CN1446983B - Method for repairing pavement by using asphalt rubber - Google Patents

Method for repairing pavement by using asphalt rubber Download PDF

Info

Publication number
CN1446983B
CN1446983B CN 02116218 CN02116218A CN1446983B CN 1446983 B CN1446983 B CN 1446983B CN 02116218 CN02116218 CN 02116218 CN 02116218 A CN02116218 A CN 02116218A CN 1446983 B CN1446983 B CN 1446983B
Authority
CN
China
Prior art keywords
asphalt rubber
pitch
concrete
impact
road surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 02116218
Other languages
Chinese (zh)
Other versions
CN1446983A (en
Inventor
埃瑞克·约斯通·库克
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Original Assignee
LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd filed Critical LANPAI IMPACT COMPACT TECHNOLOGY DEVELOPMENT (BEIJING) Co Ltd
Priority to CN 02116218 priority Critical patent/CN1446983B/en
Publication of CN1446983A publication Critical patent/CN1446983A/en
Application granted granted Critical
Publication of CN1446983B publication Critical patent/CN1446983B/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

A method for repairing pavement with asphalt rubber includes breaking the damaged pavement, compacting it and spreading asphalt rubber layer.

Description

Utilize the method for asphalt rubber redeck
Technical field
The present invention relates to utilize the method for asphalt rubber redeck, particularly utilize asphalt rubber to cooperate and impact the method that real pressure technology is repaired damaged road surface.
Background technology
Pitch and cement concrete pavement various cracks can occur through after a while use, and disrepair phenomenon takes place.At this moment, need repair the road surface that crack or breakage occur, to guarantee evenness of road surface.
Usually, the flexible pavement of breakage is repaired the method that is adopted be, utilize equipment such as air drill to smash damaged flexible pavement earlier, broken supercrust (pitch fragment) is removed from the road surface, be deposited in other places.Then, aspect impaired under original blacktop is transformed and again compacting until meeting the requirements.After this, making pitch again.Said process is not only time-consuming, consumption wealth, and can produce the old asphalt concrete that pile up like a mountain.
When the cement concrete pavement of breakage is repaired, adopt a series of discontinuous methods to smash cement concrete pavement layer usually, broken supercrust (broken concrete) is removed from the road surface, be deposited in other places.Again behind the damaged layer under the remodeling concrete road surface again compacting until meeting the requirements.Said process is not only time-consuming, consumption wealth, and can produce the old concrete that pile up like a mountain.
Because asphalt rubber has characteristics such as high viscosity, high softening-point, in recent years, people begin to utilize asphalt rubber to be processed into the asphalt rubber concrete, and use it for and build new road, particularly high-grade highway.
Summary of the invention
An object of the present invention is to provide a kind of new method of utilizing asphalt rubber to cooperate impact-rolling technique that damaged road surface is repaired.
Another object of the present invention is to save to repair damaged used time and the cost in road surface.
Another object of the present invention is to make full use of Available Material.
A method according to the present present invention comprises the following steps: rupture damaged pitch or cement concrete pavement layer; Further roll firm above-mentioned pitch that is ruptured or cement concrete pavement layer; Utilize asphalt rubber to prepare the asphalt rubber concrete; With the new road surface of asphalt rubber concrete making for preparing; Above-mentioned asphalt rubber rigid pavement is rolled.Wherein damaged pitch or the cement concrete pavement layer of fracture realized by shock compaction.Asphalt rubber extracts and processing with brand-new technology from pitch, oil plant and junked tire.
Another kind of method according to the present invention comprises the following steps: broken pitch or cement concrete pavement layer; Remove and give up pitch or the cement concrete that is broken; Remove the pitch that is broken or the impaired aspect below the layer of concrete, and with replacing new aspect; Utilize controlled shock compaction method that corresponding aspect is carried out impact-rolling, set up a new subbase; Lay new basic unit and with its compacting; Preparation asphalt rubber concrete; The asphalt rubber concrete for preparing is layered on the above-mentioned sub-surface forms the road surface; Above-mentioned asphalt rubber rigid pavement is rolled.Wherein broken damaged pitch or cement concrete pavement layer are realized by shock compaction; The pitch that is broken or the corresponding surface layer under the cement-concrete road further rolled by shock compaction realize.Asphalt rubber extracts and processing with brand-new technology from pitch, oil plant and junked tire.
Utilize method of the present invention, can save greatly and transform damaged used time and the construction costs in road surface, reduce when utilizing the prior art transformation to repair damaged road surface the influence of traffic and the time of blocked road.In addition, because the characteristic of asphalt rubber and the employing of impact-rolling technique are compared with the bituminous concrete that uses traditional asphalt binder processing, the road surface thickness of overhauling road with the asphalt rubber concrete can obviously reduce.
Embodiments of the invention are described below with reference to accompanying drawings.
The accompanying drawing summary
Fig. 1 is the schematic diagram of road section;
Fig. 2 is the schematic diagram according to an embodiment of the inventive method;
Fig. 3 is the schematic diagram according to another embodiment of the inventive method.
As shown in Figure 1, road generally include such which floor, that is, and nethermost roadbed, the subbase on it, basic unit and supercrust.Supercrust is one deck bituminous concrete or cement concrete normally.
Use or other reason owing to long-time, various cracks usually appear in the supercrust that is made of pitch or cement concrete, take place damaged.
With reference to Fig. 2, road surface for repairing or transform at first utilizes shock compaction equipment, for example the three limit types or the polygonal impact densifying-machine of South Africa Lan Pai company, to a certain degree impact-rolling is carried out on the road surface that will repair or transform, smash bituminous concrete or cement concrete pavement layer.Usually the thickness of bituminous concrete or cement concrete pavement layer will carry out impact-rolling several times between 200 millimeters to 300 millimeters, the road surface could be smashed.Therefore, smash the required impact-rolling number of times in road surface, decide by experiment according to the thickness on road surface and the tonnage of material and impact densifying-machine.Generally need 15 to 25 times punching press, 200 millimeters bituminous concrete or cement concrete pavement layers to 300 millimeters thick could be smashed.Usually supercrust to be smashed about 300 millimeters to 900 millimeters fragment.Broken supercrust other layer below it constituted the basic unit of the road that will repair.This basic unit obviously increases than the thickness of former basic unit, and intensity is obviously strengthened.
In some cases, may need bituminous concrete or the further impact-rolling of cement concrete layer, improving the degree of compaction of this layer, so that provide a firm roadbed and basic unit for improved road surface reasonable in design to smashing.At this moment should be as requested and actual conditions, by testing the number of times of determining impact-rolling, until meeting the requirements.For some location, further impact-rolling may destroy original sub-surface.Therefore, whether need the number of times of further impact-rolling and concrete impact-rolling, be according to the roadbed of construction site, basic unit with to situations such as the requirement decision of road.
Broken bituminous concrete or cement concrete pavement layer are formed the basic unit of repairing road by shock compaction, significantly reduced the expense that broken bituminous concrete or concrete pavement layer are transported, and guaranteed the utilization again of these materials.In addition, be to be undertaken owing to smash by continuous impact-rolling with compacting, therefore, saved cargo handling operation than discontinuous operating type of the prior art, thereby significantly reduced the time that influences traffic because of repairing the roads.
Available discarded object-bits crumb rubber that asphalt rubber can extract from pitch, oil plant and old tire processes.The processing of asphalt rubber binder, storage and use are to be finished by the special agitator that is positioned at the building site.Bituminous concrete can use common hot-mix asphalt mixture equipment to process.
Utilize the common equipment of paving the way with the asphalt rubber concrete making that processes on the face of old road, and roll according to relevant technical requirements.Because concrete characteristic of asphalt rubber and advantage, the thickness of the supercrust that is made of the asphalt rubber concrete can reduce about 50% than pitch or cement concrete pavement layer.
With reference to Fig. 3, under a stable condition, said method can not satisfy requirement of engineering, as not forming enough firm new subbase by further rolling, then to utilize shock compaction equipment, the for example three limit types or the polygonal impact densifying-machine of South Africa Lan Pai company, shock compaction is carried out on the road surface that will repair or transform, after smashing bituminous concrete or cement concrete pavement layer, the pitch or the cement concrete layer that then need to be broken are removed, and with the aspect of the breakage below it, remove as basic unit and subbase, replace it with new basic unit and subbase.By the control Impact Compaction Technique aspect under protobitumen or the cement concrete pavement layer is carried out restoration updating, promptly by the effect of the each impact-rolling of monitoring and the number of times of impact-rolling, reach the effect that expection requires, form new satisfactory basic unit and subbase.And then carry out subsequent handling, lay new supercrust with the asphalt rubber concrete.
More than by embodiment the present invention has been described, but the present invention is not limited thereto.Those skilled in the art can make different modifications to the present invention under the situation that does not break away from spirit of the present invention.All modifications all falls within the scope of the present invention.

Claims (2)

1. method of utilizing asphalt rubber to cooperate impact-rolling technique that damaged road surface is repaired is characterized in that comprising:
Utilize impact densifying-machine that the pitch or the cement concrete pavement layer of breakage are crushed to 300 millimeters to 900 millimeters fragment;
Utilize further firm above-mentioned pitch that is broken of impact densifying-machine or cement concrete pavement;
Utilize asphalt rubber to prepare the asphalt rubber concrete;
The asphalt rubber concrete making for preparing is formed new road surface on former supercrust;
Above-mentioned asphalt rubber rigid pavement is rolled,
Wherein, used asphalt rubber is that the available discarded object-bits crumb rubber that extracts from pitch, oil plant and old tire processes.
2. according to the process of claim 1 wherein that pitch or cement concrete pavement layer to breakage further firmly realize by shock compaction.
CN 02116218 2002-03-21 2002-03-21 Method for repairing pavement by using asphalt rubber Expired - Lifetime CN1446983B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02116218 CN1446983B (en) 2002-03-21 2002-03-21 Method for repairing pavement by using asphalt rubber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02116218 CN1446983B (en) 2002-03-21 2002-03-21 Method for repairing pavement by using asphalt rubber

Publications (2)

Publication Number Publication Date
CN1446983A CN1446983A (en) 2003-10-08
CN1446983B true CN1446983B (en) 2011-09-07

Family

ID=28048627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02116218 Expired - Lifetime CN1446983B (en) 2002-03-21 2002-03-21 Method for repairing pavement by using asphalt rubber

Country Status (1)

Country Link
CN (1) CN1446983B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100436716C (en) * 2004-09-20 2008-11-26 贺杰 Breaking method for cement concrete pavement layer
CN102041762B (en) * 2010-12-03 2012-07-04 上海市城市建设设计研究院 Road rehabilitation method for guaranteeing compaction effect of pavement structure
CN103498398B (en) * 2013-10-16 2016-04-13 南京林业大学 Concrete on fire flexible pavement residue functional performance is assessed and determines the method for recovery scenario

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5460649A (en) * 1994-06-06 1995-10-24 Strassman; David R. Fiber-reinforced rubber asphalt composition
CN1274030A (en) * 1999-05-14 2000-11-22 蓝派冲击压实技术开发(北京)有限公司 Impacting compact method for reforming concrete road
CN1286336A (en) * 1999-08-26 2001-03-07 蓝派冲击压实技术开发(北京)有限公司 Method for maintaining asphalt pavement

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5460649A (en) * 1994-06-06 1995-10-24 Strassman; David R. Fiber-reinforced rubber asphalt composition
CN1274030A (en) * 1999-05-14 2000-11-22 蓝派冲击压实技术开发(北京)有限公司 Impacting compact method for reforming concrete road
CN1286336A (en) * 1999-08-26 2001-03-07 蓝派冲击压实技术开发(北京)有限公司 Method for maintaining asphalt pavement

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
王文贵,覃淑媛.橡胶沥青在北方高寒地区公路工程中的应用.内蒙古公路与运输.1996,1-3. *
石秋侠,靳长征.利用废旧橡胶掺配制作道路用改性橡胶沥青.山西交通科技 127.1999,(127),第1栏13行-第3栏20行.
石秋侠,靳长征.利用废旧橡胶掺配制作道路用改性橡胶沥青.山西交通科技 127.1999,(127),第1栏13行-第3栏20行. *
陈桁,吕伟民.钱塘江大桥橡胶沥青桥面铺装的探讨.华东公路 92.1995,(92),第6栏14行-17行.
陈桁,吕伟民.钱塘江大桥橡胶沥青桥面铺装的探讨.华东公路 92.1995,(92),第6栏14行-17行. *
魏连雨,吕大镛,李巧茹,李国强.乳化橡胶沥青混凝土半刚性复合路面材料实验研究.河北工业大学学报29 3.2000,29(3),第1页-第3页.
魏连雨,吕大镛,李巧茹,李国强.乳化橡胶沥青混凝土半刚性复合路面材料实验研究.河北工业大学学报29 3.2000,29(3),第1页-第3页. *

Also Published As

Publication number Publication date
CN1446983A (en) 2003-10-08

Similar Documents

Publication Publication Date Title
CN104762863B (en) Bituminous mixture used for thin layer overlay of cement concrete pavement and preparation and construction methods of bituminous mixture
CN104652212B (en) A kind of Promotion Transformation method of Old cement concrete
CN104452510A (en) Immediate construction method of rural road
CN105133452A (en) Road three-slag base in-situ cold regeneration construction method
CN110878503A (en) Damaged asphalt pavement repairing method
CN1446983B (en) Method for repairing pavement by using asphalt rubber
CN107905082B (en) Crushing and utilizing method suitable for old cement concrete panel under poor support
CN103774518A (en) Fiber reinforced bituminous pavement stress absorbing layer and construction method thereof
CN110629621A (en) Paving construction process for rubblizing treatment and recycling of cement road repaired pavement
CN105625150B (en) A kind of method that asphalt pavement pit repairs border reinforcement
CN115450086B (en) Old cement concrete pavement reconstruction structure suitable for non-extra-heavy traffic grade and design method
CN110820466A (en) Quick repairing method for cement concrete pavement
CN114182595A (en) Construction method of long-life asphalt road
CN100395409C (en) Method for reconditioning road surface by using asphalt rubber
Rajani Best practices for concrete sidewalk construction
CN219032888U (en) Cement concrete pavement microcrack regeneration pre-cracking guide block
KR100692511B1 (en) Pavement Breaking Apparatus
CN113250010B (en) Large-particle-size asphalt macadam flexible ballast bed and construction method thereof
CN213867158U (en) Cement road surface rubble chemical regeneration adds spreads compound flexible basic unit rubber asphalt pavement structure
CN115506191B (en) Durable asphalt pavement structure suitable for non-extra-heavy traffic grade and design method
CN214362647U (en) Self-healing composite pavement structure using recycled aggregate
Mieczkowski et al. Heavy maintenance of concrete paved roads using the regional roads No. 102 and No. 142 as an example
JP3150582U (en) Pavement structure that uses a semi-flexible pavement plate for the intermediate layer.
CN114908632B (en) Method for repairing and improving road surface bearing capacity
Fitts Rubblization using resonant frequency equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110907