℃-200 ℃.
4. according to the process of claim 1 wherein that spraying heated bitumen rubber seal/joint sealing material utilizes mechanical system to carry out.
5. a method of utilizing asphalt rubber finishing road surface is characterized in that comprising the following steps: to utilize asphalt rubber crack sealer/joint sealing material sealing or filling asphalt pavement crack or the junction, rigid pavement that needs are repaired; The preparation asphalt rubber binder; Spray the road surface with the heated bitumen rubber binder for preparing; In the good heated bitumen rubber binder of above-mentioned sprinkling, add gathering materials with particle diameter; Roll with heavy air pressure road roller.
6. according to the method for claim 5, wherein spray heated bitumen rubber binder before, build a level surface with traditional bituminous concrete.
7. according to the method for claim 5, wherein asphalt rubber extracts from pitch, oil plant and junked tire and processes.
8. according to the method for claim 5, wherein spray heated bitumen rubber binder and utilize mechanical system to carry out.
9. according to the method for claim 5, the temperature of wherein said heated bitumen rubber binder is 195 ℃-210 ℃.
CNB02146197XA 2002-11-04 2002-11-04 Method for reconditioning road surface by using asphalt rubber Expired - Lifetime CN100395409C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB02146197XA CN100395409C (en) 2002-11-04 2002-11-04 Method for reconditioning road surface by using asphalt rubber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB02146197XA CN100395409C (en) 2002-11-04 2002-11-04 Method for reconditioning road surface by using asphalt rubber

Publications (2)

Publication Number Publication Date
CN1499017A true CN1499017A (en) 2004-05-26
CN100395409C CN100395409C (en) 2008-06-18

Family

ID=34232671

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB02146197XA Expired - Lifetime CN100395409C (en) 2002-11-04 2002-11-04 Method for reconditioning road surface by using asphalt rubber

Country Status (1)

Country Link
CN (1) CN100395409C (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831186A (en) * 2010-04-20 2010-09-15 上海大学 Road surface crack sealing and mending tape and preparation and construction process thereof
CN1629405B (en) * 2004-10-22 2010-11-10 深圳市魁道道路用材技术开发有限公司 Method for repairing crack on asphalt road pavement
CN105064167A (en) * 2015-08-14 2015-11-18 福州皇家地坪有限公司 Method for handling cracking of plastic track
CN105113356A (en) * 2015-07-28 2015-12-02 南丹县交通运输局 Repair method of road surface cracks
CN107386039A (en) * 2016-05-17 2017-11-24 上海畅富市政工程有限公司 The remodeling method of Old cement concrete

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4069182A (en) * 1966-10-21 1978-01-17 Mcdonald Charles H Elastomeric pavement repair composition
US3844668A (en) * 1972-01-13 1974-10-29 R Winters Pavement composition
US4068023A (en) * 1976-05-20 1978-01-10 Union Oil Company Of California Rubberized asphalt paving composition and use thereof
FR2580658B1 (en) * 1985-04-22 1987-06-05 Beugnet Sa COATING COMPOSITION BASED ON BITUMEN AND RECOVERY RUBBER POWDER
CN2090390U (en) * 1991-03-16 1991-12-11 陈志荣 Asphalt packing machine for joints

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1629405B (en) * 2004-10-22 2010-11-10 深圳市魁道道路用材技术开发有限公司 Method for repairing crack on asphalt road pavement
CN101831186A (en) * 2010-04-20 2010-09-15 上海大学 Road surface crack sealing and mending tape and preparation and construction process thereof
CN101831186B (en) * 2010-04-20 2012-05-02 上海大学 Road surface crack sealing and mending tape and preparation and construction process thereof
CN105113356A (en) * 2015-07-28 2015-12-02 南丹县交通运输局 Repair method of road surface cracks
CN105064167A (en) * 2015-08-14 2015-11-18 福州皇家地坪有限公司 Method for handling cracking of plastic track
CN107386039A (en) * 2016-05-17 2017-11-24 上海畅富市政工程有限公司 The remodeling method of Old cement concrete

Also Published As

Publication number Publication date
CN100395409C (en) 2008-06-18

Similar Documents

Publication Publication Date Title
CN108166348A (en) A kind of asphalt pavement crack method for repairing and mending and repairing construction
US20170167085A1 (en) Patch and method for repairing asphalt pavement
CN108118577A (en) A kind of road gap filling repair technology
CN102041764A (en) Construction method for preventing repaired crack from cracking
CN103132420A (en) Repairing and transforming method of old cement concrete pavement
CN106758711B (en) A kind of construction of the highway maintenance process
CN100395409C (en) Method for reconditioning road surface by using asphalt rubber
CN110878503A (en) Damaged asphalt pavement repairing method
CN112281572A (en) Construction method of stress absorbing layer asphalt pavement
CN112681790A (en) Grouting treatment method for concrete roof cracks
CN110359349A (en) A kind of construction method of asphalt pavement crack processing
CN108316116A (en) A kind of base joint grouting glue and apply its road gap repair technology
CN105819792B (en) It is a kind of can the concrete of rapid shaping and the renovation technique at expansion joint
CN106835923A (en) The quick temperature compensation equipment of Asphalt Pavement Damage and its technique
CN114960978B (en) Waterproof method for concrete joint without reserved embedded structure in reconstruction and expansion structure
CN106758661A (en) A kind of prosthetic device at cement flooring restorative procedure and cement flooring expansion joint
CN106884368A (en) A kind of paver for bituminous paving
CN109881569A (en) A kind of asphalt pavement pit repairing method
CN106049244A (en) Pavement thermal regeneration method
CN105199666A (en) Production and construction technologies of road sealant
CN108913045A (en) A kind of breakage marble slabs method for repairing and mending
CN211645779U (en) Durable flexible structure for treating waterproof sealing layer of high-speed railway foundation
CN110158435A (en) A kind of construction method in seamlessization punishment bituminous pavement slight lateral crack
CN206570666U (en) A kind of quick temperature compensation equipment of Asphalt Pavement Damage
CN1446983B (en) Method for repairing pavement by using asphalt rubber

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20080618

CX01 Expiry of patent term